PROJECT REVIEW COMMITTEE MEETING Project 628801 - PRNM and ARTS/MELLLA

Similar documents
GE Energy. Reactor Instrumentation for the New Era of Nuclear Power

Dynamic Behavior of BWR

U.S. Commercial Power and Fuel Supply Outlook

BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering

Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions

Feasibility Study Requirements. Qatar Development Bank

Boiling Water Reactor Systems

Nuclear Power Plant & Systems David Downing / Kenneth Green. WSP Parsons Brinckerhoff / Sargent & Lundy TUESDAY, 6 OCTOBER 2015

Nuclear Power Plant Instrumentation and Control in MEXICO

INDUSTRIAL CONTROL SYSTEMS CYBER SECURITY DEMONSTRATION

High Fraction Hybrid Solar in Canada s North

XA EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA

Application of Fuel Cells to Fork Lift Trucks

How To Improve Nuclear Power Plant Capacity Factor

November 2009 QBR Follow Ups

Rev. 02. STD DEP T (Table and Figures 7.6-1, 7.6-2, 7.6-4a) STD DEP (Table and Figures 7.6-1, 7.6-2)

N.K. Srivastava GM-R&M-Engg.Services NTPC- CC/Noida

Cisco Network Switches Juniper Firewall Clusters

CFD simulation of fibre material transport in a PWR core under loss of coolant conditions

Qualification of In-service Inspections of NPP Primary Circuit Components

[SOE LETTERHEAD] July 12, 1990

CASL: Consortium for the Advanced Simulation of Light Water Reactors: Program Update

The Piping System Model a New Life Cycle Document. Elements of the Piping System Model

DC Cook Plant Process Computer Replacement Project

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director

Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called...

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1

SOLVING REACTOR WATER CLEAN-UP SYSTEM ANOMALIES USING RELAP5 MOD3.3

Pressurized Water Reactor B&W Technology Crosstraining Course Manual. Chapter 9.0. Integrated Control System

Nuclear Power Plant Electrical Power Supply System Requirements

AUDIT OF ELECTRIC HOPKINS UNIT 2 REPOWERING PROJECT

Trust our people. Trust our expertise. eady is a professional engineering firm with highlyqualified electrical and controls personnel focused on

Turbine Controls Update

U.S. Nuclear Regulatory Commission. Plan of Action Strategic Workforce Planning

Recent Technologies in Nuclear Power Plant Supervisory and Control Systems

First Quarter 2014 Earnings Conference Call. New Nuclear Presentation Section. April 24, 2014 First Quarter 2014 Earnings Conference Call 1

The World Nuclear Supply

Auditing Capital Projects and Project Controls. March 2013

GEH Safety Enhancement Services

Swiss media visit to Olkiluoto August 15, 2014

of Nuclear Power I COVER STORY

SINGLE SOURCE CAPABILITY, RESPONSIBILITY, ACCOUNTABILITY.

Boiling Water Reactor Basics

Options for Cyber Security. Reactors. April 9, 2015

Enclosure 3. Reactor Oversight Process Task Force FAQ Log March 18, 2015

The Future of Statewide Accounts Receivables System Solution. Customer Group Meeting June 10, :00 AM 12:00 PM

NEI 06-13A [Revision 2] Template for an Industry Training Program Description

1: Levelized Cost of Energy Calculation. Methodology and Sensitivity

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario

Small Modular Nuclear Reactors: Parametric Modeling of Integrated Reactor Vessel Manufacturing Within A Factory Environment Volume 1

TELECOMMUNICATION SYSTEM HAZARD MITIGATION STRATEGIC PLANNING

Lecture 4: ERP Options and Selection Methods

Systems and services for small hydro power plants

Join the UK Nuclear Renaissance. Procurement & Quality Process

Integration of Criticality Alarm System in a Fuel Fabrication Plant

CFD Topics at the US Nuclear Regulatory Commission. Christopher Boyd, Ghani Zigh Office of Nuclear Regulatory Research June 2008

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

NORTH CAROLINA EASTERN MUNICIPAL POWER AGENCY SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1. Renewed License No. NPF-63

Making the Business Case for Positive Change. Agenda

Top of Rack: An Analysis of a Cabling Architecture in the Data Center

NEI 06-13A [Revision 0] Template for an Industry Training Program Description

BIGFIX. Free Software Is Not Free: A Quantitative TCO Analysis. Executive Summary

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Accessing finance. Developing a business case for your resource efficiency projects

Guide Contents. 7 Common Drivers for Chemical Management. Page. Page 2. Adhesive Technologies - Chemical Management

SMR Financing and Economics. The Nuclear Option: Is Small Scale Nuclear Energy an Option for Alaska?

Title of Nomination: Montana Statewide Directory Implementation Project/System Manager: Mike Boyer Title: Computing Technology Services Bureau Chief

University of Central Florida Class Specification Administrative and Professional. Network Operations Manager (Enterprise)

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS October

WHITE PAPER. How To Build A Real Green Data Centre. Contents. Part 1: Drivers for Data Centre energy efficiency. February 2008

Navigating the Pros and Cons of Structured Cabling vs. Top of Rack in the Data Center

February 3, SUBJECT: Proposed Standard Scenario Results Comparison Metrics

Feasibility Study Proposal & Report Guide. Industrial Optimization Program

ULSTER COUNTY COMPTROLLER S OFFICE Elliott Auerbach, Comptroller

Bundling small-scale energy efficiency projects

Backup Plan Examples. What s Your Backup Plan?

Recommended Practice for Software Acquisition

Project Evolution & Estimation :cash flow forecasting, cost benefit evolution techniques, risk evolution, Cost benefit analysis

Optimization in the Virtual Data Center

White Paper THE TRUTH ABOUT DUAL POWER FEEDS

Structural Integrity and NDE Reliability II

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

How To Clean Up A Reactor Water Cleanup

Basic requirements 999GG01834

PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT?

This occurrence is considered to be of no significance with respect to the health and safety of the public.

Accessing finance. Developing a business case for your resource efficiency projects

10 Nuclear Power Reactors Figure 10.1

Measures to mitigate electricity rates

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER G: INSTRUMENTATION AND CONTROL

What Can Software as a Service Do for Your Business?

NRC INSPECTION MANUAL INSPECTION PROCEDURE 88045

Borough of South River, New Jersey Alternative Energy & Conservation Committee

A risky business. Why you can t afford to gamble on the resilience of business-critical infrastructure

1. Summary. electric grid, strengthen saving programs sponsored by utilities. The project

SERVICES. Designing, deploying and supporting world class communications solutions.

Energy efficiency and cost reduction solutions for industry. PowerLogic application brochure

ST A TEMENT OF ALICE M. RIVLIN DIRECTOR CONGRESSIONAL BUDGET OFFICE

Transcription:

PROJECT REVIEW COMMITTEE MEETING Project 628801 - PRNM and ARTS/MELLLA Jim Snyder, Presenter Jim Snyder, Project Manager Nishant Chadha, System Engineer Dave Brown, Project Sponsor July xx, 2012

Statement of Action/ Decision Requested from PRC Obtain funding for the following: Additional NRC review costs ($35K) Complete General Electric Hitachi (GEH) FY12 scope for RPV Overpressurization analysis ($30K) Obtain a Vendor to prepare PRNM to PPC interface software documentation ($176.8K) Decrease ENL software documentation budget (-$56K) Use a vendor to complete preparation of the PRNM to PPC software code ($27K) Obtain field support and training for C3-ilex computer preassembly installation ($11K) 2

Problem Statement/ Description of the Issue Problem Statement The existing neutron monitoring system is obsolete. Replacement parts are costly and becoming difficult to obtain. Significant station resources are expended in corrective maintenance and surveillance costs. Also, the existing system is vulnerable to surveillance-induced half scrams and spiking of the Local Power Range Monitors (LPRM). Installation of a new safety related digital Power Range Neutron Monitoring (PRNM) system corrects these problems. PRNM is needed to be able to implement ARTS/MELLLA which will expand our current operating domain. This will provide additional operational flexibility when operating at rated power, leading to fewer downpowers to manipulate control rods, especially during the last part of the operating cycle, and would eliminate nuisance alarms caused by our current system. Cost benefit is that seven fewer fuel bundles will be needed each cycle and net electrical generation will increase due to running RRC pumps at slower speed. Surveillance costs will also be reduced. Estimated savings are $7M per year plus a one time cost savings for not having to clean jet pump nozzles. Operating Experience CGS is the last US BWR to implement ARTS/MELLLA 29 BWRs have implemented PRNM Excellent operating history since PRNM was installed at Hatch in 1996 Driver: The primary driver is obsolescence of the existing neutron monitoring system and the need to implement PRNM to allow ARTS/MELLLA to be installed 3

Current Status PRNM factory acceptance testing was completed in 2010 R-20 Work Standby Liquid Control tank boron-10 was enriched Fiber optic cables were pulled in the main control room Pre-assembly will be done in Deschutes computer lab starting in September 2012 Status/Impact to the Project s Milestones/Critical Path Design is currently expired. PDC will be updated in FY14. Work orders are being reviewed and updated PRNM to PPC interface software (power to flow map, reactor display, containment status, etc.) documentation needs to be completed prior to the PDC being updated Procedure revisions are essentially complete Need power ascension test procedure A few Operations procedures need to be finalized 4

Current Status (continued) Pre-outage work needed Pre-assembly of components in Deschutes computer lab to verify equipment is functioning, conduct training and to verify communications with PPC Simulator modification Buy-in from Support organizations has been established Installation is scheduled for R22 NRC is reviewing the License Amendment Request Approval anticipated in FY13 5

Options Do Nothing No change in budget Recommended Option 1 Approve budget change Allows project work to continue on schedule Option 2 ENL prepare software documentation Continue to use ENL employees to prepare software documentation Option 3 Eliminate C3-ilex support Eliminate C3-ilex personnel support for connecting the DASie computer to PRNM and the PPC and provide on-site training 6

Options Technical Pros/Cons Technical Pros/Cons Options Pros Cons Do Nothing Recommended Option 1 Approve Budget Increase Budget is not impacted Keeps project on schedule and transfers knowledge to ENL employees The required work wouldn t get done. The budget would be overrun to pay anticipated NRC costs. Increases total cost of project Option 2 Cost would be lower Not enough computer personnel to do the software documentation in a timely manner. Software documentation might not get done in time to support PDC upgrade. Option 3 Reduces cost by $11K Installation may take longer plus there would not be an opportunity for the new personnel to get trained. Turnover of ENL personnel has resulted in lost knowledge. 7

Options Budget/Schedule Budget Impacts Impact is only FY13 Options FY13 FY09-15 Approved Budgets ENL NENL Total ENL NENL Total Do Nothing $197K $402K $599K $1,838.4 $22,128.1 $23,966.5 Option 1 $141K $682K $823K Option 2 $197K $505K $702K Option 3 $141K $671K $812K Schedule Impacts/Recommended Schedule for LRP Options Do Nothing Option 1 - Recommended Option 2 Option 3 Schedule Impacts Likely would not have software documentation done in time to support PDC upgrade in FY14. That could lead to a missed R22 outage milestone. Would ensure success path in completing software code and documentation for the PRNM to PPC interface. This would also allow approved cost to more closely match anticipated costs associated with the NRC review and provide C3-ilex assistance during pre-assembly. EN computer personnel have not had adequate time to keep plant equipment operating and work on PRNM software documentation at a pace that would allow completion in time to support the PDC upgrade. R22 Outage milestone to have PDCs ready could be challenged if EN personnel do all the software documentation work. Would not have C3-ilex available to provide assistance and conduct training during pre-assembly 8

Recommendation Cost Flow and Timing for recommended option Requested Budget ($K) Cost Flow Based on Most FY 12 FY 13 Current Estimate Approved/Actual Approved/Requested FY 14 FY 15 Phase: 3 3 3 3 Grand Total (FY09 FY15) ENL $148.2/$97.2 $197.0/$141.0 $106.9 $370.1 $1,838.4 NENL $2301.5/$2289.5 $402.6/$695.7 $22.0 $1730.8 $22,128.1 Grand Totals $2,449.7/$2,386.7 $599.6/$836.7 $128.9 $2,100.9 $23,966.5 9

Risk Statement and Bridging Strategy Risk during implementation Lack of experienced personnel Components could be damaged Moisture carryover higher than expected Communication problems between PRNM and PPC Implementation could take longer than expected Risk if not approved Obsolete neutron monitoring equipment could fail No cost savings realized from new power to flow map using MELLLA boundaries Continued rod blocks would be received 10

Project Type Capital Impact to LRP FY09 FY10 FY11 FY12 Total Total Project Cost Nominal $K ENL NENL ENL NENL ENL NENL ENL NENL ENL NENL ARTS/MELLA $ 5,850 PRNM $ 11,942 Current LRP $ - $ - $ - $ - $ - $ 11,000 $ 28 $ 1,352 $ 28 $12,352 Total Project Cost $ 17,792 Funding Source Nominal $K Proposed LRP $ 56 $ 2,356 $ 748 $ 7,638 $ 1,315 $ 5,679 $ - $ - $ 2,119 $15,673 Sale of Existing Asset (SWU) $ 11,750 Variance $ 56 $ 2,356 $ 748 $ 7,638 $ 1,315 $ (5,321) $ (28) $ (1,352) $ 2,091 $ 3,321 Fuel Capital Budget $ 6,042 Total Funding Source $ 17,792 Impact on FY09 LRP Item/Description FY09 LRP Capital Project $K Recommended Option Change to LRP NENL $ 28.0 $ - $ 28.0 ENL $ 12,352.0 $ - $ 12,352.0 Total $ 12,380.0 $ - $ 12,380.0 PHC/EAC Approval Options Considered Option 1 - Continue Use of Existing Power Range Neutron Monitoring Option 2 - Install New Power Range Neutron Monitoring and ARTS/MELLA. Funded by sale or exchange of existing fuel assets (SWU) and other capital fuel budget Recommendation Option 2 - Install New Power Range Neutron Monitoring and ARTS/MELLA. Funded by sale or exchange of existing fuel assets (SWU) and other capital fuel budget ARTS/MELLA FY09 $K FY 2009 FY 2010 FY 2011 Total NENL GEH $ 743 $ 1,672 $ 1,301 $ 3,716 AREVA $ - $ 750 $ - $ 750 Rockett Science $ - $ 280 $ 140 $ 420 Materials (Incl with GEH) $ - $ - $ - $ - Sales and Use Tax $ - $ - $ - $ - Total NENL $ 743 $ 2,702 $ 1,441 $ 4,886 ENL Reactor Fuels Eng $ 40 $ 80 $ 200 Design Engineering $ - $ 80 $ 40 Technical Services Eng $ - $ 80 $ 40 System Engineering $ - $ 40 $ 80 Project Management $ - $ 8 $ 20 Operations $ - $ 40 $ 40 Licensing $ - $ 20 $ 20 Legal $ 8 $ - $ - Supply Chain Services $ 8 $ - $ - Training $ - $ - $ 20 $ 320 $ 120 $ 120 $ 120 $ 28 $ 80 $ 40 $ 8 $ 8 $ 20 $ - Total ENL $ 56 $ 348 $ 460 $ 864 NRC licensing fees $ - $ 100 $ - $ 100 Total $ 799 $ 3,150 $ 1,901 $ 5,850 PRNM NENL FY09 $K FY 2009 FY 2010 FY 2011 Total GEH $ 1,479 $ 3,328 $ 2,589 $ 7,396 Sargent & Lundy $ 1,200 $ 500 $ 1,700 PPCRS update $ 500 $ 500 Simulator update $ 300 $ 300 Materials $ - Sales and Use Tax $ 133 $ 408 $ 350 $ 891 Total NENL $ 1,612 $ 4,936 $ 4,239 $ 10,787 ENL Design Engineering $ 50 $ 250 System Engineering $ 50 $ 250 Project Management $ 100 $ 100 Operations $ 50 Maintenance $ 100 Licensing $ 5 IS Support $ 100 $ 300 $ 300 $ 200 $ 50 $ 100 $ 5 $ 100 Total ENL $ - $ 200 $ 855 $ 1,055 NRC licensing fees $ - $ 100 $ - $ 100 Total $ 1,612 $ 5,236 $ 5,094 $ 11,942 ARTS/MELLA & PRNM NENL FY09 $K FY 2009 FY 2010 FY 2011 Total GEH $ 2,222 $ 5,000 $ 3,889 $ 11,112 AREVA $ - $ 750 $ - $ 750 Rockett Science $ - $ 280 $ 140 $ 420 Sargent & Lundy $ - $ 1,200 $ 500 $ 1,700 PPCRS update $ - $ - $ 500 $ 500 Simulator update $ - $ - $ 300 $ 300 Sales and Use Tax $ 133 $ 408 $ 350 $ 891 Total NENL $ 2,356 $ 7,638 $ 5,679 $ 15,673 ENL Reactor Fuels Eng $ 40 $ 80 $ 200 $ 320 Design Engineering $ - $ 130 $ 290 $ 420 Technical Services Eng $ - $ 80 $ 40 $ 120 System Engineering $ - $ 90 $ 330 $ 420 Project Management $ - $ 108 $ 120 $ 228 Operations $ - $ 40 $ 90 $ 130 Maintenance $ - $ - $ 100 $ 100 Licensing $ - $ 20 $ 25 $ 45 Legal $ 8 $ - $ - $ 8 Supply Chain Services $ 8 $ - $ - $ 8 Training $ - $ - $ 20 $ 20 IS Support $ - $ - $ 100 $ 100 NRC licensing fees $ - $ 200 $ - $ 200 Total ENL $ 56 $ 748 $ 1,315 $ 2,119 Total $ 2,412 $ 8,386 $ 6,994 $ 17,792 Note 1 GEH proposal for ARTS/MELLLA+PRNM total ~$11M. Fuels will pay for this using enrichment services (SWU) based on current market prices. The book price of our SWU is significantly less than market resulting in an actual cost to EN of ~$5M. Note 2 The GEH costs for PRNM included in Rev. 0 of the contract are funded by Fuels (due to the use of SWU for payment). Additional GEH costs will need to be covered by PHC/EAC. Key Assumptions/Qualifications - Escalation Rate e 3.5% - Discount Rate v 6.5% Quantifiable Benefits Savings FY09$K Savings Frequency - Reduction of 8 fuel bundles per reload $ 4,600 per 2 years MW Savings MWH/Yr $/MWH - Increase in net electrical generation due to running RRC at lower speed 3 26,280 $ 50.00 $ 3,942 per year Save 3 MW on average @ $50/MWH - Reduction in the number of down-powers required to move control rods 8,635 $ 50.00 $ 432 per year - Elimination of jet pump cleaning campaign FY23 $ 7,000 one-time - Reduction in maint troubleshooting costs estimated to be 1500 man-hours/year $ 90 per year PRNM - Reduction in I&C surveillance costs estimated to be 3000 man-hours/year $ 180 per year PRNM - Reduction in replacement parts costs - 5 boards per year at $20K each $ 100 per year PRNM Non-quantifiable benefits - Reduction in the frequency of nuisance alarms (rod block alarms). This is an item on the Operations Aggregate Index. - Reduction in the number of down-powers required to move control rods to maintain 100%. We currently forecast weekly downpowers to 90% for approximately 1.5 hours per week (average) to move rods. This may continue for the next 8 months until the refueling outage. - Elimination of I&C time during startup to perform T-factor adjustment of APRM gain. - Replacement of obsolete equipment in the APRM and RBM systems. - Replacement of obsolete, non-supported equipment in the OPRM system. - Drastic improvement in equipment reliability. - Elimination of surveillance-induced ½ scrams which reduces overall reactor scram likelihood. - Reduction in control rod depletion rate due to lower control rod density resulting in longer installed life of control blades. - Reduction in channel distortion (bowing) due to fewer blades in the core. - Reduction in containment heat load. - Reduced sensitivity to LPRM problems / spiking. - Installation of ARTS/MELLLA+PRNM is required to go to Extended Power Uprate. Escalation Discount Capital Costs per 2 years Increased Net Generation Tangible Savings Annual Surveillance/Maint/ Parts Downpower Reductions One-time NPV CumNPV FY09 1.00000 1.00000 $ (2,412) $ (2,412) $ (2,412) 1 FY10 1.035000 0.93897 $ (8,150) $ (8,150) $ (10,561) 2 FY11 1.071225 0.88166 $ (6,606) $ (6,606) $ (17,167) 3 FY12 1.108718 0.82785 $ 3,618 $ 340 396 $ 4,354 $ (12,813) 4 FY13 1.147523 0.77732 $ 4,103 $ 3,516 $ 330 385 $ 8,335 $ (4,478) 5 FY14 1.187686 0.72988 $ - $ 3,417 $ 321 374 $ 4,112 $ (366) 6 FY15 1.229255 0.68533 $ 3,875 $ 3,321 $ 312 364 $ 7,872 $ 7,506 7 FY16 1.272279 0.64351 $ - $ 3,227 $ 303 353 $ 3,884 $ 11,389 FY17 1.316809 0.60423 $ 3,660 $ 3,136 $ 294 344 $ 7,434 $ 18,824 FY18 1.362897 0.56735 $ - $ 3,048 $ 286 334 $ 3,668 $ 22,492 FY19 1.410599 0.53273 $ 3,457 $ 2,962 $ 278 324 $ 7,021 $ 29,513 FY20 1.459970 0.50021 $ - $ 2,879 $ 270 315 $ 3,464 $ 32,978 FY21 1.511069 0.46968 $ 3,265 $ 2,798 $ 263 306 $ 6,631 $ 39,609 FY22 1.563956 0.44102 $ - $ 2,719 $ 255 298 $ 3,272 $ 42,881 FY23 1.618695 0.41410 $ 3,083 $ 2,642 $ 248 289 $ 4,692 $ 10,955 $ 53,836 FY24 1.675349 0.38883 $ - $ 2,568 $ 241 281 $ 3,090 $ 56,926 Total $ (17,167) $ 21,443 $ 39,853 $ 3,741 $ 4,692 IRR 23% Payback years Pay Back Years Business Case Payback in 7 years 11

12 Questions?