Design and Construction of a 200-foot-deep, 24-foot-diameter Conveyance System Access Shaft

Similar documents
ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Dewatering - Time and Cost Relief by way of Trenchless Construction

Geotechnical Building Works (GBW) Submission Requirements

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Force Main Condition Assessment: New Technologies & Case Studies

P.O. Box 416 Winlock WA

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Section Installation of pipe and casing for sanitary sewer by methods of augering.

Sample Project with SlurryTBM according to Anagnostou and Kovári

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

SECTION 3 SANITARY SEWER DESIGN

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

BUTE Department of Construction Management and Technology

Chapter 7 Plumbing Connections

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

SECTION SHEETING, SHORING AND BRACING

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Meeting the Challenge of Pipeline Emergency Repair

Construction Dewatering and Ground Freezing

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

UNIFIED FACILITIES CRITERIA (UFC) DEWATERING AND GROUNDWATER CONTROL

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

Proposed Minimum Subterranean Termite Treatment Standards

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Construction sites are dewatered for the following purposes:

Linear Schedules for Tunnel Projects

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Wastewater Capital Projects Management Standard Construction Specification

Annular Space Grouting of Slipline Products

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

SANITARY SEWER SPECIFICATIONS

Beacon Hill Sewer District Standard Specifications

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

SECTION 724 PIPE CULVERTS

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

Section 2100-Trenching and Tunneling

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Technical Memorandum 9B Approach to Incorporating Cost Risk into the Economic Model - FINAL

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Basement & Foundation Damage

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Pro-Lift Steel Pile Foundation Repair

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

FY08 SEWER POINT REPAIRS BID TABULATION

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East

C. Section TESTING LABORATORY SERVICE.

Cost Estimating Procedures for Raw Sewage Overflow Control Program

APPLICATION FOR GRAYWATER IRRIGATION SYSTEM PERMIT SIMPLE RESIDENTIAL GRAVITY SYSTEMS, NO STORAGE

Installation of Large Diameter Buried Pipes

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

RAM JACK INTRODUCTION

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

EMERGENCY STORAGE PROJECT

Michael B. Gilbert, P.E. Vice President

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Pine Creek Culvert Upgrade $ 560,000. Located at exiting hump dike, just south of Fire Training Center

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

2.1 Development of Risk-Based Asset Management Framework

Dry Weather Flow from Footing Drains and Service Connections

MEMORANDUM: RECOMMENDATIONS FOR PIPE MATERIAL SELECTION

TBM CROSSING OF STATIONS

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Design and Construction of Auger Cast Piles

Flowtite Jacking Pipe

LS 2540 SEWER LATERALS AND INSPECTION TEES

CHAPTER 2 HYDRAULICS OF SEWERS

SECTION 411 DRILLED PIERS

High Strain Dynamic Load Testing of Drilled Shafts

Water Main Lining A Sustainable Alternative to Open Cut Replacement

Inspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada

San Diego County Water Authority Contracting Opportunities - July 4, 2016, 1:52 a.m.

ATLAS RESISTANCE Pier Foundation Systems

Section SEWER PIPE INSTALLATION AND TESTING

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

Transcription:

Boise, Idaho September 14, 2009 Design and Construction of a 200-foot-deep, 24-foot-diameter Conveyance System Access Shaft Placeholder for photo Daniel R. Williams, P.E.

Project Overview 2

Project Location Map Treatment Plant Effluent Conveyance System Brightwater WWTP 36 MGD in 2010; Peak Flow 130 MGD 54 MGD in 2040; Peak Flow 170 MGD Membrane bio-reactor WWTP Reclaimed water facilities Conveyance Tunnels Length (feet) East 13,890 18 Central 19,020 11,590 Outside Diameter 17 17 West 21,033 13 Seattle Bellevue 3

Ballinger Way Portal Design Phase PREDESIGN REPORT: Describes a BWP large enough to serve as a retrieval shaft for two TBMs Location based maximum tunnel length and depth based on hydraulics Tunnel BT3 is 3.8 miles in length Tunnel BT4 is 3.9 miles in length Anticipates an inside diameter of 30 feet 4

Brightwater Effluent System PLAN PROFILE

Ballinger Way Portal Design Phase TECHNICAL MEMORANDUMS: Tunnel and Portal Access TM Describes inspection intervals and access requirements for Brightwater System Inspection and maintenance at BWP by remote operated vehicles (10 x 10 ) Technical Advisory Committee Report Proposes a drilled shaft 10 feet in diameter 6

Ballinger Way Portal Design Phase TASK: Evaluate consequences of reducing the inside diameter of the BWP from 30 feet to 10 feet.

Ballinger Way Portal Design Phase Why reduce the diameter? Large diameter BWP could take 15 months to construct at a cost of $13M. Drilled shaft BWP could be constructed in several months for a cost of $1.5M. Problems? Complex tunnel-to-portal and tunnel-to-tunnel connections (Drilled shaft not large to receive TBMs). 8

Ballinger Way Portal Design Phase Soil Conditions at BWP / Tunnel Interface: Flowing or unstable soil from scattered sand, silty sand, and silty gravel layers; hydrostatic head of 150 feet at base of BWP Inspection / Maintenance Requirements: Initial inspection after ten years of operation After 7.0 or larger quake 30-year intervals Submersible and crawler-type ROVs 9

Ballinger Way Portal Design Phase ALTERNATIVES: #1 Small Diameter Portal (i.e., Drilled Shaft) 1a Portal above Tunnel Intersection 1b Portal West of Tunnel Intersection 1c Portal East of Tunnel Intersection #2 Large Diameter Portal 10

11

12

Ballinger Way Portal Design Phase Constructability and Risk (Drilled Shaft Alternative): Unstable flowing soil conditions where tunnel-to-tunnel and tunnel-to-portal connections occur. Groundwater pressure at connections is 60-plus psi. Requires grouting (in absence of dewatering) to safely conduct hand-mined excavations. Effectiveness of grouting is difficult to verify; incomplete grouting could compromise hand-mined excavations, exposing workers and the tunnels to soil and groundwater. Increases the likelihood of Contractor claims and schedule delays. 13

Ballinger Way Portal Design Phase Schedule Impacts (Drilled Shaft Alternative): Drilled shaft cannot be constructed independently of tunnels (so drilled shaft is on the critical path). Cost (Drilled Shaft Alternative): Estimated cost of drilled shaft alternative is $7.2M. Large diameter portal alternative costs ranged from $6M to $14M. 14

Ballinger Way Portal Design Phase ALTERNATIVE #2 Large Diameter Portal 15

Ballinger Way Portal Design Phase TASK: Evaluate the following four alternative excavation support systems: Sequential Excavation w/ Depressurization Open Caisson Ground Freeze Wall Slurry Diaphragm Wall 16

Ballinger Way Portal Design Phase Alt 2a Sequential Excavation with Depressurization Alternative was ruled out because of concerns about volume of groundwater removal and ability of Contractor to keep shaft dewatered. 17

Ballinger Way Portal Design Phase Alt 2b Open Caisson Alternative was ruled out because of concerns about plumbness and keeping caisson moving downward at the depths required. 18

Ballinger Way Portal Design Phase Alt 2c Ground Freeze Wall Alternative was allowed because of past success on other projects similar in size and scope represented best chance for success. 19

Ballinger Way Portal Design Phase Alt 2d Slurry Diaphragm Wall Alternative was allowed because of past success on other projects similar in size and scope represented best chance for success. 20

Ballinger Way Portal Design Phase Alternative Costs: 1. Sequential Excavation w/depressurization -- $8.19M 2. Ground Freeze Wall -- $14.56M 3. Slurry Diaphragm Wall -- $9.17M 4. Caisson -- $6.3M 21

Ballinger Way Portal Design Phase Reclaimed Water Pipeline Pipe Support Design 20-inch diameter pipe, 170-foot-tall column Thermal expansion when temp rises from 40-deg to 90-deg = 0.65 inches Force imparted by pinned pipe = 165,000 lbs Therefore, pipe supports designed to allow for thermal expansion Polymer material is placed between the steel strap and the pipe itself, which allows the pipe to move vertically within the pipe support. Polymer material is used for skids on casing spacers and is used on boat docks. 22

Ballinger Way Portal Construction Phase 23

Ballinger Way Portal Construction Phase 24

Ballinger Way Portal Construction Phase 25

Ballinger Way Portal Construction Phase 26

Ballinger Way Portal Construction Phase 27

Ballinger Way Portal Construction Phase 28

Ballinger Way Portal Construction Phase 29

Ballinger Way Portal Construction Phase 30

Ballinger Way Portal Construction Phase 31

Ballinger Way Portal Construction Phase 32

Ballinger Way Portal Construction Phase 33

Ballinger Way Portal Construction Phase 34

Ballinger Way Portal Construction Phase 35

Ballinger Way Portal Construction Phase 36

Ballinger Way Portal Construction Phase 37

Ballinger Way Portal Construction Phase 38