Brisbane River Catchment Flood Study: Comprehensive Hydraulic Assessment Overview

Similar documents
The 2011 Queensland Floods

2D Modeling of Urban Flood Vulnerable Areas

ADDING VALUE TO BOM FLOOD PREDICTIONS (WITHOUT MESSING AROUND WITH MODELS)

Initial Assessment of Potential Flood Mitigation for Communities Downstream of Googong Dam

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

Application of Monte Carlo Simulation Technique with URBS Model for Design Flood Estimation of Large Catchments

Flooding in Urban Areas - 2D Modelling Approaches for Buildings and Fences

Objective 4: Enhanced community education, flood awareness and preparedness

Modelling Flood Inundation of Urban Areas in the UK Using 2D / 1D Hydraulic Models

USING DETAILED 2D URBAN FLOODPLAIN MODELLING TO INFORM DEVELOPMENT PLANNING IN MISSISSAUGA, ON

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

BRISBANE RIVER CATCHMENT FLOODPLAIN STUDIES: COOPERATIVE PLANNING FOR BETTER FLOOD RESILIENCE

Estimating Potential Reduction Flood Benefits of Restored Wetlands

The Alternatives of Flood Mitigation in The Downstream Area of Mun River Basin

Innovative Approaches in Flood Damage Reduction

FLOOD INFORMATION SERVICE EXPLANATORY NOTES

Appendix 3: Glossary. Queensland Floods Commission of Inquiry Interim Report

Contents. Figure Index. 1. Introduction Engineered solutions Conclusions 11

FLOOD MODELLING THE COMPLEXITIES OF URBAN ENVIRONMENTS MEETING THE CHALLENGE IN NEWCASTLE

Wivenhoe and Somerset Dams Optimisation Study

TUFLOW Testing and Validation

Interactive comment on A simple 2-D inundation model for incorporating flood damage in urban drainage planning by A. Pathirana et al.

Forecasts, warnings and information

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING

Appendix A Flood Damages Assessment

Flow Through an Abrupt Constriction. 2D Hydrodynamic Model Performance and Influence of Spatial Resolution

FLOODPLAIN DELINEATION IN MUGLA-DALAMAN PLAIN USING GIS BASED RIVER ANALYSIS SYSTEM

water ISSN

The AIR Inland Flood Model for the United States In Spring 2011, heavy rainfall and snowmelt produced massive flooding along the Mississippi River,

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT

AZ EGER-PATAK HIDROLÓGIAI VIZSGÁLATA, A FELSZÍNI VÍZKÉSZLETEK VÁRHATÓ VÁLTOZÁSÁBÓL ADÓDÓ MÓDOSULÁSOK AZ ÉGHAJLATVÁLTOZÁS HATÁSÁRA

The site is Lot 1 DP Survey of this lot and Willarong Road and Koonya Circuit is given in Figure 2.

APPENDIX 1 Floodplain Management Strategies & Guidelines

Flood Modelling for Cities using Cloud Computing FINAL REPORT. Vassilis Glenis, Vedrana Kutija, Stephen McGough, Simon Woodman, Chris Kilsby

How To Understand And Understand The Flood Risk Of Hoang Long River In Phuon Vietnam

Evaluation of Open Channel Flow Equations. Introduction :

Management of flooding downstream of dams

SUSTAINABLE DEVELOPMENT AND FLOOD RISK REDUCING UNCERTAINTY (BRISTOL BROADMEAD DEVELOPMENT CASE STUDY) Marc Pinnell Symonds Group Ltd

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage

APT Petroleum Pipelines Limited. Queensland Floods

Planning for sea level rise. Assessing development in areas prone to tidal inundation from sea level rise in the Port Phillip and Westernport Region

06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH

A Conceptual Software System for Water Allocation, Planning and Catchment Management

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Environmental Data Management Programs

KNOWING WHEN TO GET THEM OUT - IMPROVING FLOOD EVACUATION PLANNING THROUGH FLOOD MODELLING AND STAKEHOLDER INVOLVEMENT

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Types of flood risk. What is flash flooding? 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology. Main types of climatically influenced flooding:

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference

5.14 Floodplains and Drainage/Hydrology

Project Manager. Geoff Masotti, P.Eng. T Ext. 254 T

BEST PRACTICE GUIDELINES FOR FLOOD RISK ASSESSMENT IN THE LOWER MEKONG RIVER BASIN

Rural Flooding: The Potential Role of Forestry

SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2

Havnepromenade 9, DK-9000 Aalborg, Denmark. Denmark. Sohngaardsholmsvej 57, DK-9000 Aalborg, Denmark

Catchment Scale Processes and River Restoration. Dr Jenny Mant The River Restoration Centre therrc.co.uk

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

BURNETT RIVER FLOODPLAIN ACTION PLAN COMMUNITY REFERENCE GROUP MEETING WEDNESDAY 4 DECEMBER PM

Melbourne Water s Submission. Draft Victorian Floodplain Management Strategy

Discussion about the practicability of implementing flood risk. management and urban flood insurance in China. Longhua Gao, Xiaoqing Zhou

HYDROGRAPH ROUTING. E. Input data needed for channel routing include the inflow hydrograph and the channel characteristics

City of London Climate Change Adaptation Strategy Dealing with Extreme Rainfall Events

USSD Workshop on Dam Break Analysis Applied to Tailings Dams

Review of Seqwater and SunWater Warnings Communications

6 FLOOD DAMAGES ASSESSMENT

Flooding in Brisbane

UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION

Methods for Determination of Safe Yield and Compensation Water from Storage Reservoirs

Groundwater Flooding: a UK Perspective

Floodplain Mapping. Vision. Events: 1 in 2 year 1 in 10 year 1 in 20 year 1 in 50 year 1 in 100 year Probable Maximum Flood Climate Change Impacts

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND

Computing Stormwater Runoff Rates and Volumes

How To Develop A Flood Risk Map

Quality Assurance Reviews of Hydraulic Models Developed for the Central Valley Floodplain Evaluation and Delineation Program

Integrated Local Flood Management and Drainage Strategy OVERVIEW

How To Recover From A Flood In Bundaberg

Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1

Part 1: Assessing flood risks and sharing information

Hydrologic Engineering Techniques for Regional Water Resources Planning

11.4 Voluntary Purchase House Raising and Flood Proofing

Modelling of Urban Flooding in Dhaka City

Climate Change and Infrastructure Planning Ahead

The Mississippi River & Tributaries Project

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Chapter 3 : Reservoir models

Use of Flood Modeller Pro to Develop Linked, Alternating 1-D and 2-D Models of Overland and in-river Flows for Breach of a Large Off-Channel Ring Dam

Dynamically Linked Two Dimensional/ One-Dimensional Hydrodynamic Modelling Program for Rivers, Estuaries and Coastal Waters

Probabilistic Risk Assessment Studies in Yemen

Department of Energy and Water Supply

FLOOD PROTECTION BENEFITS

CHAPTER 3 STORM DRAINAGE SYSTEMS

THE NATIONAL PRELIMINARY FLOOD RISK ASSESSMENT (PFRA) OVERVIEW REPORT

Appendix C Asset Risk Model Data

The Rational Method. David B. Thompson Civil Engineering Deptartment Texas Tech University. Draft: 20 September 2006

Planning for Casey s Community

FLOOD PROTECTION AND ECOSYSTEM SERVICES IN THE CHEHALIS RIVER BASIN. May Prepared by. for the by Earth Economics

Managing sewer flood risk

THE EARLY WARNING NETWORK SUBMISSION. to the. Queensland Floods Commission of Inquiry. The Early Warning Network. Prepared by

Chapter 12 - HYDROLOGICAL MEASUREMENTS

Hydrologic Modeling using HEC-HMS

Transcription:

Brisbane River Catchment Flood Study: Comprehensive Hydraulic Assessment Overview Cathie Barton 1, Sharon Wallace 1, Bill Syme 1, Wai Tong Wong 2, Pushpa Onta 2 1 BMT WBM, Brisbane QLD 2 Department of Natural Resources and Mines, Brisbane QLD Introduction The Brisbane River Catchment Flood Study (BRCFS) is one of the largest and most complex flood studies embarked upon in Australia. It is governed by a Steering Committee consisting of state and local government representatives, regularly reviewed by both an Independent Panel of Experts and a Technical Working Group, and undertaken by a team of specialist consultants. A different set of specialists is undertaking each of the three major components into which the study is divided: a) data collection; b) a comprehensive hydrologic assessment; and c) a comprehensive hydraulic assessment. This paper will focus on the latter component. Background The Brisbane River has a catchment area of over 13,600km 2. The River and its major tributaries have a long history of flooding, with recorded evidence of such dating back almost 200 years. Large flood events have been experienced and recorded in 1893, 1974 and 2011. Peak flood levels recorded for these events at the Brisbane Port Office Gauge are 8.35m AHD, 5.45m AHD and 4.46m AHD respectively. It is of interest that two large distinct flood events occurred in 1893 (one in January and one in February) with peak flood levels exceeding 8m AHD in both events. Following the devastation caused by the 1974 flood event, Wivenhoe Dam was constructed in the Brisbane catchment in 1984 for the dual purpose of water supply and flood mitigation. In addition to a water supply storage capacity of 1.165 million ML, it has 1.967 million ML of flood mitigation volume available to store floodwater and thereby reduce the risk of flooding downstream. Despite the 2011 event peaking approximately 1 metre lower than the 1974 event (and 4 metres lower than the largest 1893 event) in Brisbane City, and approximately 1.5 metres lower than the 1974 event at Moggill and Ipswich, the 2011 flood caused widespread property damage in the catchment. Peak flood levels upstream of Moggill and into Lockyer Creek in 2011 were similar to, and higher than those recorded in 1974. The Queensland Floods Commission of Inquiry (Qld FCoI, 2012) was established in response to the scale of the disaster caused by the 2011 flood event in the Brisbane River catchment. The Qld FCoI recommended that a comprehensive plan to manage Brisbane River flood risk was required (Recommendation 2.2, Qld FCoI, 2012). In response, the Queensland Government instigated the Brisbane River Catchment Floodplain Studies, of which the Comprehensive Hydraulic Assessment is a component. As shown in Figure 1, the Comprehensive Hydraulic Assessment is the final stage of the Brisbane River Catchment Flood Study (BRCFS). The Hydraulic Assessment utilises outcomes and products of the prior Data Collection Study (Aurecon et al., 2013)), the Disaster Management Tool (DMT) Study (BCC, 2014a) and the Comprehensive Hydrologic Assessment (Aurecon et al., 2014c)). There has been interfacing between all of these phases. 2015 Floodplain Management Association National Conference 1

Figure 1 Positioning of the Hydraulic Assessment within the BRCFS and within the Overall Framework Hydraulic Assessment Purpose and Extent The primary objectives of the Hydraulic Assessment include the development of an integrated suite of hydraulic models, rigorous and defendable calibration to historical events, and modelling of a comprehensive range of design events to define flood behaviour over the lower Brisbane River study area. The study area extends from the mouth of the Brisbane River up to Wivenhoe Dam, from the confluence of the Bremer River into the tributaries above Ipswich, and from the confluence of Lockyer Creek to upstream of Lyons Bridge. The locality of the hydraulic assessment area is shown in Figure 2 and Figure 3. 2015 Floodplain Management Association National Conference 2

Figure 2 Hydraulic Assessment Area Locality Figure 3 Hydraulic Assessment Area 2015 Floodplain Management Association National Conference 3

Hydraulic Characteristics of the Brisbane River Catchment Hydraulically, the Brisbane River Valley below Wivenhoe Dam is a mixture of conveyance and storage dominated reaches. Lockyer Creek, due to its flat wide topography is, in a large event, highly storage dominated, with substantial volumes of floodwaters being stored and conveyed on the floodplain. Floodwaters originate from the local catchment of Lockyer Creek, or from Brisbane River floodwater backing up into the creek and floodplains. Between Lockyer Creek and the Bremer River the Brisbane River is largely conveyance dominated, with relatively minor floodplains, and floodwaters largely confined to the river channel. The river experiences high velocities and steep gradients through these reaches. The Bremer River and the Brisbane River downstream of Colleges Crossing are a mixture of storage and conveyance with both having significant floodplains that store and/or help convey the flood wave. As with Lockyer Creek, flooding in the lower reaches of the Bremer River and its tributaries can be dominated by backwater effects from the Brisbane River. The lower Brisbane River, unlike most large east coast Australian rivers, has few gentle meanders, with many of the river s reaches controlled by the hilly terrain resulting in sharp bends at numerous locations. The hydraulic consequence is that in some reaches the flood flow is often confined between the river banks and substantially higher velocities develop. Downstream of the Breakfast Creek confluence, the river and floodplain widen to the mouth and inundation is increasingly influenced by Moreton Bay storm tide. Methodology Overview The magnitude of a flood event in the mid to lower Brisbane River and major tributaries below Wivenhoe is dependent on the complex interaction of number of factors, some of which are highly variable. These include the depth and duration of rainfall, spatial and temporal distribution of rainfall, antecedent catchment conditions, downstream boundary conditions, initial water levels in Wivenhoe Dam and operation of the Dam itself. A traditional rainfall-based approach to modelling design flood behavior, which relies on AEP neutrality between rainfall and flow, is not able to replicate the complex interactions between these variables. Hence, a Monte Carlo approach has been used to account for the complex catchment conditions and high degree of variation and interaction of these variables by randomly sampling from a pre-determined set of probability distributions for each variable. Whilst there are indeed challenges in developing and applying new methodologies, it is feasible for a Monte Carlo Simulation (MCS) approach to be used in the field of hydrology, as the generally quick speed of a hydrologic model makes it suitable for the simulation of the many thousands of scenarios required. It is rare for Monte Carlo simulations to be undertaken in the field of hydraulic modelling due to the longer simulation times required, particularly for detailed hydraulic models. However, given the complex behaviour of the Brisbane River, particularly in relation to backwater effects in the tributaries and variability in conditions producing peak flood levels, a Monte Carlo Simulation approach to hydraulic modelling was needed. It is for this reason that two TUFLOW hydraulic models have been developed and used for the Hydraulic Assessment in a two-stage process: 1. Fast Model a one-dimensional (1D) model, developed as a networked 1D or quasi-2d scheme, and 2. Detailed Model a two-dimensional (2D) model with some in-bank sections modelled in 1D. 2015 Floodplain Management Association National Conference 4

Methodology Fast Model The Fast Model, as the name suggests, is designed for speed and is more amenable to computationally demanding Monte Carlo Simulation applications. It is a 1D (quasi-2d) model developed using the 1D solver of the TUFLOW software, which explicitly solves the 2nd order solution of the full 1D St Venant equations. The Fast Model comprises more than 2,500 channel sections representing the Brisbane River, major tributaries and overland flowpaths below Wivenhoe Dam. Development of the Fast Model schematisation was assisted by use of an existing 2D TUFLOW GPU model of the Brisbane River below Wivenhoe Dam. This 2D model was developed as a Disaster Management Tool (DMT) (BCC, 2014a) for the purpose of producing broad-scale disaster management maps. While DMT model results are suitable for the production of such maps, model results are not of sufficient accuracy in some locations for more localised prediction of flood levels. The DMT model was also useful in determining floodways for a range of events up to and including an estimated PMF. This was of great value in the development of the Fast Model as quasi-2d models require the modeller to explicitly define the location and hydraulic properties of floodways as channel sections in the model. The Fast Model was tested against the Updated DMT model for a number of hypothetical extreme events to ensure it appropriately represented the floodways. It was also critical that the Fast Model remained robust in extreme events, and such proofing allowed this to be tested. The Fast ModeI is calibrated to a tidal record and calibrated and verified to five historical flood events: 1974, 1996, 1999, 2011 and 2013. Manning s n and bend (form) losses were used to calibrate to the range of event magnitudes (BMT WBM, 2015; Ryan et al., 2015). The calibration of the Fast Model is being reviewed at the time of writing. Methodology Monte Carlo Simulation To ensure that locations affected by both localised flood flows and Brisbane River backwater (e.g. Ipswich), simulated events needed to account for the relative contributions of each of these flooding mechanisms. Substantial discussion and consultation on the methodology required to achieve this led to the Hydrology Assessment simulating a range of whole-of-catchment rainfall events for rainfall burst durations from 12 hours to 168 hours culminating in 11,340 scenarios. These simulations were used to provide inflow hydrographs to the Fast Model Monte Carlo Simulation runs. The Fast Model is currently being used to undertake these simulations. Once the Fast Model has completed all 11,340 simulations, results will be used to develop peak level and peak flow frequency relationships at a number of reporting locations throughout the catchment. These frequency analyses will enable peak flows and peak levels for a specified probability (AEP) to be estimated at each reporting location. Based on the outcomes of the frequency analyses, approximately 50 stochastic events will be selected from the suite of 11,340 to represent the design events. One design event (e.g. the 1% AEP event) may be represented by an ensemble of Monte Carlo events in order to best replicate the peak flows and peak levels at the reporting locations. The methodology for selecting about 50 representative events is currently being developed. Once these ensemble events have been selected, the design events will be simulated in the Detailed Model. 2015 Floodplain Management Association National Conference 5

Methodology Detailed Model The Detailed Model is a 2D model developed using TUFLOW with the full 2D hydrodynamic free-surface flow equations solved using TUFLOW s CPU based implicit, unconditional, 2nd order spatial solver. The Detailed Model is fully 2D in the lower and mid-brisbane River with 1D channels used to represent the in-bank sections of Lockyer Creek, and the upper Bremer River and its tributaries. The Detailed Model provides a more accurate and explicit representation of the floodplain and produces far superior flood maps of flood levels, depths, hazards and risk categories than the Fast Model. It is also far more capable of modelling complex flow behaviour such as in areas of high velocity and sudden changes in flow direction (e.g. at sharp bends, which are prevalent in the Brisbane River). However, the Detailed Model is substantially slower than the Fast Model and is thus unsuitable to be used in the Monte Carlo simulations. Similar to the Fast Model, the Detailed Model is being calibrated to the 2011 (major) and 2013 (minor) events and verified to the 1974 (major), 1996, 1999 (minor) events. Calibration/verification has been undertaken to recorded historical gauge level hydrographs, measured flow records, flood mark levels and derived inundation extents. The Detailed Model is also being checked against hypothetical extreme events to ensure the model is both sound and robust, and that boundaries extend to include the full extent of an extreme flood. Once calibration has been accepted and the design event ensembles selected, the Detailed Model will be used to simulate these design events and provide comprehensive design flood information including extents, levels and other parameters of interest. Sensitivity assessments for climate change, bed level changes and future floodplain conditions will be undertaken. Methodology Rating Curves Rating curves at a number of key gauges were developed as part of the Hydrologic Assessment with the intent of future reconciliation and / or refinement as part of the Hydraulic Assessment. These rating curves have been compared to both Fast Model and Detailed Model calibration results. Any significant differences between the rating curves derived during the Hydrologic Assessment and the Detailed Model may require reconciliation. Differences are expected to occur particularly in locations where the stage-discharge curves are dependent on downstream tide levels or flow or levels at other locations. One of the outcomes of this assessment and the reconciliation process will be to develop a consistent and accepted set of rating curves for nominated gauges. Accurate rating curves and understanding the influence of hysteresis on these curves plays a critical role in managing the discharges from Wivenhoe Dam. The Fast and Detailed Models will help further this understanding. Conclusion The Brisbane River is a large and complex river system entwined with major urban areas. It has a long history of flooding and recently experienced a significant flood event in 2011 that caused widespread damage. A comprehensive series of assessments is being facilitated by the Queensland Government in order to better understand the flooding mechanisms and risks and to facilitate future planning for the Brisbane River catchment. Due to the complexity and size of the physical system, the methodologies developed and used to undertake the Brisbane River Catchment Flood Study have been innovative by necessity and are more comprehensive than current standard practice. With advances in techniques, software and hardware, it will be increasingly viable to apply such methodologies to other complex flood studies and catchments. The Hydraulics Assessment is not yet complete with Fast Model Monte Carlo simulations currently underway and Detailed Model calibration being reviewed. The outcomes of the study will be of great interest to many. 2015 Floodplain Management Association National Conference 6

References Aurecon et al (2013), Collection, Collation, Review and Storage of Existing Data FINAL, Prepared for Department of State Development & Infrastructure by Aurecon, Royal Haskoning DHV, Hydrobiology, Deltares, Don Carroll PM as part of the Brisbane River Catchment Flood Study, April 2013. Aurecon et al (2014a), Hydrologic Model Recalibration Report Final Draft, Prepared for Department of State Development & Infrastructure by Aurecon, Royal Haskoning DHV, Hydrobiology, Deltares, Don Carroll PM as part of the Brisbane River Catchment Flood Study Comprehensive Hydrologic Assessment, 15 December 2014. Aurecon et al (2014b), Monte Carlo Simulation Framework and Methodology Draft Final, Prepared for Department of State Development & Infrastructure by Aurecon, Royal Haskoning DHV, Hydrobiology, Deltares, Don Carroll PM as part of the Brisbane River Catchment Flood Study Comprehensive Hydrologic Assessment, 18 December 2014. Aurecon et al (2014c), Draft Final Hydrology Report, Prepared for Department of State Development & Infrastructure by Aurecon, Royal Haskoning DHV, Hydrobiology, Deltares, Don Carroll PM as part of the Brisbane River Catchment Flood Study Comprehensive Hydrologic Assessment, 15 December 2014. BCC (2014a), Brisbane River Catchment Disaster Management Tool Model Development and Calibration Outcomes Final Report, Prepared for Department of State Development Infrastructure and Planning by Flood Management Unit, City Projects Office, Brisbane Infrastructure Division, Brisbane City Council, 19 June 2014. BCC (2014b), Brisbane River Catchment Flood Study Digital Terrain Model Development and Bed Level Sensitivity Analysis Final Report, Brisbane City Council, 268 pages. BCC (2009a), Flood Study of Fernvale and Lowood, Prepared for Somerset Regional Council by Brisbane City Council, June 2009. BCC (2009b), Brisbane River Hydraulic Model to Probable Maximum Flood, Final Report. Brisbane City Council, June 2009. BMT WBM (2010), TUFLOW User Manual, BMT WBM, Brisbane 2010. BMT WBM (2015), Milestone Report 2: Fast Model Development and Calibration, Draft Final, Prepared for State of Queensland, 30 April 2015. Qld FCoI (2012), Queensland Floods Commission of Inquiry, Final Report. March 2012. Ryan, P., Syme, W., Nathan, R., Wong, WT., Onta, P., Brisbane River Catchment Flood Study: 1D Models are Back! Monte Carlo Hydraulic Model Analysis, Floodplain Management Conference, Brisbane, May 2015 2015 Floodplain Management Association National Conference 7