EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC



Similar documents
Appendix 18 NEC3 Options

NEC3: The Engineering and Construction Contract An overview

NEC Users Group Workshop Defined Cost

NEC ECC Option F ERF 2066 Duynefontein building refurbishment

How To Write A Contract

Guidance Notes for the NEC Engineering and Construction Contract

NEC3 Engineering & Construction Contract An Overview

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

PRACTICE NOTES FOR QUANTITY SURVEYORS

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

The New Standard Construction Contracts: NZS3910, 3916 and 3917

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

JCT Standard Building Contract SBC/Q

Producing a programme under the NEC form of contract

Letters, Instructions, etc.

Bills of Quantity. D. Atkinson December Nature of Bills

Guideline for Construction Contractor Performance Reporting

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management

REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE

6.0 Procurement procedure 1 Infrastructure

ANNEX 8 Contract Management Strategy

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011

1 Supplement: IAS 11 Construction contracts

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Project Management Guide

Managing programme change on an NEC3 form of contract

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

0 - Initial Services

Activity Schedules in the NEC3 Engineering and Construction Contract

These Terms & Conditions may only be used by members of Koninklijke Metaalunie.

PROJECT MANAGEMENT FRAMEWORK

Schedule 11. The Transfer of Undertakings (Protection of Employment) Regulations 2006

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

GREENFIELD MIDDLE SCHOOL ROOF PROJECT

DIRECTORATE OF ESTATES & FACILITIES

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept

ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS Part A

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

Regional Council of Goyder

Q&As Regarding Workers Who Perform Work Activities Involved in Surveying

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

How to get value for money from service providers on major projects

HOW CHARGEABILITY IS DETERMINED AND APPLIED

SYDNEY S NORTH SHORE EXTENSION AND RENOVATIONS SPECIALIST

Contract and Vendor Management Guide

Thames Water Utilities Limited. Settlement deed

Progressive Acquisition and the RUP Part III: Contracting Basics

Subvented Social Welfare Non-Governmental Organisations Procurement Procedures

GENERAL SALES CONDITIONS POS SERVICE HOLLAND BV (Pty Ltd, Dutch Company Status)

Description: Publication Date: 9/21/2015. Closing Date/Time: Open Until Contracted

Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry

HONG KONG HOUSING AUTHORITY GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS 2013 EDITION

Building your new home. 8 simple steps to settlement

Appendix A8.1: Service Level Agreement Contents

Malta Resources Authority. Call for Quotations

QUOTE FOR THE SUPPLY AND INSTALLATION OF METAL GATES AT TRIQ IL-KUCCARD, HAL SAFI

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems).

Post Award Accounting System Audit at Nonmajor Contractors


Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities

General Terms of Purchase. of HAN University of Applied Sciences

香 港 特 別 行 政 區 政 府. The Government of the Hong Kong Special Administrative Region. Development Bureau Technical Circular (Works) No.

King Fahd University of Petroleum and Minerals

FOR INFORMATION PURPOSES ONLY

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES

THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $ EDITION

MDB Harmonised Particular Conditions

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES

Contractor Performance Report Scoring Guide

Republic of Zambia Ministry of Works and Supply Roads Department Labor-based Routine Maintenance Contract Agreement. C. Kalangwa - Box 33545, Lusaka

Comparative Study on Quality Assurance of Construction Project in Taiwan and Japan

QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC.

A JCT 2011 Minor Works Building Contract

Code of Practice for Agents Undertaking Renovation Grants

GUIDELINES FOR AUGUST 1995

Warranty Agreement. the following agreement is concluded relating to the reimbursement of warranty costs:

Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners

The Overview of Tanzania Legal Framework on Contract Management

CONTRACT MANAGEMENT COURSES

Appendix 23. Sample of Invitation Letter for Submission of Fee Proposal for Acting as a Project Consultant for Maintenance and Improvement Works

Diverted Profits Tax: Guidance

COMPETITIVE TENDER 153/16 FOR PROVISION OF DIGITAL MARKETING SERVICES. Closing Date of Tender: 29 February 2016.

Health and safety in construction procurement

Building Agreement For Minor Building work

Transcription:

2 June 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Change of Consultant s Role & Highlights of Contract Management Kelvin N. F. Lau Associate Vice President AGENDA Role of consultant in the Pilot Contract Highlights of Contract Management Compensation Event / Defect / Payment Feedback Photomontage of the proposed park under DC2008/02 2 1

Difference in Project Organization Project Organization Employer (DSD) Engineer (B&V) Contractor (CW) NEC ECC Project Organization Employer (DSD) Project Manager (DSD/DP) Supervisor (B&V) Contractor (CW) 3 Document Framework Vs NEC3 Option C Notes to Tenderers General & Special Conditions of Tender General Conditions of Contract Special Conditions of Contract Articles of Agreement NEC Notes to Tenderers General & Special Conditions of Tender Core Clauses & Secondary Option Clauses Z Clauses (i.e. Additional Conditions of Contract) Articles of Agreement - Schedule of Articles of Agreement BQ Form of Tender Activity Schedule Form of Tender Appendix to Form of Tender Contract Data Part 1 - Contract Data Part 2 Site Investigation Information (if any) (Not forming part of Contract) General & Particular Specifications Drawings Site Information Works Information Works Information 4 2

Role of the Consultant in the Pilot Contract Title of B&V in this Pilot Contract RSS in this Pilot Contract Role NEC Supervisor Supervisor s Representative (RSS post RE) Offering support to the Project Manager in execution of the day today project management Engineer Engineer s Representative Purpose of NEC conditions of contract Carry out the duties and exercise the power specified in the Contract. i.e. contract administration; watch & inspect the Works; test & examine materials; workmanship.etc Foreword to NEC conditions Stimulating good management and relationship between the parties to contract and, hence, of the work included in the contract 5 Changes in Rules changes in mindset The Contract is to be run by mutual trust and cooperation developed amongst Client, Consultant & Contractor with the interests of the project. Emphasis on effective communications new rules for responding on project matters Transparency of Information and Decision Making Risks and Responsibilities Sharing concept Payment = Contractor s actual expenses + Fees 6 3

Compensation Event (NEC characteristic) A single and unified procedure for all issues related to TIME & COST change Procedure designed with an aim to Quick Settlement (pre event agreement) Typical types of Compensation Events are listed in NEC ECC Core Clauses 60 7 Compensation Event Notification of CE NEC ECC PM within one week replies a Notification of CE (ECC61.4) No response time requirement on the Engineer More favourable to Contractor 8 4

Compensation Event compared with VO and Claim NEC ECC Quotation for CE ALWAYS covers both time and cost (ECC62.2) EOT and money are separately considered No differentiation as VO or Claim VO $ only Claim Time or Time + $ More efficient project management 9 Compensation Event compared with VO and Claim NEC ECC An Agreement process between PM and Contractor Valuation or Assessment by the Engineer Definite timeframe for both PM and Contractor No timeframe for reply Better Co operation & Quicker finalization More resources & focus onto the project works Average agreement time in FMR : 52 days 10 5

Compensation Event Assessment of Quotation for CE NEC ECC Changes to Prices are effect of the CE upon COST + Fee VO Valuation is based on contract rates (BQ rates, adjusted BQ rates or star rates as per 61) COMPENSATION principle(cost + fee) Open book account Cost information readily available Easier Agreement of Quotation + Solid Back up 11 Compensation Event Assessment of Quotation for CE CE Quotation = Estimated Actual Cost* + Fee (*Estimated cost includes Risk) Agreed CE Quotation = Change to the Prices Original ceiling (Target Price) Adjusted ceiling Agreed CE quotations = Change to the Prices CE1 CE2 CE3 Pain Gain share between Employer and Contractor Based on Final Adjusted ceiling vs Actual Cost 12 6

Compensation Event Neutral Event? There is no Neutral Event All CE covers Time + $ (vs : inclement weather, utility work, special circumstances Time only) 9 nos. CE for inclement weather agreed for DC/2008/02 CE for inclement weather covers increase in Prices more competitive bids for the Employer in long term 13 Compensation Event Assessment of Prolongation Costs NEC ECC ECC Schedule of cost components covers information on preliminaries Each IP submission contains detailed breakdown of salaries, allowance, utility charges, etc No information regarding preliminaries is provided Contractor is to give detailed particulars of the rate or sum claimed only after notification of claim Open book account Reliable Cost Data Easier Agreement 14 7

Handling of Defective Works Day to Day Tasks Issue of Notification of Defective Works Checking on Defect rectification Ensure Defects rectified within defect correction period (12 weeks after Completion) 15 Handling of Defective Works Cost of defect correction Included as part of Defined Cost Exception: Disallowed Cost (Defect corrected after Completion, Defect due to Contractor not complying constraints in Works Information) Incentive for earlier correction of Defects Focus on Clearing the Defects (Not Blame) Advance Defect notification to assist Contractor 16 8

Handling of Payment B&V 42 January February 2012 Disallowed Cost (Examples) Defects correction after completion (e.g. defect repair for roundabout) Not justified by the Contractor s record (e.g. payment record missing) Resources not used to Provide the Works (e.g. extra staff or unreasonable material wastage) Resources not taken away from the Working Area after PM s request (e.g. idle water pumps) 17 Handling of Payment Payment Mechanism B&V 42 January February 2012 Payment based on the PAID elements of Defined Cost Quick settlement of wages & payment to subcontractors and suppliers 18 9

Handling of Payment Price Adjustment for Inflation B&V 42 January February 2012 Calculated and Frozen at each IP to offset the effect of fluctuation Adjustment to Target Price (not amount due) Sharing of Adjustment to Target Price (what if Defined Cost >110%?) 19 Cutting Contract Cost together Reduction in Defined Cost PM, Supervisor and Contractor joining hands to streamline work procedure for cost saving E.g. TTA for roundabout resurfacing works (changed from 8 stages to 4 stages with joint effort) E.g. Existing nullah wall to be demolished (part of the existing wall retained and encased by permanent structure) E.g. Use of couplers specified in contract (proposal for use of starter bar with corrosion protection coating accepted for cost saving) 20 10

Feedback from Trial Experience In General More Engineering and Project Orientated Real Partnering ( building trust not hatred ) Contract Finalization Easier settlement due to Open Book Account system Stipulated timeframe makes agreement process start when things are still fresh (right people and right time) Variations Quick settlement & Compensation Principle allows focus on factual issue and less on guessing tactics Better decision making on project management (Contractor, Client & Consultant views taken) 21 Up to date Observations from Fuk Man Road NEC Main Contractor & Subcontractors Successfully made their money from the contract Consultant Less Conflicts More Job Satisfaction Client Save time Save money?? 22 11

12