By Anne Bartosewicz, Northeast Utilities, and J. Brett Williams and Jim Hogan, Burns & McDonnell

Size: px
Start display at page:

Download "By Anne Bartosewicz, Northeast Utilities, and J. Brett Williams and Jim Hogan, Burns & McDonnell"

Transcription

1

2 By Anne Bartosewicz, Northeast Utilities, and J. Brett Williams and Jim Hogan, Burns & McDonnell CONNECTICUT LIGHT & POWER SERVES ONE OF THE MOST POWER-CONSTRAINED REGIONS IN THE UNITED STATES. Recognizing the need to meet the area s growing demand for power, CL&P (Berlin, Connecticut, U.S.), a wholly owned subsidiary of Northeast Utilities (NU; Hartford, Connecticut), is strengthening the transmission capacity to the southwest part of the state. The result is the Middletown-Norwalk Project (MNP), which is now one of the largest transmission projects in the history of this industry. MODEL SELECTION At first, CL&P considered the two standard methods used for accomplishing major construction projects: the design-bid-build approach and the design-build approach. In the design-bid-build model, CL&P would act as general contractor, manage the project with internal resources and assume all responsibilities including hiring design engineers, procuring materials and equipment, developing construction work scopes and hiring contractors. Under the design-build approach, also known as engineerprocure-construct (EPC) or turnkey, CL&P would define a construction project and hire a design-build team to assume responsibility for engineering, procurement, construction and coordination of the work. As the owner, CL&P would still manage the project, but leave construction management details to the general contractor. As the scope of the MNP emerged and construction costs and timelines came into sharper focus, the utility realized the project was too critical and complex to manage entirely with existing internal resources. CL&P desired a new approach where it could manage the overall project without adding significant internal resources. CL&P determined that a partnership with a firm that was a recognized expert in the design and construction of transmission facilities was the path to a successful project. Engineering and construction firm Burns & Mc- Donnell (Kansas City, Missouri, U.S.) recognized CL&P s challenge and offered an innovative solution, the concept known as program management: a proven solution in other industries for managing complex, large-scale and capital projects. Under the program management model, the owner hires a firm that serves as the owner s manager, or agent, to oversee the entire process from design through construction. Although the program manager works for the owner, a partnership is developed with a strong focus on flexibility.

3 CL&P implements a new approach for a major system upgrade project. MIDDLETOWN-NORWALK PROJECT SUMMARY 45 miles (72 km) of new overhead 345-kV line 24 miles (38 km) of new underground 345-kV line 56 miles (90 km) of reconstructed overhead 115-kV line 1 mile (2 km) of new underground 115-kV line 2 new substations 1 new switching station 1 upgraded substation 1 upgraded switching station 18 Connecticut municipalities along route: Middletown Cheshire Milford Haddam Hamden Stratford Durham Bethany Bridgeport Middlefield Woodbridge Fairfield Meriden Orange Westport Wallingford West Haven Norwalk Note: United Illuminating Co. (New Haven, Connecticut, U.S.) is a 20% partner with CL&P on this project and will own 6.5 miles (10 km) of the underground 345-kV line and one of the new substations. PROGRAM MANAGEMENT IMPLEMENTATION In this case, the program manager assisted with the initial project design, then formulated an execution plan that identified the scope of construction and the strategy for contracting for the various parts of the project. The result was a master plan for CL&P s US$1.05 billion share of the MNP, which started construction in April 2006 and is scheduled for completion by December Program management is most successful because tasks such as planning, permitting, design and construction are advanced simultaneously whenever possible, rather than in a linear fashion. A program manager has intimate knowledge of every activity, enabling the direction and allocation of resources to support the master plan. In this case, the program manager has specific contractual functions: Real estate acquisition. Most of the MNP will be constructed on public streets and other existing rights-of-way (ROW). However, the project will require purchasing some privately owned land and easements to accommodate portions of the project and to provide construction access. The program management team works with CL&P s land acquisition team to manage the timing of land and easement purchases to support construction sequencing. Permitting and environmental planning. Many federal, state and local permits are required before construction begins. The program manager supports the permitting processes and monitors environmental compliance throughout construction. Design. Burns & McDonnell used internal resources to handle most design work, contracting some detailed elements to other firms. Preliminary design work garnered unanimous approval from the Connecticut Siting Council (CSC). Approximately 30% of the MNP was designed before the final budget and schedule were determined. This mode of operation can provide flexibility in budgeting and scheduling. Under conventional project approaches, modifications to the project can be costly and time consuming. Procurement. Project risk is heightened by competition for construction labor from major transmission projects elsewhere. To reduce this risk, the program management team has met with vendors, gathered data and analyzed market trends to keep its contracting strategy flexible. Mitigating risk is also critical in securing materials and equipment. For example, long-lead major materials and equipment were procured independent of construction to reduce scheduling risk. The 345-kV transmission cable is being specified and procured on the worldwide market. To limit manufacturing risk, no single vendor is allowed to supply the total amount of transmission cable needed, with overall cable quantities being divided into smaller lots to maintain delivery schedules, secure optimal pricing and mitigate risk. Community relations. Community relations play an important

4 SYSTEMUpgrade The new 345-kV terminal in the Scovill Rock Switching Station in Middletown, Connecticut, will be the first completed substation of the Middletown-Norwalk Project. role for the utility. This project has three full-time public relations professionals in Connecticut working with CL&P s corporate communications staff and utilizing CL&P s lessons learned to respond to public inquiries. They also meet with stakeholders to explain project details. A tollfree number and project website provides the public with an immediate avenue for project contact. Safety. Burns & McDonnell is conducting safety orientation to every person working on-site. Four full-time safety managers continually monitor the project and mitigate any safety concerns that develop along the way. The contract with CL&P is incentive based, providing financial rewards for maintaining high safety standards and, conversely, penalties for a poor safety record. Project controls. A complex financial, scheduling and change management system designed to collect and report on submittals, requests for information, drawings, meeting minutes and public feedback is in place to keep the project on schedule and help control costs. Primavera Systems P3e/c is used to track and report on the schedule. Expedition version 10.0 provides documentation for all project decisions and tracks project funding, costs and contract information based on CL&P s cost-accounting structures. Both software systems are Web-based, allowing authorized users to access the system from anywhere, anytime. Construction management. Burns & McDonnell will manage more than 50 different material and construction packages, including thousands of construction workers. The project will peak at more than 600 construction workers on-site. The construction manager is responsible for coordinating between contractors, the contracting strategies, change orders, the overall schedule, daily inspection and quality control. Bond Brothers (Everett, Massachusetts, U.S.) has been selected as the civil contractor for the underground transmission. PAR Electric (Kansas City, Missouri) has been selected as the contractor for the overhead portion of the project. Quality assurance/quality control. Requirements such as construction monitoring, safety, communications, construction records maintenance, receipt inspection of owner-supplied materials, ROW inspections and work completion inspections have been outlined. PROGRAM MANAGEMENT IN ACTION In April 2005, the MNP received Connecticut Siting Council (CSC) approval, but part of that decision required the project to reach out to the municipalities along the overhead construction path for additional input regarding the 345-kV overhead line design. CL&P was required to readdress public concerns, modify designs accordingly and submit detailed construction plans for CSC approval. This process lengthened the design phase and, under another project delivery method, could have delayed the overall schedule and increased costs. Since program management emphasizes overall project completion, not individual components, other aspects moved forward while the additional design issues were being addressed. The first in a series of CSC overhead construction plan approvals came in late 2005, and the last one was approved in late summer Successful program management is as much about managing overall project risk as it is about managing schedules and costs. Program management fits well with CL&P s development risk management program, allowing characterization and mitigations of risks associated with committing to a $1 billion construction project. During early negotiations with CL&P, the utility requested that a portion of the program manager s professional fee be placed at risk, based on a combination of project drivers such as schedule, budget, and safety and community relations. CL&P matched the at-risk fees in an escrow account set up to provide incentive for high performance. Avoiding all risk is impossible, but program management attempts to limit unknowns. A risk matrix identified the most complex part of the MNP as the underground construction, much of which will run directly beneath U.S. Route 1, a fourlane divided highway that is a major commercial artery and crosses several major bodies of water in southwest Connecticut. Installation of the underground cable will require, at a minimum, the excavation of a 4-ft-wide by 8-ft-deep (1.2-m by 2.4-m) trench for duct-bank placement. The complexity of underground construction is due in part to the amount of subsurface rock that must be removed. When the project is in full swing, standby costs for excavation crews are expected to run tens of thousands per day, translating into millions of dollars in additional construction costs should the project encounter significant rock or unexpected subsurface utilities. To mitigate this risk, extensive geotechnical investigations assessed subsurface conditions. Preconstruction testing allowed better assessment of costs and possible delays. The prime civil contractor is providing upfront comments on design alternatives and risk forecasting, to make sure there are no surprises during construction. OVERALL PROJECT BENEFITS Owners reap several benefits from program management on large, complex

5 SPOTLIGHT ON UNDERGROUND The amount of underground transmission on this project makes it one of the most complex projects being constructed today. The following are some of the underground issues being addressed. Splice Vaults. Splice vault locations are determined by cable-pulling calculations, cable reel lengths, existing utilities, system grounding method, and the locations of rock or water or railroad crossings. The vaults have 8 ft by 8 ft by 30 ft (2.4 m by 2.4 m by 9.1 m) inside dimensions and will be spaced about every 1700 ft (518 m) along the 18.5-mile (29-km) total length of underground line. Each splice vault is precast, multisectioned and watertight. The vaults are approximately 30,000 lb per section with two sections per vault. The splice vaults are grounded and contain predrilled holes for the electric and communication ducts that will be racked on one side of the vault. Cable manufacturers specified the inside vault dimensions based on construction, maintenance and National Electric Safety Code requirements. The splice vaults will be supplied by regional precasters using custom structural designs and will have 10-inch to 12-inch (254- mm to 305-mm) thick walls. (Vault design was the subject of a T&D World article Design and Test 345-kV Cable Vaults in May 2006.) Duct Bank Installation. The civil contractor is installing 50 ft to 150 ft (15 m to 45 m) of duct bank per day per crew and will run 10 to 12 vault and duct bank crews at the peak of construction. Two to three supporting crews will be employed for utility relocation, repaving and rock coring. Minimal rock is expected and blasting is not being used. The minimum size of the duct bank is 3.5 ft by 2.5 ft (1.1 m by 0.8 m) and includes horizontal and vertical curves to avoid existing utilities, buildings and landscaping. These curves increase pulling tensions, which decreases cable cut lengths. Installation includes saw cutting the road, excavating the trench, exporting the spoils, placing 10-ft (3-m) lengths of 8-inch (203-mm) PVC conduits in spacers, encasing the ducts in 2500-psi (17-Mpa) concrete, backfilling the trench with a thermally tested flowable fill and laying a temporary bituminous patch. The concrete and flowable fill will undergo thermal testing and slump testing in the field. Fluidized thermal backfill (FTB) is a diggable concrete of 100 psi to 150 psi (690 kpa to 1034 kpa) that allows heat to transfer from the energized conductors inside the duct bank, minimizing cable ampacity losses. After the FTB is placed 19 inches (483 mm) below the surface, the civil contractor applies a 10-inch (254-mm) layer of base rock and a 9-inch (229-mm) layer of class 1 and class 3 asphalt concrete hot mix as a temporary patch. The permanent pavement restoration occurs later. Upon completion of the duct banks, the civil contractor will proof the integrity of individual polyvinyl chloride (PVC) ducts by a robotic video check, swabbing and mandreling. The civil contractor then installs a mule tape to show the exact length of the in-place individual duct bank. Cable Pulling. Burns & McDonnell prequalified and selected, through competitive bidding, vendors to manufacture the four 345-kV circuits. They are Silec Cable, LS Cable and Prysmian Cable. The manufacturers are responsible for furnishing and installing the cable system. The cable for the MNP is a kcmil copper conductor with 345-kV cross-linked polyethylene (XLPE) insulation. The cable is jointly specified by CL&P and United Illuminating (New Haven, Connecticut). Three cables, weighing approximately 29 lb/ft each (209 kg/m), will carry up to 860 MVA. Maximum allowable pulling tension on the cable is approximately 21,000 lb (9500 kg), and average tension during pulling will be between 5000 to 15,000 lb (2300 to 6800 kg). Conduits are lubricated with a soap-like slurry product to lower the coefficient of friction from 0.3 (dry) to values as low as 0.1. Underground trench (duct bank) in Westport, Connecticut, showing three 8-inch PVC conduits, which will later carry the XLPE cables, and one 4-inch PVC multiduct for fiber-optic communication lines. Same as above, but with additional set of conduits for second circuit in background. In underground trench (duct bank) in Fairfield, Connecticut, conduits are encased in concrete for protection and to aid in heat dissipation.

6 SYSTEMUpgrade A KEY FIRST STEP Burns & McDonnell hired GZA GeoEnvironmental Inc. (Norwood, Massachusetts, U.S.) to conduct geotechnical investigations along the proposed underground transmission line route. Work began in early September 2005 and was substantially completed in April The geologic and hydrogeologic properties that would affect the project costs and schedule in the design and construction phases were determined. Depth to groundwater, depth to rock and rock coring to determine subsurface cross-section profiles were completed. More than 150 borings ranging in depth from 14 to 100 ft (4 m to 30 m) were completed during the investigation. Draft boring logs were ed by GZA to Burns & McDonnell within two days of drilling activities to facilitate decision making as the project data became available. Geotechnical engineering reports were issued in phases to comply with the program management schedule in time for RFPs issued for civil/construction activities. A crew obtains core samples along the line route in Fairfield, Connecticut. certified project manager. bartoab@nu.com Jim Hogan is the director of engineering for the Burns & McDonnell Transmission & Distribution Group. At the completion of the siting process for the Middletown to Norwalk Project in 2005, Hogan assumed the role of engineering manager and assistant program manager in the Kansas City office. Hogan is a professional engineer and holds bachelor s and master s degrees in civil engineering from the University of Missouri-Columbia. jhogan@burnsmcd.com Excavator removes existing concrete and pavement prior to underground trenching of duct bank in Fairfield, Connecticut. capital projects. They maintain control over the design, budget and construction processes while relying on the program manager for overall execution. The owner is freed from the requirements of hiring additional staff. Flexibility is inherent in the process, from inception through completion. A sudden change of scope or project approach is accommodated by the methodology. An owner locked into a lump-sum EPC contract, where scope schedule and price are fixed, faces difficulties implementing changes. Program managers work with owners and have a portion of their fee at risk, motivating them to work in the owner s best interest. CL&P recently selected Burns & Mc- Donnell to provide the program management of a related effort, the Glenbrook Cables Project, which consists of constructing 9 miles (14 km) of 115-kV underground transmission to connect the Glenbrook and Norwalk substations in Connecticut. Anne Bartosewicz is a project director for Northeast Utilities, where she is responsible for the Middletown to Norwalk Transmission Project. She holds a bachelor s degree in chemical engineering from the University of Connecticut and an MBA from the University of Hartford. Bartosewicz is a J. Brett Williams, a program manager for Burns & McDonnell, has worked on major-scale design-build and program management projects for the past 16 years. His expertise is in project scope development, design management and construction management from project inception through closeout. Williams holds a bachelor s degree in construction engineering technology from Pittsburg State University and a master s degree in construction science from the University of Oklahoma. jbwilliams@burnsmcd.com For more information, please contact Mike Beehler at Reprinted with permission from the February 2007 issue of Transmission & Distribution World ( Copyright 2007, Penton Business Media. All rights reserved. TD-150-EKK

Underground Transmission Lines

Underground Transmission Lines Underground Transmission Lines INTRODUCTION In today s urban, environmentally sensitive environment, how are you going to get power to the people who need it? In many cities, overhead transmission lines

More information

Underground Cable Temperature Monitoring in the Real World

Underground Cable Temperature Monitoring in the Real World Underground Cable Temperature Monitoring in the Real World Executive Summary Background Brain Storming Possible Causes to Duct Bank Over Heating Mitigating Duct Bank Overheating DTS Installation for Duct

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3

More information

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS. DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS December 20, 2004 David W. Forrest Rachel I. Mosier 1. EXECUTIVE SUMMARY CL&P

More information

Electric Service Guide for Commercial Construction

Electric Service Guide for Commercial Construction Electric Service Guide for Commercial Construction Contents Contacting KCP&L... 2 Voltages... 2 Temporary Service... 2 Customer-Provided Temporary Service... 2 KCP&L-Provided Temporary Service.... 2 Current

More information

Least Cost Cable System. Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems

Least Cost Cable System. Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems Least Cost Cable System Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems Cost Sharing of Cable Systems Underground Extensions The Company will construct

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

Stephen G. Whitley, Senior Vice President & Chief Operating Officer Peter T. Brandien Vice President, System Operations To: Stephen G. Whitley, Senior Vice President & Chief Operating Officer From: Peter T. Brandien Re: Discussion of Cable Technologies Under Evaluation

More information

Cable Consulting International

Cable Consulting International Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director www.cableconsulting.net Alan Williams BSc, CEng, MIEE Senior Consultant 1 FEASIBILITY STUDY for 500 kv AC UNDERGROUND

More information

345 kv Underground Report

345 kv Underground Report POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050

More information

C. Section 014510 TESTING LABORATORY SERVICE.

C. Section 014510 TESTING LABORATORY SERVICE. SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities

HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities HIGH- AND EXTRA-HIGH-VOLTAGE GLOBAL CABLE SYSTEM SOLUTIONS Rely On Our Experience... Experience Our Capabilities RELY ON OUR EXPERIENCE... EXPERIENCE OUR CAPABILITIES For close to half a century, Silec

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 18370 SIGNAL WIRE AND CABLE

SECTION 18370 SIGNAL WIRE AND CABLE SECTION 18370 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for all cable and wire required for signal and signal power system wiring to wayside shelters, junction boxes, and factory

More information

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET

More information

SPECIAL SPECIFICATION 5757 Power Duct System

SPECIAL SPECIFICATION 5757 Power Duct System 2004 Specifications CSJ 0353-04-088 SPECIAL SPECIFICATION 5757 Power Duct System 1. Description. This Item shall govern for the furnishing and installing of all materials, equipment, and labor listed in

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

KNOW YOUR OPTIONS: 230 KV POWER CABLES

KNOW YOUR OPTIONS: 230 KV POWER CABLES KNOW YOUR OPTIONS: 230 KV POWER CABLES 71 CONDUCTOR MATERIAL AND SIZE Conductor material is a matter of both customer preference and required current carrying capacity At 230 kv, copper is most common

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Section 5 161 kv Power Cables

Section 5 161 kv Power Cables Know Your Options: 161 kv Power Cable 61 material and size material is a matter of both customer preference and required current carrying capacity Copper conductor common for larger loads When both copper

More information

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address: City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE Know Your Options: 69 kv XLPE Power Cable 3 material and size material is a matter of both customer preference and required current carrying capacity Copper conductor common for larger loads When both

More information

COMMERCIAL CONDUIT RULES AND REGULATION

COMMERCIAL CONDUIT RULES AND REGULATION Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies\Residential 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

National Science Foundation Funds Request

National Science Foundation Funds Request University Corporation for Atmospheric Research National Science Foundation Funds Request 1. (NSF USE ONLY) 2. FACILITY NAME & LOCATION 3. PROJECT NAME 4. UCAR TRACKING NUM. NCAR Mesa Lab 15KV FEEDER REPLACEMENT

More information

Gulf Cable & Electrical Ind. Co.

Gulf Cable & Electrical Ind. Co. CONTENTS INTRODUCTION PRODUCT RANGE I PRODUCT DATA TABLES XLPE INSULATED 600/1000V CABLES Two Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 1 Three Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 2 Four Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

Construction Specifications for Keyhole Pavement Coring and Reinstatement

Construction Specifications for Keyhole Pavement Coring and Reinstatement F I N A L Construction Specifications for Keyhole Pavement Coring and Reinstatement Gas Technology Institute 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gastechnology.org Version 13 October

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

CONSTRUCTION PERMIT REQUIREMENTS

CONSTRUCTION PERMIT REQUIREMENTS CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

EDS 02-0027 11KV TRIPLEX CABLE

EDS 02-0027 11KV TRIPLEX CABLE THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 02-0027 ENGINEERING DESIGN STANDARD EDS 02-0027 11KV TRIPLEX CABLE Network(s): EPN, LPN, SPN Summary:

More information

Specification for Installation of Underground Conduit Systems

Specification for Installation of Underground Conduit Systems Specification for Installation of Underground Conduit Systems November 2008 Version 2.0 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 Table

More information

Brief Engineering Assessment: Cost estimate for building fiber optics to key anchor institutions

Brief Engineering Assessment: Cost estimate for building fiber optics to key anchor institutions Brief Engineering Assessment: Cost estimate for building fiber optics to key anchor institutions Prepared for the National Association of Telecommunications Officers and Advisors and the Schools, Health,

More information

AMSC s Superconductor Cable Technologies for Electric Utilities

AMSC s Superconductor Cable Technologies for Electric Utilities International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,

More information

NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS

NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS These guidelines are intended to familiarize Developers regarding some issues that are important to get electric

More information

Underground Electric Transmission Lines Introduction

Underground Electric Transmission Lines Introduction Underground Electric Transmission Lines Introduction This overview contains information about electric transmission lines which are installed underground, rather than overhead on poles or towers. Underground

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE

More information

Subcontractor Pre-Qualification

Subcontractor Pre-Qualification Subcontractor Pre-Qualification Thank you for your inquiry regarding subcontracting opportunities with Western Utility LLC. (WU). Construction projects bring many exciting challenges and risks associated

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

Section 100 Contractor Quality Control Program

Section 100 Contractor Quality Control Program 7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Applying For New or Revised Electric Service

Applying For New or Revised Electric Service Applying For New or Revised Electric Service Dear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. Please complete, sign and return the attached service

More information

Electric Service Guide for Residential Construction

Electric Service Guide for Residential Construction Electric Service Guide for Residential Construction Table of Contents Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Changing your electric service... 2 What you need to know before you

More information

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of

More information

Beseck Switching Station Inspection

Beseck Switching Station Inspection Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

your electric service: from overhead to underground

your electric service: from overhead to underground your electric service: from overhead to underground taking responsibility As an individual, your efficient use of energy brings benefits such as lower bills, improved comfort levels in your home and a

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

WHY CABLE TRAY? BECAUSE A CABLE TRAY WIRING SYSTEM PROVIDES SAFE AND DEPENDABLE WAYS TO SAVE NOW AND LATER

WHY CABLE TRAY? BECAUSE A CABLE TRAY WIRING SYSTEM PROVIDES SAFE AND DEPENDABLE WAYS TO SAVE NOW AND LATER Large numbers of electrical engineers have limited detail knowledge concerning wiring systems. There is the tendency by engineers to avoid becoming involved in the details of wiring systems, leaving the

More information

Morris S. Stover, P.E. Sponsor, Transmission Area

Morris S. Stover, P.E. Sponsor, Transmission Area Page 1 of 5 Job Function Morris has nearly 28 years in the power industry including design and construction of transmission line and substation facilities, He has extensive experience in contract development

More information

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress 0611-048-Mep229 12/12/06 6:44 Page 22 State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress Reinhard SCHROTH, Chairman of SC B1 2002-2006 High

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials

More information

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014 CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska February 10, 2014 QUESTIONS AND ANSWERS TO: Prospective Proposers FROM: Chugach Electric Association, Inc. 5601 Electron Drive Anchorage, Alaska SUBJECT:

More information

Electric Service Guide for Residential Construction

Electric Service Guide for Residential Construction Electric Service Guide for Residential Construction TABLE OF CONTENTS Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Building a New Home... 3 KCP&L Services at a Glance... 4 Current Transformers...

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information

SHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE

SHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE AN INFORMATION GUIDE SCOPE PROJECT MANAGER Joint Provisioning Guidelines for Shallow Utility Services in Residential Areas where the Electric, Gas, Telephone & Cable TV facilities are Buried in the same

More information

CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS

CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS I "i,, I, 1 " CHAPTER 10 PERMIT PROCEDURES AND BONDING REQUIREMENTS FOR CONTRACTORS CHAPTER 10 PERMIT PROCEDURES A N D BONDING REQUIREMENTS FOR CONTRACTORS, Section I -, INDEX :, - % I I,,J Topic b 101

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA CROSS SOUND CABLE PROJECT 330MW HVdc INTERCONNECTION BETWEEN NEW HAVEN, CONNECTICUT AND SHOREHAM, NY Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA Subordinate Status Removal and Amendment of Approved

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Geotechnical Studies Soils Analysis & Recommendations The first section, Work Type Definition, provides a detailed explanation of the work type. The second section, Work Type Submittal Requirements,

More information

Network Standard Advice No. 1420C 9/6/2011

Network Standard Advice No. 1420C 9/6/2011 Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides

More information

STABILOY BRAND FeeDeR SOLuTIONS

STABILOY BRAND FeeDeR SOLuTIONS STABILOY BRAND Feeder Solutions DATA CENTER Introduction General Cable understands that data centers depend heavily on a steady, reliable and scalable source of power. That is why our STABILOY Brand aluminum

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

General Utility Work Obligations

General Utility Work Obligations General Utility Work Obligations This Section addresses the Utility Company (or Utility Owner) requirements. It does not apply to existing stormwater facilities, irrigation ditches, Intelligent Transportation

More information

Project Implementation and Administration Seminar Case Studies

Project Implementation and Administration Seminar Case Studies BP01 PHILIPPINES EDUCATION PROJECT The project will construct and equip a new Institute of Technology in the Philippines. Table 1 provides project cost estimates. The work includes Construction of an academic

More information

4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information

4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information 4. REQUEST FOR ELECTRIC SERVICE To establish an electric service, temporary or permanent, contact UI s Customer Care Center by calling: 1-800-722-5584 (7:00 a.m. 7:00 p.m., Monday Friday and 7:00 AM to

More information

Utilities and existing services

Utilities and existing services Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for

More information

Electric Service Guide. Residential Subdivision

Electric Service Guide. Residential Subdivision January 1, 2016 Contact MID s Electric Engineering Department (electric.standards@mid.org) with any questions about this Service Guide. Check MID s website (www.mid.org) Electric Service Guide for the

More information

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES Riccardo BODEGA, Prysmian Cables and Systems, The Netherlands, riccardo.bodega@prysmian.com Henk GEENE,

More information

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 Summary of Duties: Performs professional electrical engineering work in

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Water and Sewer Service Line Policy

Water and Sewer Service Line Policy Water and Sewer Service Line Policy Effective beginning May 17, 2004 (Amended March 16, 2009) Water Service Line Policy General Statement The City of Arlington does not install or participate in water

More information

ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS

ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS Revised Cal. P.U.C. Sheet No. 20093-E Cancelling Revised Cal. P.U.C. Sheet No. 15575-E ELECTRIC RULE NO. 15 Sheet 1 APPLICABILITY: This rule is applicable to extension of electric Distribution Lines* of

More information

Hendrix Spacer Cable

Hendrix Spacer Cable Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits

More information

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF

More information

Major Communications Projects

Major Communications Projects Major Communications Projects Project Name: Completion Date: SawNet SW Washington OSP Route SC2 Skamania County, WA Ongoing Construction of a fiber optic line that connects North Bonneville and Carson,

More information

Ontario Electrical Safety Code - Info Sheet

Ontario Electrical Safety Code - Info Sheet Ontario Electrical Safety Code - Info Sheet The following are the Code requirements and explanatory material for buried electrical wiring that are applicable to most residential applications. 12-012 Underground

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these

More information

New Commercial Service Application

New Commercial Service Application Please submit with this form an application fee of $500.00 and an Electronic CAD file of your preliminary plat. CAD file can be emailed to craign@inlandpower.com. Member Information Work Order Number:

More information

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS 1 SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS TABLE OF CONTENTS I. Introduction II. General Information and Requirements A. Applying for Sewer connection B. Excavation C. Cutting Concrete and Asphalt

More information

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES Jean-Maxime SAUGRAIN NEXANS Corporate VP Technical IASS Workshop Postdam May 13, 2011 Rationale High-capacity High Temperature Superconducting

More information