TEMPORARY DRAINAGE DESIGN

Similar documents
Storm Drainage Systems

STORM DRAINS CHAPTER 7

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

DRAINAGE MANUAL CHAPTER VII STORM DRAINAGE SYSTEMS

Chapter 13 - Storm Drainage Systems Publication Edition CHAPTER 13 STORM DRAINAGE SYSTEMS

CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS

APPENDIX D INLET CAPACITY AND SPACING. The capacity and spacing design of storm drainage inlets are presented in detail in this Appendix.

Chapter Thirty-six OVERVIEW Introduction Inadequate Drainage POLICY AND GUIDELINES

DESCRIPTION OF WORK:

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

SECTION INLETS INLET LOCATIONS

CHAPTER 4 STORM DRAINAGE SYSTEMS

Outlet stabilization structure

CITY UTILITIES DESIGN STANDARDS MANUAL

Chapter 12 STORM DRAINAGE SYSTEMS SOUTH DAKOTA DRAINAGE MANUAL

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Table 4.9 Storm Drain Inlet Protetion Applicable for

SECTION STORM DRAINAGE TABLE OF CONTENTS

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

CHAPTER 3 STORM DRAINAGE SYSTEMS

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

City of Shelbyville Site Inspection Checklist

CHAPTER 13 STORM DRAINS

CHAPTER 4. STORM SEWER SYSTEM DESIGN

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

CHAPTER 13 STORM DRAINAGE SYSTEMS

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

CHAPTER 5. Storm Sewer

Chapter 9 - Storm Drains

STREETS/INLETS/STORM SEWERS

Stormwater Drainage Design for Parking Lots

1. It would create hazardous effects of storm water run-off. 3. It would increase hazardous driving conditions on the public road.

2011 HYDRAULICS MANUAL

CHAPTER 5 STORMWATER DRAINAGE SYSTEM DESIGN. Table of Contents SECTION 5.1 STORMWATER DRAINAGE DESIGN OVERVIEW

Emergency Spillways (Sediment basins)

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection

Storm Drain Inlet Protection

SE-10 STORM DRAIN INLET PROTECTION. Objectives

CHAPTER 14: GUARDRAIL and BARRIERS

Chapter 7 Street, Inlets, and Storm Drains

Storm Drain Inlet Protection for Construction Sites (1060)

Riprap-lined Swale (RS)

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

Construction Site Inspection Checklist for OHC By making use of some simple Best Management Practices (BMPs) a construction site operator can

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

SUSTAINABLE URBAN DRAINAGE SYSTEMS

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

Drainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS

Storm Drain Inlet Protection - IP

Block and Gravel Inlet Protection (BIP)

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SECTION 5 - STORM DRAINS

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION EARTH MOVING

SECTION 7- STORM SEWER

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

SECTION 5. Sediment Control Measures

Appendix 4-C. Open Channel Theory

SECTION 6A STORM DRAIN DESIGN Mar S E C T I O N 6A STORM DRAIN - DESIGN

CHAPTER 830 TRANSPORTATION FACILITY DRAINAGE

CHAPTER 2 HYDRAULICS OF SEWERS

SECTION 5: SANITARY SEWER SYSTEM DESIGN

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

City of La Quinta Public Works Department - Storm Drain Plan Review Checklist

City of West Linn Public Works Design Standards Table of Contents

Paul Deutsch. NDDOT Office of Project Development Conference November 9, 2010

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

CHAPTER 11 STORM DRAINAGE

Storm Drain Inlet Protection

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES

Architectural Processing and Inspections for Home Mortgage Insurance

Computing Stormwater Runoff Rates and Volumes

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

Town of Beaumont. Lot Grading Guidelines

CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 800 STORM SEWER SYSTEMS TABLE OF CONTENTS

Local Road Assessment and Improvement Drainage Manual

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

SECTION 5 DRAFTING STANDARDS

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DRAINAGE HANDBOOK OPEN CHANNEL. OFFICE OF DESIGN, DRAINAGE SECTION November 2009 TALLAHASSEE, FLORIDA

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

ARTICLE II STORM DRAINAGE. (From Ordinance No ; August 4, 1987; Sections III through VIII)

URBAN DRAINAGE CRITERIA

Using Hydraflow Storm Sewers Extension with AutoCAD Civil 3D 2008: A Recommended Workflow

Homeowner s Guide to Drainage

PRECAST CONCRETE BOX CULVERTS

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006

CHAPTER 8 CIVIL DESIGN

DRAINAGE PART 3 HA 102/00 SPACING OF ROAD GULLIES SUMMARY

Drainage Design and Stormwater Pollution Prevention Manual

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

Transcription:

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DRAINAGE HANDBOOK TEMPORARY DRAINAGE DESIGN OFFICE OF DESIGN, DRAINAGE SECTION October, 2001 TALLAHASSEE, FLORIDA

TEMPORARY DRAINAGE DESIGN SECTION 1 PURPOSE The primary purposes for designing temporary drainage are minimizing travel lane flooding, preventing damage to property adjacent to the project during construction, and facilitating construction activities by temporarily rerouting or altering drainage conveyances. This Handbook is a practical consideration of problems associated with drainage at roadway construction sites. The Handbook speaks directly to the drainage system designer and indirectly to other technical personnel. Use this Handbook properly by communicating with and sharing information with engineers responsible for roadway, structures, and traffic control plans. The Handbook covers problematic physical conditions that affect drainage efficiency at work-sites and offers possible solutions. SECTION 2 CRITERIA Consult the FDOT Drainage Manual for hydraulic and hydrologic criteria that apply to the design of temporary drainage systems. Specifically, refer to Table 2.2 in the Manual for design frequencies at temporary roadside and median ditches, swales, and side drains. Refer to Table 3.3 in the Manual under General Design for design frequencies at temporary storm drain systems. Refer to Table 4.3 in the Manual for design frequencies at temporary cross-drains. Some conditions are much more common in temporary conditions than in permanent. For example, water may pool along temporary barrier wall or curbing near an inside high-speed lane. In that situation, attempt to limit spread so that 8 of the high-speed lane remains open. Be aware that criteria can be different for permanent and temporary conditions on the same section of roadway, primarily because the two conditions can have differing design speeds. Consult Chapter 3 of the Manual to determine spread criteria. 1

SECTION 3 METHOD Carefully consider the temporary conditions that could arise during the construction or rehabilitation of the permanent transportation facility. Safety of travelers and workers, cost of construction, and the time required to complete construction tasks are all affected adversely when temporary drainage is not covered adequately during design. Construction delays resulting from inclement weather conditions can be reduced by a well-designed temporary drainage system. Further, unsafe traveling conditions and construction delays increase the cost of projects. Provide temporary drainage features where they are needed. Design temporary drainage for construction sites with emphasis as follows: (1) Drain detours efficiently, whether on existing streets or temporary lanes. (2) Prevent drainage problems caused by construction staging. Examine detour designs in the light of construction staging, to determine whether construction activities might divert or trap water and compromise safety and efficiency. (3) Provide details for box-culvert extensions that require a temporary rerouting of water away from work areas. Provide emergency relief that will convey storm events without substantial risk of flooding free travel lanes. SECTION 4 DETOURS This Handbook uses the term detour as it is defined in the State of Florida Standard Specifications, Sections 102-1.3 and 102-4. Detours may be either located on existing streets or constructed with temporary paved or graded lanes. Design the drainage for detours on existing streets by using the existing street drainage system while preventing overtaxing of the system on those streets. When temporary lanes or roads must be constructed, provide design for temporary drainage systems. 4-1 On Existing Streets Concentrate on construction site ingress and egress points when designing drainage for detours routed over existing streets or roads. Ensure that the construction site does not divert drainage onto the detour route in excess of the capacity of the existing streets. Conversely, ingress and egress locations cannot be allowed to divert excessive water onto the travel lanes or to accommodate surface drainage that causes erosion of the construction site. 2

4-2 Constructed Detours Refer to Figures 1 and 2. When detours are to be constructed, provide designs for temporary drainage systems that prevent storm water from pooling or backing up on lanes where traffic is maintained. Detour lanes, whether constructed in a median or off an outside edge of pavement, are often built on fill that can disrupt the flow of storm water, unless temporary measures are taken to carry the water through or around the fill area. Include directional flow arrows in the plans when a swale is used between fill for a temporary road and fill for a permanent road. See Figure 1. Consider every temporary low created when a detour road interrupts a proposed ditch gradient as a possible location for temporary drainage structures. Temporary detours sometimes have vertical curvature or gradients that are independent of the main project. Be certain that these areas are not overlooked when locating temporary drainage structures. See the temporary pipe shown in Figure 1. SECTION 5 CONSTRUCTION OF THE PROPOSED FACILITY Provide a design for temporary drainage of construction features like milled lanes, dropoffs between lanes, turnout construction and construction operations for new side-drain, cross-drain and box-culverts. Examine areas where traffic control items, especially temporary barrier walls, might pond water. Where box-culverts must be extended, provide details for any required temporary dewatering. 5-1 Milling and Drop-Offs- A drainage problem can occur where the natural sheet flow across the roadway surface is curbed by an adjacent lane; this problem will be most evident in sag vertical curves where curbed water is directed to the low point and then flows in concentrated form across an adjacent lane. The best way to avoid this is to schedule construction phasing so that an adjacent lane does not curb natural sheet flow across the roadway surface. It is difficult to avoid this curbing effect where lanes are added to the median side of a divided highway, or to the high side of a section in superelevation. When this curbing effect can t be avoided by construction phasing, provide temporary measures to prevent flooding of adjacent travel lanes. Sandbags or temporary asphalt curb can be effective in directing runoff away from travel lanes. Prevent overtopping flow at drop-offs by calling for sandbags or temporary asphalt curb to be placed along the drop-off to force water away from travel lanes. Refer to Figures 3, 4 and 5. 3

If the speed limit in a work zone is 45mph or less, intermittent transverse saw-cuts in travel lanes can be used to allow water to flow through the travel area without overtopping. 5-2 Turnouts- The construction of turnouts can cause water to pond in the turnout area and subsequently flood adjacent lanes on the roadway. Include details in the plans for the placement of sandbags or temporary asphalt curb along outside edges of pavement adjacent to turnout construction to prevent water in the turnout site from flowing across the travel lanes. Provide details for temporary flumes and inlets, where needed, to direct water at turnout sites into the storm drain system, thus preventing water-collecting lows and erosion. 5-3 Temporary Drains and Curb Inlets- Provide a note in the plans requiring temporary drains for subgrade and base at inlets in accordance with Standard Index 201, or include a similar detail in the plans. Either detail will require construction of temporary drains for water that is trapped on base and subsequent paving layers around inlets during construction. 5-4 Box-Culvert Extensions- Furnish a temporary drainage design that will provide dry work areas for box culvert extensions during common storms and provide flood protection during severe storms. When standing or flowing water occupies box culverts to be extended, divert this water away from work areas for the duration of required work. Refer to figures 6 through 10 for examples of details for inclusion in plans. Include details and notes in the plans that provide, as a minimum, the following information: 1. Provide sizes for diversion pipes that are to be inserted into existing box culverts. 2. Show the Configuration requirements for sandbagging. 3. Include measures for stabilization and erosion control. 4. List any items that must be removed prior to final grading. 5. List descriptions and quantities for items not included in the cost of the structure. 4

5-5 Temporary Barrier Wall- The temporary barrier wall most commonly used on Department projects is the Precast Concrete Temporary Barrier Wall detailed in Standard Index 415. The concrete units are available in two configurations; one has two 6 drainage slots and the other has one 31 drainage slot. Units with 31 slots are superior for drainage purposes. The units with 6 slots can cause excessive spread in travel lanes and should be allowed only on the high side of a roadway cross-section. Perform spread calculations for temporary precast concrete barrier wall, based on 4 per hour rainfall, using equations and information shown in Tables 1, 2 and 3. Another type of approved temporary barrier wall is the water-filled, steel- reinforced polyethylene barrier detailed in Standard Index 416. The water filled barrier can be drained and moved to new locations by two men. The water filled barrier is available with saddles, which raise the base of the wall unit above the ground. Saddles should be required for locations where spread in travel lanes could be a problem. Without the saddles, the water filled barrier has no slot for drainage. 5-5.1 Flow Under Temporary Barrier Walls- The equations in Tables 2 and 3 can be used as part of the calculation of spread next to temporary barrier walls. For barrier walls placed on a longitudinal grade, an approach to calculating spread, which is similar to the approach used for curb inlets, is summarized as follows. Table 4 gives spread values for typical pavement widths and slopes. 1. Determine the flow approaching the slot. 2. Assume normal depth of flow at the slot and use the modified Manning s formula for shallow channel flow to determine the spread and associated depth of flow (y) at the edge of the barrier wall. Q = (0.56/n) Sx 5/3 SL 1/2 T 8/3 Where Q = gutter flow rate (CFS) n = Manning s roughness coefficient. (See TABLE 1 below) Sx = Pavement Cross Slope, (ft / ft) SL = Longitudinal Slope, (ft / ft) T = Spread, (ft) 5

TABLE 1: Manning s n Values for Street and Pavement Gutters Type of Gutter or Pavement Manning s n Concrete gutter, troweled finish 0.012 Asphalt pavement: Smooth texture Rough texture [1] Concrete gutter with asphalt pavement: Smooth texture asphalt Rough texture asphalt Concrete pavement: Float Finish Broom Finish [2] 0.013 0.016 0.013 0.015 0.014 0.016 For gutters with small slope, where sediment may accumulate, increase above values of n by 0.002 Reference: FHWA HEC-22 (1) The Department s friction course is rough texture asphalt. (2) The Department s standard is brush (broom) finish for concrete curb. [Specification Section 520] 3. Using the depth of flow (y) at the edge of the barrier wall, determine the flow through the slot using the equation from Table 3. We suggest that the slot flow be reduced to 75% of the equation value to account for 25% blockage. 4. Subtract the flow through the slot from the flow approaching the slot to determine the flow bypassing the slot. 5. Add the bypass flow to the surface runoff for the next slot. 6. Repeat steps one through five for the length of barrier wall or until equilibrium. For sag vertical curves, a more complicated approach is likely. Several items change with changing (y) values. As the depth of ponding increases, the length of roadway draining directly (not including the bypass from approach grades) to the ponded area increases, as does the number of slots that operate in sump condition. 6

TABLE 2 Flow through Barrier Wall Slots (Sump conditions): Q = a 1 y + a 2 y 2 + a 3 y 3 Equation is based on Ponded Water Upstream of the Slot Applicable Slot Length (Index 415) range Of depth of flow (y) a 1 a 2 a 3 mm in m ft SI English SI English SI English 150 6 0 0 0.6 0.041 0.44 0.11 0.35-0.57-0.57 0.180 790 31 0 0 0.196 2.11-5.03-16.51 83.0* 83.0 0.070 790 31 0.070 0.180 0.23 0.23 0.6 0.415 4.47-1.97-6.47 4.43 4.43 *The original report has a typographical error showing this value as 3.0. TABLE 3 Flow through Barrier Wall Slots (On Longitudinal Grade): Q = b 1 + b 2 y Equation is based on Water Flowing Longitudinally along the Wall Applicable Slot Length (Index 415) range Of depth of flow (y) b 1 b 2 mm in m ft SI English SI English 150 6 0.013 0.042- -4.5 x -0.016 0.0375 0.404 0.163 0.54 10-4 790 31 0 0.070 0 0.33 0.0 0.0 0.114 1.23 Notes for Tables 2 and 3 1. Q= Flow through the slot. 2. y = Depth of flow at the edge of the barrier wall. 3. In English units, use y in feet to find Q in cubic feet per second. 4. In SI units, use y in meters to find Q in cubic meters per second. 7

TABLE 4: Spread at Temporary Barrier Walls (31 ) Slots Based on Equation for Table 3 PAVEMENT WIDTH CROSS SLOPE LONGITUDINAL SLOPE = 0.3% LONGITUDINAL SLOPE = 1% LONGITUDINAL SLOPE = 3% FT/FT Spread (ft) Spread (ft) Spread (ft) 12 24 36 0.01 2.7 2.1 1.8 0.02 1.8 1.4 1.1 0.03 1.4 1.1 0.9 0.01 3.5 2.8 2.7 (60 ) 0.02 2.3 1.8 1.5 0.03 1.8 1.4 1.1 0.01 4.1 4.1 (75 ) 4.1 (160 ) 0.02 2.6 2.1 2.0 (60 ) 0.03 2.1 1.6 1.4 Notes for Table 4 1. For most of the slopes and pavement widths in Table 4, the slots accept all the water coming to them (i.e. no bypass). The spread values for these slopes and pavement widths are based on Manning s formula for the triangular flow section next to the wall. 2. Where noted by a number in parentheses (xx ), the slots do not accept all the water coming to them and bypass flow exists. The spread values for these situations exist where the flow from the pavement (between adjacent slots) equals the flow through the downstream slot and the bypass flow does not change for successive slots. The number in parentheses is the distance to reach 95% of this equilibrium spread value. The above values are based on: * Manning s n for pavement = 0.016 * Intensity = 4 iph * Rational Runoff Coefficient = 0.95 * 25% blockage applied to the slot equations 8

Limits of permanent fill slope Limits of permanent fill slope Proposed bridge or Bridge replacement Lane Lane Grade to stream Temporary Bridge Temporary Detour Temporary pipe Limits of temporary fill slope Stream Erosion protection Limits of temporary fill slope TEMPORARY DETOUR AND BRIDGE 1. Prevent water from being trapped in the area where the limits of temporary fill overlaps the limits of permanent fill by providing a design for temporary ditches that drain positively to the stream as shown on the left side of this detail, or provide a design for temporary drains under the detour as shown on the right. 2. When the grade of a detour road is lower than ditch elevations, care must be taken to avoid any sag in the ditch grade that could collect water until it pops over and spills onto the detour. Find and solve this problem during design. A contractor should not be forced to handle it. The temporary pipe shown in Figure 1 is a possible scenario. Figure 1 9

TEMPORARY BARRIER WALLL LANE LANE TEMPORARY PIPE TEMPORARY DETOUR TEMPORARY PIPE MEDIAN LANE LANE WORK AREA TEMPORARY BARRIER WALL TEMPORARY DETOUR IN MEDIAN 1. Conditions shown here may differ as to location, amount, configuration, direction of flow, etc. with regard to temporary barrier wall, temporary drainage structures and work area. 2. Calculate the flow approaching barrier wall slots based on average rainfall of 4 inches per hour. Calculate spread using the method defined as Flow Under Temporary Barrier Walls (See Tables 1 through 4). Prepare a design for temporary conditions that meets the requirements of the FDOT Drainage Manual and this Handbook. 3. Require installation of temporary drainage structures where needed to maintain normal flow through the work area. 4. Where two or more runs of temporary barrier wall are located parallel to each other, on or adjacent to a common width of pavement, a temporary slotted drain may be required to hold spread within acceptable limits. Figure 2 10

NO TRAFFIC TRAFFIC Overtopping Spread Sandbags Drop-off SECTION SHOWING SANDBAGGING TO PREVENT OVERTOPPING 1. Place one row of sandbags, two bags deep, adjacent to drop-offs where overtopping spread may occur and where the down-slope lanes must be used to maintain traffic. 2. When possible, avoid this situation by phasing milling and pavement lifts so that the exposed sides of drop-offs face down-slope. 3. Consider using this detail wherever new pavement lifts must be placed or existing pavement must be milled, and where the exposed edge of a drop-off faces upslope. Figure 3 Typical Terminus Begin Spread Limits of Sandbagging Sandbags NO TRAFFIC 6 Limits of Spread Through Vertical Curve 6 Runoff 6 feet TRAFFIC Roadway Surface Begin Sandbags Edge of Drop-Off See Typical Terminus Detail TYPICAL TERMINUS Detail for Sandbagging To Prevent Overtopping At Drop-Offs Plan View Figure 4 LIMITS OF SANDBAGGING For Prevention Of Overtopping At Drop-Offs along Vertical Curves Profile View Figure 5 11

Figure 6 12

Figure 7 Figure 8 Figure 9 Figure 10 13