Manchester City Council Report for Information. Resources and Governance Overview and Scrutiny Committee- 15 December 2011



Similar documents
Manchester City Council Report for Information. Report to: Resource and Governance Overview and Scrutiny Committee - 15 December 2011

Managing ICT contracts in central government. An update

HEAD OF STRATEGIC INFORMATION & TECHNOLOGY SUBJECT: REVIEW OF CORPORATE TECHNOLOGY SENIOR MANAGEMENT ROLES

Annual Governance Statement

Project Appraisal and Scrutiny Committee Recommendation. , file storage system and server upgrades

Programme Governance and Management Plan Version 2

Contract Management Guideline

Cambridge City Council

POSITION INFORMATION DOCUMENT

Replacement of ICT Systems (Software) Used Exclusively within the Environmental Services Department (Highways and Transport, Technology and Recycling)

Customer Engagement Strategy 2015/ /18

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013.

Manchester City Council Report for Resolution. Strategic Director, Strategic Development

Manchester City Council Report for Resolution. Budget Proposals for the Corporate Core (Chief Executive s and Corporate Services)

EAST RIDING OF YORKSHIRE COUNCIL

a guide to contract management for PFI and PPP projects

RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION

JOB DESCRIPTION. ICT Business Analyst. All posts currently covered by National Joint Council {NJC} conditions of service.

Staffordshire Change Management Plan

Manchester City Council Report for Resolution. Greater Manchester Housing Investment Fund. The Chief Executive, City Treasurer and City Solicitor

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.

Wolverhampton City Council

Informatics: The future. An organisational summary

JOB DESCRIPTION. Procurement and Contract Management Advisor. Commercial Procurement, Property, and Contracts Team

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development)

Plymouth Council & Asset Management

Business Cases: A Summary Of Strategic & Cost Effective Project Management

Manchester City Council

Portfolio: Transformation, Modernisation and Regulation

Part B1: Business case developing the business case

Confident in our Future, Risk Management Policy Statement and Strategy

Project Appraisal and Scrutiny Committee Recommendation STRATEGY & RESOURCES 23 MARCH 2015

Project Assessment Framework Establish service capability

Case Study Addressing the Challenges of Project and Programme Management Manchester City Council

Management of Business Support Service Contracts

Medicines and Healthcare products Regulatory Agency

How To Manage A County Council Contract Management

2.3 Overall the Council s budget for the provision of these services is just under 2.7m.

PUBLIC REALM COMMUNITY SAFETY, ECONOMIC DEVELOPMENT AND REGENERATION OVERVIEW AND SCRUTINY COMMITTEE

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 9 September 2014 Item No. 6

Property and Asset Management

UNSOLICITED PROPOSALS

Audit Committee. Directors Report. Gary Hughes Chairman, Audit Committee. Gary Hughes Chairman, Audit Committee

Staff Survey A Summary of Service

A joint plan to foster a healthy and vibrant Healthcare IT market. Intellect & DH Informatics Directorate. Initial Issue

SOMERSET COUNTY COUNCIL KEY DECISION TAKEN BY THE COMMERCIAL AND BUSINESS SERVICES DIRECTOR

Governments implement PPP programmes in the healthcare sector for one or more of a number of reasons:

UoD IT Job Description

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report.

Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 April 2012

Tasmanian Cloud & Government use of public cloud services

HIGHLANDS AND ISLANDS PATHFINDER BROADBAND PROCUREMENT: APPOINTMENT OF PREFERRED SUPPLIER

4 Adoption of Asset Management Policy and Strategy

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

ADVERT POSITION: SPECIALIST: CONTRACTS MANAGEMENT JOB LEVEL: 6 DURATION 3 YEAR CONTRACT LOCATION: NATIONAL OFFICE PORTFOLIO: DSU

HEFCW Welsh Language Scheme th Annual Compliance Report

Draft Annual Governance Statement

ESKITP Manage IT service delivery performance metrics

Agency Board Meeting 28 July 2015

Jenny Obee, Head of Information Management Tel: Micailah Fleming, IT Director

Private sector partnering in the police service

Manchester City Council Report For Resolution. Report to: Personnel Committee - 25th September 2012

The Gateway Review Process

Quick Guide: Managing ICT Risk for Business

TRUST BOARD. Date of Meeting: 05/04/2011 Enclosure: 5

Risk management in public procurement of innovation

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

Position Director of Business Resources and Solutions Grade 7 Department & Location

Agenda Item No. 4. Policy and Resources Select Committee. 11 October Contract Procurement and Contract Management

Considerations for firms thinking of using third-party technology (off-the-shelf) banking solutions

(1) To approve the proposals set out in paragraphs to ensure greater transparency of partnership board activity; and

Specification Document (11/1023)

Ian Parry, Deputy Leader and Cabinet Member for Strategy, Finance and Corporate Issues said,

Procurement and Contract Management Strategy

Manchester City Council. Report For Resolution

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee

Asset Management Services

CARE AT HOME SERVICE IMPROVEMENT PLAN UPDATE

Communication and Engagement Strategy Final Version 30 th June 2014

Position Description. Te Aho o Te Kura Pounamu. Purpose Statement

Senate. SEN15-P17 11 March Paper Title: Enhancing Information Governance at Loughborough University

University of Brighton Sustainable Procurement Strategy

Manchester City Council

Procurement Capability Standards

Single Stage Light Business Case Template

Trust Board Report. Review of the effectiveness of the IM&T Committee

Agreement for the provision of IT Management Services and IT Services

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

State Services Commission. Independent Review of the Earthquake Commission s Customer Satisfaction Survey

Derbyshire County Council Performance and Improvement Framework. January 2012

Environmental management and reporting involves identifying,

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2014

TEWKESBURY BOROUGH COUNCIL

IT Risk Assessment Action Plan. South Staffordshire District Council Audit 2010/11

How are companies currently changing their facilities management delivery model...?

MPA/MPS PROCUREMENT STRATEGY TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT

Agenda Item No.6 (j) DERBYSHIRE COUNTY COUNCIL CABINET. Report of the Director of Transformation

POSITION DESCRIPTION

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note April 2000

Transcription:

Manchester City Council Report for Information Report To: Subject: Report of: Resources and Governance Overview and Scrutiny Committee- 15 December 2011 Contract Management City Treasurer Summary This report provides an update on the work being undertaken to strengthen the Council s approach to Contract Management. Recommendations Members are asked to note the progress made to-date on this project. Wards Affected: All Contact Officers: Name: Richard Paver Position: City Treasurer Telephone: 234 3564 E-mail: r.paver@manchester.gov.uk Name: Ian Brown Position: Head of Corporate Procurement Telephone: 234 3265 E-mail: i.brown@manchester.gov.uk Name: Chris Loveman Position: Project Manager Telephone: 245 7556 E-Mail: c.loveman@manchester.gov.uk Background documents (available for public inspection): Reports to the Resources and Governance Overview and Scrutiny Committee: 13 January 2011: Contract Management. 23 June 2011: Commissioning and Contract Management in Children s Services. 17 November 2011: Contract Management and Commissioning, Adults. 7

1.0 Introduction 1.1 This is the fourth report on contract management submitted to the Committee for consideration following the reports in January, June and November 2011, which have provided progress reports on the different aspects of the project. 1.2 The vision for Contract Management within the Council is to establish best in class contract management processes across the Council, applied in a consistent and effective manner to ensure value for money is achieved from all our contract activities. 1.3 The project s aim for contract management is to ensure that all officers who have responsibility for managing contracts have the right skills and support to ensure delivery of contracted services that are both effective in terms of service outcomes and are cost-effective throughout the life of the contract period. 1.4 The project will establish lessons learned and best practices programmes to streamline and improve contract management processes, standards and documentation, ensuring continuous improvement throughout all the Council s activities relating to contracts. 2.0 Background 2.1 The Contract Management Project Team was established within the Transformation Team in June 2010 and the Senior Responsible Officer for the Project is the City Treasurer. 2.2 The savings target set for the project is 1M in 2011/12 and 3M in 2012/13. 2.3 The Council currently spends around 780M each year with external providers across a wide range of goods and services to support the day-today activities of the Council for both capital and revenue requirements. 2.4 Following comprehensive research on contract management across various public and private sector bodies and the undertaking of a detailed assessment of contract management capabilities within the Council, key themes were identified which together help to define best practice in contract management: Early involvement of all stakeholders in the procurement process to develop clear, concise specifications Strong contract governance Close management of key performance indicators Control of payment mechanism Robust risk management Early dispute resolution Well documented contract change control and management 8

Highly developed supplier relationship management and continuous improvement culture 2.5 Developing strong contract management functions within the Council will deliver major benefits, including: Improved supplier performance improvement and better outcomes for client departments Improved supplier relations Cost reduction and cost recovery Reducing risks of supplier underperformance or failure Reducing the risk of challenge on procurement processes 3.0 Progress To-date 3.1 The Project Team identified the following key workstreams to improve contract management across the Council: 1. Review the structure: Design and form a contract management support function and its interface with the individual Directorates 2. Assess the Support Systems: Create an information repository to support contract performance monitoring 3. Support Review of Skills and Processes: Invest in the skills and understanding of contract management staff, and identify standard processes and build them into Business as Usual procedures and practice. 3.2 In order to support these workstreams, two key activities were necessary: 1. Establish the contract management support function within the existing Corporate Procurement resources 2. Engage external support from the market to undertake forensic reviews of high volume, high risk contracts. 4.0 The Contract Management Support Function Progress To-Date 4.1 The Contract Management Support Function 4.1.1 The monitoring and control of contracts, once they are awarded, is currently undertaken within each of the individual directorates and the project has shown that there are currently many good examples of best practice within the Council, but overall the processes and procedures are not being applied consistently. 4.1.2 Proactive management of contracts within the Council requires some upskilling of staff and supporting staff on key contracts to implement improved contract management. However, it became clear from the review work that it is essential to leave the key decision-making with subject matter experts in the Directorates with support on commercial issues being 9

provided by Corporate Procurement on a structured basis through regular contract reviews. 4.1.3 The Project Team sought the advice of the Directorates and key corporate functions to determine the optimum solution for contract management. From this consultation, it was clear the essential nature of the contract management support function should be modelled on the following key themes: Reporting to the Head of Corporate Procurement Utilising the existing staff within Procurement All staff managing contracts remain in Directorates Key strategic decisions will be taken jointly by the Directorates and the Corporate Centre to ensure all aspects of contract management are considered. Corporate Procurement is responsible for training programmes and process-checking contract management staff Corporate Procurement provides support and advice to Directorates on all major contracts Corporate Procurement oversees the contract process throughout the life of the contracts 4.1.4 The Corporate Procurement Team structure was reorganised in October 2011 to enable this support role to be formalised at no additional cost. 4.2 Forensic Review of High Value, High Risk Contracts 4.2.1 While the Contract Management Support Function concentrated on supporting Directorates to deliver the significant savings required to balance their reduced budgets in 2011/12, to deliver further benefits, the project team went out to tender to bring in external expertise to provide a forensic audit on a number of contract area s. The remit was to examine selected MCC contracts, detect opportunities for savings in them, and help the Council realise that benefit. 4.2.2 The service was procured through a competitive process in full compliance with European Procurement rules. 4.2.3 The two successful companies resulting from the tender process were Ernst & Young and KPMG. 4.2.4 Ernst & Young have been working with the project team and relevant Directorate staff on three contracts: 4.2.5 The commercial property management contract (Jacobs), where the focus is to improve performance management of the supplier, in order to deliver improved returns from Manchester s commercial estate. 10

4.2.6 The Streetlighting PFI (Amey), where the focus has been to review the detail of the 25-year contract, to identify potential savings throughout the life of the contract 4.2.7 Buildings maintenance (Manchester Working Limited), where the focus todate is on a detailed forensic analysis of spend since 2006 to identify potential savings. 4.2.8 In addition, it has recently been agreed with the Strategic Director Adults to extend the work of Ernst & Young in to the Adult Social Care spend. 4.2.9 KPMG have recently commenced work on reviewing seven of the Council s major ICT contracts which will also include a review of the Capita Building Schools for the Future contract, 4.3 The governance of these contract reviews is through the Council s Commercial Board, chaired by the Treasurer and, based on the work undertaken to-date, it is anticipated that the outcome from these reviews will deliver the targeted savings of 1M in 2011/12 and of 3M in 2012/13. 5.0 Next Steps 5.1 Building on the work already undertaken in the Adults and Childrens Directorates, work on planning the revised contract management function within Neighbourhood Services and the Corporate Core has commenced and will be complete by the 31 March 2012. 5.2 Training workshops for all Contract Managers are being arranged commencing in January and will include the provision of a best practice tool kit for contract management. Further workshops will be arranged throughout the year led by Corporate Procurement. 5.3 In relation to the use of IT systems to support the process, the Adults Directorate have created an inhouse information tool used for performance management of suppliers. This tool is being adapted for potential wider use across the Council as an interim measure pending the SAP upgrade in 2012 which will enable MCC to consider the use of the latest contract management system within SAP. 5.4 Finalise the work with Ernst & Young and KPMG to deliver the required level of savings for 2011/12 and 2012/13. 5.5 Corporate Procurement and the Transformation Team are working closely with both Ernst & Young and KPMG to ensure skills are transferred to Council staff to increase our staff capacity to undertake these reviews in the future. 6.0 Recommendations 11

6.1 Members are asked to note the progress made to date relating to delivering the improvements to contract management and the targeted savings. 12