05-455B TRENCH EXCAVATION, BEDDING AND BACKFILL SECTION

Similar documents
SECTION EARTH MOVING

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

DESCRIPTION OF WORK:

CONSTRUCTION PERMIT REQUIREMENTS

SECTION SITE PREPARATION

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

SECTION 4Aggegate Subbase

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

C. Section TESTING LABORATORY SERVICE.

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

SECTION SELECTIVE DEMOLITION

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SECTION POLYVINYL CHLORIDE (PVC) PIPE

MDWASD 8/1999 SECTION TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

SECTION STORM DRAIN SYSTEM

SECTION EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION 1 GENERAL REQUIREMENTS

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Section 2100-Trenching and Tunneling

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

LS 2540 SEWER LATERALS AND INSPECTION TEES

CITY ENGINEERS ASSOCIATION OF MINNESOTA

SECTION ABANDONMENT OF SEWER MAINS

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Division 2 Section Section 02795

Wastewater Capital Projects Management Standard Construction Specification

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION SHEETING, SHORING AND BRACING

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

Unit Price Averages Reports

Section 402. STORM SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Developer s/consultants Field Services Guidelines

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION PRECAST CONCRETE UTILITY STRUCTURES

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

Section EXCAVATION AND BACKFILL FOR UTILITIES

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Section Installation of pipe and casing for sanitary sewer by methods of augering.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

FDOT Specifications List

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

SECTION 13 REPLACEMENT AND CLEANUP SCOPE OF WORK

STANDARD PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF DOMESTIC WATER, SEWER AND RECYCLED WATER FACILITIES

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST BID PROPOSAL

SECTION GRAVITY SANITARY SEWERS

Permit No. Permit Fee: $ Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: Address:

agrees to replace at no charge any tree that dies and subsequent inspection shows that the wire basket was not properly removed.

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

550 PIPE CULVERTS, SEWERS AND DRAINS

Beacon Hill Sewer District Standard Specifications

SECTION UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SUDAS Revision Submittal Form

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

VEHICLE CROSSOVER INFORMATION PACK

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Trenching and Excavation Safety

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION 7 UNDERDRAIN SERVICE

Section TREE AND PLANT PROTECTION

STANDARD SPECIFICATIONS

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Underground Commercial Electric Service

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

DIVISION 4300 STORM DRAINAGE

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER

CLEANING, INSPECTION, AND TESTING OF SEWERS

Building Your Interlocking Concrete Pavement to Last a Lifetime

Section SEWER PIPE INSTALLATION AND TESTING

Appendix D.1. Testing Requirements for Infiltration, Bioretention and Sand Filter Subsoils

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

Transcription:

SECTION 2225-1 1.0 GENERAL 1.1 SCOPE: A. This work consists of trench excavation, trench foundation, pipe bedding, pipe zone material, trench backfill and removal or disposal of material in the installation of sewer lines, culverts, conduits, conductors and appurtenances. This work also includes but is not limited to sheeting, shoring, bracing, dewatering, importing of material and disposal of unsuitable material. B. Unless otherwise provided in the contract, other work required under this item shall include the removal of structures or portions thereof, grubbing of structure sites which are in the trench zone, the construction and removal of shoring or cofferdams, the dewatering of excavated areas, and the placement and compaction of excavated or imported material. Work under this section shall conform to all federal, state, and local safety regulations. 1.2 RELATED DOCUMENTS: A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 specification sections, apply to work of this section. B. Section 02205: Soil and Aggregate Materials 1.3 MATERIAL APPROVAL: A. All backfill, fill, and other construction materials shall be approved prior to their use. All sampling and testing necessary for the Contractor to receive approval by the Engineer and substantiate compliance with the material specification requirements shall be done at the Contractors expense. B. Approval of construction materials shall be based on an inspection of the onsite material and documentation submitted by the Contractor to the Engineer. All materials delivered to the site prior to approval by the Engineer are at the Contractors risk. If variations in materials occur or if materials appear to depart from the specifications, testing by the Contractor may be directed by the Engineer. The Engineer reserves the right to independently sample and test construction materials prior to their use.

SECTION 2225-2 C. Material that does not conform to the specification requirements and is placed on site or in the work shall be removed and replaced at the Contractors expense. 1.4 QUALITY ASSURANCE: A. Codes and Standards: Oregon State Highway Division (OSSHC), Standard Specifications for Highway Construction, Current Edition. B. American Association of State Highway and Transportation Officials (AASHTO) C. American Society for Testing and Materials (ASTM). 1.5 JOB CONDITIONS: A. Existing Utilities: The locations of existing underground utilities are shown in an approximate location only and have not been independently verified by the Owner or its representative. The Contractor shall determine the exact location of all utilities before commencing work, and agrees to be fully responsible for any and all damage, which might be occasioned by the Contractor s failure to locate and preserve any and all underground utilities. B. Should piping or other utilities be encountered during construction, notify Engineer immediately for direction or procedure. C. Do not interrupt existing utility service unless permitted in writing by Engineer and then only after temporary utility services have been provided. D. Repair damaged utilities to the satisfaction of the Owner at Contractor s Expense. E. The Contractor shall be responsible for all backfill, utility placement, compaction, surface replacement and all other activities associated with utility installation.

SECTION 2225-3 2.0 MATERIALS 2.1 TRENCH FOUNDATION STABILIZATION: A. Foundation stabilization shall be 3 inch minus rock, pit run or bar run, well graded from coarse to fine, and free from excessive dirt or organic material. Foundation stabilization shall be the same as Type D fill as listed in Section 02205. 2.2 PIPE BEDDING: A. Pipe bedding material shall be crushed rock with a maximum size of 1 inch, clean sand, or pea gravel, well graded from coarse to fine. Pipe bedding shall be the same as Type B or Type C fill as listed in Section 02205. 2.3 TRENCH BACKFILL MATERIAL: 3.0 WORKMANSHIP A. Standard trench not located in vehicular traffic areas shall be Type A fill as listed in Section 02205, clean native or common material. B. Trenches under vehicle travel ways shall be backfilled with granular material consisting of Type B or C fill. Native material may be substituted in trench lines for Type C fill, only approved in writing by the Engineer. Native material utilized in place of Type C fill shall be clean native sand. 3.1 PREPARATION OF RIGHT-OF-WAY: A. Where clearing of the right-of-way is necessary, it shall be completed prior to the start of trenching. B. The contractor shall exercise care not to unnecessarily remove existing tree limbs, or shrubbery on public or private property, unless they are within five feet of the pipe centerline, without written permission from the Engineer. Overhanging signs, canopies, or structures shall not be removed without written permission from the Engineer. 3.2 PAVEMENT, CURB. AND SIDEWALK REMOVAL:

SECTION 2225-4 A. Pavement, curb and sidewalk to be removed in the course of construction shall be neatly cut regardless of thickness, prior to excavation of the trenches. Equipment used for cutting shall be a pavement saw, jackhammer, hydrohammer, or approved pavement cutter. Width of the pavement cut will be the 6 inches wider than the width of the trench at the ground surface. Pavement removed shall be removed from the site and not used for trench backfill, unless they meet the requirements for backfill specified herein. 3.3 OPEN TRENCH LIMIT: A. The length of open trench shall be kept to a minimum. In normal cases, the open trench shall not exceed 300 feet. The Engineer may allow longer segments based upon work conditions. Related construction such as pavement, road gravel, concrete restoration, etc., shall be completed as soon as possible but within no more than 1000 feet of the open trench. 3.4 TRENCH WIDTH: A. Trench width at the ground surface shall be kept to a minimum, but in no case shall be less than 12 inches. Sheeting requirements shall be independent of trench width. As a standard, trench width shall provide a minimum clear working space of 4 inches outside the maximum diameter of the pipe on each side in the pipe zone. B. When approved by the Engineer, the Contractor may, at no additional cost to the Owner, use pipe of greater strength or install a superior pipe base in lieu of maintaining the trench widths as shown. C. Confine trench widths to a minimum, dispose of excess material in designated disposal sites or off site. 3.5 TRENCH GRADE: A. The Contractor shall excavate the trench, or supervise the excavation, to the lines and grades shown or as approved by the Engineer with proper allowance for pipe, bedding, and base thickness. If the trench is excavated below the required grade, correct the part of the trench which is over excavated at no additional cost to the Owner with the type of material specified for pipe base or bedding. Place the material over the full width of the

SECTION 2225-5 trench in layers not exceeding 8 inches deep and compact each layer to a density of 95 percent of maximum as determined by ASTM D-698 to the established grade. 3.6 DISPOSAL OF EXCESS MATERIAL: A. Excess material remaining after the completion of trench backfill, or material not allowed to be placed in the backfill will be hauled away and placed at locations and in such a manner that it does not create a hazard to pedestrian or vehicular traffic, or interfere with the function of existing drainage. Wasted material shall be neatly placed, compacted, and graded to match existing ground as much as possible. Disposing of all excess materials shall be considered incidental to trench excavation. 3.7 TRENCH PROTECTION: A. The Contractor shall provide the materials necessary to protect the trench at all times. Sheet and brace the trench when necessary to prevent caving during excavation of unstable materials, or to protect adjacent structures, property, workmen, the public, and paving. Excavated materials shall not obstruct any private or public traveled roadways, streets or driveways longer than necessary and shall be located as to not exceed the safe loading of the trench. The method of trench protection used shall according to the contractor s design, and meet all applicable safety requirements of the federal, state, and local safety codes. 3.8 COMPACTION CONTROL AND TESTING: A. All trench shall be compacted in layers and to the densities specified herein. Maximum density, as used in these specifications, shall be defined as the maximum density obtained by ASTM D 1557 (AASHTO T-99), Method A or C, Standard Proctor using a 5.5 pound hammer and 12 inch drop. In place density of compacted backfill will be determined in accordance with ASTM D 1556, or by nuclear density test procedures in accordance with ASTM D 2922 and ASTM D 3017. B. It shall be the responsibility of the Contractor to achieve the specified compaction for all classifications of backfill. The Contractor shall control his operations by conducting his own confirmation tests as required to verify and confirm that he is

SECTION 2225-6 complying at all times with the requirements of these specifications concerning compaction control and testing. C. The Contractor shall demonstrate the adequacy of compaction equipment and procedures before exceeding the original 200 lineal feet of trench backfill. Once the Contractor has established his method as meeting the requirements of this section, and as long as the backfill or character of the trench does not materially differ, additional testing is not required unless the Engineer's random testing demonstrates the trench compaction does not meet the specified requirements. If the backfill, trench conditions, or the Contractors compaction methods change, the Engineer may require the Contractor to re-demonstrate his methods as achieving the specified compaction requirements. Failure of the backfill to achieve the specified density will be just cause for rejection of all or any portions of the backfill tested. D. If compaction fails to meet the specified requirements, the Contractor shall remove and replace the backfill or fill at the proper density or shall bring the density up to specified level by other means acceptable to the Engineer. Costs of excavating, backfilling, and compaction in connection with compaction testing specified shall be borne by the Contractor and considered incidental to the trench excavation and backfill. 3.9 BACKFILL METHODS: A. Backfill Types: 1. Type A Backfill: Type A backfill shall be used in areas without surface improvements, other than vegetation. Backfill the trench above the pipe zone with backfill material. Determine and provide the type of compaction equipment, method to use, and the amount of compaction to prevent subsequent settlement. The backfill shall be slightly mounded so that at the end of the performance period the excavated and backfilled area finished surface meets the existing adjacent grade. 2. Type B Backfill: Type B backfill shall be used in areas where specified on the drawings, or in crossings of the Oregon State Highways. Backfill the trench above the pipe zone with backfill material. Top of rock elevation shall be held

SECTION 2225-7 down at least the thickness of the of the paving in areas to receive pavements. All type B backfill will be placed in 8 inch lifts and compacted to 95 percent of optimum density in accordance with AASHTO T-99. 3. Type C Backfill: Type C backfill shall be used in areas where specified on the drawings, or in any area under paving or sidewalk area that is not specified otherwise. Class C backfill shall be used above the pipe zone and below the base rock. All class C backfill shall be placed in 12 inch lifts and compacted to 95 percent of maximum density in accordance with AASHTO T-99. 4. Type D Backfill: Type D backfill shall be used as foundation stabilization or where specified on the drawings. Type D backfill shall be used as pipe zone base material, or between the pipe zone and the pavement base. Type D backfill shall not be used in the pipe zone. All type D backfill shall be compacted to a minimum of 92 percent relative density. B. Foundation Stabilization: When voids or other subsurface conditions unsuitable for support of pipe are present, over excavate the trench to remove unsuitable material as directed and backfill the trench to the pipe base with Type D backfill. Minimum depth of foundation stabilization shall be 6 inches. C. Removal of Water: Take all precautions to prevent water from entering the excavation. At all times provide and maintain ample means and devices to promptly remove and dispose of water which enters the trench during the time the trench is being prepared for pipe laying, the pipe laying and during backfill operations. Dispose of the water in a manner to prevent damage to adjacent property, silting in of other pipes and contamination of groundwater. D. Pipe Zone Material: Pipe zone material shall be a minimum of 4 inches below the pipe, the full width of the trench, and a minimum of 6 inches above the pipe. Prior to placing the pipe zone material, remove all loose or foreign materials form the trench. Hand grade the trench to proper grade ahead of the pipe laying. Pipe zone material shall be compacted as specified for Type C Backfill, with allowance for pipe laying requirements when using mechanical compaction equipment. Hand compact the pipe zone material around the pipe. Impact compactors shall not be used until

SECTION 2225-8 sufficient cover, as recommended by the pipe manufacturer, has been placed over the top of the pipe. E. Trench Backfill Above Pipe Zone: When backfill is placed mechanically, push the backfill material onto the slope of the backfill previously placed and allow to slide down into the trench. Do not push backfill into the trench in such a way to allow free fall of the material until at least two feet of cover is provided over the top of the pipe. Under no circumstances permit sharp, heavy pieces of material to drop directly on to the pipe or the compacted material around the pipe. F. Interfering Structures or Obstructions: Where rock, stumps, logs, or structures are encountered in the excavation and not shown on the plans which cannot be efficiently removed with the Contractors equipment, the Engineer may, if requested, make changes in the alignment of the trench. The cost for removal of such structures or obstructions will be considered extra work IF, in the Engineer s sole and absolute judgment, the obstruction or structure could not be efficiently removed and could roots, logs, stumps and debris shall be removed with out additional compensation by the Owner. G. Tunneling, Boring, or Jacking: Tunneling, boring, or jacking may be used as a method in lieu of open trench excavation if approved by the Engineer. The Contractor shall first show just cause and furnish the Engineer with a construction schedule outlining methods, time schedule and proposed safety measures to be incorporated in the construction. If this method is approved, the Contractor shall pothole the construction every 50 feet or as approved by the Engineer to demonstrate that the proper line and grade is being followed. 3.9 SURFACE REMOVAL AND REPLACEMENT: A. Topsoil: When specified and where reasonable topsoil conditions exist, the Contractor shall remove the topsoil to the specified depth and place the material in a stockpile. The Contractor shall not mix the topsoil with other excavated material. After the trench has been backfilled, the topsoil shall be replaced. 1. In lieu of stockpiling the existing topsoil, the Contractor may substitute approved imported topsoil to a depth specified, at no expense to the Owner.

SECTION 2225-9 2. The Contractor shall maintain the finished grade of the topsoil level with the area adjacent to the trench until final acceptance of by the Engineer and shall repair any damage to adjacent topsoil caused by work operations. B. Pavements, Curbs, and Sidewalks: All surface improvements shall be trimmed back to a neat edge and any damaged, lifted, or broken pavement shall be removed. Base course shall be placed and compacted in place. Base thickness shall be in accordance with the standard details incorporated into these specifications. When asphaltic concrete is to be placed, all manholes, pavement edges, valve boxes, curb faces, cleanout frames, etc., shall receive an asphaltic tack coat. Surface improvements shall be placed and compacted in place in such a manner that if a straight edge is placed across the patched area and along the edges of the old surfacing and the new surface, the new surface shall not deviate from the straightedge more than 1/4 inch. 4,0 MEASUREMENT AND PAYMENT 4.1 Measurement: No separate measurement shall be made for the Work described in this section. 4.2 All work associated with trenching for drainage piping, water piping, electrical improvements an miscellaneous improvements shall be included under the lump sum items for Drainage Improvements or Furnish & Install Irrigation Piping ----- or other lump sum items, whichever is appropriate as listed in the proposal. END OF SECTION