1 Lessons learned Axel Bäcker

2 Lessons learned - 1 Project planning Decommissioning planning should start well in advanced Analysis of the project based on plant inventarisation / characterisation is necessary to issue successful dismantling strategy, a consistent plan and a well structured project Planning presents an iterative process; implementation of a Decommissioning Management System assures needed flexibility in case of project revision, provides tool for handling large amount of data sets for recalculation and budget control Flexible work implementation is assured by issuing of comprehensive basic documents (project manual, dismantling manual) avoiding already in the planning phase detailed design documents for dismantling Use of operational documents adopted to decommissioning purposes

3 Lessons learned - 2 Project execution Waste management (1) Primary circuit decontamination before shut down Site characterisation (Inventorisation) - basic precondition for decommissioning System-based technical planning / room-based dismantling In time implantation of waste and (fuel) logistics Implementation of a residual material manual may give a sound basis for all material logistic issues Buffer places necessary to avoid bottlenecks early planning of that

4 Lessons learned - 2 Project execution Waste management (2) Treatment of the dismantled material in separate treatment station(s) External treatment after dismantling (warm workshop / interim storage) - continuous and rapid dismantling (no bottlenecks) - avoidance of contamination spreading - minimization of personnel radiation exposure - minimization of the project costs!!! Establishment of an interim storage with treatment capacities Use of decay storage and dismounting of large components also the high activated components cost decreasing by 15% (Dismantling is also possible with fuel in the plant)

5 Lessons learned - 3 Project management (1) Early introduction of a project structure (work break down) - clear and easy structures, connections and conditions - take into account the possibility for extension - different levels of work break down are acceptable As fast as possible perform project analysis for key decisions Necessity of project manual implementation as basic management tool Clarify operational and decommissioning modus with licensing authority Maximal 2-3 years life time of working packages as the central level in the WBS Periodical project revisions (ca. all two years) are necessary High flexibility of work breakdown changing of strategy in time - keep flexibility!

6 Lessons learned - 3 Project management (2) Introduce a separate Project Controlling organisation at an early project stage Project controlling - continuous registration of actual data basis for controlling - large amount of work for updating of project documentation Project revisions all 2 years necessary Introduce common software solution to support the management (DeManS) - project calculation - project planning - project supervision waste management (MFT)

7 Lessons learned - 4 Licensing strategy (1) One basic license for decommissioning with supplementary part licenses (step by step procedure) Detailed documentation only for authorized experts in accordance with dismantling progress - continuous work load by all parties - transparency for the public Preparation of detailed documents not before preparation of individual dismantling steps Amount and degree of detail of licensing documents must reflect the involved risks Closed co-operation with authorities/regulators decreases the costs

8 Lessons learned - 4 Licensing strategy (2) - Closed co-operation with authorities/regulators 10 Golden Rules (licensing) 1. The applicant presents the project and the licensing strategy to the authority before the application will be made and also consults the authority. 2. The applicant confines to the relevant licensing aspects in the licensing procedure and submits, as far as possible, complete, checkable and consistent documents. 3. The applicant defines the start and goal situation oriented on the protection aims and thus, reduces the necessary efforts for authorized opinions. 4. The participants in the procedure (operator licensing authority and experts) send all papers in parallel to all other persons involved so that timeconsuming detours can be excluded and everybody will have the same information level. 5. The participants in the procedure agree on a definite time schedule. The licensing authority binds its expert to check the documents on completeness and to list the additional requirements in an appropriate time.

9 Lessons learned - 4 Licensing strategy (3) - Closed co-operation with authorities/regulators 10 Golden Rules (licensing) 6. The participants in the procedure regularly organize status discussions to explain the status of the procedure, to define weak points and to specify time scheduling. 7. The licensing authority invites to technical discussions. Technical discussions are also allowed between applicant and expert; the authority decides in the individual case on the participation. 8. The participants in the procedure read the expert opinion draft together to clear up differences of opinions as fast as possible. 9. The authority only itemizes the relevant documents in the granted licence. 10. The participants agree on the necessary details and timely integration of the required documents necessary for the fulfilment of the additional requirements.

10 Lessons learned - 5 Social aspects of decommissioning (1) Personnel reduction at the start of decommissioning is necessary for budget optimization; social aspects should be taken into account The former operator personnel should manage the decommissioning project and perform as much as possible task by its own No main contractor for the overall project implementation is necessarily required contractors only for special technical cases In time site remediation for unused areas as a precondition for future reuse Creation of new projects/jobs supports personnel motivation and perspective

11 Lessons learned - 5 Social aspects of decommissioning (2) Use the decommissioning project to initiate local firms Decommissioning training only if technical sensible Decommissioning training only after restructuring of the project Early introduction of a site reuse project to start immediately with the site remediation Consideration of synergy effects for site reuse planning!!

12 Presentations- Contents 1. EWN Greifswald project management overview Wednesday 2. Case study - Project management / project planning Wednesday 3. Case studies Decomm. logistic - examples: 3.1 decommissioning TH Wednesday 3.2 decommissioning activated components Wednesday 4. Case studies: 4.1 ALARA in Practice Wednesday 4.2 Stakeholder involvement Wednesday 4.3 Social aspects of decommissioning Friday 5. Case study - Material management & treatment Thursday 6. Case study site reutilisation Friday and reuse of former operation buildings 7. Lessons learned during 20 years Friday decommissioning of NPPs

13 Thank you for your attention! Axel Bäcker EWN GmbH

How To Decommission A Nuclear Plant

How To Decommission A Nuclear Plant International Atomic Energy Agency Decommissioning of Nuclear Facilities Management of Decommissioning Projects Lawrence E. Boing Manila, Philippines, October 2006 1 Lesson Objectives Understand the management

More information

International Action Plan On The Decommissioning of Nuclear Facilities

International Action Plan On The Decommissioning of Nuclear Facilities International Action Plan On The Decommissioning of Nuclear Facilities A. Introduction Decommissioning is defined by the International Atomic Energy Agency (the Agency) as the administrative and technical

More information

THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES

THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES Introduction 1. This statement of the UK Government and devolved administrations policy on the decommissioning of nuclear facilities updates

More information

Lessons Learned at Continental Automotive

Lessons Learned at Continental Automotive Lessons Learned at Continental Automotive Basic Principle of Lessons Learned Lessons Learned is people reusing experiences of colleagues. What is Lessons Learned? A Lesson Learned IS Knowledge or understanding

More information

Government Degree on the Safety of Nuclear Power Plants 717/2013

Government Degree on the Safety of Nuclear Power Plants 717/2013 Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and

More information

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012 Outlook for RWE s nuclear operations Prof. Dr. Gerd Jäger London, 16 January 2012 Overview of German nuclear power plants Power plant Net capacity MW Commercial commissioning Shutdown German nuclear power

More information

Decommissioning of nuclear facilities

Decommissioning of nuclear facilities Seminar on Decommissioning of nuclear facilities Studsvik, Nyköping, Sweden 14 16 September 2010 A Nordic Nuclear Safety Research (NKS) seminar organised by Studsvik Nuclear AB (Studsvik) and Swedish Nuclear

More information

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND 1. NATIONAL FRAMEWORK FOR MANAGEMENT AND REGULATION OF RADIOACTIVE WASTE AND DECOMMISSIONING 1.1 National framework 1.1.1 Overview of national

More information

Standardised Decommissioning Cost Estimating of WWER-440 Nuclear Power Plants (SCE)

Standardised Decommissioning Cost Estimating of WWER-440 Nuclear Power Plants (SCE) COMMISSION OF THE EUROPEAN COMMUNITIES (5th Framework Programme) Standardised Decommissioning Cost Estimating of WWER-440 Nuclear Power Plants (SCE) Topical Information Meeting on Decommissioning of Nuclear

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EUROPEAN COMMISSION Brussels, 3.3.2015 COM(2015) 78 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL on the implementation of the work under the nuclear decommissioning assistance

More information

GAO. NUCLEAR REGULATION Regulatory and Cultural Changes Challenge NRC. Testimony

GAO. NUCLEAR REGULATION Regulatory and Cultural Changes Challenge NRC. Testimony GAO For Release on Delivery Expected at 9a.m.EDT Thursday, March 9, 2000 United States General Accounting Office Testimony Before the Subcommittee on Clean Air, Wetlands, Private Property, and Nuclear

More information

IAEA Action Plan on Nuclear Safety 1

IAEA Action Plan on Nuclear Safety 1 IAEA Action Plan on Nuclear Safety 1 In June 2011 a Ministerial Conference on Nuclear Safety was convened to direct, under the leading role of the IAEA, the process of learning and acting upon lessons

More information

SPEAKER: Harry van Huyssteen

SPEAKER: Harry van Huyssteen TOPIC: The Transport Forum as Best Practice for Collaboration SPEAKER: Harry van Huyssteen WHAT IS THE TRANSPORT FORUM? Monthly Special Interest Group events Attendance is for free, but registration is

More information

Academic Calendar for Faculty

Academic Calendar for Faculty Summer 2013 Term June 3, 2013 (Monday) June 3-4, 2013 (Monday Tuesday) June 5, 2013 (Wednesday) June 5-6, 2013 (Wednesday Thursday) June 6, 2013 (Thursday) July 3, 2013 (Wednesday) July 4, 2013 (Thursday)

More information

System/activ. ity of interest Comment Priority. Referenc. Id Category Text. Waste management Establish waste classification 5 Romuald Duperrier Waste

System/activ. ity of interest Comment Priority. Referenc. Id Category Text. Waste management Establish waste classification 5 Romuald Duperrier Waste 1 Waste management Establish waste classification 5 Romuald Duperrier Waste IAEA GSG- 1 or SSI FS 1996-2? page 34 2 Evaluate environmental impact (including workers) of the decommissioning 5 Romuald Duperrier

More information

Status, responsibilities and missions of ANDRA (France)

Status, responsibilities and missions of ANDRA (France) Status, responsibilities and missions of ANDRA (France) Marie-Claude DUPUIS ANDRA - CEO Contents 1. Legal framework, organization and general information 2. ANDRA today: An Industrial Operator An Innovating

More information

Draft IAEA Action Plan on Nuclear Safety

Draft IAEA Action Plan on Nuclear Safety Atoms for Peace Board of Governors General Conference GOV/2011/59-GC(55)/14 Date: 5 September 2011 For official use only Item 3(b) of the Board's provisional agenda (GOV/2011/46) Item 14(b) of the Conference's

More information

The Bellevue Center for Obesity & Weight Management. Program Director: Manish Parikh, MD WEIGHT LOSS SURGERY INFORMATION SEMINAR

The Bellevue Center for Obesity & Weight Management. Program Director: Manish Parikh, MD WEIGHT LOSS SURGERY INFORMATION SEMINAR Wednesday, January 7, 2015 Wednesday, February 4, 2015 Wednesday, March 4, 2015 Wednesday, April 1, 2015 Wednesday, May 13, 2015 Wednesday, June 3, 2015 Wednesday, July 1, 2015 Wednesday, August 5, 2015

More information

WEIGHT LOSS SURGERY INFORMATION SEMINAR

WEIGHT LOSS SURGERY INFORMATION SEMINAR Wednesday, January 6, 2016 Wednesday, February 3, 2016 Wednesday, March 2, 2016 Wednesday, April 6, 2016 Wednesday, May 4, 2016 Wednesday, June 1, 2016 Wednesday, July 6, 2016 Wednesday, August 3, 2016

More information

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader

More information

POSITION DESCRIPTION Number: PD:

POSITION DESCRIPTION Number: PD: POSITION DESCRIPTION Number: PD: The VALUES of The City of South Perth Customer Focus - To work together with our customers to achieve positive outcomes. Excellence - To develop a culture of flexibility,

More information

FWK Contract - Support for safety and accident analyses

FWK Contract - Support for safety and accident analyses IDM UID SKKZDR VERSION CREATED ON / VERSION / STATUS 19 Feb 2016 / 1.0 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) FWK Contract - Support for safety and accident

More information

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark Workshop on Best Practices in Policies and Measures, 11 13 April 2000, Copenhagen THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE Ole Odgaard Denmark Abstract: The

More information

CUSTOMER SERVICE & SUPPORT. Customer oriented service optimum system utilization

CUSTOMER SERVICE & SUPPORT. Customer oriented service optimum system utilization CUSTOMER SERVICE & SUPPORT Customer oriented service optimum system utilization Customer Service & Support (CSS) Customized Service Maximum availability of all systems and quick response times to service

More information

AUDIT COMMITTEE TERMS OF REFERENCE

AUDIT COMMITTEE TERMS OF REFERENCE AUDIT COMMITTEE TERMS OF REFERENCE 1. Purpose The Audit Committee will assist the Board of Directors (the "Board") in fulfilling its oversight responsibilities. The Audit Committee will review the financial

More information

Guide to nuclear decommissioning

Guide to nuclear decommissioning Guide to nuclear decommissioning Contents: What is decommissioning? Stages of decommissioning Site restoration Waste management The UK decommissioning industry The international picture What is decommissioning?

More information

2.0 Land Quality Programme

2.0 Land Quality Programme 2.0 Land Quality Programme The Sellafield site has a legacy of ground contamination from its historical use as a Royal Ordnance factory and its subsequent development as a nuclear facility. The ground

More information

DRAFT Milestones and Recommendations: Fuel Cycle OECD/IEA 2010

DRAFT Milestones and Recommendations: Fuel Cycle OECD/IEA 2010 DRAFT Milestones and Recommendations: Fuel Cycle 1 OECD/IEA 2010 Fuel cycle: - established technologies for all steps of the NFC, though R&D can help improve technologies, reduce costs, Front end: uranium

More information

Efficient Recycling and Waste Management»

Efficient Recycling and Waste Management» Efficient Recycling and Waste Management» EnBW KernkraftGmbH Jörg Klasen, Head of Nuclear Decommissioning Services with Frank Bolles, Burkhard Hartmann, Sönke Pingel 46th Annual Meeting on Nuclear Technology

More information

Operations. Transport Officer OP199. Operations Manager. Administration Officer

Operations. Transport Officer OP199. Operations Manager. Administration Officer Job Description Service Job Title Post No Salary Grade Operations Transport Officer OP199 E Hours 37 Responsible to Responsible for Operations Manager Administration Officer Purpose of Post: To support

More information

Council of the European Union Brussels, 24 November 2014 (OR. en)

Council of the European Union Brussels, 24 November 2014 (OR. en) Council of the European Union Brussels, 24 November 2014 (OR. en) 15701/1/14 REV 1 "I/A" ITEM NOTE From: To: General Secretariat of the Council No. prev. doc.: 11153/2/14 REV 2 Subject: JAI 897 DAPIX 175

More information

Licensing Process for New Nuclear Power Plants in Canada. INFO-0756 (Revision 1)

Licensing Process for New Nuclear Power Plants in Canada. INFO-0756 (Revision 1) Licensing Process for New Nuclear Power Plants in Canada INFO-0756 (Revision 1) May 2008 Licensing Process for New Nuclear Power Plants in Canada Minister of Public Works and Government Services Canada

More information

WIPP Recovery Workshop

WIPP Recovery Workshop WIPP Recovery Workshop U.S. Department of Energy Waste Isolation Pilot Plant 1 January 14, 2015 Agenda Introduction and Workshop Objective WIPP Recovery Approach Interim Performance Measurement Baseline

More information

Final Report. Comparison among different decommissioning funds methodologies for nuclear installations. Country Report Slovenia

Final Report. Comparison among different decommissioning funds methodologies for nuclear installations. Country Report Slovenia Science Centre North Rhine-Westphalia Institute of Work and Technology Institute for Culture Studies Wuppertal Institute for Climate, Environment and Energy Comparison among different decommissioning funds

More information

ELECTRONICS RESTORATION

ELECTRONICS RESTORATION ELECTRONICS RESTORATION THE POWER OF KNOWLEDGE 00:00:00 00:01:00 00:02:00 00:03:00 00:04:00 Recovery Reinstatement electronics restoration 00:02:00 00:03:00 00:04:00 SAVING YOU TIME AND MONEY BELFOR's

More information

Nuclear Safety. Policy 2013-2016

Nuclear Safety. Policy 2013-2016 Nuclear Safety Policy 2013-2016 Nuclear Safety Policy 2013-2016 T he organisational principles and actions defined in the Nuclear Safety Charter and applied within the group have achieved significant improvements

More information

Studsvik, Nyköping, Sweden April 8 10, 2014

Studsvik, Nyköping, Sweden April 8 10, 2014 International Atomic Energy Agency Organisation for Economic Co-operation and Development - Nuclear Energy Agency Studsvik Nuclear AB Symposium on Recycling of Metals arising from Operation and Decommissioning

More information

Radioactive Waste Management the French case

Radioactive Waste Management the French case Radioactive Waste Management the French case Dr Gérald OUZOUNIAN ANDRA, Director Gerald.ouzounian@andra.fr ATOMEXPO 2012 Content General policy principles and rules in France Status of radioactive waste

More information

Executive Director for Operations AUDIT OF NRC S CYBER SECURITY INSPECTION PROGRAM FOR NUCLEAR POWER PLANTS (OIG-14-A-15)

Executive Director for Operations AUDIT OF NRC S CYBER SECURITY INSPECTION PROGRAM FOR NUCLEAR POWER PLANTS (OIG-14-A-15) UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 OFFICE OF THE INSPECTOR GENERAL May 7, 2014 MEMORANDUM TO: Mark A. Satorius Executive Director for Operations FROM: Stephen D. Dingbaum

More information

MANAGEMENT STANDARD CLOSURE PLANNING

MANAGEMENT STANDARD CLOSURE PLANNING AngloGold Ashanti Limited \ Reg. No.1944/017354/06 76 Jeppe Street \ Newtown \ 2001 \ PO Box 62117 \ Marshalltown \ 2107 \ South Africa Tel +27 (0)11 637 6000 \ Fax +27 (0)11 637 6624 \ Website: www.anglogoldashanti.com

More information

Onkalo: Recent policies on the disposal of nuclear waste in Finland

Onkalo: Recent policies on the disposal of nuclear waste in Finland Onkalo: Recent policies on the disposal of nuclear waste in Finland Burkhard Auffermann, Finland Futures Research Centre Climate Policy Strategies and Energy Transition, session on Nuclear Waste Governance

More information

Development of A Risk Informed Approach to D&D Priority Setting Forensic Evaluation of D&D at Oak Ridge with a Focus on K 25 and K 27

Development of A Risk Informed Approach to D&D Priority Setting Forensic Evaluation of D&D at Oak Ridge with a Focus on K 25 and K 27 Development of A Risk Informed Approach to D&D Priority Setting Forensic Evaluation of D&D at Oak Ridge with a Focus on K 25 and K 27 James H. Clarke Henry Mayer Charles W. Powers A Risk Informed Approach

More information

INTERIM WASTE STORE CONSTRUCTION LICENCE EFFECTIVE CONTROL PLAN

INTERIM WASTE STORE CONSTRUCTION LICENCE EFFECTIVE CONTROL PLAN Interim Waste Store Construction Licence Application Document IWS-C-LA-D1 INTERIM WASTE STORE CONSTRUCTION LICENCE EFFECTIVE CONTROL PLAN (rev 2) Prepared By Australian Nuclear Science and Technology Organisation

More information

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities

More information

ORGANISATION OF EASTERN CARIBBEAN STATES INVITATION FOR EXPRESSIONS OF INTEREST

ORGANISATION OF EASTERN CARIBBEAN STATES INVITATION FOR EXPRESSIONS OF INTEREST ORGANISATION OF EASTERN CARIBBEAN STATES INVITATION FOR EXPRESSIONS OF INTEREST Consultancy to Provide Technical Assistance to the OECS Secretariat (OECSSEC) in the Integration of the OECSSEC Staff Competency

More information

Constraints to Implementing Decommissioning and Environmental Remediation in IAEA Member States MAIN OUTCOMES

Constraints to Implementing Decommissioning and Environmental Remediation in IAEA Member States MAIN OUTCOMES 55 th IAEA General Conference Side Event organised by the Waste Technology Section Division of Nuclear Fuel Cycle and Waste Technology IAEA Department of Nuclear Energy Constraints to Implementing Decommissioning

More information

HLG_p(2013-24)_117 ENSREG_REPORT_2013. Report of the European Nuclear Safety Regulator's Group ENSREG

HLG_p(2013-24)_117 ENSREG_REPORT_2013. Report of the European Nuclear Safety Regulator's Group ENSREG Report of the European Nuclear Safety Regulator's Group ENSREG July 2013 CONTENTS EXECUTIVE SUMMARY... 5 1. INTRODUCTION... 9 1.1. Content of the report... 9 1.2. Nuclear Safety in the EU context... 9

More information

Radiological Control Technician Training Technician Qualification Standard

Radiological Control Technician Training Technician Qualification Standard Part 2 of 9 Radiological Control Technician Training Technician Qualification Standard Coordinated and Conducted for the Office of Health, Safety and Security U.S. Department of Energy This page intentionally

More information

Annex 6 Recommendation on Safety Requirements for Contaminated Sites in Flood Risk Areas

Annex 6 Recommendation on Safety Requirements for Contaminated Sites in Flood Risk Areas Support for the Extension of Accident Risk Spots Inventory and Preventive Measures / Final Report Annex 6 Recommendation on Safety Requirements for Contaminated Sites in Flood Risk Areas Final Draft International

More information

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Volume Reduction by Studsvik Nuclear AB Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Streams from Industry The Nuclear Industry generates operational waste during its lifetime as well

More information

National Research Council Canada IP Prosecution and IP License Management Solution Project

National Research Council Canada IP Prosecution and IP License Management Solution Project National Research Council Canada IP Prosecution and IP License Management Solution Project Appendix 1 Statement of Work Version 6.0, 10 December 2013 ii Table of Contents 1. Instructions to Bidders...

More information

NEI 06-13A [Revision 0] Template for an Industry Training Program Description

NEI 06-13A [Revision 0] Template for an Industry Training Program Description NEI 06-13A [Revision 0] Template for an Industry Training Program Description NEI 06-13A [Revision 0] Nuclear Energy Institute Template for an Industry Training Program Description ACKNOWLEDGEMENTS This

More information

SHIRE OF MANJIMUP POSITION DESCRIPTION MANAGER TECHNICAL SERVICES

SHIRE OF MANJIMUP POSITION DESCRIPTION MANAGER TECHNICAL SERVICES SHIRE OF MANJIMUP POSITION DESCRIPTION MANAGER TECHNICAL SERVICES 1. POSITION TITLE Manager Technical Services 2. SALARY Shire of Manjimup Enterprise Agreement 2008 2011 Level C or B (dependant upon experience

More information

A Better Sight for the Environment and Your Budget! Integrated Product Policy: Environmental Product Information for Diagnostic Imaging Devices

A Better Sight for the Environment and Your Budget! Integrated Product Policy: Environmental Product Information for Diagnostic Imaging Devices A Better Sight for the Environment and Your Budget! Integrated Product Policy: Environmental Product Information for Diagnostic Imaging Devices INTEGRATED PRODUCT POLICY Diagnostic Imaging Devices Environmental

More information

Release: 1. BSBPMG509A Manage project procurement

Release: 1. BSBPMG509A Manage project procurement Release: 1 BSBPMG509A Manage project procurement BSBPMG509A Manage project procurement Modification History Not applicable. Unit Descriptor Unit descriptor This unit describes the performance outcomes,

More information

I.A.E.A. Responsible Parties

I.A.E.A. Responsible Parties I.A.E.A. Responsible Parties The principal parties having the main responsibilities for the application of these Regulations shall be: (a) those authorized by registration or license; and (b) employers

More information

Chemical Decontamination and Fluid Handling Services

Chemical Decontamination and Fluid Handling Services Chemical Decontamination and Fluid Handling Services Westinghouse is a global industry expert in decontamination and fluid handling processes, with proven abilities in decontamination and remediation work.

More information

Federal Facility Cleanup. Reggie Cheatham, Director Federal Facilities Restoration and Reuse Office

Federal Facility Cleanup. Reggie Cheatham, Director Federal Facilities Restoration and Reuse Office Federal Facility Cleanup Reggie Cheatham, Director Federal Facilities Restoration and Reuse Office NAS Best Practices Workshop January 9, 2014 Overview of Presentation Facts about Federal Facility Cleanup

More information

U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains

U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains Mary J. Simpson System Concepts 6400 32 nd Northwest, #9 Seattle, WA 98107 USA Joseph J. Simpson System Concepts

More information

Principles for barrier management in the petroleum industry

Principles for barrier management in the petroleum industry 2013 Principles for barrier management in the petroleum industry PSA 29.01.2013 Foreword Barrier management is about ensuring, on a systematic and continuous basis, that barriers are relevant, effective

More information

Invitation to Quote for consultancy services: a review of business planning arrangements

Invitation to Quote for consultancy services: a review of business planning arrangements Invitation to Quote for consultancy services: a review of business planning arrangements 1.0 Overview 1.1 The General Pharmaceutical Council (GPhC) is undertaking a review of the following processes and

More information

SOFT 423: Software Requirements

SOFT 423: Software Requirements SOFT 423: Software Requirements Week 3 Class 1 Finish Elicitation & Start Analysis SOFT 423 Winter 2015 1 Last Class Questionnaires Document Inspection Requirements Stripping Use Cases Scenarios SOFT 423

More information

WHS record keeping requirements

WHS record keeping requirements WHS record keeping requirements The table below provides details of the record keeping requirements in the Model Work Health and Safety Regulation, covering the following areas: Air-borne contaminant levels

More information

Enhancing of Regulatory Control in Georgia Main Trends and Current Developments

Enhancing of Regulatory Control in Georgia Main Trends and Current Developments Enhancing of Regulatory Control in Georgia Main Trends and Current Developments GEORGIA Department of Nuclear and Radiation Safety Ministry of Energy 11.12.2012 J. Mamasakhlisi 1 Regulatory control over

More information

Jülich Biotech Day 2015

Jülich Biotech Day 2015 Jülich Biotech Day 2015 Friday, 30 October 2015, Lecture Theatre of the Central Library, Forschungszentrum Jülich EXHIBITION INFORMATION /BiotechDay Exhibition Information Page 1 Venue The Jülich Biotech

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

Estimation of Nuclear Fuel Cycle Cost and Accident Risk Cost (Statement)

Estimation of Nuclear Fuel Cycle Cost and Accident Risk Cost (Statement) Estimation of Nuclear Fuel Cycle Cost and Accident Risk Cost (Statement) November 10, 2011 Japan Atomic Energy Commission On September 27, the Japan Atomic Energy Commission (JAEC) established the Technical

More information

PRESS RELEASE. Propertize wind-down on track. Utrecht, 3 July 2015

PRESS RELEASE. Propertize wind-down on track. Utrecht, 3 July 2015 PRESS RELEASE Utrecht, 3 July 2015 Propertize wind-down on track On 3 July 2015, Propertize published its 2014 Annual Report. The results show that in 2014, compared to 2013, total net exposure of the

More information

Ensuring Quality Going Down the Supply Chain

Ensuring Quality Going Down the Supply Chain Ensuring Quality Going Down the Supply Chain (Including Vendor Qualification) What is the Role of Operators, Vendors and Regulators? April 21, 2015 DAE-HEE LEE Contents Nuclear Quality Issues The Role

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

INTERNATIONAL ATOMIC ENERGY AGENCY WAGRAMERSTRASSE 5, P.O. BOX 100, A-1400 VIENNA, AUSTRIA FACSIMILE: (+43 1) 26007, TELEPHONE: (+43 1) 2600

INTERNATIONAL ATOMIC ENERGY AGENCY WAGRAMERSTRASSE 5, P.O. BOX 100, A-1400 VIENNA, AUSTRIA FACSIMILE: (+43 1) 26007, TELEPHONE: (+43 1) 2600 INTERNATIONAL ATOMIC ENERGY AGENCY WAGRAMERSTRASSE 5, P.O. BOX 100, A-1400 VIENNA, AUSTRIA FACSIMILE: (+43 1) 26007, TELEPHONE: (+43 1) 2600 - CRAFT - The International Project on COMPLIMENTARY SAFETY

More information

R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I O N S U P P P O R T RFP/JHB/ 037

R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I O N S U P P P O R T RFP/JHB/ 037 P.O. Box 3209, Houghton, 2041 Block A, Riviera Office Park, 6-10 Riviera Road, Riviera R E Q U E S T F O R P R O P O S A L S H U M A N R E S O U R C E S S T R A T E G I C A N D I M P L E M E N T A T I

More information

NEA discussion document

NEA discussion document Unbundling payments for radioisotopes from radiopharmaceuticals and from diagnostic procedures: A tool to support the implementation of full-cost recovery NEA discussion document This discussion paper

More information

Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office

Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office Bristol Village Activity Center Waverly, Ohio October 27,

More information

TOWARDS UNITY IN ACTION UNITED NATIONS REPUBLIC OF MOLDOVA PARTNERSHIP FRAMEWORK 2013 2017 BUSINESS OPERATIONS STRATEGY

TOWARDS UNITY IN ACTION UNITED NATIONS REPUBLIC OF MOLDOVA PARTNERSHIP FRAMEWORK 2013 2017 BUSINESS OPERATIONS STRATEGY TOWARDS UNITY IN ACTION UNITED NATIONS REPUBLIC OF MOLDOVA PARTNERSHIP FRAMEWORK 2013 2017 BUSINESS OPERATIONS STRATEGY Foreword As the UN in Moldova moves towards Delivering as One, the realization of

More information

Project Management and Planning

Project Management and Planning CO-ORDINATION NETWORK EC - CND EC - CND ON DECOMMISSIONING Project Management and Planning Final Report December 2008 AF-Colenco Ltd, Täfernstrasse 26, CH-5405 Baden, Switzerland Nuclear Research Institute

More information

IAEA Safety Standards for Regulatory Activities

IAEA Safety Standards for Regulatory Activities Safety Standards for Regulatory Activities April 2010 Gustavo Caruso Regulatory Activities Section Division of Nuclear Installation Safety International Atomic Energy Agency Content Safety Standards and

More information

Nuclear third-party insurance and liability.

Nuclear third-party insurance and liability. ROADMAP TITLE OF THE INITIATIVE Nuclear third-party insurance and liability. LEAD DG RESPONSIBLE UNIT DG ENER.D.1 DATE OF ROADMAP 08 / 2013 This indicative roadmap is provided for information purposes

More information

New legislation in the nuclear field in Sweden

New legislation in the nuclear field in Sweden 1 New legislation in the nuclear field in Sweden A presentation at INLA Congress 2012 (Manchester) - 11 October 2012 by Ingvar Persson, Swedish National Council for Nuclear Waste and PP 1 Presentation

More information

THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM

THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM G. HOLT Magnox Electric pic, Berkeley Centre, Berkeley, Gloucestershire, United Kingdom Abstract

More information

2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster

2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster 2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of

More information

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project

REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon

More information

International Experience with Stakeholder Involvement in the Rehabilitation of Contaminated Areas. Dr. Ted Lazo OECD Nuclear Energy Agency

International Experience with Stakeholder Involvement in the Rehabilitation of Contaminated Areas. Dr. Ted Lazo OECD Nuclear Energy Agency International Experience with Stakeholder Involvement in the Rehabilitation of Contaminated Areas Dr. Ted Lazo OECD Nuclear Energy Agency Objectives of Stakeholder Involvement Incorporate public values

More information

NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission

NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission Background The U.S. Nuclear Regulatory Commission (NRC)

More information

Building on the Basics

Building on the Basics Building on the Basics Towards a Strategy for Continuing Interprofessional Development Hugh Barr, PhD President Centre For The Advancement Of Interprofessional Education (CAIPE) Continuing Interprofessional

More information

REPORTING ACCOUNTANTS WORK ON FINANCIAL REPORTING PROCEDURES. Financing Change initiative

REPORTING ACCOUNTANTS WORK ON FINANCIAL REPORTING PROCEDURES. Financing Change initiative REPORTING ACCOUNTANTS WORK ON FINANCIAL REPORTING PROCEDURES consultation PAPER Financing Change initiative inspiring CONFIdENCE icaew.com/financingchange ICAEW operates under a Royal Charter, working

More information

Appendix J3 - Outline Fuel Spill Contingency Response Plan. Control room receives call on fuel spill from staff or public

Appendix J3 - Outline Fuel Spill Contingency Response Plan. Control room receives call on fuel spill from staff or public Appendix J3 - Outline Fuel Spill Contingency Response Plan Control room receives call on fuel spill from staff or public Initial Actions to be taken after Fuel Spill reported Identification of the source

More information

TR CMS 101:2011. Standard for Compliance Management Systems (CMS)

TR CMS 101:2011. Standard for Compliance Management Systems (CMS) TR CMS 101:2011 Standard for Compliance Management Systems (CMS) of TÜV Rheinland, Cologne Total scope: 22 pages Contents Foreword....- 3-0 Introduction... - 5-1 Field of application... - 5-2 Aims of the

More information

Life Cycle Asset Management

Life Cycle Asset Management Rx Whitepaper CONTENTS PAGE 1: Overview PAGE 1-2: Foundational Elements Management Strategy Development Organizational Design Long-term Asset Planning PAGE 2-7: Risk Management Concept and Design Construction

More information

6. The partners share the intention to work together via regular meetings/working groups to solve open issues.

6. The partners share the intention to work together via regular meetings/working groups to solve open issues. The purpose of this Letter of Intent is to lay down a common understanding shared between the national biomethane registries regarding their cooperation towards a cross-border trade of biomethane. 1. The

More information

EU F-Gas Regulation Guidance Information Sheet 14: Refrigeration, Air-Conditioning and Heat Pump Contractors

EU F-Gas Regulation Guidance Information Sheet 14: Refrigeration, Air-Conditioning and Heat Pump Contractors Information Sheet 14: Refrigeration, Air-Conditioning and Heat Pump Contractors Target audience for this Information Sheet This Information Sheet is aimed at contractors that carry out installation, maintenance

More information

TOR. Developing Database System for the NGOs Directorate. National Consultant. 180 days (over a period of 6 months)

TOR. Developing Database System for the NGOs Directorate. National Consultant. 180 days (over a period of 6 months) TOR Developing Database System for the NGOs Directorate National Consultant Period of assignment/services: Duty Station: 180 days (over a period of 6 months) Baghdad Estimated Starting Date: 1 May Contract

More information

GUIDELINES ON MEDICAL DEVICES

GUIDELINES ON MEDICAL DEVICES EUROPEAN COMMISSION DIRECTORATE GENERAL for HEALTH and CONSUMERS Consumer Affairs Health technology and Cosmetics MEDDEV 2.12/2 rev2 January 2012 GUIDELINES ON MEDICAL DEVICES POST MARKET CLINICAL FOLLOW-UP

More information

Advanced Financial Management

Advanced Financial Management Progress Test 2 Advanced Financial Management P4AFM-PT2-Z14-A Answers & Marking Scheme 2014 DeVry/Becker Educational Development Corp. Tutorial note: the answers below are more comprehensive than would

More information

International University of Monaco 27/04/2012 14:55 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

International University of Monaco 27/04/2012 14:55 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05 International University of Monaco 27/04/12 14:55 - Page 1 Master in International Business and Global Affairs - from 30 avril to 05 mai 12 Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday

More information

International University of Monaco 21/05/2012 16:01 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

International University of Monaco 21/05/2012 16:01 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05 International University of Monaco 21/05/12 16:01 - Page 1 Master in International Sport Business and Management - from 30 avril to 05 mai 12 Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday

More information

Mongolia: Fifth Health Sector Development Project

Mongolia: Fifth Health Sector Development Project Fifth Health Sector Development Project (RRP MON 45009) Subsector Analysis (Summary): Medical Waste Management Project Number: 45009 Loan Number: XXXX November 2012 Mongolia: Fifth Health Sector Development

More information

Background and Context. How the Topic was Handled

Background and Context. How the Topic was Handled Background and Context Alexander Litvinenko died on 23 November 2006 as a result of acute radiation poisoning. The radioactive agent involved was polonium (210Po) which was found to have contaminated a

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ONR GUIDE LC17 Management Systems Document Type: ONR Nuclear Safety Technical Inspection Guide Unique Document ID and Revision No: NS-INSP-GD-017 Revision 2 Date Issued: November 2012 Review Date: November

More information

SUPPLY CHAIN MANAGEMENT

SUPPLY CHAIN MANAGEMENT Phone:65 6829 2319 Email: enquiries@pdtraining.com.sg SUPPLY CHAIN MANAGEMENT Generate a group quote today or register now for the next public course date COURSE LENGTH: 1.0 DAYS This course by pdtraining

More information