1 Integrated Systems Project Management Process (ISPM) Overview The most valuable and least used word in a project manager's vocabulary is No. The integration of multiple building monitoring and controls systems is a very complex process involving multiple systems manufacturers, installers and contractors, multiple software platforms and communication protocols resulting in typically large databases of information. Whether new construction or renovation, project management is essential to the successful completion of any project. However, project management of integrated systems requires a very different skill set not readily available in today s marketplace. Unlike traditional project management, Integrated Systems Project Management (ISPM) has a specific focus on software platforms, communications methodologies, device naming conventions and database creation for each building system and the Enterprise or Integration System Software Platform. New Construction The ISPM process starts with the systems design for each building element including the Building Automation, Power Monitoring and Control, Security Access Control, Life Safety, Lighting Control and any other microprocessor based system that has the ability to share information with other systems. 1

2 Contractors Owner/Client Interior Designers Architect Civil Engineers Mechanical Engineers Construction Manager Electrical Engineers The typical design approach is to specify an open protocol system based on industry standard communications such as BACnet, Lonworks, Modbus, SNMP, OBIX and many others including wireless device technology. It has been the role of the Building Automation System vendor to integrate these systems either as part of the traditional Division 15 scope of work or as a separate scope under Division 25 with each system being provided under different divisions of electrical and mechanical. But the expected results in this typical approach have not met design and client expectations and have been expensive. There has been too much emphasis on communications protocols and technology gadgets and not enough attention on the intricacies of system databases. This compounds the issues with the integrated architecture for a large project. The ISPM process needs to start at Design Development with identifying the end result (client s goals and objectives) in the use of technology to operate the facilities regardless of the size of the building or portfolio of buildings. The database definitions are the result of specifying not just the physical points and types of information but must include all data that will be used by the Integrated System Software to accomplish the stated objectives. A single temperature sensor or device contained within a DDC system that uses the BACnet protocol may have as many as 30 data values for each BACnet object. Because the BACnet protocol supports Auto-Discovery, all 30 data values may be in the database at multiple levels of the system architecture. How many of those values are actually going to be used by the software and more importantly by the end user to manage their facility is just one aspect of the IBPM process that needs to be included in the overall systems design. Another aspect is the device (sensor) naming convention used by vendors that is used by all the software platforms. This one aspect has been one of the most difficult, time consuming and expensive parts of trying to implement a fully Integrated Building Systems project. To resolve this issue the IBPM process should define the naming conventions as part of the design for 2

3 each system which all vendors must follow. The device naming conventions can be part of the vendor selection pre-qualification and submittal approval process for all systems to ensure conformity and standardization of database creation. Retrofit/Existing Buildings A retrofit or existing building Integrated Systems project is even more complex than new construction when dealing with multiple systems manufacturers, different generations of hardware and software, no standard naming conventions, legacy communications protocols and outdated software platforms. One of the steps that have been typically missed in a project site survey process is an Existing Database Analysis. This is more detailed than collecting the Points List from various systems and needs to include the evaluation of the device naming conventions. Depending on the age of a system and if it has been expanded over the years, it is not uncommon to find different naming conventions in different controllers and databases within the same system. Multiply that over a large campus or portfolio of buildings and the issues can compound the reality of being able to deliver a fully integrated system solution. It is common for the Systems Integrator vendor or contractor to convert all the device names within the IS normalization database. This can extend project schedules dramatically and add costs which causes budget issues. It is better to include the Database Analysis in the site survey process and provide the Systems Integrator with all the device names that would need to be converted as part of the design and procurement process. Depending on the results of the Database Analysis it may be more cost effective to have the system vendor revise the naming conventions to a common standard prior to implementing an Integrated Systems project. Another result of the Database Analysis is validating the operating conditions of the systems. Due to no or limited systems commissioning, expansions and changes to the systems over time, the analysis will validate the physical and data point 3

4 conditions separate of the typical sequence of operations. This will save many hours, days or months of the implementation schedule and results in lower overall project costs with a better quality solution. Post Commissioning Database and Performance Analysis Part of the goals and objectives of an Integrated Systems project is to reduce the total cost of operation (TCO) over the life cycle of the building(s. The TCO usually includes energy, operations and maintenance costs per square foot, per department, per building or may include a matrix of performance indicators. Systems commissioning has traditionally validated the sequences of operations of all the systems against the design documents but has not included detailed analysis of performance measures from a more holistic perspective. A traditional cooling sequence of operation commissioning would validate that 55 degree air is being delivered by an air handler to the space to maintain a 70 degree comfort level and that 45 degree chilled water is being delivered to that air handler at a specified GPM. What it does not include is the analysis of how many spaces are actually in a cooling load, does the load need 55 degree at a certain CFM and does the load really need 45 degree water at a certain GPM. Determining what percent of CFM and GPM is really required to maintain the load and can those variables be reduced at any given time to reduce energy is a part of the Performance Analysis that should be part of the Integrated Systems Database. The Post Commissioning Database and Performance Analysis would include any algorithms or software based on principles of Fault Detection and Diagnostics for enhanced mechanical and systems performance while reducing the energy costs. The Analysis would also include relational data shared with multiple systems to accomplish specified sequences or performance. All of this would be first identified in the design documents for new and retrofit projects so all systems providers and the client will understand the expectations and there will be validation of the performance above the traditional commissioning. ISPM Coordination and Implementation 4

5 Any large project may have a Construction Manager in addition to a General Contractor with various sub- contractors especially in new construction. Regardless of the contracting structure the delivery of an Integrated Systems project requires close coordination across all trades to help manage the schedule and costs. The devil is in the details of not only knowing the systems scope but also understanding the technology and delivery of those systems to accomplish the goals and objectives per the schedule and budget. The other aspect is the typical change order issue which is almost a standard by-product of a large complex project. The ISPM process is parallel and equal to the standard contracting process and as a checks and balance should review and approve any change order that would be generated by systems vendors with a special focus on technology and schedule impact for all systems. A mechanical contractor substituting a piece of equipment that has an embedded microprocessor controller that results in the Systems Integrator having to provide a communications gateway or translator and changes the naming conventions that impacts the database generation and increases the SI schedule would not be acceptable. This is one of the roles of the ISPM process that can add significant value to the overall project. But the ISPM cannot be part of the traditional contracting tier because it needs direct communications with the owner, architect and design engineers and cannot be a conflict of interest within the traditional tier. The overall complexity of an Integrated Systems project needs specific focus and autonomy to help deliver the expected end results. Integrated Systems Information Management (ISIM) A fully integrated systems project will result in new levels of additional information just like other financial or business level software systems that will be used by the owner to help manage their business. The ultimate success factor of all integrated systems project is if the raw data from all the systems is delivered in an easy to use and understand Integrated Systems Information Management (ISIM) platform including GUI and Information Dashboards, reporting and performance analysis. In addition to the above objectives of the ISPM, defining and delivering the ISIM for the owner is the final measurable result of the project. All the raw data in all the systems is meaningless unless the owner can use it in way that fits the business and meets the project objectives. The 5

6 business objectives need to drive the design and delivery processes resulting in a usable tool with validated data regardless of the technology underpinning and methodologies. This single objective is why an Integrated Systems Project Management Process needs to an integral part of every project. For more information, write us at info@smart-buildings.com. 6

Smart Integration of Wireless Temperature Monitoring System with Building Automation System

Smart Integration of Wireless Temperature Monitoring System with Building Automation System Smart Integration of Wireless Temperature Monitoring System with Building Automation System Case Study Area of engagement Solution to integrate wireless temperature monitoring system with BMS (Building

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Comprehensive Data Center Energy Management Solutions

Comprehensive Data Center Energy Management Solutions FROM INSIGHT TO EFFICIENCY: Comprehensive Data Center Energy Management Solutions Since 1995, facility managers and BAS professionals have relied on the Niagara framework to provide full convergence of

More information

5178 EOI Direct Digital Controls Systems Strategic Plan Schedule A. Technical Submission. City of Richmond

5178 EOI Direct Digital Controls Systems Strategic Plan Schedule A. Technical Submission. City of Richmond Schedule A Technical Submission City of Richmond TABLE OF CONTENTS... 3 1 Company information... 4 1.1 Service Organization... 4 1.2 Construction Organization... 4 2 Programming Language... 5 2.1 Example

More information

Comprehensive Data Center Energy Management Solutions

Comprehensive Data Center Energy Management Solutions FROM INSIGHT TO EFFICIENCY: Comprehensive Data Center Energy Management Solutions Since 1995, facility managers and BAS professionals have relied on the Niagara Framework to provide full convergence of

More information

Control System - Enterprise Integration HVAC Concepts, Inc. (2005)

Control System - Enterprise Integration HVAC Concepts, Inc. (2005) Control System - Enterprise Integration HVAC Concepts, Inc. (2005) What is Control System Enterprise Integration? Control System Enterprise Integration is the presentation of data from multiple types of

More information

It s all open from here.

It s all open from here. It s all open from here. Never let technology impose limits on your future. That thinking drove the design of Honeywell EXCEL 5000 OPEN systems the most flexible and open communication platform for building

More information

LABOR CATEGORY DESCRIPTIONS & QUALIFICATIONS

LABOR CATEGORY DESCRIPTIONS & QUALIFICATIONS KEY LABOR CATEGORY DESCRIPTIONS PROGRAM MANAGER Description: The Program Manager is responsible for coordinating the management of all work performed under the overall contract and shall be capable of

More information

ONE DASHBOARD TO RULE THEM ALL: CASE STUDY OF AN INTEGRATED FACILITY MANAGEMENT SYSTEM. Joy M. Ulickey, Director Enovity, Inc.

ONE DASHBOARD TO RULE THEM ALL: CASE STUDY OF AN INTEGRATED FACILITY MANAGEMENT SYSTEM. Joy M. Ulickey, Director Enovity, Inc. ONE DASHBOARD TO RULE THEM ALL: CASE STUDY OF AN INTEGRATED FACILITY MANAGEMENT SYSTEM Joy M. Ulickey, Director Enovity, Inc. ABSTRACT Innovations in networkable, digital controls systems have enabled

More information

A Systems Approach to HVAC Contractor Security

A Systems Approach to HVAC Contractor Security LLNL-JRNL-653695 A Systems Approach to HVAC Contractor Security K. M. Masica April 24, 2014 A Systems Approach to HVAC Contractor Security Disclaimer This document was prepared as an account of work sponsored

More information

Newron Efficient building management

Newron Efficient building management Newron Efficient building management Everything from one source. And one head. Because today efficient buildings are intelligently networked. The suitable solutions for this can now be found by architects,

More information

It's All About HVAC Systems and Saving Big Bucks Using DDC Systems!

It's All About HVAC Systems and Saving Big Bucks Using DDC Systems! Energy-Facilities Connections Conference Leavenworth, Washington It's All About HVAC Systems and Saving Big Bucks Using DDC Systems! May 12 th, 2010 Session 2, 10-11:20 am by Greg Jourdan 1 Agenda-It's

More information

AUDITING (WITH) BAS AEE-NY APRIL 2015

AUDITING (WITH) BAS AEE-NY APRIL 2015 AUDITING (WITH) BAS AEE-NY APRIL 2015 HONEY BERK, DIRECTOR OF TECHNOLOGY MARCO ASCAZUBI, TECHNOLOGY SPECIALIST CUNY BUILDING PERFORMANCE LAB THE CITY COLLEGE OF NEW YORK APR. 21, 2015 BAS IN NYC BUILDINGS

More information

Introduction to Building Automation Systems (BAS)

Introduction to Building Automation Systems (BAS) Introduction to Building Automation Systems (BAS) Ryan R. Hoger, LEED AP 708.670.6383 ryan.hoger@tecmungo.com Building Automation Systems Centralized controls Change scheduling for multiple HVAC units

More information

System integration oriented data center. planning. In terms of ATEN's eco Sensors DCIM solution

System integration oriented data center. planning. In terms of ATEN's eco Sensors DCIM solution System integration oriented data center planning In terms of ATEN's eco Sensors DCIM solution 1. Introduction The reliability of an enterprise data center servicing either external or internal clients

More information

The Facility Manager s Guide to Building Automation Systems (BASs) Grant Wichenko, P. Eng. President, Appin Associates www.appin.

The Facility Manager s Guide to Building Automation Systems (BASs) Grant Wichenko, P. Eng. President, Appin Associates www.appin. The Facility Manager s Guide to Building Automation Systems (BASs) Grant Wichenko, P. Eng. President, Appin Associates www.appin.com Learning Objectives 1. Outline the principles of sound BAS design and

More information

High Performance Buildings Integrating Intelligent Systems Into your Business Plan

High Performance Buildings Integrating Intelligent Systems Into your Business Plan High Performance Buildings Integrating Intelligent Systems Into your Business Plan Moderator Al Underhill General Manager Building Automation Siemens Building Technologies Panel John Mathews General Manager

More information

Forum Internacional de Data & Telecomunicaciones

Forum Internacional de Data & Telecomunicaciones Forum Internacional de Data & Telecomunicaciones TAC Data Center & Telecommunications Eduardo Espinosa Agenda Company Products Data Center & Telecomm Concerns TAC Integrated Cooling, Power & Security TAC

More information

Supporting ANY PRODUCT employing

Supporting ANY PRODUCT employing Supporting ANY PRODUCT employing -BackNet -LonWorks -ModBus - XML -SNMP -OPC WEB controllers (JACE-Java Application Control Engine) - Provides server and internet power at the building level - Open & legacy

More information

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION MONTGOMERY COLLEGE JOB CLASS SPECIFICATION Title: Project Manager I (Facilities) Grade: J FLSA: Nonexempt Financial Disclosure: No Job Class Level: This includes performance level positions in the Project

More information

The DANTE NOC Network Monitoring System

The DANTE NOC Network Monitoring System The DANTE NOC Network Monitoring System Xavier Martins-Rivas, DANTE TNC 2010, Vilnius, 2 nd June 2010 The DANTE NOC Network Monitoring System The brief for the DANTE Network Operations Centre Network Monitoring

More information

Basics Value Next Steps

Basics Value Next Steps Selling TALK Basics Value Next Steps Basics Value Next Steps Terms The Tridium Niagra JACE Java Application Control Engine Tridium = Company Niagara Framework = Technology JACE Controller = Java application

More information

PHCC Educational Foundation Contractor Library Engineering Continuing Education

PHCC Educational Foundation Contractor Library Engineering Continuing Education PHCC Educational Foundation Contractor Library Engineering Continuing Education Engineering-Specific Courses This list includes engineering-specific courses only. Descriptions for all approved courses

More information

BUILDING AUTOMATION & CONTROLS, BUILDING AUTOMATION & CONTROLS, WHAT S NEW & WHAT WILL THE FUTURE BRING? WHAT S NEW & WHAT WILL THE FUTURE BRING?

BUILDING AUTOMATION & CONTROLS, BUILDING AUTOMATION & CONTROLS, WHAT S NEW & WHAT WILL THE FUTURE BRING? WHAT S NEW & WHAT WILL THE FUTURE BRING? BUILDING AUTOMATION & CONTROLS, WHAT S NEW & WHAT WILL THE FUTURE BRING? PRESENTER: GAYLEN ATKINSON PRESIDENT ATKINSON ELECTRONICS, INC. SALT LAKE CITY, UTAH BUILDING AUTOMATION & CONTROLS, WHAT S NEW

More information

Smart Offices: How Intelligent Building Solutions Are Changing the Occupant Experience

Smart Offices: How Intelligent Building Solutions Are Changing the Occupant Experience Smart Offices: How Intelligent Building Solutions Are Changing the Occupant Experience INTEL-SPONSORED WHITE PAPER Casey Talon Noah Goldstein Senior Research Analyst Research Director Published 4Q 2015

More information

SECTION 16002C CAMPUS CENTRAL METERING SYSTEM DESIGN CRITERIA 1. General

SECTION 16002C CAMPUS CENTRAL METERING SYSTEM DESIGN CRITERIA 1. General SECTION 16002C CAMPUS CENTRAL METERING SYSTEM DESIGN CRITERIA 1. General A. Electrical usage on the Brown campus is presently monitored by a Siemens-brand, web-based central metering system, which includes

More information

Strategies and Incentives for Retrofitting Commercial Buildings to Reduce Energy Consumption

Strategies and Incentives for Retrofitting Commercial Buildings to Reduce Energy Consumption Strategies and Incentives for Retrofitting Commercial Buildings to Reduce Energy Consumption Cory Vanderpool Business Development Director EnOcean Alliance Harrisonburg, VA USA ABSTRACT Rising electricity

More information

AUTOMSOFT and POWER ANALYTICS - Data Center White Space Management Realized

AUTOMSOFT and POWER ANALYTICS - Data Center White Space Management Realized Executive Summary Power Analytics has been a leading edge provider of analytical software for the Data Center market and related industries for over six years. In that time, Power Analytics has been involved

More information

BUSINESS RULES AND GAP ANALYSIS

BUSINESS RULES AND GAP ANALYSIS Leading the Evolution WHITE PAPER BUSINESS RULES AND GAP ANALYSIS Discovery and management of business rules avoids business disruptions WHITE PAPER BUSINESS RULES AND GAP ANALYSIS Business Situation More

More information

Defining and Improving IT Utilisation Efficiency through Holistic Data Centre Monitoring

Defining and Improving IT Utilisation Efficiency through Holistic Data Centre Monitoring Defining and Improving IT Utilisation Efficiency through Holistic Data Centre Monitoring Michael Rudgyard CEO Concurrent Thinking Ltd Who are we? Concurrent Thinking History A spin-out company of a well-established

More information

About Geist. geistglobal.com

About Geist. geistglobal.com About Geist Geist designs and manufactures industry leading technology and software for powering, monitoring, cooling and managing critical data center infrastructure. We produce affordable, quality products

More information

Metering & Software Solutions Patty Anderson McKinstry May 2, 2011

Metering & Software Solutions Patty Anderson McKinstry May 2, 2011 Metering & Software Solutions Patty Anderson McKinstry May 2, 2011 Discussion Topics An overview of metering and software solutions used for Active Energy Management, and a discussion on how organizations

More information

Facility Management. Robin Ellerthorpe, FAIA. Summary CLIENT NEEDS. 1 Supplemental Architectural Services 2000 AIA FACILITY MANAGEMENT SERVICES

Facility Management. Robin Ellerthorpe, FAIA. Summary CLIENT NEEDS. 1 Supplemental Architectural Services 2000 AIA FACILITY MANAGEMENT SERVICES Excerpt from The Architect s Handbook of Professional Practice, 13th edition, 2000 Facility Management Robin Ellerthorpe, FAIA As more clients recognize the benefits of integrating facility planning with

More information

Fundamentals of HVAC Control Systems

Fundamentals of HVAC Control Systems ASHRAE Hong Kong Chapter Technical Workshop Fundamentals of HVAC Control Systems 18, 19, 25, 26 April 2007 2007 ASHRAE Hong Kong Chapter Slide 1 Chapter 5 Control Diagrams and Sequences 2007 ASHRAE Hong

More information

ULTIMATE GUIDE TO BUILDING AUTOMATION SYSTEM (BAS)

ULTIMATE GUIDE TO BUILDING AUTOMATION SYSTEM (BAS) ULTIMATE GUIDE TO BUILDING AUTOMATION SYSTEM (BAS) Building Automation is monitoring and controlling a building s systems including: mechanical, security, fire and flood safety, lighting, heating, ventilation,

More information

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by

More information

Executive Summary. The purpose of this document is to provide an overview of the Niagara AX product model.

Executive Summary. The purpose of this document is to provide an overview of the Niagara AX product model. Product Model Niagara AX Product Model Overview 3951 Westerre Parkway, Suite 350 Richmond, VA 23233 Ph: 804.747.4771 Fx: 804.747.5204 www.tridium.com Executive Summary The purpose of this document is to

More information

The NES Smart Metering System. The World s Most Advanced Metering System Solution for the Smart Grid

The NES Smart Metering System. The World s Most Advanced Metering System Solution for the Smart Grid The NES Smart Metering System The World s Most Advanced Metering System Solution for the Smart Grid Making the Grid Smarter At Echelon, we believe the smart grid is an energy network. It includes not only

More information

Virtualization Reduces the Cost of Supporting Open Industrial Control Systems

Virtualization Reduces the Cost of Supporting Open Industrial Control Systems Virtualization Reduces the Cost of Supporting Open Industrial Control Systems Virtualization Reduces the Cost of Supporting Open Industrial Control Systems ii Table of Contents Introduction... 1 What is

More information

WHO ARE WE AND WHAT WE DO?

WHO ARE WE AND WHAT WE DO? 1 WHO ARE WE AND WHAT WE DO? itgroup was founded in 2010 through integration of company Net Service s 2003, modern IT management platforms and new business concept. We passed a long way and become leading

More information

Enterprise Optimization

Enterprise Optimization Enterprise Optimization Assets Energy Operations 1 Market needs what we are hearing from our customers Performance visibility across systems, buildings, and real estate portfolios Managed uptime and availability

More information

For more information, contact FieldView Solutions at 732.395.6920 info@fieldviewsolutions.com, or www.fieldviewsolutions.com

For more information, contact FieldView Solutions at 732.395.6920 info@fieldviewsolutions.com, or www.fieldviewsolutions.com A FieldView White Paper How Next Generation Monitoring Improves Data Center Infrastructure Management (DCIM) Introduction According to a global survey by DatacenterDynamics (DCD), data centers in the U.S.

More information

Managing Cooling Capacity & Redundancy In Data Centers Today

Managing Cooling Capacity & Redundancy In Data Centers Today Managing Cooling Capacity & Redundancy In Data Centers Today About AdaptivCOOL 15+ Years Thermal & Airflow Expertise Global Presence U.S., India, Japan, China Standards & Compliances: ISO 9001:2008 RoHS

More information

System and Storage Virtualization For ios (AS/400) Environment

System and Storage Virtualization For ios (AS/400) Environment Date: March 10, 2011 System and Storage Virtualization For ios (AS/400) Environment How to take advantage of today s cost-saving technologies for legacy applications Copyright 2010 INFINITE Corporation.

More information

Building Analytics Improve the efficiency, occupant comfort, and financial well-being of your building.

Building Analytics Improve the efficiency, occupant comfort, and financial well-being of your building. Building Analytics Improve the efficiency, occupant comfort, and financial well-being of your building. Make the most of your energy SM Building confidence knowing the why behind your facility s operations

More information

EC-Net AX Supervisor with 0 Niagara network connections - for. EC-Net AX Supervisor with 100 Niagara network connections. Includes

EC-Net AX Supervisor with 0 Niagara network connections - for. EC-Net AX Supervisor with 100 Niagara network connections. Includes Datasheet Overview The EC-Net AX building management system (BMS) is a comprehensive Web-based platform powered by the Niagara AX Framework. Its open structure creates a common development and management

More information

C-Bus Application Messages & Behaviour Chapter 25 Air Conditioning

C-Bus Application Messages & Behaviour Chapter 25 Air Conditioning C-Bus Application Messages & Behaviour Chapter 25 Air Conditioning Document Number: CBUS-APP/25 Comments on this document should be addressed to: Engineering Manager Clipsal Integrated Systems PO Box 103

More information

Wireless Device Management: Controlling The Wireless Enterprise And Reducing Total Cost of Ownership

Wireless Device Management: Controlling The Wireless Enterprise And Reducing Total Cost of Ownership Wireless Device Management: Controlling The Wireless Enterprise And Reducing Total Cost of Ownership Today s Wireless Environment The technology platform of today s enterprise has a rapidly growing component:

More information

Redefining Infrastructure Management for Today s Application Economy

Redefining Infrastructure Management for Today s Application Economy WHITE PAPER APRIL 2015 Redefining Infrastructure Management for Today s Application Economy Boost Operational Agility by Gaining a Holistic View of the Data Center, Cloud, Systems, Networks and Capacity

More information

H.V.A.C. Design Plumbing Design

H.V.A.C. Design Plumbing Design H.V.A.C. Design H.V.A.C. Design Mira Costa College Arts Complex CP Upgrade 1. PART 1 GENERAL 1.1. DESCRIPTION SECTION 23 09 00 HVAC INSTRUMENTATION AND CONTROL 2. PART 2 - PRODUCTS 2.1. Materials

More information

BIM Test At ASHRAE HQ

BIM Test At ASHRAE HQ This article was published in ASHRAE Journal, April 2011. Copyright 2011 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org. This article may not be

More information

Safety Plan Reviews in 3D Christopher Santulli, PE. April 23, 2012 Times Square Marriott Marquis

Safety Plan Reviews in 3D Christopher Santulli, PE. April 23, 2012 Times Square Marriott Marquis Safety Plan Reviews in 3D Christopher Santulli, PE April 23, 2012 Times Square Marriott Marquis Safety Responsibility Building Code 3301.1 Responsibility for safety (abbr.) Nothing in this chapter shall

More information

Architectural and Engineering Basic Services Fee Estimating Guidelines

Architectural and Engineering Basic Services Fee Estimating Guidelines Architectural and Engineering Basic Services Fee Estimating Guidelines Basic Services is the design work customary on a typical project to take an established building program, site, and budget, and then

More information

Intelligent System Integration for Facility Dashboards and Green Kiosks

Intelligent System Integration for Facility Dashboards and Green Kiosks ASHRAE Summer Meeting 2012 San Antonio, TX Intelligent System Integration for Facility Dashboards and Green Kiosks Ron Bernstein Chief Ambassador LonMark International Learning Objectives: Define performance

More information

Building Controls MORE than a Time Clock. Building Automation is a Tool for the building to use to manage their environment

Building Controls MORE than a Time Clock. Building Automation is a Tool for the building to use to manage their environment Building Controls MORE than a Time Clock Building Automation is a Tool for the building to use to manage their environment Speaker Ken Richardson President of Island Controls Started in the Controls Business

More information

PNNL VOLTTRON TM Application Development

PNNL VOLTTRON TM Application Development PNNL VOLTTRON TM Application Development Srinivas Katipamula DOE Building Technologies Office: Technical Meeting on Software Framework for Transactive Energy July 23-24, 2014 1 Presentation Outline Application

More information

Criteria for Building Automation Dashboards

Criteria for Building Automation Dashboards This article was published in ASHRAE Journal, May 2015. Copyright 2015 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission

More information

Next-Generation Building Energy Management Systems

Next-Generation Building Energy Management Systems WHITE PAPER Next-Generation Building Energy Management Systems New Opportunities and Experiences Enabled by Intelligent Equipment Published 2Q 2015 Sponsored By Daikin Applied and Intel Casey Talon Senior

More information

CA Data Center Infrastructure Management r4.3: Administration Bundle

CA Data Center Infrastructure Management r4.3: Administration Bundle CA EDUCATION COURSE DESCRIPTION CA Data Center Infrastructure Management r4.3: Administration Bundle Course Overview CA Datacenter Infrastructure Management (CA DCIM) captures detailed real-time information

More information

Evolving from SCADA to IoT

Evolving from SCADA to IoT Evolving from SCADA to IoT Evolving from SCADA to IoT Let s define Semantics IoT Objectives, chapters 1 and 2 Separating the hype from the reality Why IoT isn t easy An IoT roadmap & framework IoT vs.

More information

Criteria 1.7 - Performance Data Review INTRODUCTION

Criteria 1.7 - Performance Data Review INTRODUCTION Criteria 1.7 - Performance Data Review INTRODUCTION Advanced Buildings Core Performance requires under Design Process Strategies Criteria 1.7 Performance Data Review that building energy use data be collected

More information

ROI CASE STUDY MAJOR CHILDREN S HOSPITAL JOHNSON CONTROLS

ROI CASE STUDY MAJOR CHILDREN S HOSPITAL JOHNSON CONTROLS ROI CASE STUDY MAJOR CHILDREN S HOSPITAL JOHNSON CONTROLS THE BOTTOM LINE A major children s hospital used Johnson Controls Technology Contracting Services to both accelerate the completion of its new

More information

Classification of Data Center Operations Technology (OT) Management Tools

Classification of Data Center Operations Technology (OT) Management Tools Classification of Data Center Operations Technology (OT) Management Tools White Paper 104 Revision 0 by Kevin Brown Dennis Bouley > Executive summary Data centers today lack a formal system for classifying

More information

Classification of Data Center Infrastructure Management (DCIM) Tools

Classification of Data Center Infrastructure Management (DCIM) Tools Classification of Infrastructure Management (DCIM) Tools White Paper 104 Revision 3 by Kevin Brown Dennis Bouley > Executive summary Data centers today lack a formal system for classifying infrastructure

More information

Zen Internet Case Study

Zen Internet Case Study Zen Internet Case Study About Zen Internet Zen Internet is an independent Internet Service Provider (ISP) that offers a full range of data, voice, and hosting services to businesses and residential users

More information

Leveraging the Web: A Universal Framework for Building Automation

Leveraging the Web: A Universal Framework for Building Automation Proceedings of the 2007 American Control Conference, New York City, July 11-13. Copyright AACC 2007. Leveraging the Web: A Universal Framework for Building Automation Tariq Samad and Brian Frank Abstract

More information

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0. Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M

More information

Networked Wireless Building Control

Networked Wireless Building Control Networked Wireless Building Control Jump start to the Enterprise IoT Danny Yu Daintree Networks Tuesday, May 19, 2015 Our industry still needs a connectivity breakthrough Persistent value for advanced

More information

Transactive Controls: Market-Based GridWise TM Controls for Building Systems

Transactive Controls: Market-Based GridWise TM Controls for Building Systems PNNL-15921 Transactive Controls: Market-Based GridWise TM Controls for Building Systems S. Katipamula D.P. Chassin D.D. Hatley R.G. Pratt D.J. Hammerstrom July 2006 Prepared for the U.S. Department of

More information

Tim Sisson - Trane HVAC OVERVIEW

Tim Sisson - Trane HVAC OVERVIEW Tim Sisson - Trane HVAC OVERVIEW HVAC Systems System Types Acoustics Controls Modernization more than one Down to the Studs Opportunity for new System Type Renovation Possible opportunity for new System

More information

Exhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015

Exhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015 Applications... 3 1. Programmer Analyst... 3 2. Programmer... 5 3. Software Test Analyst... 6 4. Technical Writer... 9 5. Business Analyst... 10 6. System Analyst... 12 7. Software Solutions Architect...

More information

Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.

Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11. Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research

More information

Control of Computer Room Air Conditioning using Sensors in the IT Equipment. Energy Efficient Data Center Demonstration Project

Control of Computer Room Air Conditioning using Sensors in the IT Equipment. Energy Efficient Data Center Demonstration Project Control of Computer Room Air Conditioning using Sensors in the IT Equipment Energy Efficient Data Center Demonstration Project About the Energy Efficient Data Center Demonstration Project The project s

More information

Understanding Programmable Automation Controllers (PACs) in Industrial Automation

Understanding Programmable Automation Controllers (PACs) in Industrial Automation Understanding Programmable Automation Controllers (s) in Industrial Automation Meet the Modern Industrial Application Implementing a modern industrial application can present a challenging and sometimes

More information

Key Considerations for Managing Big Data in the Life Science Industry

Key Considerations for Managing Big Data in the Life Science Industry Key Considerations for Managing Big Data in the Life Science Industry The Big Data Bottleneck In Life Science Faster, cheaper technology outpacing Moore s law Lower costs and increasing speeds leading

More information

RELIABLE AND FLEXIBLE POWER FOR YOUR DATA CENTRE

RELIABLE AND FLEXIBLE POWER FOR YOUR DATA CENTRE RELIABLE AND FLEXIBLE POWER FOR YOUR DATA CENTRE Highly efficient solutions for power distribution, management and monitoring POWER DISTRIBUTION WIRE-FREE MONITORING LEAK DETECTION Daxten provides comprehensive

More information

DATA CENTER PHYSICAL INFRASTRUCTURE

DATA CENTER PHYSICAL INFRASTRUCTURE Is your datacenter running with maximum performance? Datacenter managers have been challenged to maintain or increase availability, maximize efficiency, and optimize the use of existing capacity. However,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

IoT Solutions for Upstream Oil and Gas

IoT Solutions for Upstream Oil and Gas Solution Brief Intel IoT Oil and Gas Industry IoT Solutions for Upstream Oil and Gas Intel products, solutions, and services are enabling secure and seamless Internet of Things (IoT) solutions for upstream

More information

Data Center Commissioning: What you need to know

Data Center Commissioning: What you need to know Data Center Commissioning: What you need to know Course # CXENERGY1511 AIA Provider # 50111116 AABC Commissioning Group CxEnergy Conference Henderson, NV April 30, 2015 Presented by: Judson H. Adams, P.E.,

More information

Software Development for Multiple OEMs Using Tool Configured Middleware for CAN Communication

Software Development for Multiple OEMs Using Tool Configured Middleware for CAN Communication 01PC-422 Software Development for Multiple OEMs Using Tool Configured Middleware for CAN Communication Pascal Jost IAS, University of Stuttgart, Germany Stephan Hoffmann Vector CANtech Inc., USA Copyright

More information

Next Steps for Federal Data Center Consolidation Initiative

Next Steps for Federal Data Center Consolidation Initiative Next Steps for Federal Data Center Consolidation Initiative Presented to: GDI Conference April 28 2011 Creating Value, Delivering Results 2011 eglobaltech Incorporated. Tech, Inc. All rights reserved.

More information

What Is a Smart Building? p. 1 Brief History p. 1 What Is a Smart Building? p. 3 The Foundations of a Smart Building p. 7 Overview p.

What Is a Smart Building? p. 1 Brief History p. 1 What Is a Smart Building? p. 3 The Foundations of a Smart Building p. 7 Overview p. Preface p. xiii What Is a Smart Building? p. 1 Brief History p. 1 What Is a Smart Building? p. 3 The Foundations of a Smart Building p. 7 Overview p. 7 The Framework for Referencing Integration p. 8 Physical

More information

the Revolution is Upon Us

the Revolution is Upon Us Networked Building Systems: the Revolution is Upon Us It s time to apply enterprise-wide thinking to the business of facility management By JIM LEE Cimetrics Inc Rapid changes in information technology

More information

BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT

BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT Communications Company One Company s Supply Chain Transformation Journey INTERVIEWS Senior Manager Supply Chain Operations Strategy Manager Procurement

More information

Cityzenith s 5D Smart City platform empowers users with a simple way to make sense of the torrent of data in our cities, corporate

Cityzenith s 5D Smart City platform empowers users with a simple way to make sense of the torrent of data in our cities, corporate 5D Smart City Cityzenith s 5D Smart City platform empowers users with a simple way to make sense of the torrent of data in our cities, corporate campuses, and universities, revolutionizing the way we access,

More information

Case Study -Sandy Grove Middle School First Net Positive Energy P3 School In North Carolina

Case Study -Sandy Grove Middle School First Net Positive Energy P3 School In North Carolina Case Study -Sandy Grove Middle School First Net Positive Energy P3 School In North Carolina Public-Private Partnership (P3) Government - provides incentive(s): transfer of asset (land), one time grant,

More information

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty

More information

BiSL Glossary. 5 February 2014

BiSL Glossary. 5 February 2014 Acceptance test Annual Business Information Management plan Annual information provisioning plan Application Application management ASL (Application Services Library) ASP (Application Service Providing)

More information

A Unified View of Network Monitoring. One Cohesive Network Monitoring View and How You Can Achieve It with NMSaaS

A Unified View of Network Monitoring. One Cohesive Network Monitoring View and How You Can Achieve It with NMSaaS A Unified View of Network Monitoring One Cohesive Network Monitoring View and How You Can Achieve It with NMSaaS Executive Summary In the past few years, the enterprise computing technology has changed

More information

TENDRIL LAUNCHES NEXT-GENERATION NETWORK OPERATING PLATFORM TO DRAMATICALLY SIMPLIFY PROCESS OF BUILDING, DEPLOYING AND MANAGING ZIGBEE APPLICATIONS

TENDRIL LAUNCHES NEXT-GENERATION NETWORK OPERATING PLATFORM TO DRAMATICALLY SIMPLIFY PROCESS OF BUILDING, DEPLOYING AND MANAGING ZIGBEE APPLICATIONS For Immediate Release: TENDRIL LAUNCHES NEXT-GENERATION NETWORK OPERATING PLATFORM TO DRAMATICALLY SIMPLIFY PROCESS OF BUILDING, DEPLOYING AND MANAGING ZIGBEE APPLICATIONS Tendril s Strong Silicon Partnerships

More information

Smart City & Internet of Things

Smart City & Internet of Things Smart City & Internet of Things Marzo 2014 Restricted Siemens AG 2014 All rights reserved. siemens.com/answers Smart City & Internet of Things Table of content Siemens Infrastructure & Cities Internet

More information

Power Monitoring for Modern Data Centers

Power Monitoring for Modern Data Centers Power Monitoring for Modern Data Centers December 2010/AT304 by Reza Tajali, P.E. Square D Power Systems Engineering Make the most of your energy SM Revision #1 12/10 By their nature, mission critical

More information

Empowering the Enterprise Through Unified Communications & Managed Services Solutions

Empowering the Enterprise Through Unified Communications & Managed Services Solutions Continuant Managed Services Empowering the Enterprise Through Unified Communications & Managed Services Solutions Making the transition from a legacy system to a Unified Communications environment can

More information

Control of Computer Room Air Handlers Using Wireless Sensors. Energy Efficient Data Center Demonstration Project

Control of Computer Room Air Handlers Using Wireless Sensors. Energy Efficient Data Center Demonstration Project Control of Computer Room Air Handlers Using Wireless Sensors Energy Efficient Data Center Demonstration Project About the Energy Efficient Data Center Demonstration Project The project s goal is to identify

More information

UNLOCKING VALUE IN APPLICATION OUTSOURCING RELATIONSHIPS

UNLOCKING VALUE IN APPLICATION OUTSOURCING RELATIONSHIPS 2 0 1 2 An Outsourcing Center White Paper UNLOCKING VALUE IN APPLICATION OUTSOURCING RELATIONSHIPS By Patti Putnicki, Business Writer, Outsourcing Center W W W. O U T S O U R C I N G - C E N T E R. C O

More information

RagingWire Enterprise Solutions

RagingWire Enterprise Solutions Background Enterprise Solutions was founded in May 2000 to be an enterprise-class Managed Services Provider (emsp) that could provide and support colocated data center services for Fortune 1000 customers.

More information

MISSION CRITICAL SERVICES

MISSION CRITICAL SERVICES MISSION CRITICAL SERVICES HVAC SHEET METAL & PIPING COMMISSIONING RETRO-COMMISSIONING PLUMBING BUILDING SERVICES PROCESS PIPING ENGINEERING BIM/3-D MODELING FABRICATION BUILDING AUTOMATION SYSTEMS INDUSTRIAL

More information

MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE ENVIRONMENTAL MONITORING

MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE ENVIRONMENTAL MONITORING MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE Chris C. Gaskins Vice President of Product Development RF Code, Inc. AUGUST 2010 Shawn Griggs Director of Product Management

More information

REAL- TIME COMMUNICATIONS TESTING UNH INTEROPERABILITY LAB OVERVIEW IOL TESTING BENEFITS

REAL- TIME COMMUNICATIONS TESTING UNH INTEROPERABILITY LAB OVERVIEW IOL TESTING BENEFITS OVERVIEW REAL- TIME COMMUNICATIONS TESTING UNH INTEROPERABILITY LAB The UNH InterOperability Lab (UNH- IOL) has been testing Networking and Communications since 1988. Fully owned by the University of New

More information