Smarter Network Storage The UK s largest electrical energy storage system. Martin Wilcox, Head of Future Networks



Similar documents
Smarter Network Storage Design and planning considerations for large-scale distribution-connected energy storage (SNS1.2)

Smarter Network Storage - business model consultation

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply.

Modular architecture for high power UPS systems. A White Paper from the experts in Business-Critical Continuity

Executive summary 2. 1 Introduction 4

Venteea A Smart Grid demonstrator for the DRES integration on the MV distribution networks.

Electric Utility Crossroads Includes Renewables and Storage

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

Field experience and best practices in managing MW scale Li-ion energy storage systems coupled to large wind and solar plants

Customer-Led Network Revolution Electrical Energy Storage Cost Analysis

CLASS. Customer Load Active System Services

Intensium Max. A range of ready-to-install containerised energy storage for renewable energies and grid management

EXAMPLE OF A DATA CENTRE BUILD

Energy Storage - Program 94

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman.

An Uninterruptible Power Supply Topology to Manage the Arrival of Big Data Kenny Green

Introduction to the ELSA pilots & use cases

Advanced Electricity Storage Technologies Program. Smart Energy Storage (Trading as Ecoult) Final Public Report

NIA Project Registration and PEA Document

STORAGE ELECTRICITY. Improving the world through engineering

Datacentre Studley. Dedicated managed environment for mission critical services. Six Degrees Group

Mixing Sodium and Lead Battery Technologies in Telecom Applications

SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE

ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid

ALSTOM Grid s solution

Monitoring Underground Power Networks

EssPro Energy Storage Grid Substation The power to control energy

This 5 days training Course focuses on Best Practice Data Centre Design, Operation and Management leading to BICSI credits.

7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America

Smart Grids. MIECF Conference April 2011

Safeguard your critical IT assets in a highly secure, fully redundant, environmentally-conditioned and constantly monitored hosting space to receive

Overview brochure. Energy Storage Keeping smart grids in balance

Datacentre Capability March 2015

Increasing safety, reliability and efficiency for today s data centers

Opportunity of Energy Saving in electrical path is lesser as compared to other areas

Preparing for Distributed Energy Resources

Galaxy VM. Three-phase power protection. schneider-electric.com

Smarter Buildings & Management of Buildings

Storage Battery System Using Lithium ion Batteries

ADMS(Advanced Distribution Management System ) in Smart Grid

Datacentre London 1. Dedicated managed environment for mission critical services. Six Degrees Group

Applying ICT and IoT to Multifamily Buildings. U.S. Department of Energy Buildings Interoperability Vision Meeting March 12, 2015 Jeff Hendler, ETS

Public Service Co. of New Mexico (PNM) - PV Plus Storage for Simultaneous Voltage Smoothing and Peak Shifting

Delivering results with Datacenter Clarity LC TM

Title: Design of a Shared Tier III+ Data Center: A Case Study with Design Alternatives and Selection Criteria

Containerized Infrastructure Solutions Fast and efficient deployment, anywhere, anytime

Optimum Climate Control For Datacenter - Case Study. T. Prabu March 17 th 2009

Anthony Price Swanbarton Limited, Dairy Farm, Pinkney, Malmesbury, Wiltshire, SN16 0NX Telephone

Energy Storage Systems. New solutions for a new energy environment

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist

AMI and DA Convergence: Enabling Energy Savings through Voltage Conservation

Reducing Data Center Energy Consumption

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel

Data center solutions from Siemens. For the factories of the 21 st century. siemens.com/datacenters

The Virtual Power Station - achieving dispatchable generation from small scale solar

Strategic Microgrid Development for Maximum Value. Allen Freifeld SVP, Law & Public Policy Viridity Energy

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions

BU Control Technologies, Decathlon TM Product Overview. ABB in the Data Center Overview

Trends and Standards in LAN Cabling Systems Intelligent Buildings

Yam Hong 施 耐 德 電 機 亞 太 日 本 區 (APJ) 三 相 關 鍵 電 源 市 場 開 發 經 理. Schneider Electric - Division - Name Date

Increasing Data Center Efficiency by Using Improved High Density Power Distribution

TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

Principles of Distribution charging:

RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast.

Power Management of Cell Sites

RVH/BCH Data Centres Proposals for Surge Protection and Ventilation

TECHNICAL DESCRIPTION OF THE DISTRIBUTION SUBSTATION REMOTE MONITORING SYSTEM

Monitoring & Control of Small-scale Renewable Energy Sources

Liebert APM from kw. The Compact Row-Based UPS With FlexPower Technology TM

Issue 11/2015. Technology for Professionals 100% Made in Germany Industrial IT Energy Storage

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11 th March 2015

Daikin Altherma Hybrid Heat Pump

Operating the power system while enabling more renewables : which solutions?

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.

Energy storage in the UK and Korea: Innovation, Investment and Co-operation Appendix 4.1: Stakeholder interviews from Korea

Enterprise Approach to OSIsoft PI System

Advanced Inverter Overview

Modern Power Systems for Smart Energy Society

Paralleling Switchgear

AMSC s Superconductor Cable Technologies for Electric Utilities

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC DRAFT V0.

European Distribution System Operators for Smart Grids. Flexibility: The role of DSOs in tomorrow s electricity market

Measuring Power in your Data Center: The Roadmap to your PUE and Carbon Footprint

Energy Storage System Performance Testing

ARRA Grant Case Studies SMUD s Smart Grid Program

Transcription:

Smarter Network Storage The UK s largest electrical energy storage system Martin Wilcox, Head of Future Networks

Welcome & Housekeeping 2

Agenda for the day Morning session General overview and introduction to business case Site planning and storage design/technology Afternoon session Smart Optimisation and Control IT platform Moving into 2015/6 3

Introduction to Smarter Network Storage Nick Heyward, Smarter Network Storage Project Director

What use is energy storage to network operators? Future challenges: Increased penetration of low-carbon technologies, distributed generation and greater intermittency in the energy mix Increased electricity demand Higher peak demands Thermal & voltage constraints Less predictable load & generation cycles Significant costly and disruptive network investment, without smart intervention 5

Storage can avoid these issues, and reduce network investment costs Using storage to manage peak demands, or smooth renewables output can defer or avoid the drivers of conventional reinforcement Increased electricity demand Higher peak demands Thermal & voltage constraints Less predictable load & gen cycles Greater flexibility and avoided or reduced network investment 6

Our small-scale installation has proved some of the concepts Location: Hemsby, Great Yarmouth Energy capacity: 200 kwh Real power: 200kW (600 kw (peak) for short durations) Reactive power: 600kVAr 7

helping to provide learning and confidence in the use of storage 8

Several challenges hamper widespread adoption... High CAPEX cost of commercial storage technologies = multiple stacked benefits needed Challenges in accessing multiple benefits & optimising Limited experience of any proven business models Uncertainty in policy and regulatory landscape Limited experience and confidence in storage as network-connected assets 9

which the Smarter Network Storage project hopes to help address High Demonstrate CAPEX cost multi-purpose of commercial application storage technologies of storage sharing = multiple learning stacked on the benefits realisable needed benefits Develop Challenges novel in optimisation accessing multiple & control benefits systems & for optimising storage Provide Limited insight experience & assess of any viability proven of business multiple models business model variants Uncertainty Assess regulatory in policy and & legal regulatory barriers, landscape make recommendations & develop commercial arrangements for shared use Limited Deployment experience & operation and confidence of large-scale in storage battery as energy storage network-connected adding to body assets of learning for DNOs 10

The Smarter Network Storage Project 13.2m LCN funding awarded in Nov 2012 4.0m investment by UK Power Networks Partners Suppliers 11

SNS Where are we in the Journey? Planning & Design of Storage Oct 2013 Storage Commissioned Oct 2014 2013 2014 2015 2016 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Design Build Installation Trial Application & Service trials Commercial & Regulatory assessments Business Models Consultation July 2013 SOCS IT Design & Architecture Dec 2013 Commercial arrangements for shared use Oct 2014 12

The SNS Business Case Nick Heyward, Smarter Network Storage Project Director

Drivers of the Storage Business Case Value of constraint avoidance Local evolution of demand/generation Storage Capex & Opex Storage technical capabilities Benefits streams available, and apportionment Ancillary market pricing 14

MVA The alternative to storage Grid substation 132kV to 33kV Grid Supply 45 40 Site Demand 20/12/10-21/12/10 Demand N-1 rating 35 30 Power flow Conventional intervention: 3 rd line 25 20 00:00 12:00 00:00 12:00 00:00 Time Overhead lines Primary substation 33kV to 11kV To Customers Energy Storage Single overhead line capacity Site demand / customer load 15

Why DNOs haven t yet deployed storage On a pure CAPEX basis, energy storage can seldom compete with the conventional options Third 33kV OHL and 38MVA Primary transformer 6MW/10MWh Energy Storage System 6.2m 11.2m Including labour, civil, electricals. Excluding Opex. All values in 2013 prices 16

The pathway to benefits 1/4 m Conventional Once Proven Successful 16.0 12.0 8.0 3.0 2.0 4.0 0.0 5.1 Conventional Reinforcement 11.5 Installed Cost Tech Cost Reduction / Ahead of Need Future Income Streams 2.5 System Cost Savings 4.0 Future Net Method Cost Source: UKPN analysis, Poyry Analysis. Includes Civil, Elec, Labour, Opex estimates. All values in 2013 prices. Discount factor 7.2% 17

The pathway to benefits 2/4 m Conventional Once Proven Successful 16.0 12.0 8.0 3.0 2.0 4.0 0.0 5.1 Conventional Reinforcement 11.5 Installed Cost Tech Cost Reduction / Ahead of Need Future Income Streams 2.5 System Cost Savings 4.0 Future Net Method Cost Source: UKPN analysis, Poyry Analysis. Includes Civil, Elec, Labour, Opex estimates. All values in 2013 prices. Discount factor 7.2% 18

The pathway to benefits 3/4 m Conventional Once Proven Successful 16.0 12.0 8.0 3.0 2.0 4.0 0.0 5.1 Conventional Reinforcement 11.5 Installed Cost Tech Cost Reduction / Ahead of Need Future Income Streams 2.5 System Cost Savings 4.0 Future Net Method Cost Source: UKPN analysis, Poyry Analysis. Includes Civil, Elec, Labour, Opex estimates. All values in 2013 prices. Discount factor 7.2% 19

The pathway to benefits 4/4 m Conventional Once Proven Successful 16.0 12.0 8.0 3.0 2.0 4.0 0.0 5.1 Conventional Reinforcement 11.5 Installed Cost Tech Cost Reduction / Ahead of Need Future Income Streams 2.5 System Cost Savings 4.0 Future Net Method Cost Source: UKPN analysis, Poyry Analysis. Includes Civil, Elec, Labour, Opex estimates. All values in 2013 prices. Discount factor 7.2% 20

SNS Planning and Site Selection John Hayling Investment, Policy & Low Carbon Development Manager

Planning and Site Selection Interaction of storage design drivers and design choices Site selection at Leighton Buzzard Overview of planning process Planning submission and stakeholder consultation Learning points 23

Need Reinforcement Requirement Meeting Need Conventional Storage Other E.g. DG, DM Drivers Application Requirement Safety Expansion Site / Location Budget Key Design Choice Technology Lead Supplier Main Housing Module Size Impact Noise Level Cooling Requirement Flood Mitigation Planning Requirement Foot print Fire Suppression 24

Site Selection Leighton Buzzard, Bedfordshire March Grid, Norfolk Shepway, Maidstone, Kent 25

00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Site Location Leighton Buzzard 33/11kV primary substation was selected as the site as it provides an ideal opportunity to demonstrate SNS: Demand growth MVA 45.0 would require 40.0 significant network 35.0 reinforcement A 6 MW/10 MWh Li-ion battery device will enable peak demand to be met by mitigating the thermal constraints on the incoming feeders 30.0 25.0 20.0 15.0 10.0 5.0 - MVAh overfirm Area offset Capacity Threshold Adjusted Total MVA 26

Storage Design Drivers Storage will be of most value for network upgrade deferral where the upgrade: is costly, complex or time consuming to implement would add significant over-capacity is relieved by a relatively small amount of additional capacity headroom, and/or can be deferred by a reasonable amount of time 27

Planning Process Overview Planning consent is required to build on land or change the use of land or buildings: Town and Country Planning Acts of 1947 and 1990 Electricity Act 1989 governs some development Permitted Development determination must be conducted in accordance with the development plan, policy-led rather than influence-led planning consent time scales 28

Planning Timeline May 2012 Pre-Planning Advice 25 Oct 2012 EA Advice 7 Nov 2013 Local Consultation 7 June 2013 Planning Granted Ma June 2012 August 2012 October 2012 December 2012 February 2013 April 2013 June 2013 31 July 2012 Pre-Planning Guidance Prepare D & A Statement 8 Feb 2013 Application 27 Mar 2013 Re-submission 29

Local Resident Consultation In November 2012 prior to planning submission, a local consultation was carried out 30

Learning Points Obtaining planning approval took longer than expected a tight timetable can put pressure on negotiations relating to planning obligations Look closely at what is Permitted Development operational sites can potentially be retained operational Development control within local plan, may designate intended operational land for non-electricity undertaking purpose Planning consents at a site will lock down the external size and design of the building 31

Storage Technology and Building Design Andrew Jones, Managing Director, S&C Electric Europe Ian Cooper, Technology Transfer Engineer, UK Power Networks

Storage Technology and Building Design Housing the storage system at Leighton Buzzard Storage supplier and technology Connecting storage to support the network Protecting the network and storage system Lessons learnt so far 34

Building design planning constraints Planning constraints building height/appearance designed to be in keeping with the local area building no higher than local housing 35

Building design planning and floods Flood zone 3: high probability Building raised by 2m to allow for personnel access 1.34m above 1% risk flood 0.87m above 0.1% risk flood 36

Building design Approx 240 tonnes of batteries Point loads from step-up transformers Pilled foundations to cater for ground conditions Precast planks to support loading on raised floor Sealed, bunded, slab to prevent fluid leakage 37

Building under construction 24 th February 2014 38

Who are S&C Electric Company? Specialists in electric power switching, protection, and control Headquartered in Chicago, Illinois, USA Employee-owned 2700 employees Six global business units S&C Electric Europe Ltd is delivering the project 39

S&C Electric energy storage use cases 2 x 1MW System Canada 1MW System Minnesota 1MW System Scotland 4MW System California 2MW System Ohio 2MW System Indiana 1MW System West Virginia 1MW System Missouri 1MW System Australia 1MW System New Mexico 4MW System Texas 2MW System West Virginia 2 x 1MW System North Carolina 1MW System New Mexico 2MW System Ohio 40

Why Lithium-Ion? A technology already proven under previous LCNF projects by UK Power Networks Best suited to provide the maximum flexibility to test all potential market revenues Good ageing characteristics Commercially available Different Lithium technologies available 41

Why Samsung SDI? Started development in 2000 Largest global Lithium Ion manufacturer Proven quality product Excellent financial standing Experience of commercial projects 42

Samsung SDI batteries Technology Lithium Manganese 192 cells connected in series to make strings 264 trays in racks 22 racks connected to each 500kW of SMS Air cooled 43

Power Conversion System Indoor solution Modular design in 1MW sections with 2 x 500kW connections at DC Proven design with UK installed energy storage and wind projects Capability for remote monitoring 44

Building design internal layout Control room 11kV switchgear Battery room PCS & step-up transformers 2011. UK Power Networks. All rights reserved Fire room 45

Building design internal layout Logical battery arrangements vertical in series horizontal in parallel Design to overcome manual handling risks Containerised solutions are available if conditions allow 46

Fire precautions Multi-level design strategy Fire study identified unlikely that there could be any major impact Battery cell and rack design with multiple features to prevent cause of fire Potential cascade impact evaluated by real fire test no cascade discovered Multi-stage fire suppression design 47

Fire Suppression Control panel and Status Unit Vesda Smoke Detector Manual Alarm Call Point Hold Off Button 1 st Stage Alarm Bell 2 nd Stage Alarm Bell Fire Suppression Cylinder 48

Cooling requirements battery room Maintain 23 C ± 5 to maximise battery life Fans to remove heat Air conditioning to cool 1850m 3 room 30 air changes per hour 3 x AC Units 49

Cooling requirements PCS & transformer room Remove excess heat for work environment and equipment health Variable set point options Fans to remove heat 1750m 3 room expected maximum extracted air @ 22m 3 /s 55 air changes per hour fans to be thermostatically controlled/staged dependant on internal temperature of room 50

Team Effort S&C is managing the following team to implement the project Younicos for system integration Samsung SDI batteries Hornbill electrical & equipment installation Thamsgate fire suppression Buro Happold fire modelling West Coast Cooling HVAC 51

Leighton Buzzard 33/11kV Typical primary substation design dual 33kV feeders, 33kV isolators, two transformers, 11kV switchboard 52

Support during network faults 53

Electrical design 1. 11kV switchboard 2. 11kV cabling ESS feeders 3. ESS 11kV switchboard 4. 11kV cabling inverter feeders 5. Step-up transformers 6. LV cabling inverters to transformers 7. PCS / inverter units 8. DC cabling 9. Battery racks 54

Electrical protection Solkor Bus zone Balanced earth fault Neutral voltage displacement 55

Learning applied from Hemsby Both real and reactive power provide network benefits Round trip and whole system efficiency are required to understand lifetime costs Remote monitoring is key to prevent un-necessary system down-time Operational safety in design no exposed live equipment 56

Lessons learnt Storage footprint (capacity per unit area) varies with supplier / system design as well as with technology Storage system integration with the network should not be underestimated. Due to high level of complexity where many items are pre-requisites for each other Early construction team involvement optimise the design for build-ability Multi-disciplinary team needed to deliver final safe solution 57

SNS Smarter Optimisation Control System Paz Mehta Project Delivery Manager, UK Power Networks Dr. Neal Wade Senior Research Associate, Newcastle University Robert Golding IT Architect, UK Power Networks

Contents Smarter Optimisation Control System (SOCS) Overview and Approach SOCS Logical Design Forecasting, Optimisation and Scheduling SOCS Physical Design Application, Connectivity and Architecture Question and Answers 60

Smarter Optimisation Control System 61

SOCS - Approach Bid Requirements Cut Over & Go live Design SOCS Team Training Development Integration & Testing 62

Everyday life forecasting and optimisation 63

SOCS Logical Design Dr. Neal Wade Senior Research Associate, Newcastle University Forecasting Optimisation Scheduling 64

Primary substation peak-shaving requirement 65

Learning from Hemsby Storage Project 66

Forecasting, Optimisation and Scheduling System (FOSS) Forecasting Service Management Demand Capacity Engine Service Portfolio Energy Storage System Optimisation Algorithms 67

Forecasting Requirement: anticipate demand for peak-shaving mode Approach options: Demand forecast Load model Time-series Statistical: analysis of causality Artificial Intelligence: data driven Auto-regression: good at short-term Multiple linear regression: interpretation of main and cross effects 68

Selected forecasting method Multiple linear regression, because: transparent calculable causal links manageable update process Y = β 0 + β 1 X 1 + β 2 X 2 + + β n X n + e X n terms are explanatory variables: historical demand, temperature, wind speed Analysis provides β n terms that give weighting to explanatory variables 2014. UK Power Networks. All rights reserved 69

Properties of Services and mapping to Modes Several commercial service opportunities exist for SNS STOR (committed and flexible) FFR (dynamic and static) FCDM tolling reactive power support Parameters service window definition power and energy characteristics cost/revenue information 2014. UK Power Networks. All rights reserved 70

Modes Set-point power (active/reactive) energy Automatic response power (active/ reactive) frequency voltage Triggered PowerOn frequency PowerOn external signal Tolling SOC adjustments Peak-shaving DFFR future SFFR STOR 2014. UK Power Networks. All rights reserved 71

Service Management and Opportunities Information at 24 week advance 0-11 wks 12-23 wks 24-35 wks 36-47 wks 48-59 wks 60-71 wks 72-83 wks 84-95 wks Wk 00 Demand forecast DNO -PS Wk 12 Wk 24 Demand forecast Demand forecast Wk 36 Demand forecast Wk 00 Tender opportunity DFFR Wk 12 Wk 24 Tender opportunity Tender opportunity Wk 36 Tender opportunity TR19 TR20 TR21 TR22 2012/13 2013/14 2014/15 S5 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 S5 S5 S5 S6 S6 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 S1 S2 S3 S4 S5 S6 STOR Wk 00 S3 S4 Wk 12 S4 S5 Wk 24 S6 S1 Wk 36 2014. UK Power Networks. All rights reserved S1 S2 72

Approaches to optimisation Scheduling problem is characterised by: a need to make control decisions at discrete points uncertainty in the cost and benefit of decisions opportunities changing with time Method of Dynamic Programming fits with this situation. Sub-optimal approximations to a full analytic solution are widely used: rollout algorithms certainty equivalent controllers limited look-ahead policies 2014. UK Power Networks. All rights reserved 73

Limited Look-Ahead Policy Exhaustively evaluates the consequences of following alternative control choices across a series of decision points For SNS this means that: decisions are made as to which services to combine each service combination branch is evaluated power and energy availability is tracked though-out In the example branching for the following is shown: existing schedule, peak-shaving, services (x2), value/cost calculations and state-of-charge adjustments 2014. UK Power Networks. All rights reserved 74

Sequence decision process 2014. UK Power Networks. All rights reserved 75

Further features The service calendar is mapped to output modes. This allows extensibility because new services can be mapped to existing modes The service calendar requires acceptance at key points by UKPN and 3 rd parties. Services can therefore be treated as provisional or confirmed A process to release booked calendar slots is implemented, e.g. due to service rejection from 3 rd party, or change in demand forecast 2014. UK Power Networks. All rights reserved 76

SOCS Physical Design Robert Golding IT Architect, UK Power Networks Application Connectivity Architecture 2014. UK Power Networks. All rights reserved 77

Technical Architecture Explain the technical architecture of SOCS How we arrived at the final solution. Determined by: new IT components required for SOCS integration within existing UK Power Networks Infrastructure Plenty of Acronyms! Partners 2014. UK Power Networks. All rights reserved 78

SNS Application Architecture FOSS = Forecasting, Optimisation & Scheduling System Met Office FOSS Demand Forecasting Service Portfolio Management Optimisation Battery Manager FOSS Client FOSS database KOMP = KiWi Operational Management Platform Real-Time Control DataWarehouse ENMAC HMI ENMAC FEP PI database PI SCADA Client PI KiWi KOMP Control Room Local Network SCADA / RTU BESSM = Battery Energy Storage System Management ESS ESS = Energy Storage System BESSM HMI BESSM SCADA BESSM Control BESSM Battery Control BESDM = Battery Energy Storage Device Management BESDM BESDM SMS = Storage Management System SMS HMI SMS BMS SMS/BMS BMS = Battery Management System 79

BESSM SCADA Control 80

SNS SOCS connectivity Met Office Amt Sybex KOMP (KiWi) Younicos S&C External Firewall ESB Host Data Centre FOSS DB FOSS AS PI UKPN Control ENMAC Corporate VRF Control VRF Project Office SMC Main Firewall Control Room Leighton Buzzard RTU SCADA VRF BESSM Control BESSM SCADA Future Networks VRF CCTV BESDM Alarms HVAC BMS SMS Corporate VRF 81

SOCS High Level Technical Architecture BESSM Support (Unicos) FOSS Support (AMT) Met Office Smartest Energy Kiwi Power SMS Support (S&C) Internet UKPN Data Centre DC#1 DC#2 Project Office External firewall Battery Manager IBM Integration Bus IBM Integration Bus UKPN Control Centre Security & HVAC monitoring PI Historian Corporate VRF Internal firewall FOSS Main FOSS UAT SMC Control Room Engineer ENMAC/PowerOn Front End Processors SCADA VRF Future Networks VRF Superfast Broadband 10M Ethernet LB Primary T1 Leighton Buzzard Primary X Leighton Buzzard Existing Sub-Station Sarian RTU X X X 33kV 33kV X X Incomer CB 1 X Bus Section CB Outgoing Cables / 11kV Feeders Leighton Buzzard SNS Building LB Primary T2 X Leighton Buzzard SNS feeder CB 2 3 4 5 6 7 8 9 ESS BESSM SMS HMI BESSM HMI Security & HVAC monitoring 1 Leighton Buzzard Primary Switchboard X New telemetered point 2 11kV Cabling ESS Feeder 3 4 Internal 11kV Cabling Inverter Feeders 5 ESS HV Panel Step-Up Transformers 6 Inverter Transformer LV Cabling 7 PCS / Inverters / SMS Units 8 DC Cabling X Leighton Buzzard Primary Incomer 11kV CB 11kV PCS 01 CB X X 11kV PCS 02 CB 11kV PCS 03 CB X 11kV PCS 04 CB PCS T1 PCS T2 PCS T3 BESDM BMS SMS Currently telemetered point 9 Battery Racks 82

SOCS Acronym Quiz SOCS FOSS ESS BESSM BESDM SMS BMS KOMP = Scheduling, Optimisation & Control System = Forecasting, Optimisation & Scheduling System = Energy Storage System = Battery Energy Storage System Management = Battery Energy Storage Device Management = Storage Management System = Battery Management System = KiWi Operational Management Platform 83

SOCS Summary Paz Mehta Project Delivery Manager, UK Power Networks Next steps Q&A 84

SOCS Next Steps Requirement definitions and design completed Software development started FOSS (AMT-Sybex) ESS (S&C, Younicos) Enmac, RTU & PI (UKPN) IT infrastructure communications network infrastructure and security servers, RTU and ESB messaging establish messaging infrastructure and connectivity Testing and ready for trials 85

Smarter Network Storage Looking Ahead Martin Wilcox, Head of Future Networks

SNS Upcoming milestones Storage Commissioned Oct 2014 Full assessments of regulatory & legal arrangements Sept 2015 Final report Dec 2016 Q1 Q2 2013 2014 2015 2016 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Design Build Installation Trial Application & Service trials Commercial & Regulatory assessments Training & asset management methodologies documented May 2015 Full assessment of storage value streams Mar 2016 87