HIGHWAY 63 PINCH POINT SECANT WALL

Similar documents
Safe & Sound Bridge Terminology

TRANSPORTATION MODELLING IN CALGARY

IH-635 MANAGED LANES PROJECT, SEG. 3.2

28.0 Development Permit Area #2 (Neighbourhood District)

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

ELEMENT 4 - FUTURE LAND USE ELEMENT

3.1 Historical Considerations

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

Elevated Roads for Sri Lanka

CONSTRUCTION SEQUENCE & PROGRAMME

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

Emergency repair of Bridge B421

3 Tappan Zee Bridge Rehabilitation Options

Designed and Engineered to Perform

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two.

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES

Household waste & recycling storage requirements

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

5 ALTERNATIVE SOLUTIONS AND EVALUATION

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

0.0 Curb Radii Guidelines Version 1.0.2

WELCOME PROPOSALS FOR PENTAVIA RETAIL PARK WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE.

PEDESTRIAN PLANNING AND DESIGN MARK BRUSSEL

Residential Deck Safety, Construction, and Repair

Monocouche Best Practice Guide. New-Build Housing Managing movement to avoid cracking

Hanna delivers the technical and marketing expertise needed to produce a car wash that meets the car wash customer's expectations.

Geotechnical Building Works (GBW) Submission Requirements

Uncovered Decks & Porches

HOUSE BUILDING DIGEST

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):

DESIGN GUIDELINES FOR EARTH RETENTION

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

Sector Design Concepts

TABLE OF CONTENTS. Executive Summary 1-3. Introduction 4-6. Illustrative Site Plan 7. East-West Streets 8. Cooper Street Market Street 11-14

Goals & Objectives. Chapter 9. Transportation

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Civil Engineering and Architecture (CEA) Detailed Outline

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Milan M5 metro extension the construction of Lotto station

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

Major Improvement Schemes in Basingstoke

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November Prepared by Capita Lovejoy on behalf of William Davis Limited

Page & Turnbull imagining change in historic environments through design, research, and technology

REHABILITATION PACKAGE 1-a

Chaudière Crossing Bridge Rehabilitation

720 Contour Grading. General. References. Resources. Definitions

Granger Bay Boulevard and Green Point Roundabout

OMC Study Group MEETING 3: NOTES. Section 1: Building Design Page 2 Section 2: Site Layout Page 9 Section 3: Summary Page 16

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.

Rapid Transit Backgrounder

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

LAND USE CODE CHAPTER GENERAL REGULATIONS

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Introduction to Minimal Excavation Foundations

Development Brief for New Lodge, Bank Mill Lane Berkhamsted. Adopted November 2007

ORDINANCE NO

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26


FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

SIGHT DISTANCE. Presented by Nazir Lalani P.E. Traffex Engineers Inc. WHY IS SIGHT DISTANCE SO IMPORTANT?

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

MHI. Overview of Manufactured Home Installation MANUFACTURED HOUSING INSTITUTE. This guide contains an overview. of the HUD-Code manufactured home

BRIDGES ARE relatively expensive but often are

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

MEGA GUARD COLUMN CORE GUARD DAWG COLUMN PROTECTOR. Smart Investments in Plant Safety

Cathkin Relief Road Planning Statement

CHAPTER 14: GUARDRAIL and BARRIERS

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

Report to INFRASTRUCTURE SERVICES Committee for noting

MOBILE HOME LAW. Revised November 2001

Planning Railway Safety in Canada

Permits to Dig / Permits to Excavate / Permits to work near underground services

Design and Implementation of Slot Left-Turn Lanes on the Manitoba Highway Network

WASTE STORAGE AND COLLECTION

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions

Residential Foundations and Basements

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Traffic Management Issue 1.0 Revision: v2 October 2014

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

Transcription:

AWARDS 2014: TRANSPORTATION HIGHWAY 63 PINCH POINT SECANT WALL SUBMITTED BY: Zichao Wu, Ph.D., P.Eng., P.E. 17007 107 Avenue Edmonton, AB T5S 1G3 Canada T 780.486.7000 F 780.486.7070 E zichao.wu@aecom.com

75 WORD SUMMARY 75 WORD SUMMARY Section 1

SECTION 1 75 WORD SUMMARY Alberta Transportation required upgrading of Highway 63 in Fort McMurray along an alignment with numerous geometric and geotechnical constraints, with no compromise on safety standards. AECOM designed a 420m long, 9m high secant pile retaining wall to retain a steep, unstable hillside where the roadway alignment is tightly constrained at the base of the hill by the Athabasca River. This slender wall design had to consider complex loading variables and multiple stages of wall construction. Precast facing panel architectural treatment 1

PROJECT HIGHLIGHTS PROJECT HIGHLIGHTS Section 2

PROJECT HIGHLIGHTS 2.1 INNOVATION The design and construction challenges associated with retaining walls are often underappreciated and receive far less public praise and attention than their bridge infrastructure counterparts. It is important to acknowledge the crucial role that the secant pile retaining wall has played in the Highway 63 upgrading project through Fort McMurray and to highlight the design process that required a collaborative approach between the Consultant and Contractor. To the north of the Athabasca River, the widened Highway 63 with 6 mainline lanes and adjacent collector-distributor lanes is constrained between the river and a steep, slowly creeping, vegetated hillside with residential housing on top. The substantial increase in out-toout width of the roadway corridor from 33 m to 68 m has been achieved by the combination of roadway fill supported by a tangent pile wall adjacent to the river and a cut retained by a secant pile wall adjacent to the hillside. Although both walls are equally important to the success of the overall widening scheme, the secant pile wall is the focus of this award submission and worthy of individual focus based on its sheer size, as well as the design and construction complexities. This wall is one of the longest of its type in Alberta. The secant pile wall was formed by constructing intersecting concrete piles. The unreinforced Drilling structural piles after completion of infill piles 1

PROJECT HIGHLIGHTS CONT D infill piles were constructed first with a pile tip approximately 1.5 m below the finished roadway grade in front of the wall. Subsequent construction of the structural reinforced piles involved boring the edges of the infill piles. The overlap between piles is 200 mm. The short portions of wall at each end were designed as free standing cantilevers. For taller portions of the wall, up to three ground anchors per structural pile were used as tie backs to resist loading from the hillside. Excavation in front of the wall was undertaken in controlled stages after piling was completed. It was necessary to limit the first stage of excavation to just below the top anchor position and to install these anchors before further excavation. Similar excavation restrictions were required for portions of the wall requiring two or three anchors. This was a challenging project in terms of the significant geotechnical constraints, the requirement for construction staging and a large component of traffic accommodation. In addition, the project required in-depth Consultant involvement during construction to adapt the design based on field conditions. 2.2 COMPLEXITY The most challenging aspect of the design was managing the large number of variable piles and therefore a logical and methodical design approach was essential. For design purposes, the wall was split into several zones based loosely on the wall height and the ultimate soil loading under a hillside failure condition. As well as designing the wall for the completed condition, it was equally important to check the wall during all stages of construction. This increased the design effort Pile cap concrete pour 2

PROJECT HIGHLIGHTS CONT D many times over and furthered the importance of a methodical and well-documented design procedure. The wall models created were highly adaptable to different earth loading, anchor loading and soil resistance values. Constructability was a key consideration during the wall design whereby replication of details and procedures was maximized and constraints to the schedule were minimized. The Contractor was also encouraged to develop their own details. This took advantage of their past experience and helped to improve construction efficiency. Two significant changes at the outset of construction impacted the design. Firstly, the northernmost 100 m of the wall was realigned. The wall was shifted towards the hillside to avoid a potential conflict with a major power Drilling through a structural pile prior to anchor installation L Typical Pile Section with 3 Anchors 3

PROJECT HIGHLIGHTS CONT D Location plan line serving a large population in Fort McMurray. The second change required much more thought about the behaviour of the wall. The Contractor requested a substitution of the bar anchors to strand anchors which represented a cost saving to the construction but significantly altered the flexibility of the wall under lateral loading. 2.3 SOCIAL AND/ OR ECONOMIC BENEFITS Highway 63 is the major transportation corridor in Fort McMurray and serves as a route for local traffic across the Athabasca River between many of the residential neighborhoods and the town s retail and commercial center. Highway 63 also serves as the main transportation route for people, goods and services to the large Oil Sands developments to the north of Fort McMurray, including many specialized over-dimensioned loads. The secant pile wall performs an important role in improving transportation access through 4

PROJECT HIGHLIGHTS CONT D Fort McMurray along Highway 63 from the perspective of reduced traffic congestion and improved user safety. The retaining wall is a key component in the overall scheme to accommodate local traffic in discrete lanes that are physically separated from the higher-speed highway traffic. Segregation of local and highway traffic will greatly enhance the local community. Reduced commuter travel times to the Oil Sands developments, which were significant particularly at peak hours, and improved flow of resources to these developments which rely on truck transport will have immediate and long term economic benefits at a local, regional and national level. The retaining wall is a prominent feature for the local community with architectural treatment consistent with adjacent structures and aesthetics that are sympathetic to the local surroundings. The retaining wall is one of the largest and most strategically important structures of its type in Alberta Transportation s inventory. Pile anchor bearing plates Early stages of excavation in front of the retaining wall Placing the concrete footing to support the precast facing panels 5

1 1 1 1 PROJECT HIGHLIGHTS CONT D 2.4 ENVIRONMENTAL BENEFITS The design concept and development through to detailed design was done in an environmentally responsible manner whereby tree removal on the hillside above the wall was minimized and building out into the river was avoided thus eliminating impact to fisheries and habitat in the Athabasca River at this location. The design solution at the pinch point location specifically, and along the widened Highway 63 in general, is a sustainable solution for local and regional transportation of people, goods and services. The increased road capacity is significant and will accommodate future projected traffic growth which is significant as the oil sands are developed. Improved traffic flow on this section of Highway 63 will reduce congestion, particularly during peak hours, creating fewer green house gas emissions. 2000 1500 STAGE 1 STAGE 2 STAGE 3 MAX 500 MAX 500 3 H 1 3 H 1 3 H 3 H 1500 1500 1500 STAGE 4 STAGE 5 STAGE 6 MAX 500 PILE CAP 1500 1500 SWALE 3 H 1 3 H PRECAST WALL 3 H MAX 500 1 3 H 1 3 H FINAL ROADWAY GRADE STAGE 7 STAGE 8 STAGE 9 6

PROJECT HIGHLIGHTS CONT D 2.5 MEETING CLIENT S NEEDS The secant pile retaining wall is an integral part of the widening scheme to ease traffic congestion and improve user safety along the Highway 63 corridor within Fort McMurray. The existing four lane highway has been upgraded to six new mainline lanes in addition to four new C-D lanes. The wall has allowed roadway design standards to be maintained along the entire length of the project rather than introducing hazards within the Clear Recovery Zone for errant vehicles or requiring speed limit restrictions. The open cross section also accommodates the frequent over-dimensioned loads travelling to the oil sands developments north of Fort McMurray along this corridor. All parties advanced local knowledge about secant pile walls with tie back strand anchors. This experience will likely be of future benefit to widening projects as Alberta s road infrastructure continues to expand, particularly where space behind a given wall is limited. The project demonstrated numerous examples of the Consulting team being proactive and reactive, and working with the Client and Contractor in an efficient and collaborative manner to deliver a high quality project. Widening of Highway 63 at the pinch point location and managing the required number of lanes without creating environmental or geotechnical issues was a challenge and required critical/ innovative thinking. - Rizwan Hussain, Construction Manager, Alberta Transportation. Secant Pile Wall Secant pile wall nearing completion (looking north) 7