Mechanical Testing. Tensile Compression Bend Shear Load Structures Fasteners Tensioning & Staying Systems Structural Bearings

Similar documents
PART E SPECIFICATIONS

FALL PROTECTION- Part 2 SELF INSPECTION CHECKLIST

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Technical Notes 3B - Brick Masonry Section Properties May 1993

CONTENTS 1. INTRODUCTION METHODOLOGY RESULTS & FINDINGS...9 APPENDIX

UL 580 TEST REPORT. Rendered to: ARMSTRONG WORLD INDUSTRIES. SERIES/MODEL: MW Vector PRODUCT TYPE: Ceiling System, 3' OC

FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins

PERFORMANCE TEST REPORT. Rendered to: FORMTECH ENTERPRISES, INC. SERIES/MODEL: Truline PRODUCT TYPE: PVC Seawall

Numerical modelling of shear connection between concrete slab and sheeting deck

Solar Mounting System

Connection Solutions

Construction of a Fencing Mask

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

SCAFFOLDING AUGUST making a difference ERECTING, ALTERING AND DISMANTLING PART 1: PREFABRICATED STEEL MODULAR SCAFFOLDING

TEST REPORT. Rendered to: HOMELAND VINYL PRODUCTS, INC. For:

Impact testing ACTIVITY BRIEF

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

Handling, Erection and Bracing of Wood Trusses

Aluminium systems profile selection

Pole Data Sheets (CDN) INFRASTRUCTURE FOR LIFE

MOCK-UP TEST REPORT. Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

INSTALLATION. General. Important Note. Design. Transport

IMPACT DAMAGE RESISTANT WALL SYSTEMS

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

Service life of synthetic fibre ropes in deepwater lifting operations. The 15 th North Sea Offshore Cranes & Lifting Conference Ashley Nuttall

METHOD OF STATEMENT FOR STATIC LOADING TEST

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN

ISC/Singing Tree Rope Wrench (STRW)

Designing with Gabions

AP Physics - Chapter 8 Practice Test

Mechanical arms, belts and sheets

Compression load testing straw bale walls. Peter Walker Dept. Architecture & Civil Engineering University of Bath Bath BA2 7AY.

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

SECTION GUARDA SECURITY WINDOW SCREENS

Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual

CH. 2 LOADS ON BUILDINGS

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

Hilti, Inc South 122 nd East Avenue Tulsa, OK

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

2.0 External and Internal Forces act on structures

6 RETROFITTING POST & PIER HOUSES

Designed and Engineered to Perform

Integrated Manhole Ladder System

Boom and fly capacities for this machine are listed by the following sections:

IAN BENNIE AND ASSOCIATES TEST REPORT NO S2 AWNING WITH FIXED WINDOW PROTOTYPE TEST to AS for. Finesse Window Systems Australia

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

The Collapse of Building 7 by Arthur Scheuerman December 8, 06

Overhang Bracket Loading. Deck Issues: Design Perspective

2.18 INTERIOR & EXTERIOR FINISHES VAPOR & AIR BARRIERS

INSTRUCTIONS FOR USE

TECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Fixed and Portable Ladders- A Guide to OSHA Rules

Dubai Municipality Standard DMS 1: Part 5: 2004

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT

MERCHANTS METALS SECTION ARMORLINK ALUMINIZED CHAIN LINK FENCE AND GATES 2014!

4 Installation Requirements

INTRODUCTION TO LIMIT STATES

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

Testing and appraisal of Lucobit polymer effect as an additive on asphalt mixture performance

Design of reinforced concrete columns. Type of columns. Failure of reinforced concrete columns. Short column. Long column

Prelab Exercises: Hooke's Law and the Behavior of Springs

Research on the meaning of reinforcement ductility for a behavior of double-spans reinforced concrete beam.

APPENDIX H DESIGN CRITERIA FOR NCHRP PROJECT NEW BRIDGE DESIGNS

High Capacity Hot Air Dryer

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS

GYPSUM AREA SEPARATION FIREWALLS GA

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

High Strain Dynamic Load Testing of Drilled Shafts

Robustness testing of external wall insulation systems

ROV shackles. your reliable partner


Reinforced Concrete Slab Design Using the Empirical Method

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24,

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

EDEXCEL NATIONAL CERTIFICATE/DIPLOMA MECHANICAL PRINCIPLES OUTCOME 2 ENGINEERING COMPONENTS TUTORIAL 1 STRUCTURAL MEMBERS

MECHANICAL AND THERMAL ANALYSES OF THE CABLE/ STRAND STRAIN TEST FIXTURE

Chapter 6 ROOF-CEILING SYSTEMS

Pipe Cutting and Beveling Clamshells

Details of the instrument calibration are maintained in laboratory records.

How to Design Helical Piles per the 2009 International Building Code

ALLOWABLE LOADS ON A SINGLE PILE

MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

Post and Beam Construction

Magnetic / Gravity Loading Analysis

The following excerpt are pages from the North American Product Technical Guide, Volume 2: Anchor Fastening, Edition 16.

Hilti KWIK HUS-EZ I (KH-EZ I) Internally Threaded Carbon Steel Screw Anchor

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

EVALUATION OF SEISMIC RESPONSE - FACULTY OF LAND RECLAMATION AND ENVIRONMENTAL ENGINEERING -BUCHAREST

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.

Guide to Fall Protection Regulations

How to secure your property after a disaster

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package

Transcription:

Delivery Address: Postal Address: 1/15 Pickering Road PO Box 5111 Mulgrave Vic 3170 Brandon Park Vic 3150 Telephone: 61 3 9560 2759 Facsimile: 61 3 9560 2769 Email Address: info@melbtest.com.au Web Address: www.melbtest.com.au Mechanical ing Tensile Compression Bend Shear Structures Fasteners Tensioning & Staying Systems Structural Bearings

IN CONFIDENCE TO THE CLIENT REPORT NO: MT-11/498 TESTING OF A TEMPORARY FENCE SYSTEM CLIENT: AAC TEMP FENCE 24 RAMAGE ROAD BUNINYONG VIC 3357 DATE OF TESTING: SEPTEMBER 22 ND SEPTEMBER 27 TH 2011 DATE OF REPORT: SEPTEMBER 30 TH 2011 TEST SYNOPSIS: Temporary fence panels, a number of plastic coated, concrete filled foot blocks, clamping fixtures and bracing members were delivered to the MTS laboratory for testing. Upon arrival at the laboratory the test items were inspected and the following fence identification details were supplied by the client and recorded as: Panels: 2.4m wide x 2.1m high Frame: Nominal 32mm OD diameter Back Braces: Nominal 32mm OD diameter Internal Wire: 160x60x4mm diameter wire, rectangular pattern. Foot Blocks: Weighing nominally 28kg each. L=600mm x W=230mm x D=150mm. FIG.1 FENCE TEST PANEL At the request of the client, tests were to be conducted to determine the performance attributes of individual and assembled fences in accordance AS 4687-2007 TEMPORARY FENCING AND HOARDINGS. The following tests were conducted in accordance Section 4: Simulated Climbing Impact Aperture Force Overturning Page 1 of 5

TEST PREPARATION: Temporary fence panels were prepared for testing in both single panel and continuous panel configurations. Continuous panel testing was conducted on a three panel assembly the middle panel being the focus of the testing. The temporary fencing was assembled using the supplied clamping fixtures and in accordance the manufactures assembly guidelines. SIMULATED CLIMBING TEST: Simulated climbing tests were conducted on a three panel assembly by pulling the top rail of the fence panel vertically downward. A stiffened 400mm lever-arm attached to the centre of the fence panel was used to apply the load (see Fig.2). The downward force was continuously applied until an applied load of 65kg had been achieved. This test load was maintained for a period of 3 minutes. IMPACT TEST: Impact testing was conducted by swinging a pendulum mass into the mesh infill of a braced, single fence panel (see Fig.3). Four test locations, as described in Fig.2 of AS 4687-2007 were selected and tests were conducted at an impact energy level of 150 joules. A visual inspection for damage to the fence panels, mesh infill, and infill/post connection points was conducted after each impact. FOOTHOLD TEST: (a) Aperture Width Aperture width testing was conducted by attempting to pass a 76mm x 76mm test block through a mesh aperture. Measurement of a single mesh aperture was also conducted to determine that the opening was less than the specified dimensional limit of 75mm. (b) Downward To test that the infill mesh had sufficient stiffness to resist an attempt to climb the fence, a downward load of 100kg was applied at one of the rectangular shaped openings (see Fig.4). This load was maintained for 60 seconds at which point the downward deflection of the infill material was recorded. SIMULATED WIND LOAD TEST: load testing was conducted by applying a lateral overturning load to the centre of the panel (see Fig.5). The test load was steadily increased until the footing blocks were observed to have completely lifted from the ground, rendering the fence unstable. At this point the applied test load was maintained and the peak test load recorded. load testing was conducted on unbraced panels as well as panels incorporating a back brace a combination of single and double block support scenarios. FIG.2 CLIMBING TEST FIG.3 IMPACT TEST FIG.4 INFILL DOWNWARD TEST Page 2 of 5

TEST OBSERVATIONS: SIMULATED CLIMBING The fence panels were visually inspected for signs of deformation and failure after completion of the test. No visible sign of permanent deformation or structural failure was observed in the panel or mesh upon completion of testing. The fence panel successfully supported a 65kg test load out overturning. IMPACT TESTING A single fence panel using plastic footings and no bracing, overturned after an impact collision of 150 joules was applied. A single fence panel assembled as above the addition of a single, interlocking back brace revealed the following observations after an impact collision of 150 joules was applied: No penetration of the mesh. No failure between the mesh and post/rail connections. FIG.5 WIND LOAD TEST No visible sign of cracking. No overturning due to impact. Maximum dynamic deflection recorded was 77mm which is less than the specified 300mm. FOOTHOLD APERTURE TESTS (a) Aperture Width The infill aperture horizontal width was measured to be 60mm, less than the specified maximum of 75mm. A test block measuring 76mm x 76mm could not be passed through the rectangular shaped mesh infill. (b) Downward downward load test resulted in a deflection of 5mm, less than the specified permissible maximum of 35mm. SIMULATED WIND LOAD TESTING Simulated wind load testing was conducted on various temporary fence panel erection scenarios including: 1. Panels single back braces fitted single and multiple stacked footings. 2. Panels two (2) back braces fitted single and multiple stacked footings. In each case the tested panels resisted the simulated wind loads out failure of the fence s structural frame work or infill material. ing was conducted to the point where the fence panels were on the verge of tipping. The tipping force was recorded as the peak force and is presented along the calculated equivalent wind speed for each test in Appendix A. Page 3 of 5

SUMMARY Unbraced Panels The test results confirm that an unbraced, AAC Temporary panel, as described and reported herein, meets the minimum requirements as specified in Section 4 of AS 4687-2007 TEMPORARY FENCING AND HOARDINGS for: Simulated Climbing (Clause 4.2) Aperture Width (Clause 4.4.2) Downward (Clause 4.4.3) Simulated Overturning (Clause 4.5) for Region A. A single, unbraced panel plastic footings overturned upon an impact collision of 150 joules. Braced Panels The impact test results confirm that a AAC Temporary panel footings, one interlocking back brace one footing meets the impact test requirements as specified in Section 4 of AS 4687-2007 TEMPORARY FENCING AND HOARDINGS. The wind test results confirm that a AAC Temporary panel fitted footings, one interlocking back brace and a single foot block meets the minimum wind speed requirement for Region A-D as specified in Section 4 of AS 4687-2007 TEMPORARY FENCING AND HOARDINGS. The wind test results confirm that two (2) AAC Temporary panels fitted footings, one interlocking back brace and two foot blocks meet the minimum wind speed requirement for Region A-D as specified in Section 4 of AS 4687-2007 TEMPORARY FENCING AND HOARDINGS. The wind test results confirm that one (1) shade-cloth covered AAC Temporary panel fitted one (1) interlocking back brace and three (3) foot blocks per brace, meets the minimum wind speed requirement for Region A as specified in Section 4 of AS 4687-2007 TEMPORARY FENCING AND HOARDINGS. Notes: 1) shall not be liable for loss, cost, damages or expenses incurred by the client or any other person or company, resulting from the use of any information or interpretation given in this report. In no case shall MTS be liable for consequential damages including, but not limited to, lost profit, damages for failure to meet deadlines and lost production arising from this report. This document shall not be reproduced except in full and relates only to the items tested. 2) This report is specific to the temporary fence panels described herein, in their state at the time of testing. It should not be taken as a statement that all similar temporary fence panel assemblies or components of temporary fence panel assemblies in all states of repair, would also perform in a similar manner to items described herein. 3) MTS shall take no responsibility for the procurement and authenticity of the temporary fencing as described herein. 4) MTS shall take no responsibility for the onsite installation procedures used for the temporary fencing described herein. 5) It remains the responsibility of the client to ensure that the temporary fence panels tested are representative of the entire product batch. 6) speed calculations based on AS/NZS 1170.2 2002 an importance level of 1, terrain category of 2 and topographic multiplier of 1. Page 4 of 5

APPENDIX A Single Panel (mm) (per panel) (per brace) (kn) (m/s) AS 4687 Region None N/A 0.17 15.0 Pass A 1 back brace 1 0.48 24.2 Pass A to D 1 back brace 2 0.78 30.8 Pass A to D 1 back brace 3 1.03 35.4 Pass A to D Rectangular 1 back brace 4 1.31 39.9 Pass A to D Mesh 2 back brace 1 0.83 31.8 Pass A to D 2 back brace 2 1.43 41.7 Pass A to D 2 back brace 3 2.02 49.6 Pass A to D 2 back brace 4 2.41 54.1 Pass A to D With Shade Cloth 1 back brace 3 1.03 18.6 Pass A & B TABLE A1. WIND LOAD TEST DATA FOR SINGLE PANELS Double Panel (mm) (per panel) (per brace) (kn) Rectangular 1 back brace 1 0.65 20.0 Pass A to C Mesh 1 back brace 2 0.95 24.2 Pass A to D With Shade Cloth 1 back brace 4 1.48 15.8 Pass A TABLE A2. WIND LOAD ANALYSIS FOR TWO (2) FENCE PANELS (m/s) AS 4687 Region Triple Panel (mm) (per panel) (per brace) (kn) (m/s) AS 4687 Region Rectangular 1 back brace 1 0.82 18.4 Pass A to B Mesh 1 back brace 2 1.12 21.5 Pass A to C With Shade Cloth 2 back brace 3 2.36 16.4 Pass A TABLE A3. WIND LOAD ANALYSIS FOR THREE (3) FENCE PANELS Four Panel (mm) (per panel) (per brace) (kn) (m/s) AS 4687 Region Rectangular 1 back brace 1 0.99 18.0 Pass A to B Mesh 1 back brace 2 1.29 20.0 Pass A to C With Shade Cloth 2 back brace 4 2.92 15.8 Pass A TABLE A4. WIND LOAD ANALYSIS FOR FOUR (4) FENCE PANELS Page 5 of 5