DRILLED SHAFT CONSTRUCTION

Similar documents
SECTION 411 DRILLED PIERS

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Design and Construction of Auger Cast Piles

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Anirudhan I.V. Geotechnical Solutions, Chennai

Lab 1 Concrete Proportioning, Mixing, and Testing

High Strain Dynamic Load Testing of Drilled Shafts

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Specification Guidelines: Allan Block Modular Retaining Wall Systems

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

ALLOWABLE LOADS ON A SINGLE PILE

Drilling Problems. pull

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

BUTE Department of Construction Management and Technology

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

PROPERTIES AND MIX DESIGNATIONS

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers

The Impact Of Cementing On Proper Well Control

NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT.

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

CEEN Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

Construction of Quality Hot Mix Asphalt Pavements

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

SECTION DRILLED CONCRETE PIERS (CAISSONS)

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

CIVL451. Soil Exploration and Characterization

SafetyBuletin. Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping

Basics of Reinforced Concrete Design

METHOD OF STATEMENT FOR STATIC LOADING TEST

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers

PILE FOUNDATIONS FM 5-134

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

Module 1 : Site Exploration and Geotechnical Investigation. Lecture 4 : In-situ tests [ Section 4.1: Penetrometer Tests ] Objectives

Quality Assurance Concepts. Outline

Safe & Sound Bridge Terminology

vulcanhammer.net This document downloaded from

Moving Small Mountains Vesuvius Dam Rehab

How To Design A Foundation

The Installation and Load Testing of Drilled Shafts

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Module 7 (Lecture 24 to 28) RETAINING WALLS

How To Model A Shallow Foundation

Stormwater/Wetland Pond Construction Inspection Checklist

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form

KWANG SING ENGINEERING PTE LTD

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

APPENDIX B. I. Background Information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Table of Contents 16.1 GENERAL Overview Responsibilities

USE OF CONE PENETRATION TEST IN PILE DESIGN

Foundation Code compliance and Best Practices By Michael Coello

SECTION EARTH MOVING

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

Mining with Paste Fill

SECTION ABANDONMENT OF SEWER MAINS

vulcanhammer.net This document downloaded from

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

System. Stability. Security. Integrity. 150 Helical Anchor

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Properties of Fresh Concrete

Installation PowerPoint for Grasscrete Formers

EXCAVATOR SAFETY TRAINING

Washington ,

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

PDCA Driven-Pile Terms and Definitions

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS

Table 4.9 Storm Drain Inlet Protetion Applicable for

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

Guidelines For Sealing Groundwater Wells

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

Transcription:

DRILLED SHAFT CONSTRUCTION West Tower Arthur Ravenel Jr. Bridge Photograph courtesy of Marvin Tallent, Palmetto Bridge Constructors Concrete Mix Design Considerations Dry Construction Method Wet Construction Method Casing Construction Method Equipment Inspection and Testing Slide 1 of 51

CONCRETE MIX DESIGN CONSIDERATIONS SCDOT 712.03 - Class 4000DS (see SCDOT 701) Aggregate Type Min. Cement Content (lbs/cy) Min. 28 day f'c (psi) % Fine to Coarse Aggregate Ratio Max. W/C Ratio Crushed 625 4000 40:60 0.44 Stone 625 4000 39:61 0.43 Type G or Type D w/ Type F Admixture Required Slump: 7-9 inches Nominal Coarse Aggregate: ¾ inch Slide 2 of 51

CONCRETE MIX DESIGN CONSIDERATIONS MassDOT LRFD Design Manual (2009) Section 3.2.3.2 6. The minimum clearance between reinforcing bars shall be 1-7 8 and is equal to 5 times the maximum coarse aggregate size (3 8 ) for both, the longitudinal bars as well as the spiral confinement reinforcement, to allow for better concrete consolidation during placement. Concrete mix design and workability shall be consistent for tremie or pump placement. In particular, the concrete slump should be 8 inches ± 1 inch for tremie or slurry construction and 7 inches ± 1 inch for all other conditions. Slide 3 of 51

CONCRETE MIX DESIGN CONSIDERATIONS Figure 1. Concrete Flow Under Tremie Placement (Brown and Schindler, 2007). Figure 3. Restriction of Lateral Flow (Brown and Schindler, 2007). Slide 4 of 51

CONCRETE MIX DESIGN CONSIDERATIONS Figure 5. Effects of Loss of Workability during Concrete Placement (Brown and Schindler, 2007). Figure 9-1. Free Fall Concrete Placement in a Dry Excavation (FHWA NHI-10-016). Slide 5 of 51

CONCRETE MIX DESIGN CONSIDERATIONS Self Consolidating Concrete (SSC) Project for SCDOT (S&ME 2005). Slide 6 of 51

DRY METHOD (SCDOT 712.07) Less than 6 inches of water per hour Sides and Bottom Remain Stable (Engineer can order 4 hours wait period) Loose material & water can be satisfactorily removed Temporary casing can be used Photograph courtesy of GPE Inc. Slide 7 of 51

STABLE vs. UNSTABLE SOILS Unstable Caving Soils Cohesive Soils Stable Non-Caving Soils Cohesive Soils Unstable caving soils prevent maintaining hole stability Water table Stable non-caving soils maintain hole stability Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 8 of 51

WATER TABLE AT OR BELOW THE SHAFT TIP ELEVATION Water table Stable Non-Caving Soils Cohesive Soils Water table Generally, soils cave at the water table preventing hole stability Water table below shaft tip does not impact hole stability Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 9 of 51

DRY METHOD CONSTRUCTION PROCESS Drill the shaft excavation Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Clean & Place the concrete Drill Inspect Position Place Competent, Non-Caving Soils Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 10 of 51

DRY METHOD CONSTRUCTION PROCESS Continuous Operation. No delays > 12 hrs. No entering non-cased excavations. DRILL (SCDOT 712.10) Photographs courtesy of WPC Inc. Slide 11 of 51

DRY METHOD CONSTRUCTION PROCESS CLEAN & INSPECT Photographs courtesy of WPC Inc. Slide 12 of 51

DRY METHOD CONSTRUCTION PROCESS INSPECTION OF EXCAVATION (SCDOT 712.14) Need SCDOT Qualified Inspectors EXCAVATION CLEANLINESS (SCDOT 712.14D) 50% of Base has < ½ inch of sediment AND Maximum depth of sediment < 1 ½ inches Slide 13 of 51

DRY METHOD CONSTRUCTION PROCESS POSITION (SCDOT 712.16) Spacers needed for 5 inch min. annulus. Spacer interval < 10 ft. Photographs courtesy of WPC Inc. Slide 14 of 51

DRY METHOD CONSTRUCTION PROCESS PLACE (SCDOT 712.17) ASAP after reinforcement placement. Must be completed in 2 hours (unless approved). Tremie preferred. Tremie ID > 6 x Max. Aggregate Size AND > 10 inches. Tremie Embedment > 10 ft. Concrete flow: Positive pressure and continuous. Photograph courtesy of WPC Inc. Slide 15 of 51

DRY METHOD CONSTRUCTION PROCESS PLACE (SCDOT 712.17) Photograph courtesy of WPC Inc. Freefall > 75 ft not permitted. Freefall Max. Aggregate Size ¾ inch, 7-9 inch slump. Freefall still needs chute. Must have tremie onsite. SCDOT can always order tremie. Slide 16 of 51

WET METHOD CONSTRUCTION PROCESS USE WHEN A DRY EXCAVATION CANNOT BE MAINTAINED SCDOT 712.08 More than 6in in one hour = Wet Less than 6in in one hour = Dry Figure courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 17 of 51

WET METHOD CONSTRUCTION PROCESS WHEN THE SIDES AND BOTTOM WHEN LOOSE MATERIAL AND OF THE HOLE CANNOT REMAIN WATER CANNOT BE STABLE SATISFACTORILY REMOVED Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 18 of 51

WET METHOD CONSTRUCTION PROCESS Drill Drill the shaft excavation Stabilize the hole (Plain water, slurry) Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Place the concrete Stabilize Clean Position Place Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 19 of 51

WET METHOD CONSTRUCTION PROCESS There are two forms of wet shaft construction: Static Process Circulation Process Slide 20 of 51

Drill down to the piezometric level Slurry introduced Drilling Completed 14.528 DRILLED DEEP FOUNDATIONS WET METHOD: STATIC PROCESS Hole Hole drilled cleaned to Drill completion of down slurry to & Slurry Piezometric depth cuttings added with to level hole slurry Cuttings are lifted from the hole Temporary surface casing installed (optional) Slurry Slurry Slurry Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Piezometric level Piezometric level Piezometric level level Slide 21 of 51

WET METHOD: CIRCULATION PROCESS Hole is drilled Slurry level maintained at the ground surface Cuttings and sand, is circulated to the surface, where it is cleaned and reintroduced down the hole. Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Piezometric level Piezometric level Slurry, with sand & Hole cuttings drilled is to re-circulated completion for processing depth withand reintroduced slurry level into hole. maintained at Hole ground cleaned level Temporary surface casing install (optional) Slurry Processor Slurry Processor Slide 22 of 51

WET METHOD CONSTRUCTION PROCESS SLURRY (SCDOT 712.12) Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 23 of 51

WET METHOD CONSTRUCTION PROCESS TYPES OF SLURRY Natural mineral clays Bentonite, attapulgite and sepiolite Bentonite is the most common Attapulgite and sepiolite are typically used in saltwater environments Must be hydrated Slide 24 of 51

WET METHOD CONSTRUCTION PROCESS SLURRY COMPARISONS Best Application Mixability Mix Water Sensitivity Mineral Cohesionless Difficult - Must be Hydrated Saltwater Sensitive Polymer Cohesive & Argillaceous Rock Easy Yes/No "Caking" Ability Best OK Suspension Ability Best OK Slide 25 of 51

WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY Control tests are used to maintain proper slurry condition. Tests are conducted for: Density- the slurry weight Viscosity- flow: consistency ph- acidity: alkalinity Sand Content Slide 26 of 51

WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY SCDOT 712.12 MINERAL SLURRY ACCEPTABLE RANGES Property (Units) Value Range @ Introduction Value Range @ Concreting Test Method Density (pcf) 64.3 69.1* 64.3 75.0 Density Balance Viscosity (sec/qt) 28-45 28-45 Marsh Cone ph 8-11 8-11 ph paper ph meter * Add 2 pcf in saltwater ** Sand Slide 27 of 51

WET METHOD CONSTRUCTION PROCESS CONTROLLING SLURRY FOR BOREHOLE STABILITY Proper Dosage and Solids Content for Proper Flowability and Cake Properties Thorough Mixing / Adequate Time for Hydration (Bentonite / Polymers) Maintenance of Head in Borehole Maintenance of ph, Hardness, Salts Minimize Pressures from Tools Slide 28 of 51

WET METHOD CONSTRUCTION PROCESS IMPROPER SLURRY CONTROL Fails to properly suspend and facilitate the removal of sediments and cuttings Does not control caving Does not control swelling of soils Hinders slurry displacement during concrete placement Leads to a dirty hole Slide 29 of 51

WET METHOD CONSTRUCTION PROCESS DIRTY HOLE Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods. Slide 30 of 51

WET METHOD CONSTRUCTION PROCESS SLURRY EXAMPLES Poor Slurry Job Excellent Slurry Job Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 31 of 51

CASING CONSTRUCTION METHOD SCDOT 712.09 & 712.11 Where an open hole cannot be maintained. Where soil or rock deformation will occur. Where constructing shafts below the water table or caving overburden. SCDOT Types: Construction (712.11B) & Temporary (712.11C) Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 32 of 51

CASING CONSTRUCTION METHOD Photograph courtesy of WPC Inc. SCDOT 712.11 Smooth, clean, watertight, w/ample strength Oversized must be approved by SCDOT. Temporary: Fresh concrete > 5 ft above hydrostatic pressure. Construction: Installed as one continuous unit. Welds are only approved connection. Slide 33 of 51

CASING CONSTRUCTION METHOD MassDOT LRFD Design Manual (2009) Section 3.2.3.2 1. The Designer shall consider the intended method of construction (temporary or permanent casing, slurry drilling, etc.) and the resulting impact on the stiffness and resistance of the shaft. 4. When a drilled shaft is constructed with a permanent casing, the skin friction along the permanently cased portion of the shaft should be neglected. Slide 34 of 51

CASING CONSTRUCTION METHOD TELESCOPING CASING Not Permitted by SCDOT (see 712.11C) Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 35 of 51

CASING METHOD: CONSTRUCTION PROCESS Drill the shaft excavation Install casing through caving soils and seal Clean shaft by removing the cuttings & seepage water Position the reinforcing cage Drill Case Clean Position Place Caving Soils Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 36 of 51

CASING CONSTRUCTION METHOD CONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods. Slide 37 of 51

CASING CONSTRUCTION METHOD CONSTRUCTION (a.k.a. PERMANENT) CASING EXAMPLES Figures courtesy of FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods. Slide 38 of 51

FULL-DEPTH CASING PROCESS Installation of Casing Drilling ahead of casing Remove casing Figures courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Figure 1. Concrete Flow Under Tremie Placement. Competent Soil Competent Competent Soil Soil Caving Soil Caving Caving Soil Soil Competent Soil Competent Competent Soil Soil Vibratory Driver Vibratory Driver Casing Water Table Casing Installation Remove Drilling casing ahead of Casing of casing Water Table Slide 39 of 51

CASING CONSTRUCTION METHOD TEMPORARY CASING REMOVAL (a) Prior to lifting casing (b) As Casing is Lifted. Figure 9-4. Concrete Pressure Head Requirement during Casing Extraction (FHWA NHI-10-016). Slide 40 of 51

DRILLED SHAFT EQUIPMENT TERMINOLOGY Kelly Table Power Unit Crane Tool Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 41 of 51

DRILLED SHAFT EQUIPMENT EARTH AUGERS Single Flight Double Flight Double Cut Triple Cut Earth augers are generally used in sands and cohesive materials. Photographs courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 42 of 51

DRILLED SHAFT EQUIPMENT ROCK AUGERS Rock augers are generally used in soft to hard rock formations. Tapered Geometry Conical (Bullet) Carbide Teeth Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 43 of 51

DRILLED SHAFT EQUIPMENT ROCK BITS This is typical of rock bits designed for drilling in hard to very hard rock. Circulating bit Replaceable Roller Bits Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 44 of 51

DRILLED SHAFT EQUIPMENT DRILLING BUCKET Side Cutting Teeth Gouging Teeth Ripping Teeth Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course Slide 45 of 51

DRILLED SHAFT EQUIPMENT CLEANOUT (MUCK) BUCKET This is typical of a cleanout (muck) bucket used to cleanout the cuttings and sediments from the bottom of the shaft. Photograph courtesy of FHWA NHI-132070 Drilled Shaft Foundation Inspection Course 6-51 Slide 46 of 51

DEEP FOUNDATION DESIGN GEOMATERIAL PROPERTIES NEEDED Table 13-1. Geomaterial Properties Required for Drained and Undrained Axial Resistances (FHWA NHI-10-016). Slide 47 of 51

DEEP FOUNDATION DESIGN AXIAL CAPACITY Q total = Q skin + Q tip Where: Q total = Ultimate Pile Capacity Q skin = Skin Friction (i.e. Side) Capacity Q tip = Tip (i.e. Toe) Capacity Slide 48 of 51

DEEP FOUNDATION DESIGN AXIAL CAPACITY Q skin = f s A skin Q toe = q p A toe Where: f s = Unit Skin Friction A skin = Pile Skin Area Where: q p = Unit End Bearing A toe = Pile Toe (i.e. Tip) Area Slide 49 of 51

DEEP FOUNDATION DESIGN GENERALIZED LOAD TRANSFER BEHAVIOR Q skin = R s Q toe = R b Figure 13-1 (FHWA NHI-10-016). Slide 50 of 51

REFERENCES SCDOT Standard Specifications for Highway Construction (2000). SCDOT Foundation Certification Program Notes. FHWA IF-99-025 Drilled Shafts: Construction Procedures and Design Methods. FHWA NHI-10-016 Drilled Shafts: Construction Procedures and LRFD Design Methods NHI Course 132070 - Drilled Shaft Foundation Inspection. Slide 51 of 51