ANNEX 8 Contract Management Strategy

Size: px
Start display at page:

Download "ANNEX 8 Contract Management Strategy"

Transcription

1 ANNEX 8 Contract Management Strategy Bath & North East Somerset, Bristol, North Somerset and South Gloucestershire Councils working together to improve your local transport

2 Contract Management Strategy - Ashton Vale to Temple Meads & Bristol City Centre MetroBus 1.0 General Principles The Ashton Vale to Temple Meads and Bristol City Centre (AVTM) MetroBus contracts have been procured in accordance with the West of England Joint Procurement strategy and endorsed by the Procurement Working Group (PWG) and Programme Assurance Board (PAB).The Contracts comprise of the following: Contract 1 : Guided segregated Busway Contract 2 : Ashton Avenue Swing Bridge Contract 3 : Bathurst Basin Bridges Contract 4 : Bristol City Centre loop Contract 1: The AVTM MetroBus guided Busway section from long Ashton Park and Ride to Bathurst basin Bridges will delivered through a NEC3 Engineering and Construction Contract ( ECC), Design & Build Option C ( Target Price contract with Activity Schedule ). Contract 2: Ashton Avenue Swing Bridge will be delivered through a NEC3 Engineering and Construction Contract ( ECC ),Design & Build Option A (fixed Price contract with Activity Schedule). Contract 3: Bathurst Basin Bridges will be delivered through a NEC3 Engineering and Construction Contract ( ECC ),Option A (fixed Price contract with Activity Schedule). Contract 4: Works to the City centre loop consist of twelve individual work packages and will be delivered through the Highways and Associated Works Framework (HAAWF), with design work undertaken by Bristol City Council. The HAAWF has been let as a series of individual Lots: Lot 1: up to 1M Lot 2: 1M to 3M Lot 3: above 3M, with an expected maximum contract value of approximately 7M. To reduce procurement costs, a Schedule of Rates method will be used for works up to 1M in value. For works over 1M and for special conditions, a mini-tender system will be used. The HAAWF tender documents proposed that six contractors would form Lot 1 (up to 1M), five contractors would form Lot 2 ( 1M to 3M) and five would form Lot 3 (above 3M with an approximate maximum of 7M). 2.0 Planning and Governance The Programme Assurance Board (PAB) will maintain governance through implementation of the appropriate management systems along with the AVTM Project Board. The PAB is the group which guides and steers the direction of the MetroBus Programme. Senior officers from the PAB meet quarterly, where consideration is given for highlighting and dealing with key project deliverables. Currently, the AVTM Project Board meets bi-monthly. 1

3 The Senior Responsible Owner (SRO) is responsible for providing guidance and direction to the Employers Project Manager, and in turn ensures the project progresses in line with the Project Plan and that outputs and milestones agreed by the PAB are achieved. The Employers Project Manager (PM) is responsible for delivering the project in line with agreed controls and procedures. The PM reports and is accountable to the SRO and Project Board. The primary focus of the PM will be to define the Project Plan and to ensure that the project is delivered on time and within specification and budget, seeking additional financial authorities as required. The MetroBus Procurement Working Group (PWG) meet on a monthly basis to coordinate the detailed elements of the procurement activities for all four MetroBus schemes. The PWG is made up of senior officers from the three lead authorities responsible for the schemes and makes recommendations that feed into the Governance structures provided by the Project Board, PAB and the Joint Transport Executive Committee (JTEC).The PWG plays a significant role in reviewing, endorsing and providing oversight of the MetroBus infrastructure procurement programme. 3.0 People The AVTM MetroBus Delivery Team is shown in Annex 9 of the Full Approval submission. The Employers Project Manager ( PM ) reports directly to the SRO ensuring robust accountability and clear lines of communications. The Employers PM has overall responsibility for managing the AVTM MetroBus contracts and deals with programme, monetary issues and changes to the contracts. A NEC3 (New Engineering Contract) Project Manager & supervisory team will be appointed to administer & manage the day to day running of the MetroBus contracts. The NEC3 PM will report directly to AVTM MetroBus Delivery Manager, whom has overall responsibility for the delivery and co-ordination of the overall project which as previously mentioned includes MetroBus contracts (1 to 3) and contract 4, City Centre Loop packages procured under the HAAWF. The NEC3 project team administration duties below are specific to all contracts and include but not limited to : Project Manager Instructions; Management of compensation events; Maintaining change control register across the contract; Management of early warning notifications and project risks through the contract risk register; Monitoring progress against the accepted programme and instigate collaborative team working to mitigate any programme delays; Co-ordinate and chair monthly Contractor / Client progress meetings; Production of monthly progress reports; Instigate collaborative team working to manage design changes whilst maintaining focus of project aims, constraints and risks; and 2

4 Administer contract completion including rectification of defects. The NEC3 project team will comprise of numerous works supervisor s whom duty is to ensure that the appointed contractor construct the works in accordance with the contract documentation referring, specifically to the drawings, specification & associated Works Information. Contractors appointed to undertake works across all the MetroBus contracts will report to the NEC3 PM and have their work defined by the respective contracts. The NEC3 team will provide robust and clear lines of responsibility, duties and communication which accords with the requirements of the NEC3 suite of contracts & well established industry working practice. 4.0 Quality Management System There is a requirement for the contractor to operate a QMS in accordance with BS EN ISO 9001 and described in a Quality Plan. The Quality Plan will cover: Contractors organisation and management; Contractors method statements and construction procedures; Contractors construction quality control; Suppliers quality plans; and Contractors consultation with affected parties. 5.0 Relationships and Communications Representatives of the employer, the NEC3 project manager and contractor will attend monthly progress meetings. In advance of these meetings the contractor will provide a progress report which will detail: Progress achieved to date; Delays, causes and effects of delays; Details of any comments and consultation undertaken with adjacent properties and businesses; Works programmed; Labour, plant, materials and Sub Contractors; Information received and required; Payment profile and compensation events/early warnings; and Risk. The Employers project manager will report monthly progress to the SRO and Project Board. The contractors will be required to comply with all legislation and the Code of Construction Practice which forms part of the contract documentation. The code requires the contractor to implement an Environmental Management System, obtain 3

5 Licences from the Environmental Agency, the Water Authorities & obtain Temporary Traffic Regulation Orders from the incumbent Highway Authority. There is also a requirement to appoint a nominated person within the contractors organisation tasked specifically to public liaison duties. The officer will directly liaise with both the NEC3 project teams and communication officers of both Bristol City Council and the West of England Partnership to ensure a coherent co-ordinated approach is provided with regard to public liaison. 6.0 Cost Management and Payments One of the primary functions of the NEC3 project team following appointment is to provide cost management services and include but not limited to: Administer NEC3 Conditions of Contracts; Certifying contractors monthly cost applications; Auditing contractor s costs; Maintain and facilitate financial communication between the Employers finance team and the contractor; Review compensation event quotations; Produce financial reports; Attending pre-commencement and monthly progress meetings; Provide continuous commercial & contractual support; and Prepare final accounts. Contracts 1 to 3 (NEC3 options A & C) contain Activity Schedules which forms the basis for all contractors payments. Contractor will use these Activity Schedules as means of evaluating the works completed. The NEC3 Project Manager assesses the submissions and recommends to the Employer the actual level of payment due. Cost reimbursement for contract 4 is facilitated by contractors applying for payment based on a schedule of agreed rates. 7.0 Risk Management Quantitative Risk Analysis (QRA) evaluations have been completed and used to influence the approach to scheme delivery, contract methodology and delivery team composition and size. Contracts 1 to 3 contain individual project risk registers which has identified the main risks, mitigation measures and owners. These registers will continue to be reviewed and updated at regular intervals during the delivery phases to ensure it accurately reflects changing circumstances. Mechanisms exist within the contracts for risk monitoring and review with defined routes for escalation. The NEC3 project team and contractors will meets regularly during the works, the Contract Management Strategy will continues to develop mitigation action plans in response to existing and new risks with identification of new risk owners. 4

6 Within the NEC3 conditions of contract, there is a contractual requirement to operate a formal risk register of notified events and an up to date realistic programme maintained by the contractor but used in joint decision making between the contractor and the NEC3 Project Manager. 8.0 Relationship management The New Engineering Contract (NEC3),Engineering & Construction Contract (ECC) should be viewed as a stimulus to good management which encourages collaborative working between both parties which reduces the risks inherent in construction and engineering work.. 5

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

QSS 0: Products and Services without Bespoke Contracts.

QSS 0: Products and Services without Bespoke Contracts. QSS 0: Products and Services without Bespoke Contracts. Amendment History Version Date Status v.1 Dec 2014 Updated For 2015 deployment Table of Contents 1. DEFINITIONS 3 2. INTRODUCTION 3 3. WORKING WITH

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

Health and safety policy

Health and safety policy 1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and

More information

Project Bank Account Awareness

Project Bank Account Awareness Project Bank Account Awareness Background of Fair Payment and PBAs PBAs explained Business Case Perceptions v reality HA forecast take up Impact on HA & the extended the supply chain Responsibilities KPIs

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

NEC ECC Option F ERF 2066 Duynefontein building refurbishment

NEC ECC Option F ERF 2066 Duynefontein building refurbishment NEC ECC Option F ERF 2066 Duynefontein building refurbishment Bok Breedt ECC Main Options There are six types of payment mechanism available in the main Options: Option A Priced contract with activity

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

PROFESSIONAL SERVICES SPECIFICATION

PROFESSIONAL SERVICES SPECIFICATION R64 - PAVEMENT MARKING August 1996 PROFESSIONAL SERVICES SPECIFICATION PM2 PROJECT MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT of INFRASTRUCTURE,

More information

NEC3 Engineering & Construction Contract An Overview

NEC3 Engineering & Construction Contract An Overview NEC3 Engineering & Construction Contract An Overview Delivering Professional Solutions to the Property Industry Michael Dunn FRICS FCIArb LLB LLM Director of Contract Services T: 01274 693 622 E: m.dunn@rpp.co.uk

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further

University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further revision June 2014) 1. Introduction This paper defines

More information

Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans

Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans A guide to implementing integrated assurance and approvals Version 1.0 - May 2011 Contents Introduction 03 Integrated

More information

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition. 10 32.1 4 deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 43 Contract Data Part one, 1. 3 added: (with

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

Guidance Notes for the NEC Engineering and Construction Contract

Guidance Notes for the NEC Engineering and Construction Contract The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors

More information

Information security controls. Briefing for clients on Experian information security controls

Information security controls. Briefing for clients on Experian information security controls Information security controls Briefing for clients on Experian information security controls Introduction Security sits at the core of Experian s operations. The vast majority of modern organisations face

More information

Position Description

Position Description Position Description POSITION TITLE Procurement Advisor POSITION NO 500268 DIRECTORATE DEPARTMENT Corporate Services Finance UNIT REPORTS TO Manager Finance CLASSIFICATION Band 7 LOCATION Civic Centre,

More information

South Norfolk Council Business Continuity Policy

South Norfolk Council Business Continuity Policy South Norfolk Council Business Continuity Policy 1 Title: Business Continuity Policy Date of Publication: TBC Version: 2 Published by: Emergency Planning Team Review date: April 2014 Document Owner: Document

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy October 2014 1 October 2014 Contents: Introduction 1. STATEMENT OF INTENT AND POLICY OBJECTIVES 2. RESPONSIBILITIES AND ACCOUNTABILITIES FOR HEALTH AND SAFETY 2.1 The Director

More information

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3)

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3) C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3) The conditions of contract are the NEC3 Engineering and Construction Contract (June 2005), copies of which may be obtained from the South African Institution

More information

Trust Board Report. Review of the effectiveness of the IM&T Committee

Trust Board Report. Review of the effectiveness of the IM&T Committee 1. Introduction Trust Board Report Review of the effectiveness of the The meets every eight weeks, with a specific responsibility for governance, strategic direction, approval and direction of developments

More information

CODE OF PRACTICE DEALING WITH THE RELATIONSHIP BETWEEN THE NATIONAL AUDIT OFFICE AND THE COMPTROLLER AND AUDITOR GENERAL

CODE OF PRACTICE DEALING WITH THE RELATIONSHIP BETWEEN THE NATIONAL AUDIT OFFICE AND THE COMPTROLLER AND AUDITOR GENERAL CODE OF PRACTICE DEALING WITH THE RELATIONSHIP BETWEEN THE NATIONAL AUDIT OFFICE AND THE COMPTROLLER AND AUDITOR GENERAL The Budget Responsibility and National Audit Act received Royal Assent in March

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health

More information

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE:

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE: 1. JOB TITLE Job Title: Project Manager (Transport Infrastructure) Reports to: Design Programme Manager Service: Highways and Transport Environment & Infrastructure Date: November 2014 2. JOB PURPOSE To

More information

HEALTH AND SAFETY POLICY AND PROCEDURES

HEALTH AND SAFETY POLICY AND PROCEDURES HEALTH AND SAFETY POLICY AND PROCEDURES 1 Introduction 1. The Health and Safety at Work etc. Act 1974 places a legal duty on the University to prepare and revise as often as may be appropriate, a written

More information

DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS

DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS WELDING FABRICATOR CERTIFICATION SCHEME DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS 6 th Edition July 2012 Issued under the authority of the Governing Board for Certification All correspondence should

More information

Cyber Security Consultancy Standard. Version 0.2 Crown Copyright 2015 All Rights Reserved. Page 1 of 13

Cyber Security Consultancy Standard. Version 0.2 Crown Copyright 2015 All Rights Reserved. Page 1 of 13 Cyber Security Consultancy Standard Version 0.2 Crown Copyright 2015 All Rights Reserved Page 1 of 13 Contents 1. Overview... 3 2. Assessment approach... 4 3. Requirements... 5 3.1 Service description...

More information

The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP)

The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP) The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP) January 2015 Leila du Toit Sustainable Construction Manager Environmental Minimum Requirements (EMR s) Environmental

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Better Practice Contract Management Framework

Better Practice Contract Management Framework Better Practice Contract Management Framework Better practice element Comment: What is required and why Governance Agencies contract delegations are clear and consistent with general financial delegations

More information

PROJECT BRIEF Version (insert number)

PROJECT BRIEF Version (insert number) PROJECT BRIEF Version (insert number) 1 Project Name ------------------------------------------------------------------- 1.1 The Project Project Address Nature of Work Location 1.2 DCC Client for Project

More information

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL NEFAB Project CHANGE MANAGEMENT MANUAL Version 0.5 Page 1 of 38 Revision history Version Date Description Approved 0.5 14/12/2011 Page 2 of 38 Table of Contents 1. Introduction... 4 1.1. The Scope of this

More information

This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM

This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM CONTENTS Page No 1 GENERAL REQUIREMENTS 1 1.1 Requirements 1

More information

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA Quality Manual Kellaw Road Yarm Road Business Park Darlington DL1 4YA MANUAL IDENTIFICATION This document is a controlled/uncontrolled copy. Copy Number:...of... Issued to... Title... Holders of controlled

More information

JOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning

JOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning JOB DESCRIPTION Position Title and Number: Senior Procurement Officer (100618) Grade: Department: Section: Responsible to: Responsible for: SO2 People Directorate Health, Wellbeing & Commissioning Team

More information

Update on Programme Management Controls & Risks

Update on Programme Management Controls & Risks Committee and Date Audit Committee 26/06/14 Update on Programme Management Controls & Risks Responsible Officer George Candler Director of Commissioning e-mail: George.Candler@shropshire.gov.uk Tel: 01743

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

NEC3: The Engineering and Construction Contract An overview

NEC3: The Engineering and Construction Contract An overview NEC3: The Engineering and Construction Contract An overview Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk Delivering Professional Solutions to the

More information

Place Scrutiny Briefing AGENDA ITEM 13

Place Scrutiny Briefing AGENDA ITEM 13 Place Scrutiny Briefing AGENDA ITEM 13 Meeting date: 13.7.15 Heading: Joint Spatial Plan and Joint Transport Study - Update Ward: All Bristol wards Author: Sarah O Driscoll Ext. No: 36722 Officer presenting

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

Quality Management Subcontractor QM Guide-Section Two

Quality Management Subcontractor QM Guide-Section Two SECTION TWO QUALITY MANAGEMENT SYSTEMS Version No 1. PREFACE This document has been developed to assist subcontractors to meet Monaco Hickeys (MHPL) Quality Management (QM) requirements whilst working

More information

One Government Contract Management Framework. September 2014

One Government Contract Management Framework. September 2014 One Government Contract Framework September 2014 One Government Contract Framework Table of contents 1 Introduction... 4 2 Purpose... 4 3 Scope... 5 3.1 Contract management planning starts before a contract

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression

More information

Module 1 Diploma of Project Management

Module 1 Diploma of Project Management Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination

More information

How To Write A Contract

How To Write A Contract Commercial Management the NEC Way Hong Kong Institute of Surveyors Ian.Heaphy@turntown.com Mark.Lyddon@turntown.com, July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

JOB DESCRIPTION. CHIEF ENGINEER (Infrastructure) Grade: BBB (SCP 210-213) Post No.: 051/7200 Reports to: Head of Highways & Design

JOB DESCRIPTION. CHIEF ENGINEER (Infrastructure) Grade: BBB (SCP 210-213) Post No.: 051/7200 Reports to: Head of Highways & Design JOB DESCRIPTION 1. Service: HIGHWAYS & DESIGN Location: Job Title: Barnet House CHIEF ENGINEER (Infrastructure) Grade: BBB (SCP 210-213) Post No.: 051/7200 Reports to: Head of Highways & Design 2. Context

More information

Consultancy spending approval process: Initial guidance to NHS foundation trusts

Consultancy spending approval process: Initial guidance to NHS foundation trusts Annex One Consultancy spending approval process: Initial guidance to NHS foundation trusts Summary 1. Monitor, the NHS Trust Development Authority (TDA) and NHS England are jointly implementing an approval

More information

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows JOB DESCRIPTION Position: Location of position: Reporting to: Special functional relationships: Term of Appointment: Programme Manager/Procurement Specialist Suva Capital Works Manager Capital Works Programme

More information

Ashghal (or the Public Works Authority) is the government organisation responsible for providing major infrastructure for the State of Qatar.

Ashghal (or the Public Works Authority) is the government organisation responsible for providing major infrastructure for the State of Qatar. Quantity Surveyor Summary of Position To support Commercial & Procurement section of the Expressway Department of Ashghal, in pre-contract and post contract functions required within the team. This includes

More information

Managing programme change on an NEC3 form of contract

Managing programme change on an NEC3 form of contract Managing programme change on an NEC3 form of contract Presentation: Summary of Key NEC3 Programme Principles Timing of compensation events relative to the last Accepted Programme Assessing effects of a

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

Essex Fire Authority. Fleet Management. Internal Audit Report (4.12/13) 28 February 2013 FINAL. Overall Opinion

Essex Fire Authority. Fleet Management. Internal Audit Report (4.12/13) 28 February 2013 FINAL. Overall Opinion Essex Fire Authority Fleet Management Internal Audit Report (4.12/13) 28 February 2013 FINAL Overall Opinion Essex Fire Authority Fleet Management 4.12/13 CONTENTS Section Page Executive Summary 1 Action

More information

Clients in Construction Best Practice Guidance

Clients in Construction Best Practice Guidance Clients in Construction Best Practice Guidance Published in 2009 by the, Metropolitan Building, James Joyce Street, Dublin 1. Copyright The January 2009 Clients in Construction: Best Practice Guidance

More information

Business Continuity Policy

Business Continuity Policy Business Continuity Policy 1 NHS England INFORMATION READER BOX Directorate Medical Commissioning Operations Patients and Information Nursing Trans. & Corp. Ops. Commissioning Strategy Finance Publications

More information

Minimum Standard Z/11 - Performance Evaluation

Minimum Standard Z/11 - Performance Evaluation NZ Transport Agency Page 1 of 9 Minimum Standard Z/11 - Performance Evaluation 1 Introduction The following criteria are the requirements for the completion of Performance Evaluations of suppliers using

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION

RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION TITLE: REPORTING TO: RESPONSIBLE FOR: Financial Accountant Group Accountant Assistant Accountant 1. Overall Objectives 1.1. To provide the Financial Accounting

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

PROCUREMENT MANAGER Support Services. Salary range 30,843 to 33,315 (Subject to Job Evaluation)

PROCUREMENT MANAGER Support Services. Salary range 30,843 to 33,315 (Subject to Job Evaluation) PROCUREMENT MANAGER Support Services Salary range 30,843 to 33,315 (Subject to Job Evaluation) We are looking to appoint an innovative Procurement Manager to advise and support client departments and identify

More information

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB United Kingdom Tel: +44(0)1604-893-811. Fax: +44(0)1604-893-868. E-mail: pcn@bindt.org CP14 ISSUE 5 DATED 1 st OCTOBER

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

FLEET ROAD RISK POLICY

FLEET ROAD RISK POLICY FLEET ROAD RISK POLICY SGPilliner U:\PolicieandProcedures\FleetRoadRiskPolicy\FleetRoadRiskPolicy040903 1 Fleet Road Risk Policy. 1.0 Introduction. Carmarthenshire County Council is committed to manage

More information

NEC Users Group Workshop Defined Cost

NEC Users Group Workshop Defined Cost NEC Users Group Workshop Defined Cost Ian.Heaphy@turntown.com; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption

More information

Fleet Policy. Version Number: 2 Controlled Document Director of Corporate Affairs

Fleet Policy. Version Number: 2 Controlled Document Director of Corporate Affairs Fleet Policy CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE: This Document supports: Controlled Document Number: Policy Governance To set out the principles for the management of the Trust Fleet

More information

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems).

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems). FAT MEDIA QUALITY ASSURANCE STATEMENT NOTE 1: This is a CONTROLLED Document as are all quality system files on this server. Any documents appearing in paper form are not controlled and should be checked

More information

Title: Rio Tinto management system

Title: Rio Tinto management system Standard Rio Tinto management system December 2014 Group Title: Rio Tinto management system Document No: HSEC-B-01 Standard Function: Health, Safety, Environment and Communities (HSEC) No. of pages: 23

More information

Information Governance

Information Governance Attach 8 Information Governance CCG Accredited Safe Haven Application Information Governance CCG Accredited Safe Haven Application 1 1. Introduction 1.1. From the 1st April 2013 new information governance

More information

ST ANDREWS COMMUNITY HOSPITAL AND HEALTH CENTRE PROJECT MANAGEMENT AND MONITORING THE BOARD S OBLIGATIONS

ST ANDREWS COMMUNITY HOSPITAL AND HEALTH CENTRE PROJECT MANAGEMENT AND MONITORING THE BOARD S OBLIGATIONS ST ANDREWS COMMUNITY HOSPITAL AND HEALTH CENTRE PROJECT MANAGEMENT AND MONITORING THE BOARD S OBLIGATIONS GENERAL LEAD RESPONSIBILITY OBLIGATIONS UNDER THE PROJECT AGREEMENT Deliver to Project Co the Completion

More information

Derbyshire Trading Standards Service Quality Manual

Derbyshire Trading Standards Service Quality Manual Derbyshire Trading Standards Service Quality Manual This Quality Manual has been developed to give a broad outline of how the Trading Standards Division s range of services comply with the requirements

More information

Producing a programme under the NEC form of contract

Producing a programme under the NEC form of contract Proceedings of the Institution of Civil Engineers Management, Procurement and Law 163 May 2010 Issue MP2 Pages 59 64 doi: 10.1680/mpal.2010.163.2.59 Paper 900033 Received 02/05/09 Accepted 19/08/09 Keywords:

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE 1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Appendix 17 Options for the Form of Contract

Appendix 17 Options for the Form of Contract Appendix 17 Options for the Form of Contract December 2007 Page 444 Appendix 17 Options for the Form of Contract The main forms of contract which are available are: NEC3 HA Design and Build ICE7 ICE Target

More information

LIFT MANAGEMENT. Version 01 / November 2015 Page 1 of 9 Approved by Health & Safety Committee

LIFT MANAGEMENT. Version 01 / November 2015 Page 1 of 9 Approved by Health & Safety Committee LIFT MANAGEMENT Version 01 / November 2015 Page 1 of 9 Approved by Health & Safety Committee This is a controlled document. It should not be altered in any way without the express permission of the author

More information

To verify the quality of completed Ministry of Health infrastructure projects and make recommendations for contract payments.

To verify the quality of completed Ministry of Health infrastructure projects and make recommendations for contract payments. Malawi Health Sector Strategic Plan (MHSP) Technical Assistance Component Draft Terms of Reference Supervision and Verification of MOH Infrastructure Programme Purpose To verify the quality of completed

More information

POSITION INFORMATION DOCUMENT

POSITION INFORMATION DOCUMENT POSITION INFORMATION DOCUMENT Position Title: Senior Manager, ICT Contracts Classification Code: ASO8 Division: ICT Services Directorate: ICT Contracts & Performance Management Type of Appointment: Branch:

More information

Gloucestershire Hospitals

Gloucestershire Hospitals Gloucestershire Hospitals NHS Foundation Trust TRUST POLICY In the case of hard copies of this policy the content can only be assured to be accurate on the date of issue marked on the document. The Policy

More information

QUALITY MANAGEMENT IN VTS

QUALITY MANAGEMENT IN VTS CHAPTER 18: QUALITY MANAGEMENT IN VTS Background At its twenty-fourth session, the IMO Assembly adopted resolution A.973(24) on the Code for the Implementation of Mandatory IMO Instruments and resolution

More information

POSITION: PROJECTS MANAGEMENT OFFICER

POSITION: PROJECTS MANAGEMENT OFFICER POSITION DESCRIPTION TRIM Number: (E12/6092) POSITION: PROJECTS MANAGEMENT OFFICER Our values are known as the SJ Way We aspire to be: Passionate * Fun * Caring * Diverse * Resourceful * Innovative * Rewarding

More information

EAST AYRSHIRE COUNCIL. No Goals Target Date Progress & Comments

EAST AYRSHIRE COUNCIL. No Goals Target Date Progress & Comments Page 1 of 18 No Goals Target Date Progress & Comments OBJECTIVE 1 - ENCOURAGING A POSITIVE SAFETY CULTURE INVOLVING ALL EMPLOYEES ACTION AREA 1.1 - Services will ensure the implementation of corporate

More information

Project Managing TUPE transfers when outsourcing to a Contractor An overview of pension implications and procedures for LGPS Scheme Employers

Project Managing TUPE transfers when outsourcing to a Contractor An overview of pension implications and procedures for LGPS Scheme Employers AVON PENSION FUND Project Managing TUPE transfers when outsourcing to a Contractor An overview of pension implications and procedures for LGPS Scheme Employers Project Managing TUPE transfers when outsourcing

More information

CCF Systems Gap Analysis Checklist. Civil Contractors Federation. Civil Construction Management Code

CCF Systems Gap Analysis Checklist. Civil Contractors Federation. Civil Construction Management Code CCF Systems Gap Analysis Checklist Civil Contractors Federation Civil Construction Management Code Please Note: This Gap Analysis Checklist is designed to enable Contractors to undertake an initial self

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE...

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE... POLICY Title: QAL Contract Management Policy Policy No: P801.001 Issue: 2 Revision: 3 Operative Date: 10/11/2009 Author: J McGuire Department: Company Sect./Classification: Company Category: Contract Management

More information

Asset Support Contract Model Service Information. Annex 25 Integrated Asset Management

Asset Support Contract Model Service Information. Annex 25 Integrated Asset Management Asset Support Contract Model Annex 25 Integrated Asset Management Page A25-1 SERVICE INFORMATION FOR ASC CONTRACT ANNEX 25 CONTENTS AMENDMENT SHEET Amend. No. Issue Date Amendments Initials Date Page A25-2

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

-17 2015 OUTSOURCING POLICY

-17 2015 OUTSOURCING POLICY Outsourcing Policy TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 Aim & Introduction... 3 POLICY PARAMETERS... 4 Key Terms... 4 Outsourcing Agreement Requirements... 5 MATERIAL OUTSOURCING AGREEMENTS... 6 Board

More information

Internal Audit. Capital Projects. May 2015. Final Report

Internal Audit. Capital Projects. May 2015. Final Report Internal Audit TABLE OF CONTENTS Executive Summary...3 1 Introduction...3 2 Objectives...3 3 Scope...4 4 Summary of...4 5 Overall and Opinion...4 Audit Tests and...5 6.1 Management & Delivery of Projects...5

More information

Training Management Guidelines

Training Management Guidelines Training Management Guidelines February 2009 Training Management Guidelines - February 2009 These guidelines provide a strategic approach to training and skills development in the construction industry

More information

2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY

2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY APM Procurement Guide : Draft7_RevA_Chapter 2.1_Project Procurement Strategy_Jan12 1 2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY In this stage, the project definition is developed so that decisions can be

More information