The Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.



Similar documents
US 51 Ohio River Bridge Engineering and Environmental Study

Safe & Sound Bridge Terminology

3.1 Historical Considerations

REHABILITATION PACKAGE 1-a

Informational Workshop Public Meeting Kanawha Falls Bridge Project

3 Tappan Zee Bridge Rehabilitation Options

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

Open House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/ Federal Project: BR-0252(001)D

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

CONCEPTUAL REHABILITATION ALTERNATIVE

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

Red Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

Methodology to Identify Preservation Priority Bridges

Public Information & Public Scoping Meeting

Residential Deck Safety, Construction, and Repair

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges

IH-635 MANAGED LANES PROJECT, SEG. 3.2

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

INDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

CITY OF TRAIL MEMORANDUM

Chapter 3 Pre-Installation, Foundations and Piers

1,045 m length of the Deh Cho Bridge

Optimum proportions for the design of suspension bridge

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Stay Cable Replacement of the Luling Bridge

Quality Control and Quality Assurance Guide

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

Paving Capitalization Work Categories and Treatments

Alternatives Presentation Meeting Middlebury WCRS(23)

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Overhang Bracket Loading. Deck Issues: Design Perspective

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

CHAPTER 4 EXISTING TRANSPORTATION MANAGEMENT

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

CHAPTER 4 FIELD INSPECTION, DATA COLLECTING, REPORT WRITING AND REPORT REVIEW

REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Uncovered Decks & Porches

How To Write An Analysis System For Bridge Test

CIRCULAR LETTER Page 2 of 5 November 30, 2007

Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis

HEAVY MOVABLE STRUCTURES, INC. 12 TH BIENNIAL SYMPOSIUM NW 17 TH AVENUE BRIDGE REHABILITATION OVER THE MIAMI RIVER MIAMI-DADE COUNTY

Virginia Approach Spans

STRUCTURAL FORENSIC INVESTIGATION REPORT

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

EAST LYME HIGH SCHOOL

How To Check For Scour At A Bridge

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49

Bridge Rehabilitation Alternatives

PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

Historic Bridge Alternatives Analysis Layout

Cable-Stayed Bridge Uses New Post-Tensioning System

Chaudière Crossing Bridge Rehabilitation

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Session 5D: Benefits of Live Load Testing and Finite Element Modeling in Rating Bridges

Bridge Type Selection

CAPPELEN MEMORIAL BRIDGE REHABILITATION

Elevating Your House. Introduction CHAPTER 5

PRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT. Xiaohua H. Cheng 1

5 ALTERNATIVE SOLUTIONS AND EVALUATION

Asset Maintenance Bridge Emergency Response

Truss. are both simple and A Matsuo Example continuous trusses. The

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

San Francisco Oakland Bay Bridge East Span Seismic Safety Project

6 RETROFITTING POST & PIER HOUSES

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

Value Engineering vs. Alternate Designs in Bridge Bidding

Peer Review Scope of Work

Stone Arch Bridges of Washington County, MD

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301)

INTRODUCTION TO BEAMS

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding

Surface Transportation Program (STP) Projects

Page & Turnbull imagining change in historic environments through design, research, and technology

Real-Time Performance Monitoring of the Tacony-Palmyra Bridge

Alberta Guidelines for Upgrading Bridgerails and Approach Guardrail Transitions

Risk - Based Inspection Frequencies

TABLE OF CONTENTS. Section / Article Page

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Transcription:

The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010

Replacement vs. Rehabilitation Project Background Introduction 4 Construction Contracts Main Bridge Substructure Main Bridge Superstructure Truss Widening Railroad Modifications Approaches and Main Bridge Deck Widening EXISTING BREAK Project Status Project Timeline Construction Photographs PROPOSED WIDENING

Replacement vs. Rehabilitation Bridge construction represents a large capital investment. Through time, all bridges receive routine maintenance. However, eventually they must be replaced or rehabilitated. Beyond the obvious difference in cost, there are other significant differences between these two approaches. How is the decision made? What influences the choice between these two alternatives?

Replacement vs. Rehabilitation Louisiana Dept. of Transportation and Development (LADOTD) Methodology for Selecting and Programming Bridges for Replacement and Rehabilitation Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three (3) parameters: 1. Structural adequacy 2. Functional adequacy and serviceability 3. Essential for public use

Replacement vs. Rehabilitation The three parameters are based on the following information: 1. Structural deficiency 2. Posted bridges (weight limits below statutory limits) 3. Traffic count (ADT) 4. Class of highway 5. Available detour routes 6. Bridge geometry (particularly bridges < 20 ft. wide) 7. Bridge inspection reports 8. Local district recommendations for replacement (submitted annually)

Replacement vs. Rehabilitation Federal Highway Administration (FHWA) formula for prioritizing bridges Overall rating called a sufficiency rating Sufficiency rating assigns a numeric value ranging from 0 to 100 to a given bridge with the following percentage points applied to each parameter ITEM WEIGHT Structural Adequacy 55 % Functional Adequacy and Serviceability 30 % Essential For Public Use 15 %

Replacement vs. Rehabilitation Requirement for replacement: Sufficiency Rating < 50 Classification as structurally deficient or functionally obsolete Requirement for rehabilitation: Sufficiency Rating < 80

Replacement vs. Rehabilitation As previously noted there are three elements to the Sufficiency Rating 1. Structural Adequacy 2. Functional Adequacy and Serviceability 3. Essential for Public Use Let s examine each in detail.

Replacement vs. Rehabilitation Structural Adequacy Most important factor in evaluation process as a bridge failure could be catastrophic Determined from: List of posted bridges (bridges with load restrictions) Bridge inspection reports Local district recommendations

Replacement vs. Rehabilitation Functional Adequacy and Serviceability Bridge geometry a key element Clear roadway width most important factor Narrow bridges, if structurally adequate, can be widened rather than replaced Determined from: Bridge inspection reports Local district recommendations

Replacement vs. Rehabilitation Functional Adequacy and Serviceability (con d) Serviceability is related to factors such as Stream scour Maintenance for movable bridges Deck deterioration Other important factors include frequency and severity of marine, railroad, and automotive traffic accidents

Replacement vs. Rehabilitation Essential For Public Use Determined by the: Traffic count (ADT) Class of highway Available detour routes Structural and functional adequacy of the bridge is evaluated with the traffic count in order to minimize exposure to unsafe conditions Example: two bridges with the same degree of inadequacy, the one with the higher traffic volume would receive the higher priority

Replacement vs. Rehabilitation Essential For Public Use (con d) Bridges located on a truck or school bus route or crosses a major river or stream receive extra attention Non-redundant routes (no available detours) receive a higher priority than bridges on redundant routes

Replacement vs. Rehabilitation How Select? Numerous rational methods available Recommended procedure for State of Louisiana 1. Compile 3 lists Bridges with lowest sufficiency rating Bridges with the highest priority based on local district recommendations Bridges that are most severely posted for load restrictions 2. Generally, if a bridge makes all three lists, it will have a high priority for replacement

Replacement vs. Rehabilitation Sufficiency Rating Posted Bridges List STRUCTURAL ADEQUACY Bridge Inspection Report District Recommendations Sufficiency Rating Bridge Geometry, Accidents, etc. FUNCTIONAL ADEQUACY AND SERVICEABILITY Bridge Inspection Report District Recommendations Sufficiency Rating Highway Class and Traffic Count (ADT) ESSENTIALLITY TO THE PUBLIC Available Detour Routes District Recommendations Traffic Type FINAL ORDER OF PRIORITY Source: LADOTD Bridge Design Manual

Replacement vs. Rehabilitation Other Considerations - Replacement Pros: 1. New structure would meet all current standards Loads Geometry Highway standards 2. New Construction Do not have to connect new components with existing ones. Reduced potential for surprises during construction 3. Estimating construction cost potentially more accurate Cons: 1. Potential for greater environmental impacts 2. Potential for greater costs 3. Potential need for more right-of-way 4. Can require time for public to agree on a location and other impacts related to a new structure 5. Can take more time from start of planning to final completion and delivery to public 6. Removal of an historic structure

Replacement vs. Rehabilitation Other Considerations - Rehabilitation Pros: 1. Have the potential to reuse existing elements, thus saving time and money 2. Potentially less environmental impacts 3. Potentially less right-of-way requirements 4. Can fix some legacy issues that do not meet current standards or are less than desirable Cons: 1. Increased potential for problems and unknown discoveries with the existing structure 2. Greater demands on determination of existing conditions, details, geometry, etc. in order to produce accurate plans 3. Ability to meet all current standards may be difficult 4. Accurate estimation of construction costs can be difficult 5. Modification of an historic structure

Replacement vs. Rehabilitation Other Considerations (con d) Environmental Historic structure? Impacts? Remaining life of structure Structural condition (corrosion) and capacity Remaining fatigue life

Replacement vs. Rehabilitation Other Considerations (con d) Owner s Concerns and Issues 1. Time required to perform the work 2. Funding Available local funding? Federal funds available? 3. Public Wants the work completed yesterday Does not want to be inconvenienced during the work Low cost (no increased direct costs; e.g.. taxes, tolls, etc.) While doing this work, why not fix these other problems and/or address other needs... it s only a little more $$ (scope creep)

Replacement vs. Rehabilitation Where does the Huey P. Long Bridge fit within this criteria? Structurally Adequacy? - GOOD Excellent condition; adequate strength Reduced fatigue life of stringers and floorbeam brackets Functionally Adequacy and Serviceability? - POOR 18 feet wide roadways Barriers not current standards Essential For Public Use? - ESSENTIAL Few Mississippi River crossings in metro region; essential for highway traffic Only rail crossing of Miss. River south of Baton Rouge

Location New Orleans Metro Area French Quarter Huey P. Long Bridge

Before the Bridge

Before the Bridge

Construction of The Existing Bridge

Construction of The Existing Bridge

Construction of The Existing Bridge

Construction of The Existing Bridge

Construction of The Existing Bridge

Construction of The Existing Bridge

Background Huey P. Long Bridge Completed in December 1935, the bridge is one of the longest railroad bridges in the world.

Background Huey P. Long Bridge Combined railroad highway bridge 2 tracks 4 lanes 9 ft. width

Background Huey P. Long Bridge Very heavily built Carries largest modern RR load without distress Many years of service life remaining

Project Background By widening the existing structure rather than constructing a new river crossing: Reduce environmental impact, property takings. Reduce project cost. Reuse existing right-ofway and traffic corridors. Final report published April 1988.

Project Background EXISTING PROPOSED WIDENING

Project Background 1982 1986 Study of new bridge in corridor; 5 alternates considered. High cost and large amount of ROW; project dropped. LADOTD authorized M&M to perform conceptual widening study. 3 widening alternates considered. 1990 Geotechnical investigation of soil capacity under caissons. 1992-1996 1999-2000 2000-2007 2006- Present Preliminary Design Main Bridge; Fatigue Evaluation. Line and Grade Study Approaches. Environmental Processing Agency Consensus Completion of final design plans; main bridge widening, railroad modifications, and approaches, Construction main bridge substructure widening, railroad modifications, and main bridge superstructure widening.

Huey P. Long Widening Project START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Main Bridge Pier Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Main Bridge Pier Widening EXISTING Pier A Piers I & II Pier III Pier IV PROPOSED WIDENING

Widened Pier Steel Frame Caisson Upper Encase Lower Encase

Widened Pier - Details The upper portion of the pier widening is composed of a steel frame. The steel frame significantly reduces the loads on the pier by eliminating concrete and permits the center bearing to be jacked, relieving load from the exterior bearings. This is beneficial by reducing load on the end faces of the existing concrete distribution block on top of the existing caisson.

Widened Pier - Details The steel frame will also permit more accurate setting and adjustment of the final bearing elevations after the lower encasement is poured. Inspection access will be provided for the steel metalwork in the upper portion of the pier widening.

Widened Pier - Details Constructability of Pier Frame Must be constructed around existing pier No construction access from above due to existing superstructure Staged construction Key splice locations.

Widened Pier - Details The lower portion of the encasement serves several functions The nose areas are columns to support the widening truss support bearings. The remainder confines the existing pier concrete and granite masonry blocks which currently has minimal reinforcing.

Widened Pier - Details

Widened Pier - Details

Strength of the Existing Concrete One of the major questions for widening the substructure was the strength of the existing concrete. Existing concrete was specified for 2000 psi. Based on construction records, actual strength much higher Using methods to estimate moderate amount of additional concrete strengthening with aging, 4000 psi could be used with confidence for the strength of the existing concrete.

Strength of the Existing Concrete PIER AND CAISSON CONCRETE STRENGTHS LOCATION 1930 2000-1 2000-2 USED Piers 3,800 4,500 8,800 4,000 Caisson 3,300 3,870 7,565 3,800 2000-1 = ACI Committee 209, Prediction of Creep, Shrinkage, and Temperature Effects in Concrete Structures (ACI 209R-92) 2000-2 = Properties of Concrete by A. M. Neville

Existing Pier Conditions Underwater Acoustic Inspection performed April 2006 by C. H. Fenstermaker & Associates. Piers I, II, III, & IV examined and found to be in good condition. The equipment provided detailed information of the existing conditions. Examination though the use of a diver would be more costly, must be performed in extreme low to no visibility, and is dangerous.

Existing Pier Conditions Pier I North Face

Existing Pier Conditions Pier II West Nose

Main Bridge Truss Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Main Bridge Truss Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING

Cross Sections Existing Bridge

Widened Main Bridge Features 2 new trusses added, parallel to existing trusses. Roadways widened from 18 ft. to 43 ft. Currently: 2 9 ft. lanes No offset Proposed: 3 11 ft. lanes 8 ft. shoulder 2 ft. offset

Normal terminology for truss bridges would be U.S. & D.S. trusses. Widened HPL Bridge is a multiple truss plane structure U.S. Widening Truss U.S. Existing Truss D.S. Existing Truss D.S. Widening Truss Nomenclature

2D versus 3D Analysis and Design Traditional Truss Analysis (2D) Vertical loads, e.g. D & L, supported by main (vertical) trusses Transverse loads, e.g. W, supported by top and bottom lateral trusses, sway frames, and portals

2D versus 3D Analysis and Design 3 Dimensional Analysis Used Widened bridge is multiple truss plane system 3D analysis reflects the reality of the structure and its behavior Load sharing will occur and it is beneficial Members not normally supporting live load will have live loads Need to know the amount of live load in non-traditional live load supporting members.

2D versus 3D Analysis and Design 3D SAP Computer Model

Floorbeam and Hangers Superposition needed to solve final forces in the existing and widened hangers Moment and sequence of construction affect forces

Construction and Erection Method and Sequence of Construction provided in Contract Plans Contractor proposed option also available in contract plans Contractor proposed his own method

Maintenance of Traffic Through Construction Marine Traffic Maintained same vertical and horizontal clearances Rail Traffic Maintained Vehicular Traffic Maintained by use of staged construction

Main Bridge Maintenance of Traffic WORK PERFORMED IN TRUSS WIDENING CONTRACT

Main Bridge Maintenance of Traffic - Stage 1 WORK PERFORMED IN TRUSS WIDENING CONTRACT

Main Bridge Maintenance of Traffic - Stage 2 WORK PERFORMED IN TRUSS WIDENING CONTRACT PREVIOUS STAGE

Main Bridge Maintenance of Traffic - Stage 3 WORK PERFORMED IN TRUSS WIDENING CONTRACT PREVIOUS STAGE

Main Bridge Maintenance of Traffic - Stage 4 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE

Main Bridge Maintenance of Traffic - Stage 4-5 SWITCH TRAFFIC

Main Bridge Maintenance of Traffic - Stage 5 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE

Main Bridge Maintenance of Traffic - Stage 6 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE

Main Bridge Maintenance of Traffic - Stage 7 WORK PERFORMED IN APPROACH AND DECK WIDENING CONTRACT PREVIOUS STAGE

Top laterals, bottom laterals, sway frames, and portal frames must hinge to permit movement Erect rigid part over roadways open to traffic; hinge remaining part. Deflection Issues

Railroad Modifications - Westbank START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Railroad Modifications - Westbank Project Site Railroad LA 18 Hwy. 90 EXISTING

Huey P. Long Widening Project Westbank Railroad Modifications LA18 Existing Site Conditions US HWY 90 To Huey P. Long Bridge

Huey P. Long Widening Project Westbank Railroad Modifications Replacement Support LA18 Future Roadway US HWY 90 To Huey P. Long Bridge Final Site Conditions

Huey P. Long Widening Project Westbank Railroad Modifications

Huey P. Long Widening Project Westbank Railroad Modifications

Huey P. Long Widening Project Westbank Railroad Modifications

Westbank Sequence of Construction 1. Construct foundations for new cross girders 2. Install falsework to lift existing girder spans 3. Begin 24 hour rail traffic closure 4. Lift existing girder spans off steel tower 5. Remove upper portion steel tower 6. Erect cross girders 7. Lower existing girder spans onto new cross girders 8. Restore rail traffic 9. Remove remaining portion of steel tower 24 HOUR RAIL CLOSURE

Railroad Modifications - Eastbank START PROJECT WESTBANK RR MOD EASTBANK APPR. END PROJECT WESTBANK APPR. EASTBANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Railroad Modifications - Eastbank Clearview Pkwy. EXISTING Project Site Jefferson Hwy

Huey P. Long Widening Project Eastbank Railroad Modifications Vacant Gas Station Clearview Pkwy. Power Poles & Power Line To Huey P. Long Bridge Jefferson Hwy. Existing Site Conditions QWEST Line Existing Superstructure and Towers to be Replaced

Huey P. Long Widening Project Eastbank Railroad Modifications New Bents Clearview Pkwy. Vacant Gas Station Future Elevated Roadway Future Roadway Final Site Conditions QWEST Line Jefferson Hwy. To Huey P. Long Bridge

Huey P. Long Widening Project Eastbank Railroad Modifications

Eastbank Sequence of Construction 1. Construct new concrete straddle bents 2. Prepare steel tower and other falsework 3. Begin 24 hour rail traffic closure 4. Remove girders under one of the tracks 5. Erect new girders for one track 6. Re-establish track 7. Restore rail traffic 8. Repeat girder replacement for other track (Steps 3 7 above) 9. Remove steel tower 24 HOUR RAIL CLOSURE

Approaches & Deck Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Approaches & Deck Widening Start Project Bridge City Ave. Interchange WEST BANK APPROACH Conflict w/ Existing Rdwy

Approaches & Deck Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING

Approaches & Deck Widening Jefferson Hwy Interchange End Project NOPBRR Spur Conflict w/ Existing Rdwy EAST BANK APPROACH

Approaches & Deck Widening

Approaches & Deck Widening EB APPR. EB APPR.

Approaches & Deck Widening Created using Google SketchUp

Approaches & Deck Widening W.P. CAP TRUMPET TRUMPET PC COLUMN FOUNDATION

Approaches & Deck Widening 184 - TOTAL SUBSTRUCTURE UNITS 123-4 X 6 COLUMN BENTS 8 x 14 8 x 12 6 x 12 4 x 6

Approaches & Deck Widening Column Type 4: 8 x 14 Column Type 3: 8 x 12 Column Type 2: 6 x 12 Column Type 1: 4 x 6

Approaches & Deck Widening Trumpet for 8 x 14 Columns Trumpets for 6 & 8 x 12 columns Trumpet for 4 x 6 columns 8 x 14 6 x 12 8 x 12 4 x 6

Approaches & Deck Widening Adjust Footing Depth As Necessary Typical Bent Full Height Trumpet Sub- Trumpet Size 1 Sub- Trumpet Size 2

Main Bridge Deck Widening WORK PERFORMED IN APPROACH CONTRACT

Approaches & Deck Widening West Bank Approach - West Bank Bound East Bank Approach - East Bank Bound

Approaches & Deck Widening WB APPR. Location of West Bank Steel Girder Spans West Bank Approach East Bank Bound

Approaches & Deck Widening Location of East Bank Steel Girder Spans EB APPR. East Bank Approach West Bank Bound

Approaches & Deck Widening

Approaches & Deck Widening SWITCH TRAFFIC

Project Timeline Project Schedule 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Main Bridge Substructure Railroad Modifications Superstructure Fabrication & Erection Approaches & Main Bridge Re-decking Work Completed Railroad Modifications Main Bridge Pier Widening Work Under Construction Main Bridge Truss Widening West Bank Approach, Main Bridge Deck Widening, East Bank Approach

Project Status Completed Main Bridge Pier Widening Letting Date: December 14, 2005 Notice To Proceed Date: April 10, 2006 Construction Bid: $ 98,826,907 Contractor: Massman Construction Co.

Main Bridge Pier Widening EXISTING Pier A Piers I & II Pier III Pier IV PROPOSED WIDENING

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening Distribution Block

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening G&G Steel New Orleans

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Main Bridge Pier Widening

Project Status - Completed Railroad Modifications Letting Date: May 10, 2006 Notice To Proceed Date: August 28, 2006 Construction Bid: $ 13,782,713 Contractor: Boh Bros. Construction Co.

Railroad Modifications - Westbank Project Site Railroad LA 18 Hwy. 90 EXISTING

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank G&G Steel New Orleans

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Westbank

Railroad Modifications - Eastbank Clearview Pkwy. EXISTING Project Site Jefferson Hwy

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Huey P. Long Widening Project Eastbank Railroad Modifications

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Railroad Modifications - Eastbank

Project Status Under Construction Main Bridge Truss Widening Letting Date: March 28, 2007 Notice to Proceed Date: November 5, 2007 Construction Bid: $ 452,605,568 Contractor: Massman Construction Co., Traylor Brothers Inc., and IHI, Inc.

Main Bridge Truss Widening Cantilever Truss Span Simple Through Truss Span EXISTING PROPOSED WIDENING

Main Bridge Truss Widening Industrial Steel Construction Gary, IN New Orleans

Main Bridge Truss Widening Truss Monitoring STATIC MONITORING SYSTEM 433 Members (777 Vibrating Wire Strain Gages) 5 Piers (10 Vibrating Wire Tilt Meters) Wind Speed/Direction DYNAMIC (LIVE LOAD) MONITORING SYSTEM 31 Members (50 Electrical Resistance Strain Gages)

Main Bridge Truss Widening Work Platform

Main Bridge Truss Widening Work Platform

Main Bridge Truss Widening Floorbeam Modifications Template Fit Up Check

Main Bridge Truss Widening Floorbeam Modifications Installation of Wedge Fill

Main Bridge Truss Widening Floorbeam Modifications Installation of Wedge Fill

Main Bridge Truss Widening Work on Existing Structure Bottom Chord

Main Bridge Truss Widening Work on Existing Structure Top Chord

Main Bridge Truss Widening Widening Truss Bottom Laterals

Main Bridge Truss Widening Remove Existing Sidewalk Install Temporary Steel Barrier

Main Bridge Truss Widening Main Bridge Erection - Methods A B A B B A = Stick Build B = Span by Span

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection

Main Bridge Truss Widening Main Bridge Erection December 2009

Main Bridge Truss Widening Main Bridge Erection December 2009

Main Bridge Truss Widening Contractor s Erection Scheme Span by Span Erection East Anchor Arm Suspended Span Through Truss Span

Project Status Under Construction West Bank Approach, Main Bridge Deck Widening, East Bank Approach Letting Date: March 19, 2008 Notice to Proceed Date: May 5, 2008 Construction Bid: $ 433,950,000 Contractor: Kiewit Massman Traylor Constructors

Approaches & Deck Widening START PROJECT WEST BANK RR MOD EAST BANK APPR. END PROJECT WEST BANK APPR. EAST BANK RR MOD MAIN BRIDGE PIER, TRUSS, AND DECK WIDENING

Approaches & Deck Widening Box Culverts

Approaches & Deck Widening At Grade Roadways West Bank

Approaches & Deck Widening Foundations - Westbank

Approaches & Deck Widening Foundations - Westbank

Approaches & Deck Widening Substructure - Westbank

Approaches & Deck Widening Substructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Superstructure - Westbank

Approaches & Deck Widening Substructure Pier IVA Created using Google SketchUp

Approaches & Deck Widening Substructure Pier IVA

The Rehabilitation Alternative Huey P. Long Bridge Case Study

Q & A 1. Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three parameters. Name them.? 2. Of the three parameters above, which is given the highest weight?? 3. What Sufficiency Rating is required for replacement?? 4. Bridge geometry is a key element of Functional Adequacy and Serviceability. What is the most important factor within bridge geometry?? 5. For the case study project, name one key design challenge?? 6. For the case study project, how was approach bent formwork simplified??

Q & A 1. Priority for the selection of bridges for replacement or rehabilitation with Federal bridge replacement funds based on three parameters. Name them. Structural adequacy, functional adequacy and serviceability, and essential for public use. 2. Of the three parameters above, which is given the highest weight? Structural adequacy 3. What Sufficiency Rating is required for replacement? < 50 4. Bridge geometry is a key element of Functional Adequacy and Serviceability. What is the most important factor within bridge geometry? Clear roadway width 5. For the case study project, name one key design challenge? Maintenance of traffic, deflection between existing and widened structures, not imposing deflection induced loads into the existing bridge. 6. For the case study project, how was approach bent formwork simplified? 2/3 s of the forms were the same, and the rest required only simple formwork changes