1 Introduction to NEC3 Course agenda Session 1 Background and underlying principles the concept NEC characteristics NEC family including typical NEC arrangements Key NEC3 Engineering and Construction Contract (ECC) features Course objectives Delegates should: Understand the philosophy of NEC Appreciate the extent of the NEC family Appreciate a few key features of NEC contracts NEC3:Introduction to the NEC3 nec 04/2013 Page 1
2 A bit about NEC history What is the NEC? How the NEC was developed? The role of the Institution of Civil Engineers The NEC Panel Dr. Martin Barnes OBE NEC Creator The development of the NEC 1985: ICE Industry Review 1991: Consultative edition 1993: NEC1 1994: Latham Report 1995: NEC2 2005: NEC3 NEC characteristics NEC is a family of standard contracts, each of which has these characteristics Stimulates good management Can be used in wide variety of commercial situations, for wide variety of types of work and in any location A clear and simple document - using language and structure which are straightforward and easily understood NEC3:Introduction to the NEC3 nec 04/2013 Page 2
3 NEC characteristics Flexibility Multi-disciplinary Responsibility for design by either party Choice of pricing mechanisms from lump sum to cost plus Bolt on secondary Options that allow an Employer to build up the contract to suit Allocate risks to suit For international use Y(UK)1, Y(UK)2 X4 X3 X2 X1 W1 X6 X5 Z Y(UK)3 X16 X15 X14 X13 X12 X7 W2 X20 X18 X17 A B C D E F additional conditions jurisdiction-specific Options secondary Options dispute resolution Option main (payment) Option 1-9 core clauses Drafting style NEC characteristics Clarity and simplicity Ordinary language Minimal legalistic phrases Minimised subjective phrases such as fair, reasonable and opinion Reasons for decisions stated User friendly structure NEC3:Introduction to the NEC3 nec 04/2013 Page 3
4 Drafting style Drafting objectives try to keep sentence length below 40 words use words the readers are likely to understand use only as many words as are really needed prefer the active voice unless there is good reason for using the passive voice Drafting style Drafting objectives use the clearest, crispest, liveliest verbs use vertical lists to break up complicated text put points positively when you can reduce cross references to the minimum NEC characteristics Stimulus to good management NOT a contract for the bottom drawer! Each procedure designed to contribute Clear division of roles Up-to-date programme Early warning common sense risk management Compensation events NEC3:Introduction to the NEC3 nec 04/2013 Page 4
5 Supply High Project Complexity Low PSC PSSC Professional Services Professional Services Contract Short Contract business case SC & SSC Supply Contract & Supply Short Contract ECC Engineering and Construction Contract ECS Engineering and Construction Subcontract ECSC Engineering and Construction Short Contract ECSS Engineering and Construction Short Subcontract Framework Contract Adjudicator s Contract design construction NEC family TSC Term Service Contract TSSC Term Service Short Contract operation NEC family Guidance Notes & Flow Charts To support all the NEC3 contracts NEC Procurement and Contract Strategies A guide for users in application of NEC3 contracts in different procurement and contract strategies NEC family Project Manager Designer Supervisor Employer Contractor ECC Adjudicator AC Typical Employer designed arrangement Subcontractor ECS or ECSS Supplier SC or SSC NEC3:Introduction to the NEC3 nec 04/2013 Page 5
6 NEC family Project Manager Employer Adjudicator AC Supervisor Contractor ECC Typical design & build arrangement Subcontractor ECS or ECSS Designer Supplier SC or SSC Key ECC features The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation (10.1) Key ECC features Works Information (11.2(19)) specifies and describes the works or states any constraints on how the Contractor Provides the Works Site Information (11.2(16)) describes the Site and its surroundings NEC3:Introduction to the NEC3 nec 04/2013 Page 6
7 Key ECC features early warning duty to warn of events that may affect key project objectives requirement to discuss and agree best way forward sanctions if early warning not given encourages proactive risk management talk to each other, it s a good thing! Key ECC features time control - programme clear and objective requirement for a detailed programme with statement of resources regular updates which provide an essential tool for the parties to manage the project and to notify and manage the effect of any problems, delays, etc. Key ECC features Compensation events only way to change price and/or Completion Date all in one place (almost!) and treated in the same way cost: assessed at forecast change in cost time: forecast delay based on latest Accepted Programme all to tight and defined timescales NEC3:Introduction to the NEC3 nec 04/2013 Page 7
8 Summary Objectives met? Next steps? Online test Were the course objectives met? Delegates should: Understand the philosophy of NEC Appreciate the extent of the NEC family Appreciate a few key features of NEC contracts Online test NEC3:Introduction to the NEC3 nec 04/2013 Page 8
9 Need more information? Contact the NEC support team t: +44 (0) e: NEC3:Introduction to the NEC3 nec 04/2013 Page 9
How To Write A Contract
Commercial Management the NEC Way Hong Kong Institute of Surveyors Ian.Heaphy@turntown.com Mark.Lyddon@turntown.com, July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing
More informationNEC3 Engineering & Construction Contract An Overview
NEC3 Engineering & Construction Contract An Overview Delivering Professional Solutions to the Property Industry Michael Dunn FRICS FCIArb LLB LLM Director of Contract Services T: 01274 693 622 E: m.dunn@rpp.co.uk
More informationNEC3: The Engineering and Construction Contract An overview
NEC3: The Engineering and Construction Contract An overview Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the
More informationGETTING STARTED WITH THE NEC3
GETTING STARTED WITH THE NEC3 NEC3 TERM SERVICE CONTRACT (TSC) AND NEC3 TERM SERVICES SHORT CONTRACT (TSSC) Supported by: Published by the British Institute of Facilities Management April 2015 Introduction
More informationGuidance Notes for the NEC Engineering and Construction Contract
The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors
More informationNEC3: Early Warning and Compensation Events
NEC3: Early Warning and Compensation Events Nicholas Gould January 2007 The NEC is a major attempt to draft a simple and direct standard form contract from first principles without attempting to build
More informationAppendix 17 Options for the Form of Contract
Appendix 17 Options for the Form of Contract December 2007 Page 444 Appendix 17 Options for the Form of Contract The main forms of contract which are available are: NEC3 HA Design and Build ICE7 ICE Target
More informationNEC ECC Option F ERF 2066 Duynefontein building refurbishment
NEC ECC Option F ERF 2066 Duynefontein building refurbishment Bok Breedt ECC Main Options There are six types of payment mechanism available in the main Options: Option A Priced contract with activity
More informationAppendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
More informationThe following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters
AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 43 Contract Data Part one, 1. 3 added: (with
More informationTHE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS
THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS ABSTRACT THURLOW, P.N. Thurlow Associates cc: Industrial Project Managers
More informationboth the Employer and Contractor teams access and administer contracts in a common environment available 24hrs per day, 365 days per year
CEMAR is a simple to deploy, web-based solution to contract management and reporting with a minimum 99.5% availability. CEMAR achieves compliance through tailored workflow that: covers NEC3 ECC, TSC, PSC,
More informationGuide to Procuring Construction Projects
Guide to Procuring Construction Projects Contents 1. Introduction... 3 2. The Construction Project... 4 Who s who? - The Client s Team... 4 Who s who? - Externals... 5 The Design Team... 6 The Suppliers...
More informationNEC Users Group Workshop Defined Cost
NEC Users Group Workshop Defined Cost Ian.Heaphy@turntown.com; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption
More informationinform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development
construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS
More informationNEC Compliance Management Innovation Use of NEC Contracts and Supporting Systems for MAP Projects
NEC Compliance Management Innovation Use of NEC Contracts and Supporting Systems for MAP Projects Introductions James Woods James is the NEC procurement specialist for Meridian Energy and head the MaP
More informationGilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners
Li & Partners 1 NEC Contract Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners and Justin Yuen / Stephanie Lau / Christy Yiu / Edmund
More informationNEC3: ECC Project Manager Accreditation. The NEC Gold Standard
NEC3: ECC Project Manager Accreditation The NEC Gold Standard I was very impressed with the programme and tutor, as it was completely relevant to our project and the work that I carry out on a daily basis.
More informationENHANCING PROCUREMENT CAPABILITIES
ENHANCING PROCUREMENT CAPABILITIES PROGRAMME FEBRUARY NOVEMBER 2016 Enhancing Procurement Capabilities February to November 2016 Scotland Excel s training delivery for 2016 offers a range of courses for
More informationNEC3: THE CONSTRUCTION CONTRACT OF THE FUTURE? Nicholas Gould. 8 February 2007 SINGAPORE SOCIETY OF CONSTRUCTION LAW
NEC3: THE CONSTRUCTION CONTRACT OF THE FUTURE? Nicholas Gould 8 February 2007 SINGAPORE SOCIETY OF CONSTRUCTION LAW Introduction The first edition of the New Engineering Contract (NEC) was published in
More informationClick to edit Master title style
Click to edit Master title style Presentation September 2013 Disallowance Under the NEC ICES Seminar Pioneering Bahrain Construction Public sector Energy Real estate London Tax IT Dubai Manchester Infra
More informationProducing a programme under the NEC form of contract
Proceedings of the Institution of Civil Engineers Management, Procurement and Law 163 May 2010 Issue MP2 Pages 59 64 doi: 10.1680/mpal.2010.163.2.59 Paper 900033 Received 02/05/09 Accepted 19/08/09 Keywords:
More informationThe FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
More informationActivity Schedules in the NEC3 Engineering and Construction Contract
Activity Schedules in the NEC3 Engineering and Construction Contract Prepared by Dr Ron Watermeyer Briefing Note NEC3#2 March 2013 Overview This briefing note outlines the NEC3 provisions for a Activity
More informationProject Management Procedures SECTION 3 PROCUREMENT
Property & Campus Services Project Management Procedures SECTION 3 PROCUREMENT Maintainer: pcs-project-office@unimelb.edu.au Page: 1 of 8 3.1 TABLE OF CONTENTS 3.2 INTRODUCTION...3 3.3 SELECTION OF TENDERERS...3
More informationDr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction
Speech by the Hon Rimsky Yuen, SC, JP, Secretary for Justice Hong Kong Construction Arbitration Centre & University of Hong Kong Joint Conference on Construction Dispute Resolution 2015 Resolution of Construction
More informationA Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components
Produced for SCALA and the Local Government Task Force by Rob Tate Dip Arch. Dip TP. Dip Arb. FCIArb. RIBA 01582 516662 rob.tate@ntlworld.com You can contact the Local Government Task Force tel 020 7837
More informationLong and Short Form. Contracts
www.pwc.com.au Model Forms of Contract and Contract Administration Tools Long and Short Form Model Forms of Contract and Contract Administration Tools Contracts Damian McNair 12 February 2016 Reference
More informationMaking a positive difference for energy consumers. Competency Framework Band C
Making a positive difference for energy consumers Competency Framework 2 Competency framework Indicators of behaviours Strategic Cluster Setting Direction 1. Seeing the Big Picture Seeing the big picture
More informationGovernment Construction. A Guide to the implementation of Project Bank Accounts (PBAs) in construction for government clients
Government Construction A Guide to the implementation of Project Bank Accounts (PBAs) in construction for government clients 03 July 2012 Table of Contents Overview of the Project Bank Account (PBA) Guide
More information6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
More informationQuantity Survey - Higher National Diploma (HND)
Quantity Survey - Higher National Diploma (HND) Law and Management Courses Construction Management I... 2 Course: Construction Management II... 4 Contract Law and Arbitration... 6 Conditions of Contract...
More informationEXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC
2 June 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Change of Consultant s Role & Highlights
More informationTo be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
More informationSetting SMART Objectives
Setting SMART Objectives Whilst line managers are responsible for ensuring that objectives are set it is important that, wherever possible, objectives are jointly agreed, between staff and line manager,
More informationNEC3: Common Amendments and Contract Management Issues
NEC3: Common Amendments and Contract Management Issues Introduction 1 The NEC Suite of Contracts is not universally loved among lawyers. The suite has as many detractors as it has supporters within the
More informationDeveloping a framework model of Supply Chain Management : A case study on a Mega construction project in Myanmar.
Proposal for PhD Research Yadanar Soe ID: 1140937 Course Title: PhD Research (Construction Management) soe.hemin@gmail.com, XXY037@bham.ac.uk Lead Supervisor: Dr M An Co Supervisor: Dr J Yang Title Developing
More informationCommercial Management/Quantity Surveying
Commercial Management/Quantity Surveying To exhibit knowledge of all civil engineering contracts, but also to support and recommend strategies to the other members of the construction team. It involves
More informationOffice of Government Commerce Partnering Contract Review Report of 25 September 2008
Office of Government Commerce Partnering Contract Review Report of 25 September 2008 Office of Government Commerce Partnering Contract Review Report of 25 September 2008 13 Fitzroy Street, London W1T 4BQ
More informationProject Management Framework
Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project
More informationRECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME
National Home Builders Registration Council RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME (14 October 2002) 1 Requirements of the Housing Consumers
More informationAustralian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1)
AS 4300 1995 (Incorporating Amendment No. 1) Australian Standard General conditions of contract for design and construct This Australian Standard was prepared by Committee OB/3, General Conditions of Contract.
More informationFinance Effectiveness Efficiency
Business Unit Finance Effectiveness Efficiency An overview Agenda Page 1 Efficiency - An overview 1 2 Our services 7 3 Case study 14 Section 1 Efficiency - An overview 1 Section 1 Efficiency - An overview
More informationWriting Reports BJECTIVES ONTENTS. By the end of this section you should be able to :
Writing Reports By the end of this section you should be able to : O BJECTIVES Understand the purposes of a report Plan a report Understand the structure of a report Collect information for your report
More informationCONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512
More informationEDITING YOUR THESIS Some useful pointers. Editing is all about making it easy for the reader to read your work.
EDITING YOUR THESIS Some useful pointers What is involved? Editing is all about making it easy for the reader to read your work. The editing process involves looking at the work in three distinct ways:
More informationC1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3)
C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3) The conditions of contract are the NEC3 Engineering and Construction Contract (June 2005), copies of which may be obtained from the South African Institution
More informationASDEFCON Handbook. (Shortform Services)
ASDEFCON Handbook (Shortform Services) Table of Contents 1 When should you use ASDEFCON (Shortform Services)?...1 2 Is ASDEFCON (Shortform Services) suitable for your particular Simple Procurement?...1
More informationPublic Lecture at Engineers Ireland. How the Public Works Contracts might be used in the Private Sector
Public Lecture at Engineers Ireland on How the Public Works Contracts might be used in the Private Sector by Ciaran Fahy Anthony Hussey 4 July 2013 1. INTRODUCTION In May 2004 the government decided as
More informationStandard forms: JCT 2005, NEC3 and the Virtual Contract
by Nicholas Gould, Partner Introduction This paper reviews some of the standard forms and considers some of the basic principles relating to their use in the construction industry. Basic concepts A review
More informationCross Border Debt Collection Procedures
Cross Border Debt Collection Procedures Bulgaria Hungary Serbia Slovakia Romania Time Limit Time Limit Time Limit Time Limit Time Limit Time limits are connected with prescription.standard prescription
More informationConstruction OS&H Principles of safe project management
Construction OS&H Principles of safe project management Summary Project organisation and management functions Stages of construction projects Creating a good preventative OS&H culture Enforcing good OS&H
More informationFinancial Controls over Payments to Contractors on Major Projects (IA 12 119 F) Leon Daniels, Managing Director, Surface Transport
FINAL INTERNAL AUDIT REPORT Financial Controls over Payments to Contractors on Major Projects (IA 12 119 F) Leon Daniels, Managing Director, Surface Transport Audit Conclusion: Audit Closed 28 June 2013
More information10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
More informationThe New Standard Construction Contracts: NZS3910, 3916 and 3917
The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of
More informationISM Online Course Offerings
CERTIFICATION (CPSM and CPSD ) ISM Online Course Offerings 3968 Bridge Review Online Course 21 CEHs This course is designed as a review for current C.P.M. holders as part of their preparation for taking
More informationPOLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT
POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy
More informationSCHEDULE A JOB DESCRIPTION
SCHEDULE A JOB DESCRIPTION Job Title: Work Unit: Responsible To: Responsible For: Position Purpose: Financial Delegated Authority: Pay Range: Assets & Business Efficiency Coordinator Corporate and Governance
More informationProcurement guidance Managing and monitoring suppliers performance
Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the
More informationConstruction Cost Management
Construction Cost Management In the last decade, following the Latham and Egan reports, there have been many significant changes in the role of the construction cost manager. Keith Potts examines the key
More informationBriefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication
More informationWriting for work documents
Writing for work documents Written communications in the work environment are often compiled using existing templates that guide you through most of the information that is required. Nonetheless, there
More informationAIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
More informationNetwork Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
More information1. Define and Know (D) 2. Recognize (R) 3. Apply automatically (A) Objectives What Students Need to Know. Standards (ACT Scoring Range) Resources
T 1. Define and Know (D) 2. Recognize (R) 3. Apply automatically (A) ACT English Grade 10 Rhetorical Skills Organization (15%) Make decisions about order, coherence, and unity Logical connections between
More informationAn Oracle White Paper June 2009. Successfully Managing Contract Risk by Forming Win-Win Relationships
An Oracle White Paper June 2009 Successfully Managing Contract Risk by Forming Win-Win Relationships Executive Overview This white paper identifies some of the risks involved with contract project work
More informationPreparation of a Rail Safety Management System Guideline
Preparation of a Rail Safety Management System Guideline Page 1 of 99 Version History Version No. Approved by Date approved Review date 1 By 20 January 2014 Guideline for Preparation of a Safety Management
More informationICE Legal Notes Series
ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).
More informationPREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:
Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods
More informationA Guidance Note to. Conditions of Contract for Consultancy Services (2005)
A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.
More informationPROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
More informationContract Law & Management
2016 PROFESSIONAL DEVELOPMENT Contract Law & Management AUCKLAND WELLINGTON CHRISTCHURCH BOOK EARLY TO RECEIVE SUPER SAVER DISCOUNTS See back page for details. www.brightstar.co.nz/contracts CONTRACT LAW
More informationHead of Lease Terms - Ten Steps to a Successful negotiation
Imperial College ThinkSpace Leasing Terminology Head of lease terms The principal terms upon which the lease will be drafted are detailed within a single document, entitles the Heads of Lease Terms. These
More informationProfessional Practice Commission: March 2013. Alternative Project Delivery Systems
Professional Practice Commission: March 2013 Alternative Project Delivery Systems UIA Accord Building project delivery systems. Definition Building project delivery systems are defined as the contractual
More informationEngineering Council of South Africa
Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the
More information[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
More informationOVERVIEW. stakeholder engagement mechanisms and WP29 consultation mechanisms respectively.
Joint work between experts from the Article 29 Working Party and from APEC Economies, on a referential for requirements for Binding Corporate Rules submitted to national Data Protection Authorities in
More informationDated 2015 (1) THE HALL FOR CORNWALL TRUST. and (2) [ARCHITECT] Appointment of Architect
Dated 2015 (1) THE HALL FOR CORNWALL TRUST and (2) [ARCHITECT] Appointment of Architect to provide architectural and other multi-disciplinary services in relation to the design for the Hall for Cornwall,
More informationData Centre Construction. Paul Jayson - Partner 20 March 2012
Data Centre Construction Paul Jayson - Partner 20 March 2012 Buy Benefits Control over facilities that handle and store data Bespoke rather than generic design and housing Security Disadvantages Build
More informationJOB DESCRIPTION. CHIEF ENGINEER (Infrastructure) Grade: BBB (SCP 210-213) Post No.: 051/7200 Reports to: Head of Highways & Design
JOB DESCRIPTION 1. Service: HIGHWAYS & DESIGN Location: Job Title: Barnet House CHIEF ENGINEER (Infrastructure) Grade: BBB (SCP 210-213) Post No.: 051/7200 Reports to: Head of Highways & Design 2. Context
More informationThe FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni
The FIDIC Form of Contract The Fourth Edition of the Red Book 2nd Edition Nael G. Bunni BSc, MSc, PhD, CEng, FIEI, FICE, FIStruct, FCIArb, FInstD, MconsEI b Blackwell Science Contents List of Figures List
More informationPart One: Introduction to Partnerships Victoria contract management... 1
June 2003 The diverse nature of Partnerships Victoria projects requires a diverse range of contract management strategies to manage a wide variety of risks that differ in likelihood and severity from one
More informationCONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
More informationThis project supported by a grant from:
Best Practices Guide International Association of Chiefs of Police Smaller Police Departments Technical Assistance Program Grant Writing by Bridget Newell, Ph.D. This project supported by a grant from:
More informationPPC2000 Contracts RICS East of England and CIOB - Framework and Partnering Agreements CPD 21 June 2010 Richard Cooke. Contents.
PPC2000 Contracts RICS East of England and CIOB - Framework and Agreements CPD 21 June 2010 Richard Cooke Contents Background Parties and Contracts Documents Early Involvement Pre-Construction Phase Construction
More informationPROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
More informationIf I don t receive your feedback by 5:00pm next Wednesday, I will deem that yu are OK with the content of the attached document.
Email Tune-up 02: Asking for comments Original Email Subject: Please review this document Dear Emily, I should be glad if you review the attached document. Please can you let me know if you have any inputs,
More informationSchedule of Prices. Project Name Contract No. Contract Number
Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule
More informationDISPUTE RESOLUTION GRIEVANCE PROCEDURE FOR TEACHING & SUPPORT STAFF IN SCHOOLS
DISPUTE RESOLUTION GRIEVANCE PROCEDURE FOR TEACHING & SUPPORT STAFF IN SCHOOLS PLEASE NOTE: This document replaces the previous Grievance and Dignity at Work Policies and Procedures. 1. INTRODUCTION It
More informationHow to write an Outline for a Paper
How to write an Outline for a Paper What is an outline? An outline can be defined as an organizational plan to help you draft a paper. Writing an outline before beginning a paper is the most effective
More informationHow to get value for money from service providers on major projects
How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the
More informationSenior Governance Manager, North of England. North Tyneside CCG Quality and Safety Committee (01/12/15)
Corporate IG02: Data Quality Version Number Date Issued Review Date V4 07/12/2015 01/01/18 Prepared By: Consultation Process: Senior Governance Manager, North of England Commissioning CCG Quality & Safety
More informationBusiness Resources. QCF Units of Assessment Final NVQ Units April 2010
Business Resources QCF Units of Assessment Final NVQ Units April 2010 6 Graphite Square Vauxhall Walk London SE11 5EE T: 0207 0919620 F: 0207 0917340 Info@skillscfa.org www.skillscfa.org Contents No. Title
More informationQUALITY MANAGEMENT SYSTEM (QMS) MANUAL
Printed QMS Documentation is Uncontrolled Page 1 of 19 QUALITY MANAGEMENT SYSTEM (QMS) MANUAL ISSUE/ REVISION DATE DESCRIPTION ISSUE HISTORY PREPARED/ APPROVED BY 09/04/2014 Initial issue G.Rees 11/04/2014
More informationEiBCM - A Model For Success
Conducting Conflict Aware Business Management A User s Perspective on Dispute Boards Northrop Grumman (Northrop) is a global aerospace security company with 65,000 employees worldwide. It is involved in
More informationWeek 4: Procurement of Highway Maintenance. Day 2 - Tuesday 18 June 2002. The Procurement Process CONTENTS
Week 4: Procurement of Highway Maintenance Day 2 - Tuesday 18 June 2002 The Procurement Process CONTENTS Overview of Partnering and the Procurement Process...1 1. Overview of Partnering...1 2. Overview
More informationSIMPLE KEYS TO BETTER BUSINESS WRITING. by Linda Vanderwold, CSP Americas #1 Clear Writing Coach
3 SIMPLE KEYS TO BETTER BUSINESS WRITING by Linda Vanderwold, CSP Americas #1 Clear Writing Coach LETTER FROM LINDA VANDERWOLD Dear Friend, I m thrilled that you are interested in learning cutting-edge
More informationPOSITION DESCRIPTION
POSITION DESCRIPTION Position Title: Reports to: DEVICES CATEGORY MANAGER MANAGER, DEVICES FUNDING Date: September 2014 PHARMAC S MISSION Our legislative objective is: to secure for eligible people in
More informationJOB DESCRIPTION GBS 1 ST DRAFT DRAFT V02 DRAFT V03 GBS GBS
JOB DESCRIPTION JOB TITLE: SERVICE DESK MANAGER DOCUMENT CONTROL VERSION DATE OF ISSUE AUTHOR REASON FOR REVISION DRAFT V0.1 1 ST NOVEMBER 2013 GBS 1 ST DRAFT DRAFT V02 DRAFT V03 31ST MARCH 2014 3 JULY
More information