Decommissioning of CANDU Nuclear Power Stations. by G.N. Unsworth



Similar documents
THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM

10 Nuclear Power Reactors Figure 10.1

International Action Plan On The Decommissioning of Nuclear Facilities

Chemical Decontamination and Fluid Handling Services

Office for Nuclear Regulation

HOW DOES A NUCLEAR POWER PLANT WORK?

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

Government Degree on the Safety of Nuclear Power Plants 717/2013

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES AUSTRALIA NATIONAL NUCLEAR ENERGY CONTEXT

Lessons learned from the radiological accident in Mayapuri, New Delhi, India

APPENDIX CC NUCLEAR WASTE STORAGE

SECTION TWO PACKAGING, TRANSPORTATION AND STORAGE OF RADIOACTIVE MATERIALS

NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission

Hazard Classification of the Remote Handled Low Level Waste Disposal Facility

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND

RADIOACTIVE WASTE MANAGEMENT PLAN

Replacement of steam generators at Ringhals nuclear power plant.

Radioactive Waste Management at Paks NPP

IBC Nuclear Energy Liability Exclusion. Explained

Spent Fuel Project Office Interim Staff Guidance - 17 Interim Storage of Greater Than Class C Waste

Categorisation of Active Material from PPCS Model Power Plants

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]

Radioactive Waste Storage Facility and Tank System Design Criteria Standards

Decommissioning situation of Nuclear Power Plant in Japan

Trip Parameter Acceptance Criteria for the Safety Analysis of CANDU Nuclear Power Plants

INFO-0545 RADIOISOTOPE SAFETY MONITORING FOR RADIOACTIVE CONTAMINATION

Maine Yankee INDEPENDENT SPENT FUEL INSTALLATION (ISFSI) OFF-SITE DOSE CALCULATION MANUAL CHANGE NO. 32. Approved: Approval Date: 0"/06

Fact Sheet on U.S. Nuclear Powered Warship (NPW) Safety

Developing a Safety Case for Ontario Power Generation s L&ILW Deep Geologic Repository

Treatment Centers for Radioactive Waste

Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3

Safety Analysis for Nuclear Power Plants

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010

How To Decommission A Nuclear Plant

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012

IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI

Naturally Occurring Radioactive Material (NORM)

Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2

Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling

How To Clean Up A Reactor Water Cleanup

Radiation Protection s Benefits in the Production of Iodine-131

MATERIALS LICENSE. In accordance with the letter dated January 15, 2009,

11. Radioactive Waste Management AP1000 Design Control Document

Regulatory Compliance Statement

NUCLEAR POWER PLANT SYSTEMS and OPERATION

Underground Storage Tanks

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE

DEMONSTRATION ACCELERATOR DRIVEN COMPLEX FOR EFFECTIVE INCINERATION OF 99 Tc AND 129 I

Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management

Nuclear Energy of Ukraine - History

Guide to nuclear decommissioning

INTRODUCTION. Three Mile Island Unit 2

5. State the function of pulveriser. The pulverisers are the equipments which are used to powdered coal.

DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Activities of Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) Yasuharu Igarashi

SILICON VALLEY CLEAN WATER. May 2015

V K Raina. Reactor Group, BARC

NORM MANAGEMENT GUIDELINES & PRINCIPLES

The ACR : Advanced Design Features for a Short Construction Schedule

Technical concepts for storing HLW - Monitoring, renewal and refurbishment of storage facilitites

Transportation of Radioactive Material

Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation. G.. d Amored

British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006

Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called...

TYPES OF REGULATORY DOCUMENTS

Andreeva Bay Facilities for SNF Management. CEG IAEA Workshop - February 2010

RADON AND HEALTH. INFORMATION SHEET October What is radon and where does it come from?

Radioactive waste managment in Estonia past, present and future

CRIIRAD report N Analyses of atmospheric radon 222 / canisters exposed by Greenpeace in Niger (Arlit/Akokan sector)


GUIDELINE TITLE: ASBESTOS DISPOSAL AT WASTE DISPOSAL GROUNDS. BRANCH/DIVISION: Environmental Approvals / Environmental Stewardship

Boiling Water Reactor Systems

7.1 General Events resulting in pressure increase 5

GUIDE FOR THE PREPARATION OF RADIOACTIVE MATERIAL APPLICATIONS FOR WELL LOGGING OPERATIONS IN KENTUCKY

Nuclear Waste A Guide to Understanding Where We've Been and Where We're Going

OPG READY TO DELIVER REFURBISHMENT OF DARLINGTON NUCLEAR STATION OPG also planning continued operation of Pickering Station

Regulatory Requirements and Licensing of OPG s DGR Project

Canadian National Report for the Convention on Nuclear Safety

centre for radiation protection

DECOMMISSIONING OF THE GEORGIA TECH RESEARCH REACTOR. Steve Marske, Robert Eby, Lark Lundberg CH2M HILL

MBJ Environmental Programmes

Nuclear Emergency Response Program

HOW IT WORKS ELECTRICITY GENERATION

A Guide to Hazardous Substance Storage Capacity

Nuclear Energy: Nuclear Energy

CHARACTERISTICS OF RADIOACTIVE WASTE FORMS CONDITIONED FOR STORAGE AND DISPOSAL: Guidance for the Development of Waste Acceptance Criteria

PRESENT ISSUES FOR CENTRE DE LA MANCHE DISPOSAL FACILITY

Security and Safeguards Considerations in Radioactive Waste Management. Canadian Nuclear Safety Commission

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario

ATTACHMENT 1-9 CHWSF CONTAINER MANAGEMENT

Engineered Media for Removal of Fission Products from Aqueous Streams Abigail Holmquist, UOP - A Honeywell Company

Transcription:

Decommissioning of CANDU Nuclear Power Stations by G.N. Unsworth

This publication It a revised edition of a report previously published as Chapter S of AECL-S800.

Decommissioning of CANDU Nuclear Power Stations by G.N. Unsworth Mr. Unsworth is Head, Maintenance and Construction Branch, Whiteshell Nuclear Research Establishment at Pinawa, Manitoba. He is an electrical engineer with 20 years' experience in reactor operations. April 1979 AECL - 6332

This report summarizes the results of a detailed study of the various procedures and costs associated with decommissioning a CANDU reactor. The three internationally recognized "stages" of decommissioning (mothballing, encasement, and dismantling) are discussed. It is concluded that decommissioning is possible with presently available technology, and tha costs could be financed by only a marginal increase in the cost of electricity during the life of the reactor. The environmental impact would be no greater than that of any large construction project. Ce rapport resume les resultats d'une etude detaillee des diverses methodes et des couts associes a la mise hors service d'un reacteur CANDU. Les trois etapes de mise hors service (la mise en reserve, le scellement et le demontage) reconnues internationalement sont examinees. Cette etude conclut que la mise hors service peut etre realisee dans le cadre de la technologie actuelle et que les frais encourus peuvent etre finances facilement par un accroissement marginal du cout de I'electricite durant la vie utile du reacteur. L'incidence de I'impact sur I'environnement ne serait pas plus levee que cede provenant de tout grand projet de construction.

INTRODUCTION Operating The term "decommissioning" means shutting down and placing a plant permanently out of service. The operation must be capable of being performed safely and in such a manner as to impose no responsibility on future generations. The decommissioning of nuclear reactors will involve the expenditure of material and manpower and will require careful planning. This summary is based on a study* 11 of decommissioning a single 600 MW(e) CANDU* reactor station (Figure 1). The "design" life of a reactor is normally considered to be 30 years and usually this is chosen as the capital repayment period. There is little likelihood that a utility will choose to decommission a reactor before the end of its design life and, indeed, there will be considerable economic incentive to operate it beyond the design life. Therefore, barring major incidents involving damage to the reactor, it is reasonable to assume that a utility will not consider decommissioning a facility until at least 30 years after start-up and, more likely, will not be involved in decommissioning until more than 40 years after start-up. There are many possible ways to decommission a reactor. They range from simply shutting down the Figure 1 Simplified Vitw of a 600 MW(t) Reactor Building italnment building Calandrla (containing heavy watar moderator ' CANidt Deutarlum Uranium Figure 2 Stage* of Decommissioning a Nuclear Power Station

reactor, to completely dismantling the reactor and releasing the site for other uses. It has been agreed internationally 12 ' that, when referring to nuclear power facilities, three "stages" for decommissioning may be defined. In the order of least complexity to greatest complexity, these are: Mothballing, Encasement, and Dismantling and Removal. Figure 2 shows a schematic representation of the different stages. ACTIVITIES PRIOR TO DECOMMISSIONING A number of factors must be considered prior to decommissioning a reactor and they may affect the option selected. The total inventory of radioactive substances on the site must be determined. This allows an assessment of: the man-rem * exposure expected for any operation, the merits of delaying completion of decommissioning to permit the radioactivity to decay, the weight, volume sr>d specific activity of the material to be shipped to and buried in a waste repository, the weight, volume and specific activity of equipment which will be left on site. Removal of the fuel, heavy water and radioactive waste material will reduce the long-lived radioactive inventory by approximately 98.5 per cent. The remaining "fixed" radioactivity will be due to activation of pressure tube, calandria and shielding materials. Negligible amounts of fission products and actinides will be present. After two to three years, the primary source of gamma activity is cobalt-60. After 20 years, the rate of decay of total activity will be governed by the half-life of nickel-63 and there will be approximately 10 6 curies of activity. After 25 years, most of the material will meet IAEA transport regulations for Low Specific Activity material' 3 '. The major proportion of the activity is associated with the calandria shell, end shields and associated equipment. Decontamination will be required if the gamma fields associated with the out-of-core portions of the primary heat transport system are high or if the system is contaminated with fission products and actinides as a result of fuel defects during the life of the reactor. Decontamination costs can be high, and some of the outof-core portions of the primary heat transport system may be seriously contaminated. Therefore, consideration should be given to allowing the activity to decay (and paying for surveillance costs during the decay period) rather than carrying out decontamination. However, on the assumption that decontamination is to be done, aggressive reagents should be used to ensure 2 that a high decontamination factor is obtained. This is * A measure of human radiation exposure; it Is the total dose In rem received by the Individuals In a given population. possible since corrosion of the components by these reagents need no longer be a major concern. In the case of a 600 MW(e) CANDU reactor the cost of a full decontamination would be approximately $1 200 000*. It is assumed that decontamination will reduce the radioactive fields to a level that will not require any significant man-rem expenditures. Removal of the fuel, heavy water and radwaste will eliminate the capability of operating the reactor and greatly reduce the probability of release of any radioactive material. Therefore, an application to the regulatory authorities for a change in operating licence would be justified so that manpower and surveillance requirements can be reduced. The availability of facilities for the storage of radioactive waste material and the cost of transportation to the storage site will also affect decisions regarding decommissioning. Decommissioning wastes which contain long-lived radioactivity would be placed in a deep underground waste repository when it is available 14 *. Some points that must be considered when developing the specifications for a repository for waste from the decommissioned station and for transporting the waste to it are: (a) The decontamination procedures associated with decommissioning will be effective in removing long-lived fission products or actinides. Therefore, the material to be stored will be solids of relatively low specific activity. Most of the gamma activity will have short half-lives and will decay fast enough to eliminate the necessity of constructing gamma shielding of high integrity and resistance to aging. The only major concern is to provide facilities that ensure the stored solid components will not corrode or dissolve at a rapid rate. (b) The fuel will be stored, as described elsewhere* 4 ), and it is expected that the amount of actinides and fission products in the decommissioning wastes will be reduced to negligible values by decontamination. Therefore, the only material containing significant amounts of these radioactive substances will be those that can easily be separated and will have relatively small volumes, e.g., ion exchange resins, decontamination products, etc. (c) Consideration should be given to retrievable storage. It would seem desirable to store some of the decommissioning wastes in such a fashion that they could be retrieved and re-used after the radioactivity has decayed. There are advantages to this approach since it means the disposal facility does not need to accommodate them and a future scrap value can be attached to some of the waste. (d) The hazards and risks involved in transporting the decommissioned material will be low and easy to manage, since the specific activity levels are low ' All cost estimates are In 1975 dollars.

and the material will be made up primarily of large solid pieces. It can be assumed that the regulations published by the IAEA will apply. Time and cost estimates are required to determine what activities are significant cost items and to obtain an appreciation of what effect the cost of decommissioning might have on a utility's financing. The reactor designer will want to know in which areas the significant cost items lie so that he can investigate whether changes can be made to the original design to reduce decommissioning costs. The owner of a nuclear power plant may use the cost estimates to help decide whether it is more economical to repair a major breakdown or to decommission the reactor. If sinking fund financing is used to defray the eventual costs, only minor changes in cost per kilowatt hour of electricity would be required to cope with large differences in decommissioning costs (Table 1). Actual decommissioning costs are discussed in the next section. Table 1 Assumptions: Discount rate Inflation rate Increments in power cost required to develop a sinking fund of $100 000 000 after "N" years "N" (years) 20 30 40 True discount rate DECOMMISSIONING = 12% per annum = 8% per annum ' 1.08 Increment In Cott (mills per kilowatt hour) 0.82 0.45 0.27 1.037 = 3.7% per annum Mothballlng For "mothballing", the primary containment (piping and equipment associated with the primary cooling circuits) is maintained intact. All systems containing liquids that are radioactive are drained and sealed to prevent escape of contaminated material. The secondary containment (building) is maintained in a condition such that the probability of a release of radioactive material to the atmosphere is no greater than during reactor operation. The atmosphere inside the containment building is controlled to prevent the spread of contamination, and access to the inside of the containment building is controlled. The entire facility is maintained under surveillance, and equipment for monitoring radioactivity both inside and outside the containment building is kept in working order. Inspections are carried out to ensure that both the primary and secondary containment systems are being maintained in an acceptable condition Ṫhe specific actions involved in mothballing are: 1. Remove fuel from reactor and ship all irradiated fuel from used fuel bays off-site. 2. Remove all heavy water and ship it off-site. 3. Decontaminate systems as required. 4. Process and ship to an active disposal area all active waste such as ion-exchange resin, filters, and decontamination solutions. 5. Perform a detailed radiation survey and calculate the total amount of activity on the site. 6. Apply for a change in licence which will specify a reduced minimum staff requirement based on the fact that the potential hazards and risks have been reduced. The surveillance and monitoring requirements will consist of gathering data and submitting reports for quarterly inspection and semi-annual environmental surveys. In addition, effort will be required to maintain and operate the necessary systems. It is expected that the total cost required for activities necessary to mothball a 600 MW(e) CANDU reactor will be approximately $6 000 000 and these activities will occupy one year. The annual expenses to maintain and operate the mothballed facility would be approximately $80 000. The cost of mothballing will not be affected greatly by changes in reactor size. When mothballing is complete, the predominant amounts and types of radioactivity remaining will be: 8 x 10* curies of iron-55 3 x 10 6 curies of cobalt-60 7x10= curies of nickel-63 1 x 10 5 curies of zirconium-95 After 25 years, the predominant activities will be: 6 x 10 5 curies of nickel-63 1 x 10 s curies of cobalt-60 7x 10 3 curies of iron-55 Encasement For encasement, all easily removable parts are dismantled and removed, as are all components that are radioactive to the extent that they will remain a health hazard longer than the life of the proposed encasement structure (<100 years). All radioactive components remaining inside the biological shield are sealed and the building is modified as necessary to provide adequate shielding and containment. The containment building itself and the ventilation system can then be modified or removed since they are no longer required as part of the safety system. If the containment building is left standing, access to it would normally be permitted without any monitoring of personnel for radiation exposure. Surveillance will be required but at a reduced level from that of mothballing since the only concern is to detect possible escape of

radioactivity from within the encasement due to deterioration of the encased structure with age. With an encasement life of less than 100 years, the vessel and all its internal components, including the steel shot from the shield tank (used to provide shielding around the reactor), must be removed from the site. In addition to the steps involved in mothballing, the following activities are required: 1. Disconnect, cut, and/or remove as much of the process piping and equipment as can be handled using the existing access to the building. 2. Build a water-filled "work bay" in the moderator room to permit handling and loading of active sections removed from the core. 3. Remove pressure tubes and ship off-site. 4. Remove and ship off-site all adjuster rods, ion chambers, flux detectors and other in-reactor equipment that was essentially designed for removal and for which removal facilities and flasks are available as routine maintenance equipment. 5. Install a water-tight cover-plate over the outer face of each end shield. Cut out calandria shell, calandria tubes, and end shield inner tube sheet. Remove the steel shot and drain the shield cavity or shield tank. The total estimated cost for encasing a 600 MW(e) CANDU reactor is $17 500000 over a four-year period. The annual monitoring and surveillance costs are estimated to be $60 000. It will cost approximately 30 per cent more to encase a station which is double the size of the reference station, and 20 per cent less for a station which is half the size of the reference station. There will be very little activity left after the encasement work is complete. A very conservative (high) estimate would be 20 curies of cobalt-60 in the vault liner and one curie of iron-55 in the concrete. There will be less than 100 millicuries of nickel-63. The amount of radioactivity that will be sent to burial will be approximately 10 s curies each of nickel- 63, iron-55 and cobalt-60. Dismantling and Removal This is the most complete method of decommissioning. Following the steps outlined for mothballing and encasement, the boilers are removed and the remainder of the active material is dismantled and shipped off-site, including the active concrete from the biological shield. The remaining equipment and structures are dismantled and the material shipped to a local inactive burial site. Finally, the reactor site is backfilled and graded, and released without restriction for other uses. After removal is completed, no further surveillance, inspection or tests will be required. The total estimated cost for dismantling and removal of a 600 MW(e) CANDU power station is $30 000 000 over a six-year period. It is estimated that the dismantling costs for a plant double the size and half the size of the 600 MW(e) station will be 45 per cent greater and 25 per cent less, respectively, than the costs for dismantling the reference station. Dismantling, although the most expensive method, has the advantage over the others that the site becomes reusable and therefore the value of the site is a credit against the cost. MANREM EXPOSURES There should be no need to experience higher exposures or have a higher man-rem expenditure as a result of decommissioning of a nuclear power plant than would be encountered during normal operation and maintenance of the plant. Estimated exposures for each stage of decommissioning are shown in Table 2. Exposure by ingestion or inhalation of radioactive dust and gases should be negligible. Table. 2 Stag* Dismantling Encasement Mothballing Man-ram Exposures Decommissioning Total exposure (maimem) 600 400 plus 0.1/yaar of surveillance 250 plus 0.5/ye«rof surveillance ENVIRONMENTAL IMPACT Involved in Avenge exposure, per inaiif per year (run) 1.0 1.0 plus 0.05 during period of surveillance 1.0 plus 0.1 during period of surveillance None of the decommissioning stages will have other than minimal effect on the local environment and, in fact, the only effect that would not normally be encountered with any large construction project would be that due to disposal of the radioactive inventory. All shipments of radioactive material will be in approved shipping containers and made in such a way as to meet all relevant requirements. These shipments will not create any undue hazard to the public or result in exposure of the public to levels of radiation above those permitted by the AECB. None of the decommissioning activities should result in the release of any significant amount of active gases or dust to the atmosphere or otherwise externally from the containment. In respect to disposal requirements, the estimated volumes of the various types of material resulting from each decommissioning method are low. For dismantling, which involves the highest volume, the specific requirements are:

1. The highly active material will be encased in concrete or lead liners and will occupy approximately 250 m 3. 2. The remaining active material will occupy a volume roughly estimated at 7000 m 3. 3. The components of systems that are not contaminated will, wherever possible, be sold as scrap but the remaining material to be disposed of will occupy a volume of approximately 25 000 m 3. For encasement, the highly active material will be the same as for dismantling and the volume will therefore be 250 m 3. For mothballing, there are no disposal requirements. study for the heavy water remaining when the station is decommissioned. The value of this material is comparable to the dismantling costs. Assuming that satisfactory provisions are made for disposal of the fuel, heavy water and radioactive waste, and that suitable sites can be found for disposal of active components, the environmental impact of decommissioning a reactor will be no greater than that of any large construction project. SUMMARY AND CONCLUSIONS Table 3 summarizes the more significant data for each decommissioning stage considered. The following conclusions may also be drawn: 1. Decommissioning to any of the three stages is possible and can be done without development of new technologies or equipment. 2. The cost of decommissioning a nuclear power plant should not be a major concern to a utility; it could be covered by sinking fund financing, which would increase the mill-rate by less than 0.2 mills per kilowatt hour for the most expensive process (dismantling and removal). No financial credit is given in this Tabto 3 Summary of finding* of this study 1. Time required 10 and removal ayeari 4 yeere 1 y&ar 2 Radiation expoeure to personnel during WO Man-ram WO Man-ram 400 Man-ram MO Man-rani decommiaaloninfl.;.. 3. Amount of radioactivity on ene at and of Negligible Negligible 20curlei lixio^curlei decommieatonlng period 4. Amount of radioactivity In dlapoaal at and of decommmlodtng period (does not (Delude fuel, heavy water or radioactlvewaett) 4.2x10 e eufle» 6.3x10* curie* 0 5. Dlepoeal valuma required 72S0m 3 of active 250 m 3 of active 0 (doe* not Mduda fuel, volume volume heavy water or radioactive waata) bytruokofmlnw H 000 m 3 of inactive volume (Ma lafm torap metal) 300-400 Meooet 1*0000000 117 M0 000 phie M0 ON 0#f WHNM1 ' lermveera ' M 000 000 eluenoom

REFERENCES (1) G.N. Unsworth, Decommissioning of the CANDU- PHW Reactor, Atomic Energy of Canada Limited, Report AECL-5687 (April 1977). (2) Decommissioning of Nuclear Facilities, Report of a Technical Committee Meeting, International Atomic Energy Agency, Report IAEA-179, Vienna (October 20-24, 1975). (3) Regulations for the Safe Transport of Radioactive Materials (Revised Edition), Safety Series No.6, International Atomic Energy Agency, Vienna (1973). (4) R.G. Hart, Management of Nuclear Waste, Atomic Energy of Canada Limited, Report AECL-6333.

Copies of this publication are available from: Atomic Energy of Canada Limitad Public Affair* OfNca Shtridan Park Raaaarch Community MiMitsauga, Ontario L5K1B2

Atomic Energy L'Energie Atomique of Canada Limited du Canada, Limitee AECL-6332 April 1979 La prgsente publication est egalement disponible en frangais