INTERNATIONAL. Technical journal for piping system integrity and efficiency



Similar documents
contents Group Profile Key Personnel Overview Industry Engineering Telecom Services

Investigations of a Long-Distance 1000 MW Heat Transport System with APROS Simulation Software

Liquid Applied Internal Flow Coatings for Oil Transmission Lines

The Intended Nationally Determined Contribution of the Kingdom of Saudi Arabia under the UNFCCC

A 360 Approach To Optimise Network Efficiency

Advanced gas carburizing technology for the automotive industry

Offshore Forum. How can we optimise off/onshore cost and operation? 28 May 2014

GROUNDWATER RESOURCES MANAGEMENT IN SAUDI ARABIA

WEKO-SEAL Internal Joint Sealing WEKO-SEAL. internal pipe-joint sealing

INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By

PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT?

TECHNICAL INFORMATION ABOUT NATURAL GAS TRANSPORT

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)

FILMTEC Membranes Strategies for Using FILMTEC Elements to Lower Your Total Cost of Seawater Desalination

Making Things Right IFAT Media Dialog

Comparison of multiple port and end port connections for pressure vessels

Concrete Pipes. Concrete Pipes

BEUMER solutions for the

Spiral pipe plants. Tailor-made solutions with measurable benefits

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Appendix A: Acceptable pipe and fitting materials

Design Criteria & Service Goals

Leak detection in virtual DMA combining machine learning network monitoring and model based analysis

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar

ASSET MANAGEMENT STRATEGIES FOR METALLIC MUNICIPAL TRANSMISSION PIPELINES

SOLARPACES: Development of an integrated solar thermal power plant training simulator

CHAPTER 3 STORM DRAINAGE SYSTEMS

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Overview of pipelines in Europe advantages and disadvantages

Innovative Methods to Assess Sewer Pipe Risk and Improve Replacement Planning Decisions

DESIGN CHALLENGES AND OPERATIONAL EXPERIENCE OF A MEGA MED SEAWATER DESALINATION PLANT IN TIANJIN

Optimizing the hydraulic designing of pressurized irrigation network on the lands of village Era by using the computerized model WaterGems

U l t i m a t e e f f i c i e n c y D re D ging

PRESENTATION. Improving the performance of Public Water Utilities A case study of Bangalore N.C. MUNIYAPPA, Chairman, BWSSB LOCATION MAP OF BANGALORE

White Paper.

LNG Monitoring. Fiber-Optic Leakage Detection System. Pipeline leakage detection. Regasification and liquefaction monitoring

Introduction. Chapter The Motivation

Smart solutions for fleets of all types & sizes of power generation. Marcus König, E F IE SGS / September 2013

H i g H E n E r gy, M u lti-stag E, D i ffu s E r type, Bar r E l Cas E, B Oi le r fe E D pu M p

System 800xA Fully automated ESD System for major gas plant increases safety

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

Water Supply. Simulation of Water Distribution Networks. Mohammad N. Almasri. Optimal Design of Water Distribution Networks Mohammad N.

Safer.Smarter.Tyco. Watermist fire protection Technology you can trust

Gas Supplies & Pricing Law

SHELL HAUSWÄRME-STUDIE. Nachhaltige Wärmeerzeugung für Wohngebäude Fakten, Trends und Perspektiven

SWAN. The Value of Online Water Network Monitoring SUMMARY

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Plastics Engineering SYSTEM BEKAPLAST. Mechanically anchored thermoplastic lining for extreme conditions

Guidelines for FEASIBILITY STUDY

Seawater corrosion resistant piping systems for large diameters up to 100 / 2.5 metres O.D.

Asset Management Strategy

Passive Cooling Systems Air Conditioning Without the Need of Energy

AMIPOX GRE Pipe systems. Glass Reinforced Epoxy Pipe Solutions for various Applications

Water Efficiency Self-Assessment Guide from

Real-time energy and water quality management system designed for success!

Company and Product Presentation

ROTEX gas hybrid heat pump. A strong team.

Utilizing Furukawa Optical Fiber Technology. Optical Fiber Sensing System

PIPE REHABILITATION. Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes

Stationary Energy Storage Solutions 3. Stationary Energy Storage Solutions

MAR Sincerely,

Controlling hygienic tank cleaning

A Green Sector Overview

Smart Grids initiative. Electrical Engineering Institute of Renewable Energies Dipl.-Wirtsch.-Ing. Alexander von Scheven 1

PRESSURE PIPE REHABILIATION CIPP TECHNOLOGIES

INTRODUCING PUMPED STORAGE IN LEBANON: TOWARDS A PROSPECTIVE NATIONAL MASTER PLAN

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

ASSET & FACILITIES MANAGEMENT CORPORATE ENERGY EFFICIENCY POLICY

Challenges and Opportunities for Small Businesses Engaged in Energy Development and Energy Intensive Manufacturing

Mechanical Property Changes in Steel during the Pipe Making Process Brent Keil 1

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

DecisionSpace Well Engineering Software

ESBI Carbon Solutions. Partnering with Countries to Achieve their Full Carbon Credit Potential

Real-time Monitoring Platform to Improve the Drinking Water Network Efficiency

Pressure drop in pipes...

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

Water hammering in fire fighting installation

Force Main Condition Assessment: New Technologies & Case Studies

Managing sewer flood risk

PE-80 Pipe Systems: 17 Years of Successful Application in the Public Sewer Network of Göttingen

Water and Renewable Energy Resources in the Red Sea Region. Eng. Sayed Mansour Eng. Mahmoud Eisa

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

Thermodynamic and Kinetic Hydrate Inhibition Performance of MEG Solution and its Synergistic Inhibition with PVCap

Water Security and Desalination in the GCC Countries. Dr. Muhammad F. Al Rashed Executive Director Water Research Center

Mallnow Natural Gas Compressor Station. Climate-friendly gas supply

METHOD OF STATEMENT FOR STATIC LOADING TEST

A comprehensive range

HEAVY DUTY SEVERING AND BEVELLING MACHINE TNO FAB-SERIES

Special Linings for unusual service conditions. Please contact ACIPCO.

Amir Bashirzadeh Tabrizi, Nassir Gifani. TOOSSAB Consulting Engineers Company

Hashemite Kingdom of Jordan Ministry of Water and Irrigation. Water in Jordan: Water security and protection

Corporate Profile ROYAL. MODERN ROYAL ELECTRIC Ideal Power Solution MRE ELECTRICAL, INSTRUMENTATION & COMMUNICATION SYSTEMS

SECTION 3 SANITARY SEWER DESIGN

All Products Brochure

Project Finance in Saudi Arabia

Transcription:

INTERNATIONAL Technical journal for piping system integrity and efficiency Special 2/2011 ISSN 0340-3386 K 1252 E Vulkan-Verlag, Essen, Germany Special Issue: Water & gas distribution Sewer systems Rehabilitation Innovations and Technological Developments in Long Distance Water Transmission Systems Case Study of Riyadh, Saudi Arabia By Bernhard Lässer and Alexander Heinz

Innovations and Technological Developments in Long Distance Water Transmission Systems Case Study of Riyadh, Saudi Arabia By Bernhard Lässer and Alexander Heinz Summary: Cities in arid and semi-arid climatic conditions very often depend on reliable and economic water transmission schemes to import water from distant places. With the first Riyadh Water Transmission System, ILF Consulting Engineers had adopted an innovative design approach by applying a closed hydraulic, high pressure system. This design approach was then further developed taking also advantage of the more recent developments in pipe material and equipment design. In order to reduce the investment and operation costs of water pipeline systems, without compromising safety and ease of operation, the design philosophy has been adopted by ILF to numerous water pipeline systems worldwide, providing the optimised solution for each project. Introduction The development of cities in arid and semi-arid climatic conditions with increasing population and industrial activity depend on a reliable and economic potable water supply. Very often the water has to be transported to the consumers from distant locations through water transmission pipeline systems. Riyadh, the capital of the Kingdom of Saudi Arabia, is characterized by its arid climate location with very low rainfall of only 116 mm average per annum. Due to the energy richness of the country and the associated rise in living standards, the continuous population growth and a rapidly growing industry, the demand for drinking water has steadily increased. In the late 1970s the demand could no longer be covered with supply from ground wells in the wider area of Riyadh. Hence other supply options for the city located at 613 m above sea level and about 400 km from the coast had to be considered. As a result, the construction of a seawater desalination plant at Al-Jubail on the Gulf Coast and the largest long-distance water transport system, the Riyadh Water Transmission System (RWTS) was then completed. This major project was at that time designed and implemented with very innovative approaches. Since its completion in 1983 the system has been expanded and further technical advancements have been applied. ILF Consulting Engineers have been significantly involved as Owner s Engineer for the customer, Saline Water Conversion Corporation (SWCC) in all phases of the projects. This article provides an outline about the innovations applied for the first project and the further developments implemented in the extension phases. FIGure 1: Pipeline routes Special-Edition 2 / 2011 15

Water & Gas Distribution FIGure 2: Open pipeline system FIGure 3: Closed pipeline system Technical Innovation RWTS Line A + B The first pipeline system to deliver desalinated water from the Arabian Gulf to Riyadh was Line A + B with 466 km length running from Jubail to Riyadh (see Figure 1). The system was designed as a hydraulically closed high pressure system. At this time such an approach was not common since traditionally water pipeline systems had been designed as open systems (for comparison see Figures 2 and 3). The closed system design required to develop special hydraulic software tools to study the system behaviour under all normal (steady state) and abnormal (transient) operation conditions as well as the installation of surge protection equipment. At that time recognised university professors predicted that the design will fail. This innovative and optimised design approach enabled to lower the investment costs as well as specific transportation costs and higher reliability could be achieved compared to conventional systems. By adaption of the closed system approach the number of pumping equipment could be considerably reduced since no intermediate tank capacity and booster pumps are required at the five intermediate pumping stations. In addition the related piping and electro-mechanical equipment associated with these tanks and booster pumps could be eliminated, leading to a more efficient mode of operation and lower energy consumption as well as lower maintenance cost. The system was designed as a 60" twin carbon steel pipeline with cement mortar lining and six pumping stations with a total installed power of 430 MW. Different pipe steel grades along the line, well distributed according the calculated pressure requirements, reaching up to X60 with a minimum pipe wall thickness and a wall thickness / diameter ratio of 1% were selected to mini- FIGure 4: Construction works of RWTS Line A + B FIGure 5: Pumping Station of RWTS Line A + B 16 2 / 2011 Special-Edition

Conical ring coupler KM-XL d 1000 d 1200 mise the investment. The system was designed for a maximum throughput of 830,000 m³ / day. RWTS Line A + B has been in operation with full capacity since its completion in 1983 without any major shut down. The investment cost was about 1.6 billion US$. For a tabulation of the technical data see Table 1 and for pictures see Figures 4 and 5. Summarising the following innovations had been implemented in RWTS Line A + B: Closed hydraulic system High pressure system with operating pressure up to 52 bar Wall thickness / diameter ratio of 1 % Line pipe diameter 60" spiral welded Material grade well distributed T-Pieces d 250 d 400 Elbow 90 d 250 d 315 Developments RWTS Line C To expand the capacity of RWTS Line A + B a new system had been implemented, called Line C, which is an independent system. A more direct route of 375 km along the new Dammam - Riyadh highway could be chosen (see Figure 2). The system was implemented as a 60" steel pipeline with cement mortar lining and four pumping stations with total installed power of 150 MW. The maximum throughput is 380,000 m³ / day. Line C was commissioned in 1995 and is in operation to this day. The investment cost was 400 million US$. Ras Al Khair-Riyadh (Line D + E) Currently there is a further system Ras Al Khair-Riyadh (Line D + E) under execution, linking the new desalination plant at Ras Al Khair approximately 100 km north of Jubail with a direct route through the desert to Riyadh (see Figure 2). The optimised system configuration chosen consists of a double carbon steel line with 72" diameter and steel grades up to X65 with three pumping stations with a total installed power of 271 MW. A simplified hydraulic profile is displayed as Figure 6. The maximum throughput is 947,000 m³ / day. The system shall be put in op- FRIALEN XL Safe joining technology on a grand scale Comprehensive product and service portfolio for an optimal and quick joining of large pipelines made of HD-PE Spigot saddles SA-XL d 315/225 d 1000/160 Repair saddles RS-XL d 250 d 1000 FIGure 6: Simplified hydraulic profile of Ras Al Khair - Riyadh Special-Edition 2 / 2011 info-frialen@friatec.de www.friatec.com 17

Water & Gas Distribution FIGure 7: Pipeline installation works of Ras Al Khair - Riyadh eration in 2013 and the investment will be around 2.5 billion US$. For a tabulation of the technical data see Table 1 and for pictures see Figure 7. Whilst the design of Line A + B can be considered as a real innovation in water pipelines at that time in terms of efficiency and operational security, for the following projects the system layout was further enhanced taking advantage of the more recent development in pipe production and welding technology as well as availability of enhanced mechanical equipment. The following developments were included in the later projects: Increase in design pressure for mechanical equipment and pipes Wall thickness / diameter ratio of 0.77 % Steel grades up to X65 (limited as per availability in KSA) Pipe diameter up to 72" Reduced number of pumping stations Optimisation of Water Pipelines The aim of the optimisation during the design stage of a water pipeline project is to minimize the investment and operating costs for a given operating period of the system while not compromising on safety, reliability and ease of operation of the system. All such requirements are to be considered adequately with the aim to achieve the lowest possible specific transportation costs under the given boundary conditions. The lowest specific transportation costs are a result of the best balance of low investment for material and construction, low energy consumption, low operation and maintenance cost and high availability of the system. It is for this reason that the designer of a water transmission system must be aware of the fact that appropriate decisions can only be taken after thorough financial analysis. In general, the following criteria provide the basis for a comparison on pipeline system alternatives from the economic point of view: Minimum cost for construction and operation Minimum energy consumption Minimum unit cost per cubic meter of liquid transported Maximum reliability of the pipeline system In addition it has to be emphasised that in practice the time value of money with a view to interest paid for the use of money is a factor which has a great impact on the total cost of a project. The interest rate quite frequently proves to be the predominant factor, especially in projects with low operating costs but high capital requirements. The comparison of costs is based on the Net Present Value Method or Discount Method which is used to obtain comparative costs. The present value of all expenditures in the past and in the future will be determined for one definite point in time (see Figure 8). The objective of a pipeline optimization is to develop the best system (number and sizing of required pumping stations, single or twin pipeline system) and the optimum pipe diameter at which the material and construction cost of the system added to the operating cost (power consumption, maintenance, etc.) will be at a minimum for a definite period of time and throughput scenario (see Figure 9). The following items are used as variables within the possible technical limits and the specific transportation costs are compared for all options: TAB. 1: Comparison of technical data System length km throughput m 3 /d dia. main line pump stations/ installed power RWTS Line A + B 466 830,000 2 x 60" 6 nos. 430 MW RWTS Line C 375 380,000 60" 4 nos. 150 MW Ras Al Khair-Riyadh (Line D + E) 374 + 92 947,000 2 x 72" 3 nos. 271 MW line pipe material year of completion invest in mil. US$ Grade B to X60 1983 1,600 Grade B to X60 1995 400 Grade B to X65 2013 plan. 2,500 18 2 / 2011 Special-Edition

FIGure 8: Net present value method FIGure 9: Pipeline diameter optimisation Longitudinal profile of the pipeline (elevation profile, pipeline routes, etc.) Pipes (available diameter, wall thickness, steel grades, number of lines, pipe roughness, etc.) Throughput rates Discount method (time points for investments, optimization period, interest rates, etc.) Energy costs Maintenance costs Other design parameters (safety factors, special design boundaries like fixed locations, etc.) Conclusion The innovative design approach chosen by ILF Consulting Engineers has proven to be successful and has then been further enhanced over the last thirty years on various projects worldwide. Now with the long term operational experience of the RWTS and several systems in other countries, the used technology proved to be reliable and efficient. www.ilf.com The results for system configurations with different pipe diameters may be indicated graphically by two curves (CAPEX & OPEX) with varying gradients. The sum of those two curves finally represents the most economic diameter for the pipeline system for the considered time period (see Figure 9). Authors E N G I N E E R I N G E X C E L L E N C E Your Ultimate Partner for Infrastructure and Energy Projects Dipl.-Ing. MBA Bernhard Lässer ILF Consulting Engineers, Munich Germany Tel. +49 89 255594-0 E-mail: bernhard.laesser@ilf.com Dipl.-Ing. Alexander Heinz ILF Consulting Engineers, Innsbruck Austria Tel. +43 512 2412-0 E-mail: alexander.heinz@ilf.com ILF Consulting Engineers ranks among the world s leading engineering firms in the areas of its core expertise. We offer comprehensive design, engineering and consulting services in the following areas: Water & Environment Oil & Gas Energy & Climate Protection Transport & Structures ILF Beratende Ingenieure ZT GmbH Feldkreuzstrasse 3 6063 Rum / Innsbruck, Austria Phone: +43 / 512 / 2412-0 Fax: +43 / 512 / 2412-5900 Email: info@ibk.ilf.com ILF Beratende Ingenieure GmbH Werner-Eckert-Strasse 7 81829 Munich, Germany Phone: +49 (89) 25 55 94-0 Fax: +49 (89) 25 55 94-144 Email: postmaster@ilf.com Special-Edition 2 / 2011 19