DEEP SOIL MIXED WALL AND JET GROUTING FOR AN EXCAVATION SUPPORT SYSTEM AT THE MUSEUM OF FINE ARTS IN BOSTON, MASSACHUSETTS

Similar documents
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

BUTE Department of Construction Management and Technology

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

PILE FOUNDATIONS FM 5-134

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Design and Construction of Auger Cast Piles

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

Geotechnical Building Works (GBW) Submission Requirements

Hunter College school of Social Work Thesis Proposal

Chapter 9 Remedial Measures

METHOD OF STATEMENT FOR STATIC LOADING TEST

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1

Deep Underground Basements for Major Urban Building Construction

Designed and Engineered to Perform

SECTION SHEETING, SHORING AND BRACING

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

EAST LYME HIGH SCHOOL

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

Emergency repair of Bridge B421

Safe & Sound Bridge Terminology

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Elevating Your House. Introduction CHAPTER 5

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

PDHonline Course S151A (1 PDH) Steel Sheet Piling. Instructor: Matthew Stuart, PE, SE. PDH Online PDH Center

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

Page & Turnbull imagining change in historic environments through design, research, and technology

6 RETROFITTING POST & PIER HOUSES

COMMONLY USED RESIDENTIAL BUILDING CODES

Chapter 3 Pre-Installation, Foundations and Piers

Construction Dewatering and Ground Freezing

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

Numerical Simulation of CPT Tip Resistance in Layered Soil

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

DIRECTIONAL DRILLING

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT

Construction sites are dewatered for the following purposes:

The International Workshop on Micropiles, 2007

Module 7 (Lecture 24 to 28) RETAINING WALLS

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

symptoms of a faulty foundation

King Post Wall Information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

High Strain Dynamic Load Testing of Drilled Shafts

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION

Contiguous Pile Wall as a Deep Excavation Supporting System

Technical Notes 3B - Brick Masonry Section Properties May 1993

EVALUATING THE IMPROVEMENT FROM IMPACT ROLLING ON SAND

Detailing of Reinforcment in Concrete Structures

Chapter. Restoration of Damaged Structures

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

How To Design A Foundation

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

DESIGN AND CONSTRUCTION CONSIDERATIONS FOR DEEP EXCAVATION.

ALLOWABLE LOADS ON A SINGLE PILE

Underpinning Systems 14.1 FOUNDATION REPAIR. Helical Piles

The demand for new roadway

Breakaway Walls

Engineered Wood Foundations

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

Transcription:

DEEP SOIL MIXED WALL AND JET GROUTING FOR AN EXCAVATION SUPPORT SYSTEM AT THE MUSEUM OF FINE ARTS IN BOSTON, MASSACHUSETTS Harry Schnabel, P.E., Director of Business Development, Schnabel Foundation Co, Sterling, Virginia, USA Steven Hinterneder, P.E., Northeast Branch Manager, Schnabel Foundation Co, Southborough, Massachusetts, USA Daren Zywicki, Ph.D., P.E., Research Engineer, Schnabel Foundation Co, Sterling, Virginia, USA A 6200 m² cement deep soil mixed (CDSM) wall was constructed for an addition to the Museum of Fine Arts in Boston, Massachusetts. The addition was located along the east side of the existing museum within an existing courtyard and in the area of a recently demolished structure. The basement for the new addition extended up to 9.1 m below the floor slabs of the adjacent buildings. The adjacent buildings are supported on a variety of foundations including; shallow spread footings on alluvial sand deposits, low capacity piles bearing in the alluvial sands and Boston blue clay, and caissons bearing on the alluvial sands and clay. Groundwater was less than one meter below the top of the CDSM wall. The new addition was founded on shallow foundations in the desiccated crust of the Boston Blue Clay. The CDSM wall was selected as the most economical means to control deep seated ground movements, limit movements of adjacent structures, and inhibit groundwater flow into the excavation. Braces and a continuous wale were used to support the CDSM wall where it was located adjacent to structures. Tiebacks were used where there were no structures. Other geotechnical construction at the site included: Jet grouting (JG) to improve the ground and provide an impervious subgrade layer at the west end of the addition, Concrete pier underpinning was used to support an existing structure on the west end of the site, and A secant pile wall using alternating drilled shafts and jet grout columns was used for earth support and a barrier to groundwater flow to allow for the installation of a storage tank at the south end of the site. Inclinometers, total station surveying, vibrating wire strain gauges on the braces and wales and load cells on the tiebacks were used to monitor performance of the excavation support system. The excavation support system performed better than required limiting lateral movements of the adjacent structures to less than 13 mm and vertical settlement to less than 8 mm. No settlements or movement were detected during the construction of the wall. Lateral movement of the CDSM wall was typically below 15 mm with the maximum movement occurring near subgrade. PROJECT DESCRIPTION To increase exhibit and storage space, an addition was constructed at the Museum of Fine Arts located on Boylston Street in Boston, Massachusetts. The original museum structure was built in 1909. A number of additions to the original structure were constructed between 1915 and 1969. The original structure and additions are supported on a variety of foundations including spread footings, concrete caissons, and piles (Table 1). Building Original Museum Structure Evans Wing Picture & Connecting Gallery Decorative Arts Wing Year Built 1909 1915 Foundation Type Footings and Belled Caissons Footings and Belled Caissons 1928 Concrete Piles Textile Gallery 1967 Concrete Piles Archive Addition (Demolished) Table 1 - Existing Foundations Bearing El -1 m 1 m Not Known Not Known 1969 Caissons 0 to 2 m

Subsurface conditions at the site consisted of 3.3 to 6.2 m of granular fill and organics over 2.6 to 3.3 m of alluvial sand over Boston blue clay. A glaciolacustrine deposit lies beneath the clay at depths of 48 to 52 m. The top of the clay varies between elevation 0 and -4 m sloping downward from west to east. There is also a silty fine sand layer in the clay between at a depth of 13.4 and 18.1 m, which acts as a confined aquifer. The silty fine sand layer was up to 5 m thick with a bottom between elevation -9.2 and -12.8 m. Groundwater elevations varied between elevation 1.7 and 2.9 m. A typical soil profile is shown in Figure 1. PERIMETER CUT-OFF WALL (CDSM) Construction of the new addition required cuts of up to 9.1 m below the floor slabs of the adjacent existing structures. In some cases, the edge of excavation for the addition was within 1 m of the existing structures. A CDSM wall was chosen as the method of earth retention around the majority of the building perimeter as it is relatively stiff and impermeable which facilitates control of deep seated ground movements, limits movements of adjacent structures, and provides a relatively impermeable barrier to groundwater flow. Other earth support systems considered included sheet piles, secant pile walls, and slurry panel walls. The Owner/Engineer selected a CDSM wall over sheet piles because of the risks associated with the vibrations caused by sheet pile installation and a CDSM wall is less permeable than sheet piles. The CDSM wall was selected over a secant pile wall and slurry panel wall because it was more economical and would take less time to construct. Figure 1 Typical Soil Profile The new addition was constructed in the shape of a T. The stem portion of the T, called the spine, and the two ends at the top of the T, called the north and south pavilions, were located in an existing courtyard and within the footprint of a recently demolished structure. Existing site grades varied from elevation 5 to 6 m. The site was pre-excavated to elevation 3.3 m prior to construction to reduce the overall height of the excavation support system. The new addition is supported on shallow foundations bearing in the desiccated clay. The bottom of footing elevation for the new structure varies between elevations -5 and -6 m. The new addition and surrounding existing structures are shown in Figure 2. Figure 2 - Museum of Fine Arts Plan View The CDSM wall consists of overlapping 914 mm CDSM columns drilled at 686 mm on center. Steel soldier beams, typically placed in every other column (1.37 m on center), were used to reinforce the CDSM wall. The soldier beams varied in size from a W460X74 to a W610X217. The soldier pile spacing was decreased to a pile in every hole, 0.686 m on center, in areas close to adjacent structures where a stiffer wall was

required. The soldier beams typically had a tip elevation of -10.7 m. The CDSM wall extended below the bottom of the soldier beams to about 1.5 m below the bottom of the confined sand seam aquifer. The soil-cement was designed to span between the soldier beams and have an unconfined compressive strength of 760 KPa. CDSM WALL CONSTRUCTION The CDSM wall was constructed using multiauger mixing equipment designed to mix an element of 4 soil-cement shafts in one stroke. Separate positive displacement pumps delivered the grout slurry through the center of the augers to the bottom of each shaft. Mixing paddles counter rotated and blended the cement grout slurry with the soil as the augers were inserted and extracted. The mixing shafts rotated at 12 RPMs on the down stroke and 24 RPMs on the upstroke and during re-stroking of the element. The mixing shafts were advanced at around 0.46 m per minute during the down stroke and 0.91 m per minute during the up stroke. Soldier beams were set in the semi-fluid soil-cement mix prior to initial set. Work proceeded in a continuous manner with around 15 m of wall completed on a typical day. In all, around 6,200 m 2 of CDSM wall was installed. Figure 3 shows the equipment used to construct the CDSM wall. The mixing paddles on the four auger shafts are evident in this Figure. This figure also shows the protective plastic sheet and plywood cover over the windows installed by the Construction Manager to protect the existing building from splatter caused by soil/cement falling off the augers. Figure 4 shows the cutting heads at the end of the augers. Figure 4 - Detail of Soil Mixing Cutter Heads No movement of the nearby structures was measured during the CDSM wall installation. Extensive sampling and testing of the soil mix was performed during construction of the CDSM wall as part of a QA/QC program. Unconfined compression tests were conducted on wet grab samples at 3, 7, and 28-days. The results of these tests are shown in Figure 5 and show that the minimum strength at 28 days exceeded the required design strength of 760 KPa. Figure 5 CDSM Strength vs Time Figure 3 Installation of Soil Mix Wall Lateral support for the CDSM wall was provided by two levels of internal cross lot braces, corner braces, and/or tiebacks. Internal bracing was used where the CDSM wall was adjacent to buildings as installation of tiebacks under buildings was not allowed by the Owner due to potential conflicts with existing foundations. The elevation and location of the braces was selected by the Owner to avoid penetrations in the new structure. The load from the CDSM wall

was transferred to the braces using a continuous steel wale designed to resist both bending and thrust loads. The braces were pre-loaded to 50 percent of their design load after installation. The pre-load was locked into the braces using steel wedges. Support piles connected to a header beam were used to support the braces at mid-span. A section through the braced portion of the excavation support system (ESS) at the spine is shown in Figure 6. The completed excavation showing the braces and support piles is shown in Figure 7. Figure 6 - Section Through ESS at Spine conventional design, such as brace loads and wall stiffness, for input. Three numerical models were developed to estimate the movements of the braced wall system. Both a Mohr-Coulomb (MC) and Hardening Soil (HS) model were used in the simulations for various structural entities, with initial soil parameters primarily from Shawkat s (1993) PhD dissertation on the properties of Boston Blue clay and MFA geotechnical reports (Haley and Aldrich, 2003; McPhail Associates, 2006). The hardening soil model with small strain stiffness (HSsmall) was not available in the PLAXIS versions utilized in these studies. The movements were estimated for a number of construction stages including the initial stage, excavation for the top strut, installation of the top strut, excavation for the second strut, installation of the second strut, excavation to subgrade, and removal of the bottom strut after the new foundations were complete. FEM estimates performed prior to availability of any measured deflections showed deep-seated movements of up to 18 mm below elevation -3 m. After completion of the project and when measured data was made available, a model was developed (Katkhuda, 2008) that continued to show larger than measured deep seated movements of greater than 25 mm at elevations below -9 m. Katkhuda concluded that the effects of non-linear small-strain stiffness must be taken into account to appropriately model the deflections. Figure 7 - Completed CDSM Wall and Bracing The tiebacks were installed using concentric rotary duplex drilling methods with water flushing. Each tieback was re-grouted at least once after initial grouting. The tiebacks were tested and locked off against a continuous wale. The initial design of the wall was conducted using conventional methods. The wall was designed to resist combinations of earth and water pressures, construction surcharges and building surcharges. The principal concern in the design was to limit movement of the CDSM wall and surrounding structures. Wall movements were estimated using a plane strain finite element simulation using PLAXIS. This simulation relied on elements of the SFC continued to develop the model, concluding that the following were important aspects for modeling the deflections: (1) The undrained modulus should be used for the Boston blue clay for the project and measurement time-periods involved, (2) A small-strain stiffness must be utilized, particularly for the deeper soil regions that are undergoing smaller strains, and (3) Appropriate K 0 values must be utilized in the over-consolidated Boston blue clay layers. SFC varied the parameters to achieve a relatively good fit, including adjusting the small-strain moduli of the layers based on the average strain in the layer. The results of the SFC finite element simulation at the end of excavation are compared with inclinometer measurements near the Evans Wing Picture Gallery in Figure 8.

The maximum lateral movement was expected to be around 20 mm based on the initial FEM analysis conducted prior to starting the work. The actual movement measured in the inclinometers was typically less than 15 mm with the maximum movement occurring at subgrade as predicted. Figure 8 Comparison of Measured Movements and FEM Model Field monitoring of the lateral movement of the CDSM wall was accomplished using eight conventional inclinometers, three automated in place inclinometers, and robotic and manual total stations and webcam. The inclinometers were installed in drill holes located just behind the CDSM wall. The automated inclinometers gave erratic data or did not work and their data was not used. The conventional inclinometers gave consistent data and were used to measure ground movements behind the wall. Lateral and vertical deflection of the existing structures and the tops of the piles in the CDSM wall were measured using robotic and manual total stations. The readings were taken using prisms attached to the structures and tops of piles. The vertical movement of the existing structures was confirmed by monitoring fixed points on the structure using a level. The loads in the wales and braces were monitored using 62 vibrating wire strain gages. The strain gages were placed in groups of 3 spaced 120 degrees apart on the braces and near the center of the wales. Loads in the tiebacks were monitored using load cells. Lateral and vertical deflections at the tops of the piles, measured using the robotic webcams and a conventional total station, showed similar movement trends to that indicated in the inclinometers although the magnitudes were much greater than the movements at the tops of the piles shown in the inclinometers. Lateral movement at the tops of the piles was typically less than 12 mm with the greatest amount of movement occurring in the piles which were braced above subgrade in the north and south pavilions. A small amount of movement (<6 mm) was also measured parallel to the wall in the area of the corner braces. Measurements of the vertical (settlement or heave) and lateral movement of the existing structures was erratic but never exceeded 13 mm. In all cases the movements were less than the project requirements. Crack gages installed across pre-existing cracks in the existing structure also showed no relative movement or widening and there was no observable damage to the structure. The strains and temperatures in the braces and wales were recorded several times per day using an automated data logger. Temperature measurements were taken to allow the loads in the braces to be corrected for thermal effects. In general, the loads measured in the strain gages, after a brief period of time, were less than the design lock off load measured in the jacks. When the lower braces were cut, around 20% to 30% of the load was transferred to the upper braces. The strain gages in the wales were installed prior to the installation and jacking of the braces. The loads measured in the wales were erratic and may have been affected by temperature. JET GROUTING At the west of the spine jet grouting (JG) was used to cut off the upward flow of groundwater, partially underpin an existing structure, and improve the ground for a mat foundation. In addition, hand excavated concrete pier underpinning was used to underpin the existing

Evans Wing building at the west end of the addition. The JG was performed in the fill and alluvial sand. A section through the JG and underpinning is shown in Figure 9. Figure 10 - Installation of Jet Grouting Figure 9 Section through Jet Grout and Underpinning Three hundred and six over-lapping columns were jetted in the 36.6 by 6.4 m area. The jet grout comprised about 2040 m of drilling and 1220 m of jetting. The average total drill length was 6.1 m and the jet length was 3.7 m. Column diameters varied between 0.8 and 0.9 m. The jet grout columns were laid out in a pattern to provide total coverage of the area to be treated. The perimeter columns along the existing Museum wall were jetted partially beneath the wall footing or underpinning pits to help support the structure. The perimeter columns were spaced at 460 mm on center to provide additional support of the existing structure and cut off vertical and horizontal groundwater flow. Interior columns were spaced on a 910 mm by 910 mm grid in order to improve the bearing capacity for the mat and inhibit upward flow of groundwater. Installation of the JG is shown in Figure 10. The location of each jet grout hole had to be carefully surveyed as significant amounts of spoil were generated which buried any previously set survey marks. Wet samples of the jet grout spoil were taken to test the unconfined compressive strength of the jet grout. These strengths are shown in Figure 11. Figure 11 Jet Grout Strength VS Time Secant Pile Wall A cantilevered secant pile wall was constructed at the south end of the south pavilion to allow for excavation of an underground storage tank. The secant pile wall consisted of overlapping drilled shafts (primary piles) and jet grout columns (secondary shafts). The primary piles, with soldier beams (W530X74), were installed in 750 mm cased drilled holes and backfilled with 20.7 MPa concrete. The primary piles were located on 1.5 m centers. The primary piles had a length of 7.7 m and supported a cut of 3.3 m. Single fluid jet grout columns were constructed between the drilled shafts to complete the secant pile wall. The jet grout columns terminated in the Boston blue clay at Elevation -1.54 m. The use of jet grout columns as the secondary shafts allowed for a savings in the construction schedule.

CONCLUSIONS The following conclusions and observations can be gained from the design, construction, and performance of the CDSM wall, jet grouting, and secant pile wall at the Museum of Fine Arts: McPhail Associates, Inc. (2006), Foundation Engineering Report: Proposed Phase I of the Museum of Fine Arts, Boston, Massachussets, prepared by R.C. Hoyles, May 30, 2006. A stiff CDSM cutoff wall was successfully used for the excavation support system at the MFA. Adjacent structures experienced no significant movement or damage during either construction of the CDSM wall or subsequent excavation. Jet Grouting was effective at creating a groundwater cutoff, strengthening the existing soils, and underpinning an existing building at the MFA. A drilled shaft and jet grout secant pile wall provided excavation support and cut off the groundwater for a tank excavation. Monitoring of deep excavations in low strength clays should not rely on points at the tops of the piles as most of the movement may occur at subgrade. Total station monitoring may not be accurate enough to monitor the small movements that occur in surrounding structures. Finite element modeling of deflections requires using a small-strain stiffness model, undrained moduli and appropriate K o values for the overconsolidated clays. References Hawkes, Martin (2007), Geocomp Memos to Schnabel Foundation Company Regarding Museum of Fine Arts Plaxis Finite Element Analysis, December 2006 to May 2007. Katkhuda, Izzat (2008), Automated Monitoring and Performance Evaluation of the MFA Excavation in Boston, MA, M.S. Thesis, Northwestern University, June 2008,145 pp. Shawkat, Ali (1993), Engineering Properties of Undisturbed Samples of Boston Blue Clay, PhD Dissertation, University of Illinois, Urbana- Champaign, 399 pp. Haley and Aldrich, Inc. (2003), Report on Soil Parameters and Engineering Properties: Museum of Fine Arts, Boston, Massachusetts, prepared by B.J. Aldinger, H.B. Scranton and M.X. Haley, March 18, 2003.