Chapter 10 Project Monitoring and Control

Similar documents
technical tips and tricks

A Gentle Introduction to Earned Value Management Systems

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

700 Analysis and Reporting

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

CPM -100: Principles of Project Management

INSE 6230 Total Quality Project Management

technical tips and tricks

Applied Project Management ( APM )

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

PERCEPTION. Tracking Progress & EAC

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

How To Manage A Project

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Basic Concepts of Earned Value Management (EVM)

Estimating Cost at Completion - Judgment & EV Information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Project Management: Tracking Progress and Earned Value with MS Project 2003

COINS EVA Earned Value Analysis

An introduction to Earned Value Analysis

VIII. Project Management Glossary

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Introduction to earn value management in Civil Engineering

Earned Value Management Guidelines

PROJECTS SCHEDULING AND COST CONTROLS

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Brainstorm. What is Cost and Project Cost Management?

Basics of Cost and Schedule Control

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Orange County Convention Center Orlando, Florida June 3-5, Using SAP PS Earned Value to Manage IT Projects Michael Kim

Project Management Glossary

plans based on actual cost, schedule and technical progress of work [1, 9].

Earned Value Formulae

Project Cost Management

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Tracking Software Development Progress with Earned Value and Use Case Point

Using Earned Value Management for Improving Processes. By Cynthia K. West

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget

Appendix D Glossary Of Terms

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM,

Basics of Cost and Schedule Monitoring. Nathaniel Osgood 4/5/2004

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Project Cost Management

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision

Simple Earned Value (Using MS Project 2010)

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Project Execution - PM Elements

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Project Control with ProTrack

A Short Introduction to Project Management

Since 1985, the Test Program Set (TPS) development

AACE International Recommended Practice No. 86R 14

PROJECT TRACKING and CONTROL

Chapter 7: Project Cost Management. Munawar

Earned Value User s Guide

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Project Management Using Earned Value

Accounting System. Page 1 of 9

Tracking Budgets and Schedules

DCMA DCMA-EA PAM October 2012

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

PMP Exam Preparation Answer Key

IST 302 : Project Cost Management

PROJECT SCHEDULING AND TRACKING

Chapter 7. (PMBOK Guide)

Project Control. 1. Schedule Updating

MTAT Software Economics. Lecture 6: Software Cost Estimation (part II)

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Earned Value and Agile Reporting

Earned value method as a tool for project control

What is the Health of my Project?

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Earned-Value Benchmarks for Re-baselining Your Project

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

L10: Budgeting and Cost Control. Olivier de Weck

Project Cost Management

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

PM in construction industry

Applied Software Project Management

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Forecasting Project Schedule Completion by Using Earned Value Metrics

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Software Project Scheduling. - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

Transcription:

Chapter 10 Project Monitoring and Control

Project Monitoring and Control Monitoring collecting, recording, and reporting information concerning project performance that project manger and others wish to know Controlling uses data from monitor activity to bring actual performance to planned performance

Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?

Why do we monitor? Simply because we know that things don t always go according to plan (no matter how much we prepare) To detect and react appropriately to deviations and changes to plans

What do we monitor? Men (human resources) Machines Materials Money Space Time Tasks Quality/Technical Performance

What do we monitor? Inputs Time Money Resources Material Usage Tasks Quality/Technical Performance Outputs Progress Costs Job starts Job completion Engineering / Design changes Variation order (VO)

When do we monitor? End of the project Continuously Regularly Logically While there is still time to react As soon as possible At task completion At pre-planned decision points (milestones)

Where do we monitor? At head office? At the site office? On the spot? Depends on situation and the whats

How do we monitor Through meetings with clients, parties involved in project (Contractor, supplier,etc.) For schedule Update CPA, PERT Charts, Update Gantt Charts Using Earned Value Analysis Calculate Critical Ratios Milestones Reports Tests and inspections Delivery or staggered delivery PMIS (Project Management Info Sys) Updating

Meetings Some monitoring issues What problems do you have and what is being done to correct them? What problems do you anticipate in the future? Do you need any resources you do not yet have? Do you need information you do not have yet? Do you know anything that will give you schedule difficulties? Any possibility your task will finish early/late? Will your task be completed under/over/on budget?

Project Control Cycle ACTION Correct deviations from plan RE-PLAN as necessary PLAN Specifications Project Schedule Project budget Resource plan Vendor contracts COMPARE Actual status against plan -Schedule -Cost MONITOR Record status Report progress Report cost

Project Control Control process and activities needed to correct deviations from plan Control the triple constraints time (schedule) cost (budget, expenses, etc) performance (specifications, testing results, etc.)

Techniques for monitoring and control Earned Value Analysis Critical Ratio

Earned Value Analysis A way of measuring overall performance (not individual task) is using an aggregate performance measure - Earned Value Earned value of work performed (value completed) for those tasks in progress found by multiplying the estimated percent physical completion of work for each task by the planned cost for those tasks. The result is amount that should be spent on the task so far. This can be compared with actual amount spent.

Earned Value Analysis Methods for estimating percent completion The 50-50 estimate. 50% is assumed when task is begun, and remaining 50% when work completed. 0-100% rule. This rule allows no credit for work until task is complete, highly conservative rule, project always seem late until the very end of project when everything appears to suddenly catch up Critical input rule. This rule assigns progress according to amount of critical input that has been used. Labor or skilled dependent, machine critical input buy machine complete task may be misinformation Proportional rule. This rule divides planned (or actual) time-todate by total scheduled time(or budgeted (or actual ) cost-todate by total budgeted cast] to calculate percent complete. This is commonly used rule.

Earned Value Analysis Refer to earned value chart basis for evaluating cost and performance to date If total value of the work accomplished is in balance with the planned (baseline) cost, and actual cost then top mgmt has no particular need for a detailed analysis of individual tasks Earned value concept combines cost reporting & aggregate performance reporting into one comprehensive chart

Earned Value Analysis Baseline cost to completion referred to as budget at completion (BAC) Actual cost to date referred to as estimated cost at completion (EAC) Identify several variances according to two guidelines 1. A negative variance is bad 2. Cost and schedule variances are calculated as earned value minus some other measure

Earned Value Chart basis for evaluating cost & performance to date

Earned Value Analysis - Variances 4 types of variances; Cost (spending) variance (CV) difference between budgeted cost of work performed (earned value) (BCWP) and actual cost of that work (ACWP) Schedule variance (SV) difference between earned value (BCWP) and cost of work we scheduled to perform to date (BCWS) Time variance (TV) difference between time scheduled for work performed (STWP) and actual time to perform it (ATWP)

Earned Value Variance - Formula CV = BCWP ACWP (negative value - cost overrun) SV = BCWP BCWS (negative value - behind schedule) TV = STWP ATWP (negative value - delay) Index (Ratios) Cost Performance Index (CPI) = BCWP/ACWP Schedule Performance Index (SPI) = BCWP/BCWS Time Performance Index (TPI) = STWP/ATWP

EXAMPLE Assume that operations on a Work Package cost RM 1,500 to complete. They were originally scheduled to finish today. At this point, we actually spent RM1,350. And we estimate that we have completed two thirds (2/3) of the work. What are the cost and schedule variances? CV = BCWP ACWP = 1500 (2/3) 1350 = - 350 SV = BCWP BCWS = 1500 (2/3) 1500 = - 500 CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74 SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67 Spending higher than budget, and given what we have spent, we are not as far along as we should be (have not completed as much work as we should have)

Possible to have one of indicators to be favorable while the other unfavorable Might be ahead of schedule and behind costs Six possibilities (see figure next slide)

6 Possibilities Earned Value Analysis

EXERCISE (Text P.544 Problem 4) A project to develop a country park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes. $ Planned (Baseline) 475,000 Actual cost 350,000 Value completed 300,000 BCWS ACWP BCWP Time t Month 17

Solution BCWS = 475,000 BCWP = 300,000 ACWP = 350,000 CV = BCWP ACWP SV = BCWP BCWS CV = 300,000 350,000 = -50,000 (negative value - cost overrun) SV = 300,000 475,000 = -175,000 (negative value - behind schedule) Cost Performance Index (CPI) = BCWP/ACWP = 300/350 = 0.86 Schedule Performance Index (SPI) = BCWP/BCWS = 300/475 = 0.63 Time Performance Index (TPI) = STWP/ATWP Scheduled Time Work Performed (STWP) can be estimated Time t = Schedule Variance/Slope of Planned costs = -175,000/ (475,000/17) = - 6.26 months Time Difference= 17-6.26 = 10.74 TV = 10.74/17 = 0.63

Critical ratio Sometimes, especially large projects, it may be worthwhile calculating a set of critical ratios for all project activities The critical ratio is actual progress scheduled progress x budgeted cost actual cost If ratio is 1 everything is probably on target The further away form 1 the ratio is, the more we may need to investigate

Critical ratio example Calculate the critical ratios for the following activities and indicate which are probably on target and need to be investigated. Activity Actual progress Scheduled Progress Budgeted Cost A 4 days 4 days 60 40 B 3 days 2 days 50 50 C 2 days 3 days 30 20 D 1 day 1 day 20 30 Actual cost E 2 days 4 days 25 25 Critical ratio (CR)

Critical ratio example Can be on schedule and below budget (Act A) Why so good? Cutting corners? Can be behind schedule but below budget (Act C) Can be on budget but physical progress lagging (Act E) Can be on schedule but cost running higher than budget (Act D) On budget ahead of schedule (Act B)

Summary Need proper project monitoring and control mechanisms Tools available to help in monitoring and controlling activities There are human control and management aspects not covered here