Federation of Piling Specialists July 2010



Similar documents
Federation of Piling Specialists

hs2 Ground A non-technical guide

Design and Construction of Auger Cast Piles

BUTE Department of Construction Management and Technology

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Federation of Piling Specialists Testing Datasheet No 1

Emergency repair of Bridge B421

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

Asset Data Dictionary Definition Document Continuous Flight Auger Piles (CFA) Uniclass Classification

Safe & Sound Bridge Terminology

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

METHOD OF STATEMENT FOR STATIC LOADING TEST

SERVICES 2015 ISO 18001

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

ATLAS RESISTANCE Pier Foundation Systems

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

Geotechnical Building Works (GBW) Submission Requirements

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

Walking and Working Surface Checklist:

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Excavation Safe Working Practices

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

SECTION EARTH MOVING

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

Supplier ID: Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

High Capacity Helical Piles Limited Access Projects

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Recommendations to improve the safety of existing lifts

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Now That s IDEAL. Now That s IDEAL. LISTEN. RESEARCH. DESIGN. DELIVER.

SECTION SELECTIVE DEMOLITION

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

Level 1 Award in Health and Safety in a Construction Environment

BRIDGES ARE relatively expensive but often are

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

High Strain Dynamic Load Testing of Drilled Shafts

J. & W. LOWRY LIMITED. This case study has been prepared for J & W Lowry Limited By Thomas Elliott Foster

Accidents - how to deal with them

Moving Small Mountains Vesuvius Dam Rehab

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

90 Brighton Road, Surbiton, Surrey

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

HYDROCARBON SPILLS PROCEDURE SIG-ENV-PR003

BRITISH GEOLOGICAL SURVEY

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Lighthouse Engineering, L.L.C.

GUIDANCE FOR CARRYING OUT RISK ASSESSMENT SURFACE MINING OPERATIONS

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Pro-Lift Steel Pile Foundation Repair

GUIDE TO TRENCH EXCAVATIONS (SHORING SUPPORT AND DRAINAGE MEASURES)

SECTION SITE PREPARATION

Sewer Rehabilitation Design Requirements

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

Procedure for Working in or around Excavations

Embedded Parts Introduction - Anchors

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No M (Supersedes Report No.

Hanson Building Products. precast basement solutions

TECHNICAL REVIEW OF SECONDARY CONTAINMENT SYSTEM TECHNOLOGY FOR ALASKA

For ease of reference the clauses are arranged in 12 sections as follows:-

AUSTRALIAN INSURANCE SOLUTIONS PTY LTD

SECTION ABANDONMENT OF SEWER MAINS

GEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS

SECTION SUPPORT OF EXCAVATION

Trenching and Excavation Safety

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Unit Price Averages Reports

Table of Contents 16.1 GENERAL Overview Responsibilities

GLOSSARY OF TERMINOLOGY

Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting

Chapter 9 Remedial Measures

and the design of construction working platforms

68 Metal Industry Guidelines for Safe Work

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Building façade maintenance

Managing the risk of falls while working on roofs in housing construction

Mobile cranes overturning on construction sites. A guide to loss prevention

Guide to Carrying Out Engineering Works within Road Structure Safety Zone and Engineering Activity on Land adjoining Public Streets

Traffic Management Issue 1.0 Revision: v2 October 2014

Transformer Deluge Systems

TECHNICAL NOTE: SI 01 SPECIFIC REQUIREMENTS FOR THE ACCREDITATION OF INSPECTION BODIES FOR SITE INVESTIGATION

SITE SPECIFIC FALL PROTECTION PLAN

Basement construction and waterproofing: Construction, safety, insulation and services. good building guide

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Transcription:

Examples of Hazards associated with Piling and Diaphragm Walling Works and how these might be managed within the design phase of a project (neither exhaustive nor exclusive) This list of examples has been produced to assist designers but given the unique nature of each individual project can not be considered exhaustive. The designer must consider the issues relevant to every new situation when engaging in the risk management process. It is important here to be aware that by designing out one hazard and eliminating the associated risk quite often another hazard will be introduced into the process. Sequencing of piling work. Piles located in positions with restricted working space, e.g. corners of site and adjacent to public areas outside the site. Piling near to the top of slopes. Working in excavations. Inadequately designed/constructed/maintained working platforms. Conflict with other parts of the project construction creating unsafe working conditions. Personal injury from falling debris, crushing. Unsafe removal of guards or auger cleaners. Risk to third parties. Slope failure, rig overturning. Access ramps and wall props can impede working space. Rig overturning, unsafe working conditions for operatives. Plan for safe, practical and economic working, not just for time. Avoid return visits for piling rigs if possible. Design the foundation so that the plan position of piles or alignment of the wall allows adequate working space with rig guards fitted and operational. Only in extreme situations, and after consultation with the CDM Co-ordinator, a controlled procedure according to FPS Notes for Guidance on PUWER Regulations in relation to Guarding and Cleaning of Augers on Piling Operations (March 2010) may be implemented. Consider the type and size of rig(s) to be used, track bearing pressures and the requirements for adequate safe working space, exclusion zones and storage areas. The physical limits of the designed platform should be clearly defined on site. Evaluate the balance between optimum earthworks scheme and optimum pile foundation scheme. Ensure working platform is designed, constructed and maintained in accordance with published guidance or other appropriate best practice. Specify site investigation works to take account of the need for measuring near surface soil properties required for design. Construct platform according to specification, inspect regularly and maintain to original specification. Operate proper procedures for excavations (e.g. for removal of obstructions) and reinstatement. Page 1 of 6

Underground services. Unexploded explosive ordnance (UXO). Overhead services. Working adjacent to major highways or railways Static load tests using kentledge as the reaction for loading. Personal injury or death, loss of amenity, delay to project. Personal injury or death, damage to construction plant and/or surrounding property, delay to project. Injury to workforce, electrocution, fire, loss of amenity, delay to project. Plant or materials falling onto road or rail Dangers of working at height. Enquiries with utility companies to establish presence of services. Arrange pile positions to bridge over services. Instigate permit to dig/work systems. Undertake preliminary risk assessment and if possibility of UXO is identified notify client of his CDM responsibilities should it appear they have not been discharged. Follow on with detailed assessment and risk mitigation. Implement UXO risk management strategy and emergency response plan. Instigate appropriate method statements and lifting plans. Agree working clearances with utility companies. Utilise smaller/low headroom plant if required, possibly with a change of construction technique if technically acceptable. Instigate appropriate method statements and lifting plans. Agree working clearances with relevant authority. Utilise smaller plant possibly with a change of construction technique if technically acceptable. Wherever technically feasible use reaction piles or other means of providing the reaction. CFA auger changes. Personal injury. Limit number of pile sizes on one project where possible by varying pile lengths. Hand tying of reinforcement cages. Racking of/damage to reinforcement cages while lifting. Open pile bores or wall panel excavations, with or without support fluid. Diaphragm wall panel instability prior to concreting. Repetitive strain injuries. Injury to operatives from falling steel bars. Operatives falling into open bore or excavation, injury and possible drowning. Instability of heavy plant at surface with potential for overturning. Use automated cage making equipment or tying tools. Consider design of reinforcement cages to ensure adequate robustness for temporary lifting stresses. Consider provision of lifting rings etc. Avoid leaving pile bores open, implement suitable protection measures such as barriers and life-jackets. Ensure adequate slurry head above high groundwater level. Avoid excessive surcharge and/or ground borne vibration near panel. Page 2 of 6

Displaced pile/panel support fluid during concreting. Contaminated spoil. Ground water contamination. Immediate environmental impact. Excessive vehicle movements on/off site. Flighting of soils during pile installation. Incorrect retaining wall excavation sequence. Temporary wall props. Contamination of open water courses. Infection of piling operatives, contamination of the site and the surrounding area. Damage to water resources. Unacceptable levels of noise and/or vibration, hearing damage to operatives. Traffic incidents, personal injury, air pollution, noise. Damage to/instability of adjacent buildings. Excavation below design depth leading to potential wall failure. Wall collapse if props are damaged. Adequate containment by bunding and control by pumping and tanking/settlement tanks as necessary. Use displacement piling methods unless these are technically unsuited to the site soil conditions or performance requirements of the foundation. Carry out foundation risk assessment in accordance with Environment Agency guidelines (1). Consider increasing pile size or number of piles to allow piles to stop above water table Determine acceptable levels of both effects that can be tolerated by the nearest receptors (both human and non-human). Compare these with predicted levels from piling techniques suited to the ground conditions and load bearing requirements, remembering to take account of anticipated programme periods and all ancillary operations. Enforce hearing protection zones. Use quiet hammers or alternative non-percussive installation methods (e.g. contiguous flight auger). Piling techniques that reduce or eliminate spoil will reduce this risk. Consider the susceptibility of soils to flighting due to piling method or plant employed. Implement suitable monitoring/construction controls or alternative piling methods or plant. Ensure excavation sequence (including levels) is communicated to project team. Design with minimum propping. Consider possibility of changing the construction sequence Failure of retaining wall props. Collapse of excavation. Ensure propping levels, sequencing and loads are communicated to project team and that responsibilities for design and implementation of propping are clearly defined. Page 3 of 6

Pre-stressed ground anchors. Overall stability of embedded Stability of a slope above a Base fracture by hydraulic heave or piping. Excess surcharge placed behind Sudden release of prestress energy, personal injury, damage to surrounding area. Failure passing beneath toe of Failure on slope entirely top of Rapid flooding of excavation and potential retaining wall collapse. Collapse or distress of Ensure adequate information regarding the details of pre-stressed anchors is passed on to project team so it may be incorporated in the H & S file/maintenance manual Ensure responsibility for considering this failure mode has been assigned and communicated to project team. Ensure responsibility for considering this failure mode has been assigned and communicated Consider hydraulic aspects of wall design and incorporate the necessary measures into the design. Communicate construction controls (e.g. water level to be maintained if excavating in the wet) to project team. Ensure surcharge loads/limits are clearly specified and accounted for in the design. Ensure any limitations on surcharges are communicated to project team. Ground movements behind retaining walls. Pile trimming to cut-off level and exposing of reinforcement. Scabbling pile surface. Exposed ends of reinforcement after pile trimming. Damage/instability of adjacent structures. Vibration white finger injuries. Personal injury from flying debris, vibration white finger injuries. Personal injury. Consider the effect of ground movements arising out of pile installation and wall excavation on adjacent structures. Consider if any monitoring is required. Communicate any construction controls (including responsibilities) to project team. Correct use of mechanical pile croppers or other means of pile trimming that do not involve the excessive use of hand-held tools. Consult Federation of Piling Specialists guidance (4) on breaking down of piles. Consider the possibility and practicality of debonding reinforcement above cut off level. Use pile concrete retardant to enable lighter methods of achieving scabbled finish to pile surface. Use protection caps on the bars after pile trimming and before placing foundation concrete. Page 4 of 6

Inadequate access to piles for integrity testing. Congested reinforcement in pile caps around head of pile during integrity tests. Voids and collapsed deep mine workings, opencast quarry edges. Shallow mine workings. Solution features in weak rocks such as chalk and marl. Inadequate or non-existent ground investigation report. Personal injury trips and slips. Personal injury to integrity testing operatives Loss of concrete with cast insitu piles, loss of base support to all pile types, possibly damaged or broken piles. Collapse of ground, loss of support to piling plant, delay to project. Loss of platform support, loss of concrete, delay to project. Inaccurate assumptions about soil parameters & profile leading to inadequate pile performance. Ensure safe access to pile head avoid steep sides of excavations for pile caps provide safe means of access and egress. Ensure there is uncluttered access to pile heads at time of test. Plan for integrity testing to taken place between pile trimming and placing of pile cap steel. Obtain Coal Authority Report (2) to determine existence of abandoned deep/opencast workings or shafts/high walls and consider also local anecdotal evidence. Grouting may be required or it may be possible to relocate structures to avoid some features. If desk study indicates likely presence Coal Authority Report (2) must be a part of the site investigation works. Use properly designed piling platform appropriate to the intended rig. Grouting may be required Resistivity imaging, electromagnetic conductivity, microgravity, can all be used in conjunction with (gamma) cone penetration testing to identify these features. Educate the Client regarding the value of a good GI and specify a scope of intrusive investigation works that is appropriate to the nature of the project and the anticipated ground conditions, starting with a good desk study. Confirmation of bedrock levels. Bedrock or boulders? Establish from desk study the expected depth to bedrock and treat shallow refusal of cable percussion boring with suspicion. Continue for an appropriate depth below rockhead with rotary drilling to prove the rock. Over reliance on pile end bearing in variable/layered rocks. Concrete durability. Excessive pile settlement possible pile failure. Inadequate concrete specification. Consideration of partial factor of safety greater than unity on shaft resistance only or reduced end bearing component. Ensure that ground and groundwater samples are collected and tested to establish the chemical properties required to apply BRE SD1 (3) protocol for classification. Page 5 of 6

Further sources of information and references: - (1) Federation of Piling Specialists papers on a number of subjects related to this guidance note can be found on the FPS website http://www.fps.org.uk/fps/guidance/guidance.php (2) Institution of Civil Engineers specification for piling and embedded retaining walls Second edition (2007) is published by Thomas Telford Publishing, Thomas Telford Limited, 1 Heron Quay, London E14 4JD http://www.thomastelford.com/books/ (3) Environment Agency Guidance Piling in layered ground: risks to groundwater and archaeology Science Report SC020074/SR, Piling and Penetrative Ground Improvement Methods on Land Affected by Contamination: Guidance on Pollution Prevention National Groundwater & Contaminated Land Centre report NC/99/73. Both documents are published by: - Environment Agency, Rio House, Waterside Drive, Aztec West, Almondsbury, Bristol, BS32 4UD Tel: 01454 624400 Fax: 01454 624409 http://www.environment-agency.gov.uk (4) Coal Authority Reports can be obtained from http://www.coal.gov.uk/services/ (5) BRE Special Digest 1: 2005 Concrete in aggressive ground can be ordered from: - BRE Bookshop, Garston, Watford, WD25 9XX, http://www.projects.bre.co.uk/sd1/wheretobuy.html (6) The services of the British Geological Survey can be accessed at http://www.bgs.ac.uk/ Disclaimer Although every effort has been made to check the accuracy of the information and validity of the guidance given in this document, neither the FPS or its members accept any responsibility for mis-statements contained herein or misunderstanding arising herefrom. Federation of Piling Specialists Forum Court 83 Copers Cope Road Beckenham Kent BR3 1NR Tel: 020 8663 0947 Email: fps@fps.org.uk www.fps.org.uk Page 6 of 6