MS Project Tutorial for Senior Design Using Microsoft Project to manage projects



Similar documents
Introduction to Microsoft Project 2010

OVERVIEW. Microsoft Project terms and definitions

ELECTRO-MECHANICAL PROJECT MANAGEMENT

Microsoft Project 2010

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

University of Sunderland. Microsoft Project. Basic Guide

technical tips and tricks

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

Microsoft Project 2013

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

Creating a New Project

Using Microsoft Project 2000

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Using MS Project in Translation Projects Management

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Planning and Managing Projects with Microsoft Project Professional 2013

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

MS Project 2007 Quick Guide

Microsoft Project 2013 Guide to Task and Resource Planning

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

WBS Schedule Pro. User's Guide

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

technical tips and tricks

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

MS Project 2000 Tutorial: Introduction

Computer Training Centre University College Cork

Microsoft Project 2007 Level 1: Creating Project Tasks

Beginning Microsoft Project

Lab 1 Introduction to Microsoft Project

Laboratory 1 Initiating a Project

Project Initiation and Revision Training Manual. Table of Contents

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Developing a Gantt and PERT Chart

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Managing Projects with Microsoft Project Professional 2013

Revealing the Secrets of Microsoft Project

MICROSOFT PROJECT TUTORIAL

What is a Mail Merge?

Microsoft Office 2010

Pivot Tables & Pivot Charts

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

Project 2010 Introduction

Microsoft Access 2010 handout

Sample Table. Columns. Column 1 Column 2 Column 3 Row 1 Cell 1 Cell 2 Cell 3 Row 2 Cell 4 Cell 5 Cell 6 Row 3 Cell 7 Cell 8 Cell 9.

Open Workbench. User Guide. v2.0.00

PERCEPTION PERT-PAC Using Microsoft Project 2000

Getting Started with Access 2007

Appendix A: Brief Guide to Microsoft Project 2010

Project Management Quick Reference Guide for MS Project 2010

Lesson 07: MS ACCESS - Handout. Introduction to database (30 mins)

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18

Scheduling Document Creation

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Word 2007: Basics Learning Guide

Creating a Database in Access

TILOS GETTING STARTED & EXERCISES

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

Mail Merge Creating Mailing Labels 3/23/2011

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Mac Outlook Calendar/Scheduler and Tasks

POS Connector Installation and Setup Guide

To export data formatted for Avery labels -

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)

Creating Web Pages With Dreamweaver MX 2004

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Step Sheet: Creating a Data Table and Charts

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

5. Creating a Gantt Chart

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

Handout: Word 2010 Tips and Shortcuts

Aras Corporation Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability

Microsoft Excel Basics

Creating Electronic Portfolios using Microsoft Word and Excel

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

Every project requires communication and collaboration and usually a lot of

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider :: :: info@bluepecan.co.

Introduction to Microsoft Access 2007

Intro to Excel spreadsheets

Microsoft Project Activity

ACCESS 2007 BASICS. Best Practices in MS Access. Information Technology. MS Access 2007 Users Guide. IT Training & Development (818)

4.0 - Using the Microsoft Project Plan

Getting Started with Excel Table of Contents

1. INTRODUCTION PRODUCT Installation Documentation Website workbench features...2

MERLIN. The Quick Start Guide to professional project management ProjectWizards GmbH, Melle, Germany. All rights reserved.

Avery Wizard: Using the wizard with Microsoft Word. This is a simple step-by-step guide showing how to use the Avery wizard in word

Open Workbench Warrior. Beginner's Guide to Open Workbench

As in the example above, a Budget created on the computer typically has:

Advanced Presentation Features and Animation

Review on Using Packages to Enhance the Teaching of Critical Path Networks

Microsoft Outlook 2013 Part 1: Introduction to Outlook

Snap 9 Professional s Scanning Module

Basic Formatting of a Microsoft Word. Document for Word 2003 and Center for Writing Excellence

Transcription:

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects in an informal way: they have a deadline to meet, and they monitor progress of the project as it moves along. However, computer resources are available for managing team projects more formally. This tutorial will introduce you to Microsoft Project, a software package that helps to plan and track projects. You will walk through instructions for project planning, and then for project tracking and finally communicating progress. In managing projects, there are essentially two steps: project planning, and project tracking. Projects consist of several tasks, each of a certain duration, that are to be carried out in a certain sequence. Project planning happens at the start of a project; at this stage the team identifies the tasks involved, estimates task duration, and guesses at task sequence. As the project progresses, some of this may change: task sequences may have to be altered, and tasks may take longer or shorter than originally planned. Project tracking involves recording these various changes, and making appropriate changes to the proposed schedule; tracking must take places throughout the life of the project. Tutorial Objectives: Become familiar with features of MS project and project management Opening and saving files Linking tasks Defining tasks Organizing projects Tracking project completion Understanding milestones and comments Using MS project to communicate Initial Steps: To launch Project, double-click on the Microsoft Project icon. When the Welcome! message box is displayed, click on the button next to Start a New Project. The various parts of the Project screen are as follows: Below the menu bar is the tool bar. This contains a number of buttons that can be clicked to carry out certain common operations. Below the toolbar, to the left side of the screen is the Task Table. This looks like a spreadsheet, with information about each task in a row. To the right of the Task Table is the Gantt Chart. Using horizontal bars, the Gantt Chart graphically represents the task schedule.

Project Planning: Project planning involves identifying the tasks involved, their durations, and the relationships among the tasks. Microsoft Project then automatically computes the total project duration and other related information. To enter information about a task, click on an empty cell in the Task Table, type in the name of the task, and press enter. The task name appears in the cell, and a default duration of one day is assigned. To change the default duration, click on the cell in question, type in the correct duration, and press enter. 1. Enter the list of tasks shown below together with their duration: To insert a new task, select in the Task Table the row above which the new task is to be inserted. Choose the Insert Insert Task menu item to insert a blank row in the Task Table. Type in the name of the new task and its duration. 2. Add two new tasks: Project start at the head of the list, and Project finish at the end of the list. Assign them both durations of 0 days. A special kind of task is the milestone. This is usually has a duration of one or zero days, and is used to indicate an event rather than a task. To create a milestone, double-click on its cell in the Task Table. In the resulting Task Information dialog box, choose the Advanced tab and click on the box next to Mark Task as Milestone. 3. Project start and Project finish are milestones in the project we are working on. Mark them as such. You can create hierarchies of tasks: main tasks and their subtasks. To create a hierarchy with a main task and its subtasks, list the subtasks immediately below the main task. Highlight the subtasks, and click on the demote button,, in the toolbar. The highlighted subtasks are indented, and the main task is shown in bold. This action can be reversed by highlighting a subtask and clicking on the promote button, toolbar. To hide the subtasks under a main task, click on the collapse button, toolbar; reverse this action using the expand button,., in the, in the

4. Insert a new task labeled Study phase above Conduct survey and make it the main task containing the subtasks Conduct survey, Collect secondary data, and Analyze data. The Task Table should look as follows: To identify the sequence of tasks, double-click on each task in turn, and designate predecessor tasks: those that logically precede the current task. In the Task Information dialog box, choose the Predecessors tab. As shown in the graphic below, first click on a blank cell under Task Name, then click on the drop button indicated, and from the drop list select the predecessor task. As links are created between tasks, the Gantt Chart will change to reflect these links.

5. Set the predecessors for each task as shown in the graphic below. (The number refers to the ID number of the predecessor task; for instance, task ID 1 is Project Start. To change the timescale of the Gantt Chart, choose Format Timescale... In the resulting Timescale dialog box, set the major and minor scale units as follows: 6. The Gantt Chart should look as follows: To change the appearance of the Gantt Chart, choose Format Gantt Chart Wizard... To display critical tasks, for example: in Step 2, choose Critical Path, and click Next. In Step 9, choose Dates, and click Next. Keep clicking Next in the remaining steps, until you get to click on Format It. Click Exit to close the Wizard. The chart should appear as follows:

The red bars indicate that these tasks are critical: they must be completed on time if the project is not to be delayed beyond the target date. The default relationship between a predecessor and a successor task is as follows: when the predecessor Finishes the successor Starts (FS). This may not be what is desired. Instead, for instance, five days after the predecessor Starts, you may wish to Start the successor (SS, with 5 days lag time). To change the relationship between two linked tasks, double-click on the successor task in the Task Table. In the Task Information dialog box, choose the Predecessors tab. Click on Type cell of the target predecessor. Click on the button with the downward arrow that appears under Predecessors. From the list that drops down, choose the appropriate relationship. In the Lag cell of the predecessor, type in the desired lag time, and press enter. Lag time is the number of days between the finish or start of the predecessor and the finish or start of the successor task; it can be a positive number or a negative number. 7. Set Write proposal to start 5 days after Analyze results starts. Note how the duration of the entire project is reduced. The project has been fast-tracked. Once the initial project schedule has been determined, it has to be recorded as the baseline plan; future adjustments to the schedule will be compared to this baseline. To do this, choose Tools Tracking Save Baseline... In the resulting dialog box, choose Baseline and Entire Project, and click the OK button. (In this dialog box, you can also save upto five different interim project schedules.) The current view (whatever is on the screen) can be either printed (choose File Print Preview and then print) or copied and pasted into a Microsoft Word document: To copy the Chart, first highlight all the tasks that must be included in the picture to be copied. Then, click on the button in the toolbar. In the resulting dialog box, choose For Printer for high-resolution pictures. You can now switch to the other application and paste the picture.

To save the project information, use File Save As for the first time, and File Save for later times. To exit Microsoft Project, use File Exit. Project Tracking: To track projects in Microsoft Project, a distinction is drawn between planned, actual, and scheduled information about tasks. Planned task dates (start, finish, duration) are those that are assigned in the initial schedule that is created. As the project progresses, actual dates are recorded; these may or may not be different from the planned dates. In response to changing circumstances, the project may have to be rescheduled; this new information is recorded as scheduled dates. The three different types of information make it possible to keep track of how a project is progressing with regard to the initial plan. Enter the actual completion data for tasks that are already complete or under way. To do this, click on each task that is complete, and select Tools Tracking Update Tasks... In the Update Task dialog box, type the percentage of work completed or the actual finish date. For this exercise, Identify site finished on 3/13/03; Meet Residents and Collect secondary data are 100% complete; Conduct survey is only 60% complete. Note that there is a bar through each task showing how much is complete. If the project is on schedule, then all tasks finishing before today's date should have a bar extending their whole length. Tasks currently under way should have a bar extending till the current date. Clearly there is a problem with Conduct survey; it is behind schedule. We must adjust our schedule to allow for the slippage. Here is how it can be done: Increase the time allotted to the task so that 60% of the task represents the number of days till today's date. Click on the task Conduct survey, and choose the Tools Tracking Update Tasks... menu item. In the Update Task dialog box, increase the Remaining Duration to 10, and click OK. The task is now going to take longer, but the completion bar is still short of today's date. Choose the Tools Tracking Update Tasks... menu item again, and in the Update Task dialog box, change the % Complete back to 60%. Now, the schedule is approximately as we want it:

Choose a different view to get a better sense of how the project has changed. Choose View More Views... In the More Views dialog box, choose Tracking Gantt Chart (this is the last in the list), and click on Apply. (You will have to change the Timescale as described earlier.) The Gantt Chart now looks as follows: The gray bars are the baseline schedule; the upper bars are the current schedule. The impact of the work slippage is now clearly visible. Communicating Progress: Now that you can manage your schedule with MS project, you need to use it as a communication tool with your group members, customer and instructors. Preview the project before you print it with the print preview icon. You can edit the print view by clicking on page setup at the top menu in the print preview screen. Click the legend subheading and then click none to remove the legend and make more space on the page. To print the document click the Print button in the preview screen, and adjust the dates for printing to 3/4/03 to 5/22/03. Print the project. Other communication with MS project might include adding it to your web site. You can save the file as an HTML document from the save as command. You may also screen capture a portion of your project schedule to add to reports or presentations.

This ends the tutorial. Microsoft Project allows much more powerful planning and tracking of projects including the resources consumed in completing tasks. It also allows charts and reports to be very highly customized.