Bundling small-scale energy efficiency projects
|
|
- Georgina Hamilton
- 7 years ago
- Views:
Transcription
1 Bundling small-scale energy efficiency projects Issue Paper Introduction Energy efficiency projects are characterised by a large variety of size in terms of reduction of energy inputs and emissions Whereas supply-side energy efficiency projects, such as refurbishments of power plants or improvements of heating plants, tend to be larger both in investment and in reduction effects, energy efficiency projects on the demand side mainly generate only limited effects in terms of quantity of emission reductions due to their size. UNIDO experience of energy efficiency project in industry 1 shows that improving systems efficiency does not necessarily involve investment in expensive new technologies with long paybacks. However, the techniques and procedures for identifying and quantifying potential energy savings are complex, requiring information on a wide range of technical subjects as well as knowledge and skills acquired through extensive experience and high levels of specialization. Projects addressing small-scale energy efficiency improvements could deliver considerable contribution to sustainable development and productivity growth in industry. However, despite these potential benefits, these projects could be discouraged because of the relatively high transaction costs. Because of technical complexities in project identification and high transaction costs, energy efficiency projects currently represent only a negligible share in the national CDM project portfolios that are currently undergoing development and screening 2. Some examples to illustrate this: A project that improves the pumping system s effectiveness by applying proper pumps and adding a Variable Frequency Drives (VFD) to the system reduces annual electricity consumption by 1,060 MWh. Carbon savings of this project will be in the order of 1,000 t of CO 2 per year assuming saved electricity is coal based 3. In a cardboard plant, the existing compressor station (installed capacity 430 kw) is replaced by new compressors with increased efficiency (installed capacity 265 kw). Yearly electricity consumption is reduced by 570 MWh. This gives a CO 2 emission reduction of about 500 tons per year. 4 1 China Motor System Energy Conservation Project FI/CPR/00/122 2 UNIDO 2003, CDM Project Portfolio for Brazil GLO/99/HO6, Vienna China Motor System Energy Conservation Project FI/CPR/00/122 4 Energy efficiency project of a private company in a JI country.
2 The JI and CDM project cycle When projects shall be put forward as Joint Implementation (JI) or Clean Development Mechanism (CDM) 5 projects, a certain procedure is necessary to generate emission reductions, which can then be transferred to carbon purchasers. Following the agreements reached in Marrakesh, the project cycle is in many phases very determined and requires the elaboration of specific documents. The documents and procedures involved in project preparation are very extensive in order to ensure additionality of emission reductions. The extra costs that are inevitably encured in this process discourage small scale projects, which as a result, stand a small chance of implementation under the CDM or JI. The project cycle, both for JI and CDM projects, is illustrated in Graph 1. The main steps in the development of a JI or CDM project, which in most cases also require the involvement of external partners at certain costs, are: Project Design Document (PDD): This is the main document in the creation of carbon revenues. It describes the project, analyses the baseline scenario, provides arguments for the additionality of the project and gives an estimate on the emission reductions generated. The PDD includes the Baseline Study and the Monitoring Plan, central documents in the entire project cycle. Validation: Once the PDD including the Baseline Study and the Monitoring Plan are prepared, these document are validated by an external third party. This validation checks, whether the assumptions in the documents are accurate and the expected emission reduction is likely to happen. Monitoring, verification, certification: Once the project is implemented and operating, the performance of the project and the real emission reductions generated will be monitored. The generation of emission reductions will be verified and in the case of CDM also certified. 5 There will be a special methodology for small-scale projects under CDM. These rules for small-scale CDM projects have been drafted, but no decision has been reached up to now. Small-scale CDM projects will not be considered in this Issue Paper.
3 JI Project Cycle Check eligibility and potential CDM Project Cycle Check eligibility and potential Project Design Document (PDD) Project Design Document (PDD) Approval at national level (host country, investor country) Approval at national level (host country, investor country) Validation Validation Registration with CDM Executive Board Project implementation Project implementation Monitoring and verification Monitoring, verification and certification Transfer of ERUs CERs issued and transferred Graph 1: Project cycle for JI and CDM projects
4 Transaction costs As mentioned above, a number of the steps in the JI and CDM project cycle require external experts and lead to certain costs. Validation of the Project Design Documents and verification (in CDM projects also certification) of the emission reductions achieved has to be performed by independent entities. For the other steps in the project cycle, such as developing the Baseline Study or the Monitoring Plan, external support is not required, but will be a valued contribution to achieve the standards necessary to pass validation. Also the project type, the host country, and technologies involved will have an influence, whether more or less support is necessary. All in all, certain transaction costs (baseline analysis, preparation of monitoring plan, contract negotiation, achievement of host country s acceptance, validation, registration etc.) will arise. An analysis for the Austrian JI/CDM Programme showed that these costs will be in a range of about 30,000 to 100,000 per project, depending mainly on project type and framework conditions in the host country It is typical that these costs are almost independent on the size of the project. So smaller projects have the disadvantage that a bigger share of the revenues from the sale of emission reductions is eaten up by transaction costs. Bundling as a strategy for reducing transaction costs As laid down in the introduction, typical demand side energy efficiency projects are generally small in terms of emission reductions. One strategy to overcome this disadvantage is to bundle a number of energy efficiency projects. In order to be able to bundle, a number of requirements has to be fulfilled: Projects should be of the same type: The advantage of bundling is that the documents to be prepared (Project Design Document, Baseline Study, ) can be used for more than one project. This requires that projects are of the same type. Whereas it is easy to bundle a number of motor efficiency projects in different companies, it will be difficult to combine a motor efficiency project with a steam efficiency project. The main reason is that for a specific project type a certain approach is chosen in the Baseline Study and the Monitoring Plan. So it is possible to aggregate smaller sub-projects in different sectors (e.g. motor, industrial steam plants, thermal manufacturing processes), to projects resulting in a generation of carbon assets of sufficient amount to improve cost-efficiency of the generation of emission reductions. Projects should be in the same geographic area: Projects can only be bundled, if they are in the same country. Within a country it is preferred to have the projects within a geographic area, as framework conditions will be similar. Projects should be in a similar development stage: The JI or CDM project cycle has to be integrated into the conventional project cycle for the development of an investment project. If projects are in different stages (e.g. project idea, feasibility study, detailed planning), it will be difficult to synchronize the JI/CDM project cycle. Projects have to be aggregated by an institution: Bundling of project works, when one institution/company is aggregating the different sub-projects. The task of this institution is to act as a single contact point for the carbon purchaser, which is
5 coordinating the preparation of the documents, the implementation of the projects and the monitoring of the emission reductions. This institution will also have the main responsibility against the carbon purchaser for the performance and the accurate implementation of the different projects. Open issues for discussion Is it possible to generate a number of sub-projects within the same project type, the same area and a similar development stage to bundle them to a sizeable JI or CDM project? Can institutions take over the responsibilities for the preparation, implementation and operation of a number of sub-projects in a project bundle? Which strategies do exist to reduce costs for the development of the requested JI and CDM documents further? Can monitoring for a number of sub-projects be organised in a way, which keeps costs at a minimum? Can ESCOs or other intermediaries undertake the task of bundling energy efficiency projects and aggregating them into a larger size CDM/JI projects? What should be done to enable ESCOs to undertake this task?
Carbon Projects and Potential Source of Revenue for Microfinance Institutions to Accelerate Renewable Energy Lending in Nepal
Carbon Projects and Potential Source of Revenue for Microfinance Institutions to Accelerate Renewable Energy Lending in Nepal By: Marco van der Linden, Carbon Finance Advisor: MarcovanderLinden@snvworld.org
More informationHow To Get A Carbon Credit
Energy Saving Technologies & CDM - Business Opportunity with Japan - Clean Energy Finance Committee Mitsubishi UFJ Securities Contents 1. Technology & CDM: Why this is a new business model? 2. CDM: revenue
More informationWHO WE ARE. THE COMPANY
Every journey starts with a single step. WHO WE ARE. THE COMPANY One of the major challenges of our day and age is the efficient and sustainable use of the resources available to us whilst considering
More informationGreen Power Accounting Workshop: Concept Note For discussion during Green Power Accounting Workshop in Mexico City, May 13th 2011
Introduction As more companies and government organizations prepare greenhouse gas (GHG) inventories that reflect the emissions directly and indirectly associated with their operations, they increasingly
More informationProject Procurement Standard
Project Procurement Standard Version: June 2008 This document presents the procurement standard for all carbon offsetting projects under the myclimate label. It provides a summary of all applicable standards
More informationA Summary of the Kyoto Protocol and the Marrakesh Accords By James G. Derouin Fredric D. Bellamy David R. Nelson Mark E. Freeze 1
A Summary of the Kyoto Protocol and the Marrakesh Accords By James G. Derouin Fredric D. Bellamy David R. Nelson Mark E. Freeze 1 The Kyoto Protocol is an outgrowth of the United Nations Framework Convention
More informationThe Clean Development Mechanisms (CDM) What is it? And how can it be used to promote climate protection and sustainable development?
The Clean Development Mechanisms (CDM) What is it? And how can it be used to promote climate protection and sustainable development? World Bank Institute Distance Learning Course: Climate Change: An African
More informationCONTRACTING (EPC) GUIDEBOOK
ENERGY PERFORMANCE Energy Performance Contracting (EPC) Guide CONTRACTING (EPC) GUIDEBOOK Prepared by The CarbonSmart Secretariat Hong Kong Productivity Council June 2014 Table of Content 1 INTRODUCTION
More informationVER+ A robust Standard for Verified Emission Reductions (Criteria Catalogue)
VER+ A robust Standard for Verified Emission Reductions (Criteria Catalogue) A. Introduction Verified emission reductions are commonly understood as tradable emission reductions that have been generated
More informationDeveloping the Project Design Document
THE CLEAN DEVELOPMENT MECHANISM: A USER S GUIDE CHAPTER 3: Developing the Project Design Document The project design document, or PDD, is the central component in the CDM project cycle, and its preparation
More informationProject Idea Note: Solar Water Heating Fee-For-Service Program in the Caribbean
PROJECT IDEA NOTE (Based on the World Bank s PIN Template, with Some Adaptations) A. Project description, type, location and schedule Name of Project: Solar Water Heating Fee-for-Service Program in the
More informationfor Energy Efficiency Parminder Sandhu, P. Eng
Certifying Manufacturing Plants for Energy Efficiency Parminder Sandhu, P. Eng Strategic Goals of Plant Certification Fosters an organizational culture of continuous improvement in energy efficiency i
More informationBuilding capacity for IEE services in developing and emerging economies
UNIDO Industrial Energy Efficiency Programme Building capacity for IEE services in developing and emerging economies Presented by: Aimee McKane 1 and Marco Matteini 2 12-13 November 2009 Farmleigh House,
More informationConcrete Example of CDM Project : Lages Methane Avoidance Project
Concrete Example of CDM Project : Lages Methane Avoidance Project By Electrabel Suez Trading and Portfolio Management Wépion, June 5th 2008 1 Agenda CDM projects : Why / How? Lages Cogeneration Project
More informationAssessment Report for CDM proposed standardized baseline (Version 01.0)
Assessment Report for CDM proposed standardized baseline (Version 01.0) (To be used by the UNFCCC secretariat in assessing the quality of a proposed standardized baseline only when requested by eligible
More informationTax and the Environment: a world of possibilities
Tax and the Environment: a world of possibilities Netherlands A - Direct Taxation 2. Exemptions for profits related to primary-sector activities There are several exemptions for profits related to primary-sector
More informationNew business segments for the energy saving industry Energy efficiency and decentralised energy systems in the building & housing sector
New business segments for the energy saving industry Energy efficiency and decentralised energy systems in the building & housing sector Workshop on ESCOs Energy Service Companies March 28-29, 2012, Ramat
More informationGreen-e Climate Stakeholder Process Voluntary GHG Project Certification Programs
VOLUNTARY GHG PROJECT CERTIFICATION PROGRAMS This document provides information to stakeholders about the Gold Standard, a voluntary GHG project certification program. This document is distributed to stakeholders
More informationUN Carbon Market Mechanisms: Business opportunities for the Caribbean
UN Carbon Market Mechanisms: Business opportunities for the Caribbean Guest Lecture, 9 th February 2015 Department of Business and Management St. George s University Karla Solís, Eng.D. Team Lead CDM Regional
More informationElectrical infrastructure serving the city of London CITY OF LONDON. 2012 Corporate Energy Consumption Report
Electrical infrastructure serving the city of London CITY OF LONDON 2012 Corporate Energy Consumption Report September 2013 TABLE OF CONTENTS CORPORATE ENERGY MANAGEMENT - UPDATE... 3 1 CORPORATE ENERGY
More informationMethodological tool Tool for the demonstration and assessment of additionality
CLEAN DEVELOPMENT MECHANISM TOOL01 Methodological tool Tool for the demonstration and assessment of additionality TABLE OF CONTENTS Page 1. INTRODUCTION... 3 2. SCOPE, APPLICABILITY, AND ENTRY INTO FORCE...
More informationGUIDELINES FOR USERS OF THE JOINT IMPLEMENTATION PROJECT DESIGN DOCUMENT FORM. Version 04. Revision history of the document
Joint Implementation Supervisory Committee page 1 GUIDELINES FOR USERS OF THE JOINT IMPLEMENTATION PROJECT DESIGN DOCUMENT FORM Document version Adoption Revision Revision history of the document Version
More informationNAP II in Denmark The challenges
NAP II in Denmark The challenges 28 August 2006 Ture Hammar Energistyrelsen Overview The Danish commitment to control GHGs Development in emissions since 1988 Contents of NAP I & II in Denmark Major challenges
More informationT@W Good Practice Form
T@W Good Practice Form Setting Title: Public-private Partnership Leading to a New CHP Plant Utilising Fibre Sludge and Biomass Country: Location: Sweden Mariestad in West Sweden Region Start date: 1999
More informationGHG Accounting Guidance Note Manufacture of Renewable Energy Climate Related Products
GHG Accounting Guidance Note Manufacture of Renewable Energy Climate Related Products IFC CLIMATE BUSINESS GROUP SEPTEMBER 2011 Introduction The following is an overview guidance for IFC investment staff
More informationMaking Coal Use Compatible with Measures to Counter Global Warming
Making Use Compatible with Measures to Counter Global Warming The J-POWER Group is one of the biggest coal users in Japan, consuming approximately 2 million tons of coal per year at eight coal-fired power
More informationDATA CENTRE DESIGN AND
SPUSC 2008 SOUTH PACIFIC USER SERVICES CONFERENCE DATA CENTRE DESIGN AND ENERGY INITIATIVES Presented by Jarrad Clift Electrical Engineer Greenstar Accredited Presentation Content Data Centres General
More informationHow to Earn the LEED Green Power Credit
3D EG REES WH ITE PAPER How to Earn the LEED Green Power Credit Using on-site and off-site renewable energy to mitigate the impact of greenhouse gas emissions associated with a LEED project s energy use
More informationDraft Large-scale Consolidated Methodology ACM00XX: Construction of a new natural gas power plant
CLEAN DEVELOPMENT MECHANISM CDM-MP66-A01 Draft Large-scale Consolidated Methodology ACM00XX: Construction of a new natural gas power plant COVER NOTE 1. Procedural background 1. The Executive Board of
More informationLegal & Contracting Issues in the CDM. Glenn S. Hodes UNEP Risø Center
Legal & Contracting Issues in the CDM Glenn S. Hodes UNEP Risø Center CD4CDM MAURITIUS, Third National Workshop, September 2008 http://cd4cdm.org/publications.htm An Overview of Guidebook Builds on CD4CDM
More informationEnergy Efficiency and Renewable Energy Sources in Sweden
Energy Efficiency and Renewable Energy Sources in Sweden Swedish Energy Agency www.stem.se Yelena Varasteh yelena.varasteh@stem.se Slovakia, 24-25 April 2006 Total energy supply in Sweden in 2004 Total
More informationEnMS under China s Top- 10,000 Program
EnMS under China s Top- 10,000 Program Program Summary China s mandatory energy conservation target- setting policy for large energy users, known as the Top- 10,000 Program (*1), was introduced in 2011.
More informationhttps://www.cdp.net/en-us/pages/search-for-the-file+-search.cdproject.net%2frespon...
Page 1 of 9 English Português Español 日 本 語 中 文 aparsons@anglogoldashanti.com Home What we do Members & signatories Reporting to CDP Reports & data Our partners News & events My CDP Search Results Respondent
More informationCrediting the displacement of non-renewable biomass under the CDM
Crediting the displacement of non-renewable biomass under the CDM Submission by Öko-Institut to the public call by the Executive Board of the Clean Development Mechanism Berlin, April 2007 Lambert Schneider
More informationAddendum. Part Two: Action taken by the Conference of the Parties serving as the meeting of the Parties to the Kyoto Protocol at its first session
UNITED NATIONS Distr. GENERAL FCCC/KP/CMP/2005/8/Add.1 30 March 2006 Original: ENGLISH CONFERENCE OF THE PARTIES SERVING AS THE MEETING OF THE PARTIES TO THE KYOTO PROTOCOL Report of the Conference of
More informationClean Development Mechanism Status and outlook
Presented by: Neeta Hooda UNFCCC Secretariat Clean Development Mechanism Status and outlook Presented at: UNFCCC Media Training Workshop, Accra, 26 August 2008 1 The Kyoto Protocol Entry into force on
More informationREPORT OF THE CONFERENCE OF THE PARTIES ON ITS SEVENTH SESSION, HELD AT MARRAKESH FROM 29 OCTOBER TO 10 NOVEMBER 2001. Addendum
UNITED NATIONS Distr. GENERAL FCCC/CP/2001/13/Add.2 21 January 2002 Original: ENGLISH CONFERENCE OF THE PARTIES REPORT OF THE CONFERENCE OF THE PARTIES ON ITS SEVENTH SESSION, HELD AT MARRAKESH FROM 29
More informationAnnex 1 Tool for the demonstration and assessment of additionality
page 1 Tool for the demonstration and assessment of additionality 1. This document provides for a step-wise approach to demonstrate and assess additionality. These steps include: Identification of alternatives
More informationE N G I N E E R I N G
Purpose If the customer s proposed project proceeds to Gate 1 of the Integrated Customer Solutions (ICS) process (see the ICS Process and Proposal Submission Guide), the customer must prepare a Load Displacement
More informationESCO Financing. State of Israel Ministry of National Infrastructure. Pierre Baillargeon. March 2007 ECONOLER INTERNATIONAL
ESCO Financing State of Israel Ministry of National Infrastructure Pierre Baillargeon March 2007 Agenda Evaluation of the EE market Introduction to the ESCO concept Introduction to performance contracts
More informationRules of Thumb Energy Efficiency in Buildings
Energy Efficiency in Buildings Energy Savings Cost Savings Increased Productivity Economic Development Other Standard lighting retrofits: $0.90-$1.20 per square foot. High-efficiency packaged and split
More informationScenario analysis of Carbon Trade for Energy Efficient Renovations of. Operation Manual (take Beijing as an example)
Scenario analysis of Carbon Trade for Operation Manual (take Beijing as an example) 1 st step: choose cities Choose the target city in the list ranked by energy consumption demand. As shown in Fig. 1,
More informationSASSA LOW PRESSURE SOLAR WATER. May 19, 2011 Department of Energy, Pretoria
SASSA LOW PRESSURE SOLAR WATER HEATER PROGRAMME May 19, 2011 Department of Energy, Pretoria AGENDA 1. The Programme 2. Why SWH and this programme? 3. Approach THE PROGRAMME THE PROGRAMME Installs 110 litre
More informationInterview: Aurélie Faure, Financial Analyst at Dexia Asset Management
Research letter n 09/03 October 2009 http://www.carbonium.fr/pdf/research0903.pdf CONTENTS Interview: Aurélie Faure, Financial Analyst at Dexia Asset Management... p. 1 Hot topics in Copenhagen... p. 3
More informationEnergy Management Plan <Template>
APPENDIX K ENERGY MANAGEMENT PLAN Energy Management Plan Prepared by: Name of Employee Department Company Name TABLE OF CONTENTS PREFACE TO THE ENERGY MANAGEMENT PLAN TEMPLATE:...3 EXECUTIVE
More informationSupporting Small Alternative Energy Enterprises
Supporting Small Alternative Energy Enterprises Mission contributing to sustainable development by supporting Small and Medium Sized Enterprises (SMEs) Fields of expertise SME s for sustainable development
More informationStandard Clean development mechanism project standard
CLEAN DEVELOPMENT MECHANISM CDM-EB65-A05-STAN Standard Clean development mechanism project standard TABLE OF CONTENTS Page 1. INTRODUCTION... 6 1.1. Background... 6 1.2. Objectives... 6 2. SCOPE AND APPLICABILITY...
More informationRevision to the approved baseline methodology AM0011
CDM Executive Board AM00011 / Version 02 Source Revision to the approved baseline methodology AM0011 Landfill gas recovery with electricity generation and no capture or destruction of methane in the baseline
More informationJASPERS Networking Platform. Training on general State Aid issues in infrastructure projects CASE STUDY
JASPERS Networking Platform Training on general State Aid issues in infrastructure projects CASE STUDY The national authorities of an EU Member State are designing four investment programmes which will
More informationESBI Carbon Solutions. Partnering with Countries to Achieve their Full Carbon Credit Potential
ESBI Carbon Solutions Partnering with Countries to Achieve their Full Carbon Credit Potential ESB International ESB International (ESBI) is a growing international energy company and one of Europe s leading
More informationCDM: Cheap Development. transition to clean energy. CSE, November 2012
CDM: Cheap Development Mechanism : : Failed to give us the transition to clean energy CSE, November 2012 CDM CDM Clean Development Mechanism is a mechanism under the Kyoto Protocol that t allow developed
More informationGuidance for U.S. Positions on MDBs Engaging with Developing Countries on Coal-Fired Power Generation 1
October 29, 2013 Guidance for U.S. Positions on MDBs Engaging with Developing Countries on Coal-Fired Power Generation 1 The following guidance is intended to be adapted by individual MDBs and incorporated
More informationActivities of the UNFCCC Regional Collaboration Centre in the Caribbean
Activities of the UNFCCC Regional Collaboration Centre in the Caribbean Karla Solís Team Lead, Regional Collaboration Centre St. George s St John s, Antigua 10-11 June 2014 CDM Regional Collaboration Centre,
More informationCutting Costs through Energy Audits and Conservation
Cutting Costs through s and Conservation Shanghai China May 2012 Outline Sea ice, 1979 Sea ice, 2005 ESD China Ltd, conservation, audit, Practical tips. China audit ESD China Offices Shanghai, Beijing,
More informationThe Project Design Document
Downloaded from orbit.dtu.dk on: Jan 06, 2016 The Project Design Document Olsen, Karen Holm Publication date: 2012 Link to publication Citation (APA): Olsen, K. H. (2012). The Project Design Document [Sound/Visual
More informationFeasibility Study Proposal & Report Guide. Industrial Optimization Program
Feasibility Study Proposal & Report Guide Industrial Optimization Program Table of contents 1.0 Industrial Optimization Program overview 2 2.0 Feasibility Study offer eligibility 2 3.0 Purpose of the Feasibility
More informationThe role of carbon finance in business plan for clean energy projects
The role of carbon finance in business plan for clean energy projects CTI PFAN West Africa Forum for Clean Energy Financing (WAFCEF) Lome, Togo, 4 July 2013 Chunyu Liang, Technical Officer UNFCCC secretariat,
More informationFiscal Year 2011 Resource Plan
Salt River Project Fiscal Year 2011 Resource Plan Page 1 Last summer SRP hosted three resource planning workshops for a diverse group of stakeholders and customers to explain the planning process, discuss
More information1. Whether the concept of materiality can be applied in the context of the CDM
Project Developer Forum input on materiality Preamble In the current version of the Draft Clean Development Mechanism Project Standard published in conjunction with annotated agenda to EB63, section 12.8.4.1
More informationDEFINING COMPONENTS OF NATIONAL REDD+ FINANCIAL PLANNING WORKSHOP ON BUILDING MULTI-SOURCE REDD+ FINANCING STRATEGIES
DEFINING COMPONENTS OF NATIONAL REDD+ FINANCIAL PLANNING WORKSHOP ON BUILDING MULTI-SOURCE REDD+ FINANCING STRATEGIES Antigua, Guatemala July 17 and 18, 2014 Objectives of REDD+ Financial Planning Financial
More informationELENA. A new KfW-Facility in favour of sustainable investments of small and medium sized municipalities. Dr. Johannes Feist Berlin
A new KfW-Facility in favour of sustainable investments of small and medium sized municipalities Dr. Johannes Feist Berlin Objective of the Facility ELENA: a IEE (Intelligent Energy Europe II) technical
More informationGeneva: 2-4 April 2007 Insurance Instruments for GHG Projects: Private Sector Options. UNECE Ad Hoc Group of Experts on Coal Mine Methane
Geneva: 2-4 April 2007 Insurance Instruments for GHG s: Private Sector Options UNECE Ad Hoc Group of Experts on Coal Mine Methane Warren Diogo Risk Consulting Practice, Marsh Ltd Agenda Risk Profile of
More informationEnergy Efficiency Finance in Pennsylvania
Energy Efficiency Finance in Pennsylvania Summary: Propel increases in non-utility delivered demand-side energy efficiency by providing education, access and funding for innovative energy efficiency finance
More informationEnergySTEP (Sustainability Tiered Efficiency Program) Our Approach to Energy Efficiency
TM EnergySTEP (Sustainability Tiered Efficiency Program) Our Approach to Energy Efficiency Agenda Our Vision and Mission EnergySTEP, Our approach to Energy Efficiency Capabilities Case Study Incentives
More informationEXAMPLES OF SUCCESSFUL POLICY TOOLS FOR EMISSION REDUCTION
Submission of the United Nations Environment Programme (UNEP) Sustainable Building Initiative (SBCI) to the Ad Hoc Working Group on Long-Term Cooperative Action under the Convention (AWG-LCA) 24 April
More informationISO 50001 Energy Management System
ISO 50001 Energy Management System DETAILED GUIDE ISO 50001 Background It has been estimated that the ISO 50001 Energy Management Standard could have a positive impact on some 60% of the world s energy
More informationDraft consolidated baseline and monitoring methodology ACM00XX
Draft consolidated baseline and monitoring methodology ACM00XX Consolidated baseline and monitoring methodology for new grid connected fossil fuel fired power plants using a less GHG intensive technology
More informationESBI Company Profile. ESB International. Bringing Energy Innovation to the World...
ESBI Company Profile ESB International Bringing Energy Innovation to the World... ESB International ESBI is one of Europe s most progressive and commercially focused electricity consultancy firms with
More informationResidential Property Climate Bonds
Residential Property Climate Bonds Certification methodology Low Carbon Buildings Technical Working Group ABSTRACT This paper sets out guidance by the Low Carbon Buildings Technical Working Group on the
More informationChapter 1.3 Energy management & audit
Chapter 1.3 Energy management & audit Part I: Objective type questions and answers 1. The judicious and effective use of energy to maximise profits and enhance competitive positions. This can be the definition
More informationEmission monitoring, reporting, and verification (MRV) for U.S. cap and trade programs. Jeremy Schreifels US EPA
Emission monitoring, reporting, and verification (MRV) for U.S. cap and trade programs Jeremy Schreifels US EPA Principles of MRV for cap and trade programs Cap & trade requires a complete record of total
More informationThe Economics of Climate Change C 175. To Kyoto and Beyond. Spring 09 UC Berkeley Traeger 7 International Cooperation 22
To Kyoto and Beyond 7 International Cooperation 22 International Cooperation on Climate Change 1988 United Nations General Assembly adopted resolution urging the protection of global climate for present
More informationGREENHOUSE GAS EMISSIONS INVENTORY
GREENHOUSE GAS EMISSIONS INVENTORY The first step in developing a plan to reduce greenhouse gases was to identify sources and quantities of greenhouse gases emitted in Fort Collins. An emissions inventory
More informationIdentifying and Monitoring of Sustainable Development Benefits on CDM Projects and PoAs
Identifying and Monitoring of Sustainable Development Benefits on CDM Projects and PoAs Presented by: Albert Altarejos MAGALANG Climate Change Office-Environmental Management Bureau Department of Environment
More informationThe University Of Sheffield Energy Policy
The University Of Sheffield Energy Policy Endorsed by Professor RF Boucher, Vice-Chancellor, The University of Sheffield on 28 April 2004 The University of Sheffield Energy Policy Page 1 of 7 The University
More informationColumbia University Master Planning & Optimization
Columbia University Master Planning & Optimization February 20, 2014 Mr. Frank Martino Vice President, Operations 1 Agenda Columbia University Campus District Energy Overview Evolution of Columbia s District
More informationAll about Allowances: from a power company perspective
All about Allowances: from a power company perspective Francisco Grajales Global Emissions Vattenfall Energy Trading Netherlands N.V. October 2014 History of Vattenfall From a domestic Swedish hydro power
More informationERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update
ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update ERCOT Public October 16, 2015 ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update In August 2015, the U.S. Environmental
More informationGuidance to the CDM & JI Pipelines February 2008 By Joergen Fenhann, UNEP Risø Centre Denmark, Phone (+45)46775105, j.fenhann@risoe.
Guidance to the CDM & JI Pipelines February 2008 By Joergen Fenhann, UNEP Risø Centre Denmark, Phone (+45)46775105, j.fenhann@risoe.dk General content and criteria s of the CDM & JI Pipelines spreadsheets.
More informationHOW EMR MAKES THE CASE FOR ENERGY EFFICIENCY MORE ATTRACTIVE. Smart businesses are seeing EMR as an opportunity, not just an overhead.
HOW EMR MAKES THE CASE FOR ENERGY EFFICIENCY MORE ATTRACTIVE. Smart businesses are seeing EMR as an opportunity, not just an overhead. WELCOME Many businesses are currently focused on the cost that Electricity
More informationConsumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured Electricity Markets. Jared Moore and Jay Apt.
Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured Electricity Markets Jared Moore and Jay Apt Supporting Data Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured
More informationEIB and the Energy Sector: Potential Synergies with the MED Programme to Support Energy Efficiency Investments
EIB and the Energy Sector: Potential Synergies with the MED Programme to Support Energy Efficiency Investments Marina Galindo Energy Efficiency and Small Energies Division Projects Directorate EUROPEAN
More informationClean Energy and Carbon Finance Consultant, Workshop on CDM Accreditation Standard Mumbai 25 May 2010
Vinay Deodhar Clean Energy and Carbon Finance Consultant, Clean Tech Solutions Workshop on CDM Accreditation Standard Mumbai 25 May 2010 Presentation Outline Introductiont d ti Evolution of Validation/Verification
More informationSmart homes utilising technology in social housing
Digital Housing Smart homes utilising technology in social housing Matthew Rhodes February 2015 Encraft works at the leading edge of the low carbon built environment We support housing providers and the
More informationCHP & ENVIRONMENTAL COMMODITIES: MARKET & POLICY UPDATE FOR MONETIZING RENEWABLE ENERGY CREDITS FROM CHP PROJECTS. Thomas Jacobsen October 2012
CHP & ENVIRONMENTAL COMMODITIES: MARKET & POLICY UPDATE FOR MONETIZING RENEWABLE ENERGY CREDITS FROM CHP PROJECTS Thomas Jacobsen October 2012 ELEMENT MARKETS US Emissions House of the Year Launched in
More informationStructuring the Deal: Funding Options and Financial Incentives for On-site Renewable Energy Projects
Structuring the Deal: Funding Options and Financial Incentives for On-site Renewable Energy Projects Derek Price Program Manager Renewable Energy Solutions Johnson Controls, Inc. Introduction More public
More informationSolar PV For Surrey Schools - Information Pack
Solar PV For Surrey Schools - Information Pack Solar PV for Surrey Schools: Summary of options and key considerations School interested in solar PV OPTION 1 Own investment: School is responsible for the
More informationThermax Sustainable Energy Solutions Limited
Thermax Sustainable Energy Solutions Limited mcarbon PoA Case Studies Challenges and lessons learnt Energy and Agriculture Sectors Rajesh Madiwale 7 th May 2011 1 Thermax Evolution: A Snapshot Established
More informationFact sheet: The Kyoto Protocol
Fact sheet: The Kyoto Protocol The Kyoto Protocol was adopted at the third Conference of the Parties to the UNFCCC (COP 3) in Kyoto, Japan, on 11 December 1997. The Protocol shares the objective and institutions
More informationMeasurement & Verification Plan
Measurement & Verification Plan University of Florida UF-# Project Name City, Florida Insert Project Rendering/Photo Here Prepared By: University of Florida Department of Facilities, Planning & construction
More informationInternational Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center)
International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center) Good morning. Sayin Bakanım. Members of Parliament. Ladies and Gentlemen. Slide 1: Opening
More informationENERGY EFFICIENCY AUDITING
GUIDANCE NOTE ON ENERGY EFFICIENCY AUDITING July 2003 ENVIRONMENTAL PROTECTION AGENCY An Ghníomhaireacht um Chaomhnú Comhshaoil PO Box 3000, Johnstown Castle, Co.Wexford, Ireland Telephone: +353-53-60600
More informationSustainable Bio Energy technologies in the CDM market
FP6 T@W Project BIOMASS and BIOGAS WORKSHOP Sustainable Bio Energy technologies in the CDM market Lessons from registered CDM biogas project activities in Germany ZREU GmbH info@zreu.de Regensburg/Germany
More informationGreenhouse Gas Offsets and Renewable Energy Certificates: Distinct Commodities in an Evolving Market The Climate Trust
Greenhouse Gas Offsets and Renewable Energy Certificates: Distinct Commodities in an Evolving Market The Climate Trust Introduction The framework for future climate policy is emerging in the United States
More informationFixing the Leaks: What Would it Cost to Clean Up Natural Gas Leaks?
FACT SHEET AND ANALYSIS Fixing the Leaks: What Would it Cost to Clean Up Natural Gas Leaks? About the Authors: The study was designed, carried out, and written by Carbon Limits, a Norwegian consulting
More informationBill Younger, Manager Business Energy Management Puget Sound Energy Bellevue, Washington
Bill Younger, Manager Business Energy Management Puget Sound Energy Bellevue, Washington Multifunction Portals for Commercial and Industrial Customers Customer Needs Energy Information Pipeline Customer
More information10 Nuclear Power Reactors Figure 10.1
10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of
More information5.5 QUALITY ASSURANCE AND QUALITY CONTROL
0 0 0. QUALITY ASSURANCE AND QUALITY CONTROL.. Introduction The IPCC Good Practice Guidance and Uncertainty Management (GPG000, IPCC, 000), Chapter, Quality Assurance and Quality Control, defines quality
More informationSIMAIN Energy Optimization for Industry and Infrastructure
Industrial Technologies SIMAIN Energy Optimization for Industry and Infrastructure Using valuable energy more efficiently www.siemens.com/simain A holistic approach to cut energy costs sustainably. Energy
More information