Interconnection Process Queue Reform BPM Evaluation and Discussion IPTF 1/14/16

Similar documents
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation and Transmission Interconnection Process

Generator Interconnection and Deliverability Study Methodology Technical Paper

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

GIP Net Zero Interconnection Service.

Distributed Generation: Frequently Asked Questions

Vectren Integrated Resource Plan (IRP) Stakeholder Meeting 3 of 3. Discussion of Analysis Results September 24, 2014

NTTG Study Plan for the Public Policy Consideration Scenario

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

Levelized Cost of New Electricity Generating Technologies

Appendix C-2. Entergy Services, Inc. June 8, 2016

Full Scale Program for Renewable Energy in Egypt

E N G I N E E R I N G

Our Key Objectives. A free service to Members

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015

AAPG 2011 Annual Convention & Exhibition April 10, 2011

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233

RE-POWERING MARKETS Market design and regulation during the transition to low-carbon power systems

Kyrgyzstan: Power Generation & Transmission

Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration

Brazilian Smart Grid: Regulatory Issues and R&D Projects

Austin Energy Resource, Generation and Climate Protection Plan to 2025: An Update of the 2020 Plan

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

2016/2017 RPM Base Residual Auction Results

Appendix A. Glossary. For Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC

Main variations of business models for Flexible Industrial Demand combined with Variable Renewable Energy

ALL ISLAND GRID STUDY WORK STREAM 4 ANALYSIS OF IMPACTS AND BENEFITS

Demand Response Market Overview. Glossary of Demand Response Services

petratherm Explorer and Developer of Geothermal Energy Renewable Energy 2007 Impetus for Economic Energy Market Transformation REGA Forum

About Southern California Edison

New ISO-NE Return on Equity Rate Could Impact Future Transmission Decisions

Combined Heat & Power. Discussion with Connecticut Energy Advisory Board. February 23, 2010

Deliverability Testing

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

TERMS AND CONDITIONS

Table of Contents. 4 PLAN DEVELOPMENT Plan Objectives Planning Tools Planning Process

Glossary of Terms Avoided Cost - Backfeed - Backup Generator - Backup Power - Base Rate or Fixed Charge Baseload Generation (Baseload Plant) -

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles. Stakeholder Call August 23, :30 a.m. - 12:00 p.m.

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

2015 Integrated Resource Plan Project Quarterly Update November 3, 2014

Ancillary Services and Flexible Generation

RELIABILITY PLANNING CRITERIA

Frequently Asked Questions

HOUSE BILL No Koch, VanNatter

Google s Green PPAs: What, How, and Why

Grid codes for renewable energy integration

Abstract. s: phone: , fax:

Overview on SEA output

Siemens Hybrid Power Solutions. Cost and emission reduction by integrating renewables into diesel plants

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

The Natural Gas-Electric Interface: Summary of Four Natural Gas-Electric Interdependency Assessments WIEB Staff November 30, 2012

Green Industries, Department of Trade and Industry

NARUC International Relations Committee Meeting February 5, 2012 Washington, D.C. Jay Godfrey Managing Director, Renewable Energy

Appendix D. Minimum Requirements For Developmental Resources. For

On June 28, 2011, the Municipal Services Committee recommended that the City Council adopt the recommendations stated in the subject agenda report.

Hybrid Solar and Fossil Power Generation

Steam Turbine Concepts for the Future Volatile Power Market

Commonly asked Question about Green Power, and Kit Carson Renewable Energy Program.

SCHEDULE 1. Scheduling, System Control and Dispatch Service

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

RENEWABLE ENERGY INFEED R Herman, M Malengret and CT Gaunt University of Cape Town, South Africa

Western Power Networks Price Publication - Part E. Support Services Prices for the South West Interconnected System 1 July December 2005

Guidance for U.S. Positions on MDBs Engaging with Developing Countries on Coal-Fired Power Generation 1

Fiscal Year 2011 Resource Plan

Optimal Energy Flow of Integrated Energy Systems with Hydrogen Economy Considerations

Workshop B. 11:15 a.m. to 12:30 p.m.

Potential Cost Impacts of a Vermont Renewable Portfolio Standard. Presented to the Vermont RPS Collaborative

Modelling framework for power systems. Juha Kiviluoma Erkka Rinne Niina Helistö Miguel Azevedo

UTILITY RATE STRUCTURE

Phakwe group. Growing with Africa

European Distribution System Operators for Smart Grids. Flexibility: The role of DSOs in tomorrow s electricity market

Alternative Power Purchase Agreements

Addressing Barriers to Renewable Energy Procurement. In association with the EPA Green Power Partnership

Energy Systems Integration

Electricity Costs White Paper

California s Energy Future

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

STANDARDS FOR INTERCONNECTION OF DISTRIBUTED GENERATION TABLE OF CONTENTS

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Context: significant penetration of DG = increased risks for system security

Addendum Combined Heat and Power Revisions to the CPUC GHG Calculator Revised Report

DESIGNING AUSTIN ENERGY S SOLAR TARIFF USING A DISTRIBUTED PV VALUE CALCULATOR

Q140 Cluster Addendum

G8 - Contracts for Difference Metering

Transmission Planning in the ERCOT Interconnection

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Midwest Reliability Organization Procedure For NERC PRC-012

Solar Power Plant Design and Interconnection

Electric Utility Business Models

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ) Reliability Technical Conference ) Docket No.

Reliability and security of electricity supply: the Italian blackout

Transcription:

Interconnection Process Queue Reform BPM Evaluation and Discussion IPTF 1/14/16

Recap of the Action Items (BPM) from 2015 Develop a study calendar for the future DPP cycles Revise Business Practice manual to align with the revised Tariff Discuss if there is a need to change the existing ERIS criteria (5%/20%) Engage the IPTF to refine reliability analysis requirements Determine the need to revise existing study modeling assumptions, including discussions related to turbine change and repower scenarios Evaluate the potential for creating standard business practices to capture varying TO local planning criteria. Develop templates for System Impact Study and Facilities Studies reports Work with the Transmission Owners to expedite all administrative steps related to Facilities Studies

Study Calendar 1. Currently under development 2. First DPP cycle under new process to begin tentatively on October 17 th, 2016 3. Application Deadline September 2 nd, 2016

Existing ERIS analysis thresholds MISO Initially proposed to reduce the 20% df threshold to a lower percentage Majority of stakeholders seemed opposed to the reduction MISO did not proceed with it during the queue reform efforts, in 2015 Unless there is significant support to reduce the 20% df threshold to a lower value, MISO will not be implementing this change in the BPM

Turbine Change Requirements: Current Practice Turbine change requests for projects already in the queue are allowed IC must submit technical analysis that demonstrates that the electrical performance of the new turbines is either similar or better than the turbine model submitted during the Interconnection Request Application Based on the submitted analysis, MISO will determine if a turbine change would constitute as a Material Modification or whether such change is permissible under the Tariff

Repower: Some questions MISO has heard from ICs How is Repower different than just changing a turbine? I am just changing everything behind the boiler, without changing the turbine/generator. Do I have to go through the Interconnection Process I want to replace a 100MW Wind plant with a 100MW Solar plant I want to replace 50MW, of a 100MW Wind plant, with a 50MW Solar plant I want to retire 500 MW of Coal plant, at Location X, with a 500 MW of Gas at Point of Interconnection X I want to retire 500 MW of Coal plant, at Location X, with a 500 MW of Gas Plant at Point of Interconnection Y. I want to retire 500 MW of Coal plant, at Location X, with a 400 MW of Gas Plant at Point of Interconnection Y.

Repower: General Observations and Comments Change resulting in a reduction in MW size, compared to existing Interconnection Rights, does not have to go through a full blown reliability analysis under the GI process MISO will only study the project for Transient Stability, Reactive Power and Short Circuit, as necessary No need to study project for Steady State thermal analysis from an Att X perspective. Any incremental MW, based on existing Interconnection Rights, must go through the full blown reliability analysis under the regular DPP Studies Existing capacity will get studied for Transient Stability and Short Circuit, as necessary Incremental capacity will get studied for Transient, Short Circuit, Steady State thermal analysis and any other reliability analysis that may need to be performed as part of the regular DPP Studies

Turbine Replacement and Repower: Questions for Stakeholders Should MISO treat Turbine replacement and Repower requests the same way as New Interconnection Request get treated under the GI process? Should Turbine replacement be studied for Steady State Thermal Analysis even if the new/revised Injection MW are lower than the existing Interconnection Rights? Should Repower requests be studied for Steady State Thermal Analysis even if the new/revised Injection MW are lower than the existing Interconnection Rights? Should MISO request M2, M3 and M4 for Turbine Change/Repower projects where there is no increase in MW compared to their existing Interconnection Rights?

MISO BPM and TO LPC alignment 1. Study Models Addition to Peak and Off Peak? 2. Study Criteria ERIS 5% and 20% and Outlet Constraints Transmission Owner Local Planning Criteria 3. Other Study Scenarios Power Transfers Contingency combinations Combination of Power Transfers, Study Models and other

MISO BPM and TO LPC alignment 1. Can MISO and Transmission Owners agree to using the same ERIS thresholds? 2. What additional scenario should MISO study, in addition to Summer Peak and Shoulder Peak that would make is consistent throughout the MISO footprint) 3. Do TOs have LPC just for Generator Interconnections that are different than what would be generally used for Reliability based Planning? 4. Is 1% Steady State Voltage Deviation criteria really required? Is there a better way to capture steady state voltage deviation pre and post contingency?

Facilities Study Coordination with Transmission Owners What do the Transmission Owners require from MISO in order to start work on Facilities Studies next day after MISO handoff? Would an Umbrella Agreement fix the sequential delay shown below? MISO issues the Purchase Order Purchase Order goes through the TO Accounting System TO Billing Code is created TO Project Manager can then start charging for the project MISO will expedite its own process and review any changes needed to the Accounting System

Current NRIS Modeling - What s the problem? 1. Disconnect between NRIS evaluation for Intermittent Resources and associated Capacity Accreditation 2. ICs developing Wind projects may be required to pay for Network Upgrades to achieve 100% NRIS; yet receive only 13% Capacity Accreditation 3. Annual MTEP Deliverability process may identify Network Upgrades that the Transmission Owners have to build for maintaining NRIS rights that can t be counted towards 100% Capacity Accreditation

Opportunity to fix the problem 1. Model NRIS levels for each unit, reflective of the class average for each fuel type, in the DPP System Impact Study Analysis 2. No need to model wind at 100% since capacity accreditation is currently set at 13% (approx) 3. Example: Model an existing 100 MW wind unit at 13 MW under the following Deliverability Study for new projects requesting NRIS MTEP Annual Deliverability Study for maintaining existing NRIS Future Market Transition Deliverability Studies 4. Model new wind projects at the class average capacity accreditation values for NRIS evaluation instead of 100% 5. Existing units with NRIS values above capacity accreditation values will be kept whole from a capacity perspective

Contact Vikram Godbole vgodbole@misoenergy.org Tim Aliff taliff@misoenergy.org Amanda Jones ajjones@misoenergy.org