Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Similar documents
Project Cost Management

Module 5 Cost Management PMP Exam Questions

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

IST 302 : Project Cost Management

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Brainstorm. What is Cost and Project Cost Management?

Chapter 7. (PMBOK Guide)

PMP Exam Preparation Answer Key

Using Earned Value Management for Improving Processes. By Cynthia K. West

How To Manage Project Cost Management

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Project Cost Management

INSE 6230 Total Quality Project Management

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Project Cost Management. Richard Boser

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Chapter 7: Project Cost Management. Munawar

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Earned Value Formulae

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Project Cost Management

An introduction to Earned Value Analysis

Earned Value Management Guidelines

Chapter 3: Project Cost Management

How To Manage A Project

PROJECTS SCHEDULING AND COST CONTROLS

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

PROJECT COST MANAGEMENT

Project Cost Control: The Way it Works By R. Max Wideman

Simple Earned Value (Using MS Project 2010)

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

700 Analysis and Reporting

Tracking Budgets and Schedules

Project Management for Scientists

Estimating Cost at Completion - Judgment & EV Information

Chapter 5: Project Cost Management

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

CPM -100: Principles of Project Management

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Introduction to earn value management in Civil Engineering

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

Net Present Value and Capital Budgeting. What to Discount

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

Certification Exam Objectives: PK0-003

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Making project management indispensable for business results. Project Management 101

PERCEPTION. Tracking Progress & EAC

PMI Lexicon of Project Management Terms

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Applied Project Management ( APM )

EVM.01. Earned Value Analysis Why it Doesn't Work

Project Control with ProTrack

earned value management

COINS EVA Earned Value Analysis

A Gentle Introduction to Earned Value Management Systems

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Earned Value and Agile Reporting

PMP Handouts Dr Pratul Sharma Project Management Framework

PROJECT COST MANAGEMENT

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Tracking Software Development Progress with Earned Value and Use Case Point

Project Cost Management - 2 Days

Project Management Using Earned Value

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Project Cost Management.

Agile and Earned Value. A white paper. October Author Stephen Jones, Sellafield Ltd

Program Title: Advanced Project Management Program ID: # Program Cost: $3,780 Duration: 37.5 hours. Program Description

Which projects should the corporation undertake

L10: Budgeting and Cost Control. Olivier de Weck

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A

Exercise 2 Cost Management

Chapter 9 Cash Flow and Capital Budgeting

Project Cost Management

Principles of Project Management

AACE International Recommended Practice No. 86R 14

Certified Project Management Professional VS-1079

Earned Value Analysis Exercise

The To Complete Performance Index

DICTIONARY OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT

Project Evolution & Estimation :cash flow forecasting, cost benefit evolution techniques, risk evolution, Cost benefit analysis

Project Prioritization

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: # Program Cost: $4,690 Duration: 52.

Appendix D Glossary Of Terms

Transcription:

PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02. Estimate at completion (EAC) is a periodic evaluation of: A. Cost of work completed. B. Value of work performed. C. Anticipated total cost at project completion. D. What it will cost to finish the job. 03. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV)? A. 350. B. -75. C. 400. D. -50. 04. Double declining balance is a form of: A. Decelerated depreciation. B. Straight line depreciation. C. Accelerated depreciation. D. Life cycle costing. 05. Analogous estimating: A. Uses bottom-up estimating techniques. B. Is used most frequently during the executing processes of the project. C. Uses top-down estimating techniques. D. Allways uses actual detailed historical costs. 06. The cost of choosing one project and giving up another is called: A. Fixed cost. B. Sunk cost. C. Net present value (NPV). D. Opportunity cost. 07. The main focus of life cycle costing is to: A. Estimate installation costs. B. Estimate the cost of operations and maintenance. C. Consider installation costs when planning the project costs. D. Consider operations and maintenance costs in making project decisions. 08. Cost performance measurement is best done through which of the following? A. Asking for a percent complete from each team member and reporting that in the monthly progress report. B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance. Página: 1

C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost. D. Focusing on the amount expended last month and what will be expended the following month. 09. A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned. B. When the project is completed we will have spent 89 percent more than planned. C. The project is only progressing at 89 percent of that planned. D. The project is only getting 89 cents value out of every dollar invested. 10. A project schedule performance index (SPI) of 0.76 means: A. The project is over budget. B. The project is ahead of schedule. C. The project is only progressing at 76 percent of the rate originally planned. D. The project is only progressing at 24 percent of the rate originally planned. 11. Which of the following is not needed in order to come up with a project estimate? A. WBS. B. Network diagram. C. Risks. D. Change control procedure. 12. Which of the following is an example of a parametric estimate? A. Dollars per module. B. Learning bend. C. Bottom-up. D. CPM. 13. A less rough order of magnitude estimate is made during which project management process group? A. Project planning. B. Project closing. C. Project executing. D. Project initiating. 14. How close to actual costs should a definitive budget estimate is? A. -75 percent to +25 percent. B. -10 percent to +15 percent. C. +10 percent to -25 percent. D. -15 percent to +20 percent. 15. Which factor would not be considered when choosing between two projects to undertake? A. Net present value (NPV). B. Benefit cost ratio (BCR). C. Payback period. D. Law of diminishing returns. 16. If project A has a net present value (NPV) of U.S. $30,000 and project B has an NPV of U.S. $50,000, what is the opportunity cost if project B is selected? A. $23,000. Página: 2

B. $30,000. C. $20,000. D. $50,000. 17. Which type of cost is team training? A. Direct. B. NPV. C. Indirect. D. Fixed. 18. Project setup costs are an example of: A. Variable costs. B. Fixed costs. C. Overhead costs. D. Opportunity costs. 19. Value analysis is performed to get: A. More value from the cost analysis. B. Management to buy into the project. C. The team to buy into the project. D. A less costly way of doing the same work. 20. Who has the cost risk in a fixed price (FP) contract? A. Team. B. Buyer. C. Seller. D. Management. 21. What formula is used to calculate the EAC, when deciding that the future will be able to meet the approved plan for the project? A. AC + ETC. B. AC + (BAC - EV). C. BAC / CPI. D. AC + ((BAC EV) /CPI X SPI). 22. In calculating the project TCPI using the formula (BAC - EV) / (BAC - AC), we obtain a value of 1. 6 How should we interpret this result? A. Because the index is greater than one, the project goes well, both in cost and on time. B. The project is well on cost, because the index is greater than one C. Because the index is greater than one, the project goes well to the deadline. D. There is not enough budget to complete the work to be done. 23. Meet the project scope required to submit a photocopy machine to the customer. A model costs 10,000 and 5 years. The B model costs 16,000 and lasts 10 years. Maintenance costs of the two models are similar. Following the approach of life cycle cost, which photocopy machine you would choose. A. Model A, the criterion we should deliver the cheapest. B. Model B, because it has a cost closer to his life. C. Model A, because the project budget must be as low as possible. D. Model B, since you always have to deliver the highest quality components. Página: 3

24. What better expresses the difference between management reserve and contingency reserve? A. The management reserve is made for known risks and contingency reserve for unknown hazards. B. The management reserve belongs to the project manager and the contingency reserve to the project sponsor. C. The contingency reserve is made for known risks and management reserve for unknown hazards. D. The management reserve is part of the baseline and the contingency reserve is outside. 25. What better expresses the difference between a reserve and padding? A. The reserve is known and shared by the team, while the mattress is hidden by individuals. B. The reserve is estimated to detail (bottom up) and padding at high level (top down). C. Reserve is for known risks and padding for unknown risks. D. Reserve is economic and padding is temporal. Página: 4

PMP Test C07_01 Solution Question Area Answer 01 Cost D 02 Cost C 03 Cost D 04 Cost C 05 Cost C 06 Cost D 07 Cost D 08 Cost B 09 Cost D 10 Cost C 11 Cost D 12 Cost A 13 Cost D 14 Cost B 15 Cost D 16 Cost B 17 Cost A 18 Cost B 19 Cost D 20 Cost C 20 Cost C 21 Cost B 22 Cost D 23 Cost B 24 Cost C 25 Cost A Página: 5