Control Number : 37897. Item Number : 9. Addendum StartPage: 0



Similar documents
1. Who is CenterPoint Energy Houston Electric, LLC?

345 kv Brazos Valley Connection Project FAQs

Houston Region Import Capacity Project

Item 8: Houston Import RPG Project

Report on Existing and Potential. Electric System Constraints and Needs

Grid Operations and Planning

LSE Registration ERCOT Region. By Derrick Davis Texas RE Corporate Counsel

Austin Energy Resource, Generation and Climate Protection Plan to 2025: An Update of the 2020 Plan

How To Write A Letter To The Public Utility Commission Of Texas

PJM LMP Market Overview

HVDC Transmission Line Project for Moving ERCOT Wind Into SERC

ERCOT Long-Term System Assessment. Executive Summary

2014 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market

REPORT ON EXISTING AND POTENTIAL ELECTRIC SYSTEM CONSTRAINTS AND NEEDS WITHIN THE ERCOT REGION

Control Number: Item Number : 301. Addendum StartPage : 0

Experience in Electricity Market Restructuring. Texas: Mostly Good. Jay Zarnikau Frontier Associates And University of Texas at Austin.

Control Number : Item Number: 373. Addendum StartPage: 0

All routes and route segments included in this notice are available for selection and approval by the Public Utility Commission of Texas.

CenterPoint Energy Robert B. Frazier Director of Electric Technology

2013 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market

GDS Associates, Inc. Senior Project Manager Page 2 of 7

Generator Interconnection and Deliverability Study Methodology Technical Paper

Form 409 General Information (Articles of Amendment Limited Liability Company) Commentary. Procedural Information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Control Number : Item Number : 262. Addendum StartPage: 0

Control Number : Item Number : 516. Addendum StartPage : 0

CLIENT INFORMATION: GUIDELINES ON ADMINISTRATION & BILLING

INVESTIGATION OF BULK POWER MARKETS. ERCOT (Texas)

Wind and Energy Markets: A Case Study of Texas.

ITP Evaluation Process Plan Cross-Tie Transmission Line

Transmission Planning in the ERCOT Interconnection

Control Number : Item Number : 298. Addendum StartPage: 0

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update

Grid. Outline Grid: Transmission and Distribution ERCOT. Based on. - Electricity. Chapter 2.2 of Energy Trading and Investing. D. Edwards, 2010.

Order Authorizing Securitization of Certain Additional Transition Costs and Related Transactions

Sale of Partnership and LLC Interests: A Walk Through Purchase and Sale Agreements

BCSE Briefing: Driving US Economic Growth and Jobs. Chris Perrault, Vice President January 26, 2011

Texas Smart Energy v1.0 HAN Deployment. Delivery

PENNYWISE POWER RESIDENTIAL TERMS OF SERVICE

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Industries Association. ERCOT Successes and Challenges

CenterPoint Energy Electric & Natural Gas Utilities in Texas Bill Rogers, EVP & Chief Financial Officer Scott Doyle, SVP Regulatory & Public Affairs

5/27/2015. Overview of Energy Storage Value Propositions and Business Cases. Utility Cost-Function: Foundation of Energy Storage Economics.

MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION

COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF


NRG Energy to Combine with Texas Genco Creating the Leading Competitive Power Generation Company in the United States

Oncor s Pioneering Transmission Dynamic Line Rating (DLR) Demonstration Lays Foundation for Follow-On Deployments

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

lllll Ill II IIIIII IIII I) Control Number: 20366

P.O. Box 578, Deer Park, TX Home Equity Loans

Executive Search Announcement

INVESTING IN A CLEAN FUTURE. Austin Energy s Resource, Generation and Climate Protection Plan to 2020 Update

Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT

SOLAR PURCHASE POWER AGREEMENT (PPA) FREQUENTLY ASKED QUESTIONS. UPDATED: October 28, 2015

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

California s Energy Future

Form 205 General Information (Certificate of Formation Limited Liability Company) Commentary

Transcription:

Control Number : 37897 Item Number : 9 Addendum StartPage: 0

PROJECT NO. 37897 PUC PROCEEDING RELATING TO PUBLIC UTILITy/^OI^IMISSIO^ RESOURCE AND RESERVE ^CL_^ ADEQUACY AND SHORTAGE OF TEXAS PRICING COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC On May 11, 2011, the Electric Reliability Council of Texas ("ERCOT") issued a report entitled "Review of the Potential Impacts of Proposed Environmental Regulations on the ERCOT System" ("the Study"). The Study analyzed the impact of four potential regulations that could be imposed on electric generation facilities. The system topology used for the Study included all transmission improvements that have been endorsed by the ERCOT Board of Directors, which would include the Fayetteville to Zenith 345 kv transmission project proposed by CenterPoint Energy Houston Electric, LLC ("CenterPoint Energy" or "the Company"). On May 20, 2011, the Public Utility Commission of Texas ("the Commission") published a public notice of a workshop in this project and requested input on two issues. Comments are due by June 6, 2011. CenterPoint Energy submits the following comments in response to the Commission's published notice. 1. Please provide any comments on the Review of the Potential Impacts of Proposed Environmental Regulations on the ERCOT System. CenterPoint Energy is a transmission service provider ("TSP") providing service within the ERCOT Region with its service territory including Houston and surrounding communities. As set forth below, the findings contained in the Study are of significant concern to CenterPoint Energy. The Study determined that "[t]he retirement of intra-urban generation resources would result in the need to import more power to serve load, leading to potential overloads and increased reactive power requirements." It also determined "the two areas of specific concern for transmission reliability are the Dallas/Fort Worth region and the Houston region." The section that addressed concerns with the Houston region stated "it is likely that at least two new import pathways into the Houston region would be required to maintain system reliability.", ^

CenterPoint Energy has been diligently working to increase import capacity into the greater Houston area since import constraints into the Houston area were first identified by ERCOT in 2002. During the intervening years, the Company has completed a number of improvements that have increased import capacity into the Houston area. In 2007, CenterPoint Energy constructed a new Hi11je Substation and 345 kv double circuit transmission line from Hillje to W. A. Parish as well as other related projects. The Singleton 345 kv Substation was completed in May 2009. In April 2011, the Zenith 345 KV Substation was constructed increasing the North to Houston transfer capacity to the extent possible without building new transmission lines. Most recently, the ERCOT Board of Directors approved the Fayetteville to Zenith transmission project that is being developed. The additional import pathways discussed in the Study would be in addition to these improvements. The need for additional import transmission pathways into the Houston area, in addition to the currently planned Fayetteville to Zenith transmission project, has not been definitively established. However, in order to meet a potential need for transmission projects in 2017, costeffective solutions would need to be developed at this time. Therefore, CenterPoint Energy is concerned about the potential impacts upon the Houston area identified in the Study. As reflected in the Study, the proposed environmental regulations have potential impacts upon generation capacity reserve margins. Setting aside the potential effects of the proposed environmental regulations, preliminary results from ERCOT's Long Term Study effort also indicates the current ERCOT market design (i.e. energy only versus capacity) may not support sufficient generation capacity investment to maintain an acceptable generation capacity reserve margin within the ERCOT Region. Preliminary analyses for the Long Term Study effort likewise indicates that additional import paths, in addition to the currently planned Fayetteville to Zenith transmission project, may be needed into the Houston area regardless of the proposed environmental regulations. However, the time frame for the potential necessary transmission capacity is much longer without the proposed environmental regulations than it is with the proposed regulations. 2

In addition to evaluating sufficiency of generation capacity within the entirety of the ERCOT Region, it is suggested that it would be beneficial for ERCOT and the Commission to evaluate generation capacity adequacy within significant, potentially transmission-constrained load areas. The value of evaluating sufficiency of generation capacity in such a manner would be to identify potential need for additional transmission capacity in sufficient time to allow necessary additional facilities to be constructed or, alternatively, to allow the Commission to identify and implement alternative means to incent new generation capacity or demand response in the transmission-constrained areas to avoid or delay the need for additional transmission capacity, if the Commission determines it is practical and cost-effective to do so. The significant, potentially transmission-constrained load areas used by ERCOT in preliminary Long Term Study analyses are Houston, Dallas-Fort Worth, and the Rio Grande Valley. CenterPoint Energy believes these are reasonable load areas for ERCOT and the Commission to evaluate. The additional evaluation CenterPoint Energy proposes would be a capacity demand reserve calculation for each of these three load areas that account for import capacity into the load area. To illustrate the concept, the following hypothetical example is provided. The load area is assumed to have a peak load of 10,000 MW, generation within the load area of 7,000 MW, and import capacity of 5,000 MW. In this hypothetical example, the capacity available to serve the 10,000 MW of peak demand in this load area is 12,000 MW (7,000 MW of local generation plus 5,000 MW of generation that potentially can be imported), so the "local" reserve margin is 20% (2,000 MW/10,000 MW). The capacity demand reserve for a local area may necessarily need to be higher than the region-wide capacity demand reserve margin due to a smaller generation fleet available to serve the localized area and transmission limitations due to outages or other network conditions that limit import capacity below the maximum potential import capacity with all transmission facilities in-service. 3

2. What reserve margin levels can be reasonably expected within the ERCOT system with the proposed changes in environmental regulations? CenterPoint Energy does not have any comments at this time. Respectfully submitted, h ^C GrIJ^ ^p$th'1/ss^^h SCOTT E. ROZZE L Executive Vice President and General otfns State Bar No. 17359800 DEANN T. WALKER State Bar No. 20696840 1005 Congress, Suite 650 Austin, Texas 78701 (512) 397-3032 (512) 397-3050 (fax) ATTORNEYS FOR CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC 4