1 1269 A Framework for Post-Disaster Facility Restoration Management: Needs and Requirements for the Use of Hybrid Simulation Moonseo PARK 1 ; SangHyun LEE 2 ; Hyun-Soo LEE 3 ; Minji CHOI 4 ; Sungjoo HWANG 5 ; MyungGi MOON 6 ; Seulbi LEE 7 ; and Jae-Ho PYEON 8 1 Prof., Dept. of Architecture and Architectural Engineering, Seoul National Univ., 1 Gwanak-ro, Seoul, Korea, mspark@snu.ac.kr 2 Assistant Prof., Dept. of Civil and Environmental Engineering, Univ. of Michigan, 2350 Hayward St., Ann Arbor, MI 48109, shdpm@umich.edu 3 Prof., Dept. of Architecture and Architectural Engineering, Seoul National Univ., 1 Gwanak-ro, Seoul, Korea, hyunslee@snu.ac.kr 4 PhD Student, Dept. of Architecture and Architectural Engineering, Seoul National Univ., 1 Gwanak-ro, Seoul, Korea, mjchoi7@hotmail.com 5 PhD Student, Dept. of Architecture and Architectural Engineering, Seoul National Univ., 1 Gwanak-ro, Seoul, Korea, nkkt14@snu.ac.kr 6 PhD Student, Dept. of Civil and Environmental Engineering, Univ. of Michigan, 2350 Hayward St., Ann Arbor, MI 48109, mgmoon@umich.edu 7 Master s Course Student, Dept. of Architecture and Architectural Engineering, Seoul National Univ., 1 Gwanak-ro, Seoul, Korea, lee130@snu.ac.kr 8 Associate Prof., Dept. of Civil and Environmental Engineering, San Jose State Univ., One Washington Square, San Jose, CA 95192, jae.pyeon@sjsu.edu ABSTRACT Catastrophic disasters can cause fatal damage to civil infrastructures and facilities that provide basic services to the region. The malfunctioning restoration conditions (e.g., resource supply system and work environment) and lifeline systems (e.g., electric power) in the region have a significant influence on an individual facility restoration operation. Therefore, it is necessary to analyze the impact of regional-level recovery conditions for an effective implementation of facility restoration operation. Since it is hard to analyze interactions among diverse recovery efforts with a single stand-alone simulation approach, this research introduces a hybrid simulation framework for post-disaster facility restoration management. This is based on data exchange between different simulation modules of regional-level restoration conditions, lifeline systems, and facility operation. The use of hybrid simulation enables users to fully utilize each advantage of different simulation methods. The simulation results of the prototype imply that external recovery conditions can have significant impacts on a facility restoration operation, which highlights the necessity of considering external conditions for project management after a disaster. A better understanding of the surrounding conditions (i.e., the effect of the resource supply system, work environment, and lifeline system) can thus support project managers in implementing appropriate restoration planning to avoid project delays.
2 1270 INTRODUCTION Catastrophic disasters generate a large and immediate functional loss of a built environment due to the fatal damage of structures (Olshansky et al. 2012). Since the interrupted function of facilities may cause tremendous inconveniences to residents, appropriate restoration plans need to be immediately employed to recover social and economic activities in communities within a limited amount of time. Due to the need for the rapid recovery of a facility s function, facility restoration project planners are required to initiate their projects with wellimplemented plans as soon as possible. However, a post-disaster recovery situation, where resource and time limitations are strongly imposed, may cause the following negative outcomes to facility restoration operations that may lead to unexpected delays and additional project costs: (a) resource availability (e.g., materials, equipment, and workforces) and lifeline services (e.g., water, electricity, and gas) become limited due to damaged production systems and the excessive demand for restoration at the same time (Orabi et al. 2010); (b) damage to existing buildings and infrastructure can cause delays in the overall restoration process by obstructing work spaces with debris and resource delivery capability (Olshansky et al. 2012); and (c) restoration resources are unevenly allocated due to interdependency and competition among various types of facilities/infrastructures (Shoji and Toyota 2009). These possible outcomes imply that restoration management should incorporate comprehensive investigations into various elements in terms of both external recovery conditions (e.g., resource supply systems, lifeline systems, and work environment) and facility restoration operations. For the purpose of comprehensively analyzing the diverse levels of recovery efforts i.e., both regionaland individual facility-level a hybrid simulation framework for post-disaster facility restorations is introduced. Hybrid simulation, the idea to combine different simulation paradigms, is currently in place in many research fields necessitated by the increasing need for comprehensive analysis of complex systems (Mosterman 1999). Due to its advantage in the analysis of large and complex systems that requires both strategic and operational point of view, hybrid simulation can offer a better understanding of external conditions for facility restoration, which are affected by an interdependent restoration process among a regional-level built environment and lifeline systems. As a result, an integrated model is developed as a prototype to display the hybrid simulation with data exchange requirements. Finally, the research outcome is expected to assist facility managers with appropriate restoration planning to minimize the waste of time, cost, and resources. PRELIMINARY STUDY The importance of efficient disaster recovery planning has been highlighted in the civil and construction research areas. In general, previous research on construction processes and operations considers resource logistics and schedule performance as the main interests (Peña-Mora et al. 2008). However, the most severely restricted aspects of the restoration activities were inefficient resource supply and unavailable required services for work. Numerous research efforts regarding regional-level planning thus included resource supply chain management (Orabi et al. 2010) and debris disposal management (Swan 2000). To address
3 1271 restoration conditions in a more specific manner, particular attention was also paid to critical infrastructures of the region. O Rourke (2007) developed the concept of a lifeline system to describe the large and geographically distributed principal networks, including electric power, gas, and water supply. Lifeline systems play a primary role in securing the functionality for the entire region as well as individual facilities/infrastructures by providing basic requirements and services for everyday lives. The recovery of a lifeline system was thus treated as one of the most urgent priorities at an early recovery phase (Shoji and Toyota 2009). Despite the academic contributions toward alleviating the negative impacts of the regional environment on facility restoration operation, such challenges as the analysis of how and to what extent regional-level restoration conditions affect individual facility restoration still exist. This is because: (a) an analysis on various scope considering detail facility restoration operations and comprehensive regional-level recovery conditions is necessary; (b) interdependency among different facilities/infrastructures should be determined; and (c) interactions among regional- and facility-level restoration efforts need to be identified for effective operation management. NECESSITY OF HYBRID SIMULATION Since computer simulation techniques can articulate the complex behavior of an interest over time (Harrison et al. 2007), they have been widely applied in the construction engineering and management sectors. In particular, discrete event simulation (DES) is regarded as an effective tool for construction process analysis due to its advantages in describing process and operational details, including resources (Law and Kelton 2006). An event-based modeling technique can be helpful when dealing with the detailed restoration operation process of an individual facility where available resources are strictly limited and where the sequence of various activities is highly intricate. On the other hand, a system dynamics (SD) simulation provides an analytic solution for complex, nonlinear, and dynamic systems by focusing on interactions among variables and understanding their structures (Sterman 2000; Harrison et al. 2007). Based on the cause-and-effect relationship among variables, SD can be applied to model the behavior of a system as a whole. While existing operation analysis methods (e.g., DES) focus on the detailed description of process, SD modeling at the macro-level is stronger for analyzing surrounding resource supply systems and the work environment caused by feedback processes among the interdependent restoration operations of the overall built environment. In addition, the available functionality of lifeline systems should be taken into account by considering their networks and functional interdependencies within the local level. In this research, agent-based modeling (ABM) can be used to determine strong interdependency and connection among lifeline systems with its ability to formulate the actions and interactions of autonomous decision-making entities called agents (Bonabeau 2002). The utilization of ABM enables a representation of the different physical or functional state of each facility/infrastructure that is considered an individual agent that may compete for repair resources. The physical/functional state generates both direct and indirect interaction with other lifeline systems connected by pre-assigned network rules. Although three different simulation methods (i.e., DES, SD, ABM) can be helpful for experimenting with "what-if" scenarios to make effective recovery plans
4 1272 for both facility- and regional-level management in chaotic situations, interactions among diverse levels of recovery efforts are hard to analyze with a single stand-alone simulation approach. This difficulty is due to the gap of the goal, scope, and detail level of analysis between each simulation method. In this situation, there has been a growing interest in hybrid simulation because seamless integration of each simulation model supported capturing many complex problems in large systems (Mosterman 1999; Venkateswaran et al. 2004). Hybrid simulation approach was successfully used to analyze the impact of higher level decision on the lower level and vice versa (Venkateswaran et al. 2004). This research thus applies hybrid simulation to fully utilize the benefits of different simulators with specific purposes, as well as to conduct comprehensive analysis on restoration management. Similarly, Lee et al. (2009) applied a hybrid simulation in the construction field in order to facilitate a better understanding of complex interactions among various processes in large-scale construction. In this context, hybrid simulation provides analytic capabilities for understanding multi-dimensional aspects of disaster restoration situations, including the operation itself and the critical surroundings affecting the operation. Furthermore, it enables the investigation of each restoration management level (i.e., individual facility restoration, regional built environment, and lifeline systems) as well as its interaction from a detailed and comprehensive perspective. FRAMEWORK FOR RESTORATION MANAGEMENT USING HYBRID SIMULATION The interactions among regional restoration conditions, lifeline system recovery, and facility reconstruction operation are visualized in Fig. 1. Each simulation module produces useful data output based on its specific purposes. The restoration conditions constitute the resource supply system and work environment (affected by work space and resource delivery system) that determine resource availability and the work effectiveness of the restoration process. They eventually influence the progress of both lifeline system recovery and facility reconstruction operations with its ability to provide available resources and effective work conditions. The recovered lifeline system provides required services to facility reconstruction operation; this may include gas, water, power supply, and so forth. These basic services are indispensable requirements for commencing the operation smoothly, and for significantly changing the quality of the recovery environment. After regaining the functionality of the lifeline system, an intensive reconstruction or full restoration is initiated with the reconstruction of the individual facility/infrastructure. While the restoration process of the individual facility is affected by regional recovery conditions, a restored individual facility can also improve overall restoration conditions. For instance, the early restoration of an industrial facility that produces construction materials can be helpful in recovering overall resource supply capability. To effectively analyze the diverse restoration processes, both at the regional and facility level, ABM can be helpful to model lifeline system networks and interconnection among nodes. SD can provide a comprehensive solution to analyze overall restoration efforts and restoration conditions at the regional level with a consideration of policy factors. With a detailed event-oriented view, in addition, DES can create a model of a detailed reconstruction operation.
5 1273 Figure 1. Interactions among Different Post-Disaster Restoration Phases PROTOTYPE OF THE HYBRID SIMULATION Prototype Overview Fig. 2 visualizes an overview of a hybrid simulation prototype that can be applied to the recovery phase after a catastrophic earthquake. Each section of the diagram represents a lifeline system recovery focusing on power supply (A in Fig. 2), resource supply and work environment (B in Fig. 2), and the restoration operation for a residential/commercial complex building (C in Fig. 2). The simulation methods of agent-based modeling, system dynamics, and discrete event simulation are applied respectively to analyze the behavior at each level. In a lifeline system, developed by ABM, the agents are assigned to the major supply system and connection nodes of the power supply station at a local level. Based on each agent s damage state and interdependency with others, repair resources are given to the agent to carry out the functional recovery process. As a result, the simulation module generates a lifeline service (i.e., electric power) supply ratio to other modules to deliver information on the availability of the service. While the lifeline system module focuses on assessing interdependency and the damage states of corresponding agents, resource supply and the work environment simulation module using SD comprehensively deal with various facilities/infrastructures in an overall region. The restoration work rate of a damaged facility/infrastructure depends on resource allocation; this is an outcome of both governmental recovery plans and resource competitions among various types of facilities/infrastructures (loops B1 and B2) and resource availability from production ability (loop R1). In addition, a functional interdependency among different facilities/infrastructures also determines the work delay ratio, influencing the restoration work rate (loops R2 and R3).
6 1274 Lastly, the DES module for the facility reconstruction operation simulates a four-day cycle of core work operations in a 70-story high-rise residential/commercial complex building as an example. This simulation incorporates the information of lifeline service supply, resource supply, and construction work delay ratio from previous modules. The operation module aims to examine the changes in restoration operation according to changes in regional-level recovery conditions. Figure 2. An Overview of Hybrid Simulation Prototype
7 1275 Behavior Test of Simulation and Analysis Based on the developed prototype presented in Fig. 2, this research conducts simulation for the comprehensive understanding of facility restoration to inspect the impact of post-disaster damage patterns on restoration. This is implemented by four different scenarios: (a) a normal situation that only the DES module is simulated (graph line 1 in Fig. 3); (b) an interrupted situation with the effects of the damaged lifeline system that ABM and DES modules are interacted (graph line 2 in Fig. 3); (c) an interrupted situation with the effects of damaged built environment that SD and DES modules are interacted (graph line 3 in Fig. 3); and (d) an interrupted situation with the effects of complex damage to both lifeline system and built environment that ABM, SD, and DES modules are all interacted (graph 4 in Fig. 3). For instance, information of unavailable lifeline services and inefficient resources are analyzed by ABM and SD simulation modules and then relayed to DES modules as external conditions for construction operations during the simulation in the fourth scenario. Simulation results can be validated by conducting a comparative analysis between the actual construction operation and the recovery patterns from past earthquakes. Figure 3. The Effects of Damaged Lifeline System and Restoration Conditions on Construction Work Delay As a result of the hybrid simulation prototype, Fig. 3 illustrates the effects of a lifeline system and built environment restoration on construction work delay after disaster. The general assumptions are set for four cases: as the disaster event takes place, at week 10, and when the restoration project starts at week 20. Graph line 1 displays construction work progress completed in 56 weeks in the pre-disaster situation where the functionality of the lifeline system and recovery environment is assumed to be normal. In actuality, the core work process of this building took 60 weeks, including 3 to 4 weeks of break in the winter season, which shows the
8 1276 similarity with simulation results of normal construction operation. However, significant delays are shown in graph lines 2, 3, and 4 as 80, 105, and 116 weeks, respectively. In particular, lifeline restoration after a disaster in the real world is expected to require 3 to 6 months (RA 2013). Lifeline restoration from the 2011 Japanese earthquake was completed almost 25 weeks after the event, which led to delays in commencing the full restoration (RA 2011). These past recovery patterns can explain the cause of delays in graph lines 2, 3, and 4 of Fig. 3. In addition, two years later the overall restoration of residential and commercial buildings was only about 40% completed due to the excessive need for reconstruction, while other core facilities were 80 90% done within the same time (RA 2011). From this actual recovery tendency, it is expected that limited resources may cause delays in facility restoration operation, as shown in Graph lines 3 and 4 of Fig. 3. The differences in simulation results imply the significant impact of external recovery conditions on the progress of facility restoration operation, and highlight the necessity of considering external conditions for project management after a disaster. In addition, it could be inferred from comparing graph lines 2 and 3 in Fig. 3 that damaged built environment restoration reacts more sensitively in regard to construction work delay than lifeline systems do. In other words, problems in resource availability caused by resource competition and availability have greater influences on project delays (i.e., 25 weeks of delay) than lifeline system problems do. This is because the recovery of lifeline systems normally takes place in the first emergency response phase after disaster, which is before or at the beginning of project initiation. However, resource availability is severely limited due to excessive needs for resources as a huge number of facilities/infrastructures are being repaired at the same time after the recovery of prioritized systems in the region is completed. Figure 4. The Effect of Project Initiation on Construction Work Progress
9 1277 On the other hand, Fig. 4 demonstrates what kinds of information can assist the project manager s decision-making planning phase (in particular, determining project initiation). When there are complex effects on a damaged lifeline system and built environment restoration simultaneously, significant delays can be generated after project initiation. Graph lines 1, 2, and 3 in Fig. 4 imply that reconstruction duration can vary according to project start time after a disaster event accompanying a malfunctioning lifeline system and recovery environment. If a project is initiated shortly after the occurrence of the disaster, entire project duration would inevitably be prolonged until basic requirements from lifeline and resources are available. However, graph lines 2 and 3 show a more effective reconstruction work process as the project initiation is postponed to week 70 and 120. In terms of both time and cost management, the latter displays more efficient behavior by reducing both wasted time and the indirect cost of running the unproductive site. By suggesting the effects of different project initiation times on reconstruction work progress, this result can be utilized to assist project managers during the project planning phase when encountering difficulties in resource and lifeline service supply. EXPECTED OUTCOME & FUTURE DEVELOPMENT This research aims to apply a hybrid simulation to incorporate the impact of regional-level damaged built environment and lifeline systems into facility restoration operation management at the post-disaster level. A comprehensive analysis of various levels of recovery effort is performed while determining interactions between regional levels and individual facility levels. The interactions are realized by a data exchange among each simulation module of DES, SD, and ABM. The research outcome implies that damaged built environment restoration reacts more sensitively on construction work delay than lifeline systems, and that the time of the project initiation at the post-disaster stage is likely to influence the reconstruction s duration. The use of a hybrid simulation approach is expected to offer a better understanding of the surrounding conditions (i.e., the effect of resource supply system, work environment, and lifeline systems) of individual facility restoration. It can also support project managers in implementing appropriate restoration planning to improve the recovery process of a damaged facility after a disaster, which may enable the reduction of the project time/cost, and the swift recovery of functionality of the facilities for public convenience in a chaotic situation. However, further development is required to enhance the applicability of the proposed research outcome. For instance, disaster simulators (e.g., earthquake) and spatial information of a facility/infrastructure can be supplemented. The interoperability within the integrated sub-simulators and modeling can potentially provide the simulation with extendibility to future types of disaster and to the all-time management of post-disaster restoration management. ACKNOWLEDGMENT This research was supported by both a grant (12TRPI-C ) from the R&D Program and by a grant (13AUDP-C ) from the Architecture & Urban Development Research Program, which are funded by the Ministry of Land, Infrastructure, and Transport Affairs of the Korean government.
10 1278 REFERENCES Bonabeau, E. (2002). "Agent-based Modeling: Methods and Techniques for Simulating Human Systems." In Proceedings of the National Academy of Sciences, 99 (3): Harrison, J. R., Lin, Z., Carroll, G. R., and Carley, K. M. (2007). Simulation Modeling in Organizational and Management Research Academy of Management Review, 32(4), Law, A., and Kelton, W. D. (2006). Simulation Modeling and Analysis, 3th, McGraw-Hill, Lee, S., Han, S., and Peña-Mora, F. (2009). Integrating Construction Operation and Context in Large-Scale Construction Using Hybrid Computer Simulation. The Journal of Computing in Civil Engineering, ASCE, 23(2), Mosterman, P. J. (1999). An Overview of Hybrid Simulation Phenomena and Their Support by Simulation Packages. Hybrid Systems: Computation and Control, Lecture Notes in Computer Science 1569, Olshansky, R. B., Hopkins, L. D., and Johnson, L. A. (2012). Disaster and Recovery: Processes Compressed in Time. Natural Hazards Review, ASCE, 13(3), Orabi, W., Senouci, A. B., El-Rayes, K., and Al-Derham, H. (2010). Optimizing Resource Utilization during the Recovery of Civil Infrastructure Systems. The Journal of Management in Engineering, ASCE, 26(4), O'Rourke, T. D. (2007). Critical Infrastructure, Interdependencies and Resilience. Engineering for the Treat of Natural Disaster, National Academy of Engineering, 37(1), Peña-Mora, F., Han, S. Lee, S., and Park, M. (2008). Strategic-Operational Construction Management: Hybrid System Dynamics and Discrete Event Approach. The Journal of Construction Engineering and Management, ASCE, 134(9), Reconstruction Agency of Japanese Government (RA) (2011). Recovery Status of Major Infrastructures. < (Aug. 12, 2013). Reconstruction Agency of Japanese Government (RA) (2013). Current Status and Path Toward Reconstruction. < (May 20, 2013). Shoji, G., and Toyota, A. (2009). Modeling of Restoration Process Associated with Critical Infrastructure and its Interdependency to a Seismic Disaster. In Proceedings of the 2009 Lifeline Earthquake Engineering in a Multihazard Environment, ASCE, Reston, VA, Sterman, J. (2000). Business Dynamics: System Thinking and Modeling for a Complex World, Boston: Irwin Mcgraw-Hill, New York, NY. Swan, R. C. (2000). Debris Management Planning for the 21st Century. Natural Hazard Review, 1(4), Venkateswaran, J., Son, Y., and Jones, A. (2004). Hierarchical Production Planning Using a Hybrid System Dynamic-Discrete Event Simulation Architecture. In Proceedings of the 2004 Winter Simulation Conference, Piscataway, New Jersey: Institute of Electrical and Electronic Engineers, Inc.
Korean Real Estate Market Mechanisms and Deregulation of Mortgage Loans: Qualitative Analysis
Korean Real Estate Market Mechanisms and Deregulation of Mortgage Loans: Qualitative Analysis Sungjoo Hwang 1, Moonseo Park 2, Hyun-Soo Lee 3 Abstract The Korean real estate market is currently experiencing
More informationA Dynamic Approach for Evaluating the Validity of Mortgage Lending Policies in Korean Housing Market
A Dynamic Approach for Evaluating the Validity of Mortgage Lending Policies in Korean Housing Market Sungjoo Hwang 1, Moonseo Park 2, Hyun-Soo Lee 3 1 Ph.D. Candidate, Dept. of Architecture, Seoul National
More informationMethods for Assessing Vulnerability of Critical Infrastructure
March 2010 Methods for Assessing Vulnerability of Critical Infrastructure Project Leads Eric Solano, PhD, PE, RTI International Statement of Problem Several events in the recent past, including the attacks
More informationResearch on Dynamic Effects of Employability of Vocational College Students in Taiwan
Research on Dynamic Effects of Employability of Vocational College Students in Taiwan Pin-Chang Chen Department of Information Management, Yu Da University of Science and Technology, Miaoli, Taiwan ABSTRACT
More informationAssessment of natural hazards, man made hazards, technical and societal related risks and associated impact.
Aon Business Continuity Planning The Aon Business Continuity Planning practice provides consulting services that allow Aon clients to measure and manage their strategic and tactical risks through Crisis
More informationAPPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE
APPLICATION OF SIMULATION IN INVENTORY MANAGEMENT OF EOL PRODUCTS IN A DISASSEMBLY LINE Badr O. Johar, Northeastern University, (617) 3737635, johar.b@husky.neu.edu Surendra M. Gupta, Northeastern University,
More informationA New Paradigm in Urban Road Network Seismic Vulnerability: From a Link-by-link Structural Approach to an Integrated Functional Assessment
A New Paradigm in Urban Road Network Seismic Vulnerability: From a Link-by-link Structural Approach to an Integrated Functional Assessment Gonçalo Caiado goncalo.caiado@ist.utl.pt Rosário Macário rosariomacario@civil.ist.utl.pt
More informationBig Data Collection and Utilization for Operational Support of Smarter Social Infrastructure
Hitachi Review Vol. 63 (2014), No. 1 18 Big Data Collection and Utilization for Operational Support of Smarter Social Infrastructure Kazuaki Iwamura Hideki Tonooka Yoshihiro Mizuno Yuichi Mashita OVERVIEW:
More informationEarthquakes have caused significant damage to electric power and
Restoration Modeling of Lifeline Systems by Rachel A. Davidson and Zehra Çagnan Research Objectives The main objective of this research is to develop improved models of the post-earthquake restoration
More informationGESKEE Database an Innovative Tool for Seismic Risk Assessment and Loss Scaling
GESKEE Database an Innovative Tool for Seismic Risk Assessment and Loss Scaling COSMIN FILIP 1, CRISTINA SERBAN 1, MIRELA POPA 1, GABRIELA DRAGHICI 1 Faculty of Civil Engineering, Ovidius University of
More informationINFRASTRUCTURE MANAGEMENT AND SECURITY AREA OF STUDY Zachry Department of Civil Engineering Texas A&M University
INFRASTRUCTURE MANAGEMENT AND SECURITY AREA OF STUDY Zachry Department of Civil Engineering Texas A&M University INTRODUCTION Large-scale, distributed infrastructure systems such as communications, power,
More informationKeys to Narrowing Business Continuity Planning Gaps: Training, Testing & Audits
Keys to Narrowing Business Continuity Planning Gaps: Training, Testing & Audits Betty A. Kildow, CBCP, FBCI, Emergency Management Consultant Kildow Consulting 765/483-9365; BettyKildow@comcast.net 95 th
More informationA Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Overview.
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Andersen Consultng 1600 K Street, N.W., Washington, DC 20006-2873 (202) 862-8080 (voice), (202) 785-4689 (fax) albert.sweetser@ac.com
More informationNetwork Traffic Management under Disaster Conditions. Hediye Tuydes PhD Candidate Northwestern University
Network Traffic Management under Disaster Conditions by Hediye Tuydes PhD Candidate Northwestern University Motivation Most Common Disasters Natural Earthquakes Hurricanes Floods Volcanic eruptions Fires
More informationDevelopment and Recovering From Disaster
Development and Recovering From Disaster hasan.coban@kalkinma.gov.tr International Symposium on Disaster Economics 3-5 April 2013, Istanbul Natural Disaster in Turkey Other disasters 4% Avalanche 2% Multiple
More informationTELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING
TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING A.K. Tang 1 1 President, L&T Engineering and Project Management Consultant, Mississauga. Canada Email: alexktang@mac.com ABSTRACT: Telecommunication
More informationDesktop Scenario Self Assessment Exercise Page 1
Page 1 Neil Jarvis Head of IT Security & IT Risk DHL Page 2 From reputation to data loss - how important is business continuity? Neil Jarvis Head of IT Security (EMEA) DHL Logistics IT Security Taking
More informationRESTORING THE LOS ANGELES WATER SUPPLY SYSTEM FOLLOWING AN EARTHQUAKE
RESTORING THE LOS ANGELES WATER SUPPLY SYSTEM FOLLOWING AN EARTHQUAKE T.H.P. Tabucchi 1, R.A. Davidson 2, and S. Brink 3 1 Catastrophe Risk Analyst, Risk Management Solutions, Inc., Newark, CA, USA 2 Associate
More informationAnalytically comparing disaster recovery following the 2012 derecho
Analytically comparing disaster recovery following the 2012 derecho Christopher W. Zobel Virginia Tech czobel@vt.edu ABSTRACT This work in progress paper discusses analytically characterizing nonlinear
More informationIslamic Republic of Afghanistan, Post Disaster Need Assessment (PDNA) Training Manual
Islamic Republic of Afghanistan, Ministry of Rural Rehabilitation and Development (MRRD) Ministry of Rural Rehabilitation & Development Post Disaster Need Assessment (PDNA) Training Manual Social Protection
More informationInitiating the CCSF Lifelines Council. Interdependency Study
LAURIE JOHNSON CONSULTING Initiating the CCSF Lifelines Council Urban Planning Risk Management Disaster Recovery Interdependency Study Lifelines Council Meeting #7 November 17, 2011 (Source: JIIRC-UBC)
More informationThe Role of GIS in a Disaster Recovery Plan 2010 GIS-T CONFERENCE
The Role of GIS in a Disaster Recovery Plan 2010 GIS-T CONFERENCE S A N D Y M E H L H O R N Introduction Four phases of disaster related planning Mitigation Preparation Response Recovery Considerable emphasis
More informationA Study on Integrated Operation of Monitoring Systems using a Water Management Scenario
, pp. 55-64 http://dx.doi.org/10.14257/ijseia.2015.9.9.06 A Study on Integrated Operation of Monitoring Systems using a Water Management Scenario Yong-Hyeon Gwon 1, Seung-Kwon Jung 2, Su-Won Lee 2 and
More informationEvaluation of Fire Protection Capacity in Disasters Based on Disaster Resilience Curve
Evaluation of Fire Protection Capacity in Disasters Based on Disaster Resilience Curve N. Hirayama, T. Yamada, M. Wada, S. Itoh, and C. A. Davis ABSTRACT After the 2011 Tohoku disaster, water supply utilities
More information10. Lifeline utilities
10. Lifeline utilities Summary Lifeline utilities are entities that provide infrastructure services to the community such as water, wastewater, transport, energy and telecommunications. Lifeline utilities
More informationUsing Simulation to Understand and Optimize a Lean Service Process
Using Simulation to Understand and Optimize a Lean Service Process Kumar Venkat Surya Technologies, Inc. 4888 NW Bethany Blvd., Suite K5, #191 Portland, OR 97229 kvenkat@suryatech.com Wayne W. Wakeland
More informationBusiness Unit CONTINGENCY PLAN
Contingency Plan Template Business Unit CONTINGENCY PLAN Version 1.0 (Date submitted) Submitted By: Business Unit Date Version 1.0 Page 1 1 Plan Review and Updates... 3 2 Introduction... 3 2.1 Purpose...
More informationDISASTER MANAGEMENT. Goals To instill an understanding of the disaster management process
DISASTER MANAGEMENT Goals To instill an understanding of the disaster management process Learning outcomes After completing this session, you will be able to Affirm the usefulness of integrating management
More informationOrganizational Strategies to Support Sustainability in the Construction Company
Organizational Strategies to Support Sustainability in the Construction Company Speakers: Lee, Kang Hee 1 ; Ahn, Yong Han 2 ; Jeon, Myunghwa 3 ; Suh, Min Jae 4 1 Andong National University, Andong, South
More informationUniversity of Nottingham Emergency Procedures and Recovery Policy
University of Nottingham Emergency Procedures and Recovery Policy Guidelines for High Hazard Schools and Departments 1. Introduction The University of Nottingham is committed to the identification and
More informationThe Dynamics of Disaster Economics: The Philippines Recovery and Response to Typhoon Haiyan (Yolanda)
The Dynamics of Disaster Economics: The Philippines Recovery and Response to Typhoon Haiyan (Yolanda) Antonio Louis A. Holmes Industrial Engineering Department, De La Salle University-Manila 2401 Taft
More informationGUIDELINES FOR BUSINESS CONTINUITY IN WHOLESALE MARKETS AND SUPPORT SYSTEMS MARKET SUPERVISION OFFICE. October 2004
GUIDELINES FOR BUSINESS CONTINUITY IN WHOLESALE MARKETS AND SUPPORT SYSTEMS MARKET SUPERVISION OFFICE October 2004 1 1. Introduction Guaranteeing the efficiency and correct operation of money and financial
More informationDynamic Change Management for Fast-tracking Construction Projects
Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations
More informationSAMPLE IT CONTINGENCY PLAN FORMAT
SAMPLE IT CONTINGENCY PLAN FORMAT This sample format provides a template for preparing an information technology (IT) contingency plan. The template is intended to be used as a guide, and the Contingency
More informationESF 12: Energy & Utilities
Table of Contents 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Scope... 1 1.3 ESF Activation & Plan Maintenance... 2 1.4 Policies... 2 2.0 Situation & Assumptions... 2 2.1 Situation... 2 2.2 Assumptions...
More informationDisaster Recovery Plan (DRP) / Business Continuity Plan (BCP)
Preface Computer systems are the core tool of today s business and are vital to every business from the smallest to giant organizations. Money transactions, customer service are just simple examples. Despite
More informationConstructing Urban Vulnerability Index for Major U.S. Cities
CREATE Research Archive Research Project Summaries 2009 Constructing Urban Vulnerability Index for Major U.S. Cities Haydar Kurban Howard University, HKURBAN@HOWARD.EDU Mika Kato Howard University, mkato@howard.edu
More informationUniversity of San Francisco EMERGENCY OPERATIONS PLAN
University of San Francisco EMERGENCY OPERATIONS PLAN University of San Francisco Emergency Operations Plan Plan Contact Eric Giardini Director of Campus Resilience 415-422-4222 This plan complies with
More informationSusan A. Brink. Summary
s.brink@kit.edu Susan A. Brink Summary Hertzstraße 16 76187 Karlsruhe Civil engineer with a PhD and research experience in computer modeling and assessment of risk, disaster response and recovery and significant
More informationDynamic Strategies for Apartment Brand Management in Korean Housing Market
Dynamic Strategies for Apartment Brand Management in Korean Housing Market Minji Choi 1, Moonseo Park 2, Hyun-Soo Lee 3, Sungjoo Hwang 4, Chanhyuk Park 5 1 Ph.D. Student, Dept. of Architecture and Architectural
More informationBusiness, Resiliency and Effective Disaster Recovery. Anne Kleffner, PhD Haskayne School of Business, University of Calgary
Business, Resiliency and Effective Disaster Recovery Anne Kleffner, PhD Haskayne School of Business, University of Calgary CRHNet October 2012 Agenda Business resilience and community resilience in disaster
More informationPublic-Private Partnerships in Emergency Management. Victor L. Weeks CEPP Program Coordinator U.S. EPA Region 4
Public-Private Partnerships in Emergency Management Victor L. Weeks CEPP Program Coordinator U.S. EPA Region 4 Public-Private Partnerships (P3s) The International Association of Emergency Managers recognizes
More informationD 8.2 DELIVERABLE PROJECT INFORMATION
D 8.2 DELIVERABLE PROJECT INFORMATION Project Title: Acronym: Systemic Seismic Vulnerability and Risk Analysis for Buildings, Lifeline Networks and Infrastructures Safety Gain SYNER-G Project N : 244061
More informationCreating common operational pictures for disaster response with collaborative work
Risk Analysis IX 393 Creating common operational pictures for disaster response with collaborative work T. Chen, G. Su & H. Yuan Institute of Public Safety Research, Department of Physics Engineering,
More informationA Critical Juncture and an Emerging New Paradigm of Health Insurance Policy in Korea: A Theoretical Review
, pp.36-41 http://dx.doi.org/10.14257/astl.2015.88.08 A Critical Juncture and an Emerging New Paradigm of Health Insurance Policy in Korea: A Theoretical Review JongEun Yim 1, MyungHee Kim 2* 1 Department
More informationKABBALAH: ON SPATIO-TEMPORAL DATABASE VISUALIZATION WITH HISTORICAL EVENTS: A CASE STUDY OF HISTORY FLOW OF CHIA-YI BEIMEN STATION
KABBALAH: ON SPATIO-TEMPORAL DATABASE VISUALIZATION WITH HISTORICAL EVENTS: A CASE STUDY OF HISTORY FLOW OF CHIA-YI BEIMEN STATION T. W. Hsu a, S. C Chiou a, J. H. Lee b a National Yunlin University of
More informationMoving forward in a difficult time
Moving forward in a difficult time Purpose The purpose of recovery planning is to anticipate, to the maximum extent possible, what will be needed to restore the community to full functioning as rapidly
More informationWhy Should Companies Take a Closer Look at Business Continuity Planning?
whitepaper Why Should Companies Take a Closer Look at Business Continuity Planning? How Datalink s business continuity and disaster recovery solutions can help organizations lessen the impact of disasters
More informationChatham County Disaster Recovery Plan Recovery Planning Update. Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015
Chatham County Disaster Recovery Plan Recovery Planning Update Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015 Welcome Introduction to Recovery Planning Recovery Planning Process
More informationSeismic Practices to Improve Water System Resilience
Seismic Practices to Improve Water System Resilience C.A. Davis 1 1 Geotechnical Engineering Manager, Department of Water and Power, Los Angeles, California. Email: Craig.Davis@ladwp.com ABSTRACT : The
More informationFORMULATING YOUR BUSINESS CONTINUITY PLAN
WHITE PAPER Page 0 Planning for the Worst Case Scenario: FORMULATING YOUR BUSINESS CONTINUITY PLAN 9 Wing Drive Cedar Knolls, NJ 07927 www.nac.net Page 1 Table of Contents Overview... 2 What is Disaster
More informationSUSTAINABLE BUSINESS PROCESS MANAGEMENT MODEL FOR CONSTRUCTION COMPANIES
SUSTAINABLE BUSINESS PROCESS MANAGEMENT MODEL FOR CONSTRUCTION COMPANIES Young Woong, Song 1 and Yoon Ki, Choi 2 * 1 MEST-NRF Research Professor, Ph.D., Research Institute of Frontier Technology, Soong
More informationEarthquake Disaster Recovery Plan in TMG
Earthquake Disaster Recovery Plan in TMG Pre-disaster Management Measures by District and Recovery from Expected Earthquake Directly Underneath Tokyo Planning Section Urban Development Projects Division
More informationOperational Performance Metrics in Manufacturing Process: Based on SCOR Model and RFID Technology
Operational Performance Metrics in Manufacturing Process: Based on SCOR Model and RFID Technology Gyusun Hwang, Sumin Han, Sungbum Jun, and Jinwoo Park Abstract Performance measurement is the fundamental
More informationSecure Access at the Speed of Life. JASON SMITH Programmer Authorized LAURA WILLIAMS Account Manager Authorized
Secure Access at the Speed of Life JASON SMITH Programmer Authorized LAURA WILLIAMS Account Manager Authorized Secure Access at the Speed of Life FST Biometrics Secure Access at the Speed of Life In a
More informationDisaster Recovery Strategy in the Modern Market A PRACTICAL GUIDE FOR BUSINESS. Your Proven Partner in Communications Solutions
TM Disaster Recovery Strategy in the Modern Market A PRACTICAL GUIDE FOR BUSINESS Your Proven Partner in Communications Solutions Contents What is Disaster Recovery? 1 Components of Disaster a Recovery
More informationBusiness Continuity Training and Testing: Narrowing the Gaps
Business Continuity Training and Testing: Narrowing the Gaps Betty A. Kildow, CBCP, FBCI, Emergency Management Consultant Kildow Consulting 765/483-9365; BettyKildow@insightbb.com 93 nd Annual International
More informationChange and contract management modules of intelligent-rogram management information systems (i- PgMIS) for urban renewal projects
Change and contract management modules of intelligent-rogram management information systems (i- PgMIS) for urban renewal projects Yong Woon Cha, Run Zhi Jin *, Myoung Jin Son, and Chang Taek Hyun Department
More informationCustom Software Development Approach
Custom Software Development Approach Our approach to custom software development combines benefits from several standard development process models. We tend to have a well-defined, predictable and highly
More informationAgent-based Modeling of Disrupted Market Ecologies: A Strategic Tool to Think With
Paper presented at the Third International Conference on Complex Systems, Nashua, NH, April, 2000. Please do not quote from without permission. Agent-based Modeling of Disrupted Market Ecologies: A Strategic
More informationDisaster Recovery Planning as a Means to Resilient Development. PDNA Course
Disaster Recovery Planning as a Means to Resilient Development PDNA Course Key Challenges towards Effective Recovery Following a disaster: o large public interventions may be needed. o countries may experience
More informationEXPERIMENTAL INVESTIGATION OF THE INTEGRATION OF VIRTUAL MODELS AND THE PHYSICAL CONSTRUCTION
EXPERIMENTAL INVESTIGATION OF THE INTEGRATION OF VIRTUAL MODELS AND THE PHYSICAL CONSTRUCTION Abiola A. Akanmu 1, Chimay J. Anumba 2, John I. Messner 2, Sanghoon Lee 2, and Deepa Kundur 3 abiola.akanmu@wmich.edu,
More informationWhite Paper HOW TO INCREASE YOUR COMPANY S VALUE WITH PREDICTIVE ANALYTICS. What is Predictive Analytics?
Investment Banking Valuation & Forensics White Paper A Mariner Holdings Company Business Advisory HOW TO INCREASE YOUR COMPANY S VALUE WITH PREDICTIVE ANALYTICS Predictive analytics has long been used
More informationDisaster and Emergency Management Activities in Turkey
Muhammed SAHIN, Himmet KARAMAN, Turan ERDEN, Turkey Key words: Disaster and Emergency Management, Loss Estimation, TABIS, Earthquake SUMMARY After the two devastating earthquakes in the Marmara Region
More informationEffect of Lead Time on Anchor-and-Adjust Ordering Policy in Continuous Time Stock Control Systems 1
Effect of Lead Time on Anchor-and-Adjust Ordering Policy in Continuous Time Stock Control Systems 1 Ahmet Mutallip and Hakan Yasarcan Industrial Engineering Department Bogazici University Bebek Istanbul
More informationThe purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.
CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision
More informationSECTION 12 Emergency Management and Response Field Investigation
SECTION 12 Emergency Management and Response Field Investigation Types of Data to Be Collected and Recorded Reconnaissance activities should provide a general description and preliminary analysis of the
More informationInfrastructure Interdependencies
Infrastructure Interdependencies Terrence K. (Terry) Kelly, Ph.D. Senior National Security Officer White House Office of Science and Technology Policy based in part on an article to appear in IEEE Control
More informationBusiness Continuity Guidelines
Provisional Translation Business Continuity Guidelines Strategies and Responses for Surviving Critical Incidents Third Edition Cabinet Office, Government of Japan Notes on This Revision This is the second
More informationResponse, Recovery, and Resilience
Response, Recovery, and Resilience KATHLEEN TIERNEY ATURAL HAZARDS CENTER NIVERSITY OF COLORADO RESILIENCE THE ABILITYOF PHYSICAL SYSTEMS AND SOCIAL UNITS TO: Mitigate Hazards Contain the Effects of Disasters
More informationCASE STUDY. Jefferson County EMA Alabama Recovery Plan
Jefferson County EMA Alabama Recovery Plan NOTE: Jefferson County EMA contracted with ERI International / All Hands Consulting to fully develop the county's recovery plan and program. The original concept
More information(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
More informationIntegrating Software Services for Preproject-Planning
Integrating Software Services for Preproject-Planning Edward L DIVITA M.Sc., Ph.D. Candidate divita@stanford.edu Stanford University Stanford, CA 94305-4020 Martin FISCHER Associate Professor fischer@ce.stanford.edu
More informationAssessment of Interdependent Lifeline Networks Performance in Earthquake Disaster Management
Performance in Earthquake Disaster Management Hüseyin Can Ünen Istanbul Technical University, Turkey unen@itu.edu.tr Muhammed Şahin Istanbul Technical University, Turkey sahin@itu.edu.tr Amr S. Elnashai
More informationMeasurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
More informationBusiness Continuity Planning for Risk Reduction
Business Continuity Planning for Risk Reduction Ion PLUMB ionplumb@yahoo.com Andreea ZAMFIR zamfir_andreea_ileana@yahoo.com Delia TUDOR tudordelia@yahoo.com Faculty of Management Academy of Economic Studies
More informationReview of Recent Bridge Asset Management Systems
Review of Recent Bridge Asset Management Systems Takeshi Hanji 1 and Kazuo Tateishi 1 1. EcoTopia Science Institute, Nagoya University, Nagoya, Japan Abstract: A number of transportation agencies throughout
More informationDr. Pedro Basagoiti, Jose Frias Software AG Espana
POSTER SESSIONS 107 GEOGRAPHIC INFORMATION AND EXPERT SYSTEMS INTEGRATION: SITUATION, REQUIREMENTS AND EXAMPLES Dr. Pedro Basagoiti, Jose Frias Software AG Espana Abstract I n this paper, the problem of
More informationDeveloping a Business Continuity Plan... More Than Disaster
Developing a Business Continuity Plan..... More Than Disaster Recovery! April 19, 2010 UHY / MMA Business Survival Series Webinar Focus.... Understanding the components of Business Continuity Planning
More informationAn Analysis of Mental Process within Construction Workforces for Project-level Safety Management
An Analysis of Mental Process within Construction Workforces for Projectlevel Safety Management Mingyu Shin 1, HyunSoo Lee 2, Moonseo Park 3, Seulbi Lee 4 1 M.S., Dept. of Architecture and Architectural
More informationEmergency Operations California State University Los Angeles
Business Continuity Plan Emergency Operations California State University Los Angeles 1. Objective & Scope 2. Definition of Disaster 3. Risk and Business Impact Analysis Summary 4. Business Continuity
More informationDynamics of Knowledge Based Industries in Korea
Dynamics of Knowledge Based Industries in Korea Associate Professor, Taehoon Moon Department of Urban and Regional Planning, Chung Ang University San 0- Daeduck Myun Ahnsung City, Kyung Ki Do Republic
More informationBusiness Continuity Planning. Presentation and. Direction
Business Continuity Planning Presentation and Direction Thomas Bronack, president Data Center Assistance Group, Inc. 15180 20 th Avenue Whitestone, NY 11357 Phone: (718) 591-5553 Email: bronackt@dcag.com
More informationSupplemental Tool: Executing A Critical Infrastructure Risk Management Approach
Supplemental Tool: Executing A Critical Infrastructure Risk Management Approach Executing a Critical Infrastructure Risk Management Approach Risk is defined as the potential for an unwanted outcome resulting
More informationPROJECT ON THE ECO-FRIENDLY RENOVATION OF SCHOOL BUILDINGS AND ENVIRONMENTAL EDUCATION
17-014 The 2005 World Sustainable Building Conference, PROJECT ON THE ECO-FRIENDLY RENOVATION OF SCHOOL BUILDINGS AND ENVIRONMENTAL EDUCATION Sachiko ZENYOJI 1 Naoki TAKIGUCHI 2 1 2 Organic Table K.K.,
More informationEmergency Management Program
Emergency Management Program The Emergency Management and Civil Protection Act, R.S.O. 1990,c.E.9 and its associated regulations and standards, requires all Ontario Municipalities to implement a mandatory
More informationANALYTICS STRATEGY: creating a roadmap for success
ANALYTICS STRATEGY: creating a roadmap for success Companies in the capital and commodity markets are looking at analytics for opportunities to improve revenue and cost savings. Yet, many firms are struggling
More informationCHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION
CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION 37.01 Authority 37.07 Temporary Regulations 37.02 Purposes 37.08 Demolition of Damaged Buildings 37.03 Definitions 37.09 Temporary and Permanent Housing
More informationBusiness Continuity Planning at Financial Institutions
Business Continuity Planning at Financial Institutions July 2003 Bank of Japan Table of Contents Introduction...2 1 The Bank s View of Business Continuity Planning 1) Significance of business continuity
More informationHow To Manage Water Quality In Korea
RR 2004 3rd European Conference on River Restoration RIVER RESTORATION 2004 Zagreb, Croatia, 17-21 May 2004 Integrated watershed management system in Korea Ji-Yong Choi ABSTRACT: A watershed management
More informationDemand-Driven Curriculum for Embedded System Software in Korea
Demand-Driven Curriculum for in Korea Suehee Pak Dongduk Women s University 23-1 Hawolgok-dong, Sungbuk-gu Seoul 136-714, Korea Eunha Rho Sungkonghoe University 1-1 Hang-dong, Kuro-gu Seoul 152-716, Korea
More informationThe Current Situation and Circumstances Regarding the Great Earthquake Damage
The Current Situation and Circumstances Regarding the Great Earthquake Damage Ishinomaki District Water Supply Authority Junichi Takaki, Deputy Technology Director 116 Shinkaminuma Hebita Ishinomaki-city
More informationCover page. Introduction to the Earthquake Resistance Capacity Assessment and Reinforcement of Taipei Water Department Office Building.
Cover page Title: Authors: Introduction to the Earthquake Resistance Capacity Assessment and Reinforcement of Taipei Water Department Office Building. Ming-Fuw Wang (Presenter and Contact person) Chief
More informationSTATE OF CALIFORNIA DEPARTMENT OF INSURANCE 45 Fremont Street, 21st Floor San Francisco, California 94105 AMENDED TEXT OF REGULATION
STATE OF CALIFORNIA DEPARTMENT OF INSURANCE 45 Fremont Street, 21st Floor San Francisco, California 94105 AMENDED TEXT OF REGULATION DATE: October 27, 2010 REGULATION FILE REG-2010-00001 Standards and
More informationTOCOM s Approach to the Business Continuity Plan (BCP)
TOCOM s Approach to the Business Continuity Plan (BCP) Tokyo Commodity Exchange, Inc. Tokyo Commodity Exchange (TOCOM) administers the markets of the commodity futures trading. In the recent years, various
More informationPrototype Curriculum for Associate Degrees in Emergency Management
Prototype Curriculum for Associate Degrees in Emergency Management G230 Principles of Emergency Management This 3-day course replaces the Introduction to Emergency Management course. The new course consists
More informationState-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On
Proceedings, Construction Congress V, ASCE Stuart D. Anderson,ed State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On by Julio C. Martinez 1 and Photios G. Ioannou 2 Abstract Critical path
More informationUNOPS Risk-Sensitive Planning for Resilient Infrastructure Development
UNOPS Risk-Sensitive Planning for Resilient Infrastructure Development 5 th Africa Regional Platform for Disaster Risk Reduction Abuja, Nigeria by Jeffrey Crawford, UNOPS 14 May 2014 What is Resilient
More informationIncreasing Energy Reliability & Resiliency NGA Policy Institute for Governors' Energy Advisors Denver Colorado, September 11, 2013
+ Increasing Energy Reliability & Resiliency NGA Policy Institute for Governors' Energy Advisors Denver Colorado, September 11, 2013 Jeffrey R. Pillon, Director, Energy Assurance Programs National Association
More informationA PRELIMINARY INFORMATION MODEL FOR A SUPPLY CHAIN SIMULATION
A PRELIMINARY INFORMATION MODEL FOR A SUPPLY CHAIN SIMULATION Y. Tina Lee 1, Charles McLean 1, Shigeki Umeda 2 1 National Institute of Standards and Technology, Gaithersburg, MD 20899-8260, USA {leet,
More information