How To Test For Strength

Similar documents
A Simple Method of Gripping Prestressing Strands for Tension Tests

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

METHOD OF STATEMENT FOR STATIC LOADING TEST

TEST REPORT. Rendered to: LMT-Mercer Group, Inc. For: PRODUCT: 4" x 4" and 5" x 5" PVC Porch Posts with Aluminum Reinforcing

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

1.2 Advantages and Types of Prestressing

MAINTENANCE AND INSPECTION OF BRIDGE STAY CABLE SYSTEMS

Evaluating. A Case Study

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

Measuring the Condition of Prestressed Concrete Cylinder Pipe

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

DIGITAL DISPLACEMENT RISING STEP LOAD LRA/RSL TEST EQUIPMENT

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM

C E L CONSULTING A D I V I S I O N O F C O N S O L I D A T E D E N G I N E E R I N G FOR THE

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

Step 11 Static Load Testing

SECTION GUARDRAILS

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

SEISMIC REHABILITATION OF COLUMN TO PIER CAP ACCELERATED BRIDGE CONSTRUCTION CONNECTIONS AND ACOUSTIC EMISSION MONITORING ASSESSM ENT

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Impact Echo Scanning Technology for Internal Grout Condition Evaluation in Post-Tensioned Bridge Ducts

TEST REPORT. Rendered to: INTEX MILLWORK SOLUTIONS, LLC. For: Rigid Cellular PVC Guardrail System Hampton RS40

SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE

Method Statement for Static Load Testing (Compression) for Micropiles

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

SERIES NG 1800 STRUCTURAL STEELWORK

Detailing of Reinforcment in Concrete Structures

PERFORMANCE TEST REPORT. Rendered to: FORMTECH ENTERPRISES, INC. SERIES/MODEL: Truline PRODUCT TYPE: PVC Seawall

TZ WEDGE ANCHOR FOR CRACKED AND UNCRACKED CONCRETE

GUARDRAIL POST STEEL

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

CORROSION PERFORMANCE OF PRESTRESSING STRANDS IN CONTACT WITH DISSIMILAR GROUTS

There are as many reasons to test metals as there are metals:

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

T A B L E T 1 T E S T S A N D I N S P E C T I O N C A B L E P C U T A N D P C U T - A

Structural Bolting. Notice the Grade 5 has a much smaller head configuration and a shorter shank then the A325 structural bolt. Rev.

The Effects of Hole Cleaning on Post-Installed Anchor Systems in Concrete

DYWIDAG-SYSTEMS INTERNATIONAL. DYWIDAG Barrier Cable System. Glendale Galleria Parking Structure, Glendale, California

BRIDGE DESIGN SPECIFICATIONS APRIL 2000 SECTION 9 - PRESTRESSED CONCRETE

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

Value Engineering vs. Alternate Designs in Bridge Bidding

SECTION PRECAST CONCRETE UTILITY STRUCTURES

PART E SPECIFICATIONS

Objectives. Experimentally determine the yield strength, tensile strength, and modules of elasticity and ductility of given materials.

Using Williams Products

APE T CFRP Aslan 500

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

Two-Way Post-Tensioned Design

Prestressed Storage Tanks

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

Installation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: No.: SE-...

Hilti, Inc South 122 nd East Avenue Tulsa, OK

SECTION 1 GENERAL REQUIREMENTS

Material property tests of Smooth-on Vytaflex60 liquid rubber

Series Direct Load Creep Testing Systems. Maximum Reliability at Minimum Cost

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

Hardened Concrete. Lecture No. 14

ICC-ES Evaluation Report

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

PCI BIG BEAM COMPETITION

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

The Stabilizer TM. Benefits. Supplemental support system for sagging beams and floor joists within a crawl space

REPAIRS, MODIFICATIONS, AND STRENGTHENING WITH POST-TENSIONING

MATERIALS AND MECHANICS OF BENDING

Submittal Information

Working at Heights and Fall Protection

Pressure Vessel Assessment Report

Hilti KWIK HUS-EZ I (KH-EZ I) Internally Threaded Carbon Steel Screw Anchor

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Wastewater Capital Projects Management Standard Construction Specification

Embedded Parts Introduction - Anchors

Why HARDOX in tipping trailers?

Stay Cable Replacement of the Luling Bridge

Pent Up Load and Its Effect on Load Test Evaluation

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Structural welding is a process by which the parts that are to be connected are heated and

Repair or Replacement - Band-Aids vs. Surgery

The Strength of Concrete

Torsion Tests. Subjects of interest

Tensile Testing Laboratory

Type of Force 1 Axial (tension / compression) Shear. 3 Bending 4 Torsion 5 Images 6 Symbol (+ -)

Retrofitting By Means Of Post Tensioning. Khaled Nahlawi 1

Implosive Connectors. for overhead transmission lines

FLEXURAL BEHAVIOUR OF HYBRID FRP-UHPC GIRDERS UNDER STATIC LOADING

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

Stress Strain Relationships

TEST REPORT. Rendered to: FAIRWAY BUILDING PRODUCTS, LP. For: LandMarke Railing System. PVC Guardrail System "Patent Number 7,487,941"

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality

The pretopped double tee is a very common precast,

Hilti, Inc South 122 nd East Avenue Tulsa, OK

Transcription:

Tensile Test Results of Post Tensioning Cables From the Background The Midbay bridge, located on State Road 293 between State Road 2 and U.S. 98 in Niceville, Florida is a concrete segmental box bridge with approximately 14 spans. The bridge uses a total of six external post-tensioning cables as the primary live load resistance system, with three of the six cables on either side of the boxes. Each cable is composed of 19.6 diameter steel cables that are stressed to 31, pounds each at the time of construction. The cables are held in place between steel anchors and surrounded by a protective sleeve. The primary anchorage system consists of end steel blocks with post-tensioning wedges, while the secondary anchorage system relies on a grout that is pumped into the casing surrounding the strands. An inspection of the post-tensioning system during the year 2 revealed that a significant number of these cables were exhibiting signs of corrosion and possibly, improper grout. The corrosion has been speculated to have been caused by trapped moisture in voids where grout should have existed. Inspection using a borescope inserted into a hole drilled through the anchorage assembly revealed that several wires in various individual strands have ruptured and others have had some level of corrosion. Objective A request was made to the Structural Research Center to test the strands from one of the corroded cables to determine the tensile capacity remaining for the reinforcement. Test Method The AASHTO Standard Method of Test for Mechanical Testing of Steel Products, designation T 244-92 (ASTM Designation A 37-92) was followed to determine the tensile properties of the strands. More specifically, section A7 of the procedure Method of Testing Uncoated Seven-Wire Stress-Relieved Strand For Prestressed Concrete was referenced directly for the test procedure. 1

Specimens Two portions of cables were removed from the bridge and transported to the Structural Research Center in Tallahassee. The first portion was reported to be a damaged cable with significant corrosion on various strands. The cable was cut approximately 15 from the anchorage end and removed from the bridge. The second portion consisted of strands that were reported to be in acceptable condition with no sign of corrosion and chosen to be used as control specimens. Visual inspection of the anchorage assembly revealed corrosion of the anchor wedges, both inside the grip area and between the anchorage plate and the wedges (See Photos 1 3). No sign of slip was apparent in the wedges. The strands that were still connected to the anchorage assembly had enough corrosion to cause pitting of the steel surface for approximately the first 8 of length outside the anchor region (See Photos 4 7). The strands were removed from the anchor plate preserving the entire length of the cable that was provided to the. Each corroded cable was cleaned using an abrasive pad to determine the extent of the pitting. In all cases the deepest pitting reached a maximum average depth of.15. Test procedure The strands were cut to a length of 6 and gripped using a post tensioning anchor with a universal chucking device. Steel sleeves were inserted between the chucks and inserted in the V-Grip assembly of the load frame. This sleeve insures that hydraulic gripping pressure from the load frame is not directly applied to the specimen. The combination of steel sleeve and chucks leaves a 36 gauge length exceeding the minimum requirement of 24 stipulated by AASHTO (See Photos 8-12). Several individual wires were instrumented with electrical resistance strain gauges at the center of the gauge length. The steel assembly was placed in the gripping portion of an MTS-55 universal material testing system load frame. This load frame is capable of applying a force of 55 kips in tension or compression and is fully controllable in terms of load rate, whether through displacement or load control to satisfy the requirements of the testing procedure. Following the AASHTO test procedure, each strand was loaded to approximately 1 percent of the expected minimum breaking strength of the specimen, which was assumed at 5 kips, prior to beginning the test. The load rate was set at 125µε/second and proceeded until rupture of the specimen. The load, stress and strain were all monitored using a high speed data acquisition system with readings being taken twice every second throughout the duration of the test. The instrumentation used was as follows: 1 A minimum of two electrical resistance strain gauges with an accuracy of ±5 µε and a maximum elongation of 2, µε. 2

2 The load frame load cell with an accuracy of ±5 lbs with the most recent calibration occurring in June 2. All instruments used in the test are standard instruments used by the Structural Research Center on a regular basis and have proven to be highly accurate and reliable. Test Results The following table summarizes the results observed during the test: Specimen Number Initial Condition Yield Strength f y (ksi) Ultimate Strength f u (ksi) CONT-1 OK Control Specimen 246.6 279.4 CONT-2 OK Control Specimen 244.7 278.8 CORR-1 light pitting, corrosion 245.9 248. CORR-2 light pitting, corrosion Not achieved 24.7 CORR-3 light pitting, corrosion Not achieved 24.4 CORR-4 mild corrosion 253.1 264.4 CORR-5 light pitting, corrosion 24.1 25.7 CORR-6 light pitting, corrosion 246.1 246.8 CORR-7 light pitting, corrosion 245. 245. TABLE 1 Test Result Summary F y, according to the AASHTO test procedure is achieved at a 1% extension of strain or 1, µε. For specimens CORR-2 and CORR-3, this extension is not achieved until after rupture of the first wire, which is defined as failure for the specimen. The average results are as follows: Specimen Type Yield Strength f y (ksi) Ultimate Strength f u (ksi) Control 245.65 279.1 Corroded 246.4 * 248. TABLE 2 Test Result Averages * Note: The value reported in this table of yield strength for the corroded strands does not include specimens CORR-2 and CORR-3 since they did not achieve the requirements of the AASHTO test procedure. Additionally, note should be made that specimen CORR-7 fails at the yield point (See Figure 9). 3

For the corroded specimens, failure always occurred within the pitted portion of the strand, with the exception of Specimen CORR-4, which failed in a manner similar to that of the control specimens. Photos 13 18 show the condition of the strands at failure for all corroded specimens except CORR-4. Figures 1 9 show the stress vs. strain relationship for each of the strands tested. Note that the ultimate strength for the control specimens can not be shown on the plot since it occurs at an elongation far beyond the capacity of the measurement device. 4

Photo 1 End View of Anchor Plate Photo 2 Side View of Anchor Plate Photo 3 Anchor Wedges With Corrosion Photo 4 Close-up Of Pitting Corrosion Photo 5 Pitting Corrosion Photo 6 Strand Ends After Removal From Anchor 5

Photo 7 Strand After Removal From Wedge Photo 8 Insertion of Specimen in Chucks Photo 9 View of Chucked Specimen Photo 1 Chucked Specimen With Blocking Sleeve Installed Photo 11 Blocking Sleeve Being Placed Into V-Grips Photo 12 Specimen in Load Frame 6

Photo 13 Failure of Corroded Specimen # 1 Photo 14 Failure of Corroded Specimen #2 Photo 15 Failure of Corroded Specimen #3 Photo 16 Failure of Corroded Specimen #5 Photo 17 Failure of Corroded Specimen #6 Photo 18 Failure of Corroded Specimen #7 7

3 25 2 15 f y= 246.6 ksi f u= 279.4 ksi 1 5 Figure 1 - Stress vs. Strain Specimen CONT-1 3 25 2 15 f y = 244.7 ksi f u= 278.8 ksi 1 5 Figure 2 - Stress vs. Strain Specimen CONT-2 8

3 25 2 15 f y= 245.9 ksi f u= 248 ksi 1 5 Figure 3- S tress vs. S train Specimen CORR-1 3 25 2 15 f = 24.7 ksi u 1 5 Figure 4 - S tress vs. S train Specimen CORR-2 9

3 25 2 15 f = 24.4 ksi u 1 5 Figure 5 - S tress vs. S train Specimen CORR-3 3 25 2 15 f y= 253.1 ksi f u= 264.4 ksi 1 5 Figure 6 - S tress vs. S train Specimen CORR-4 1

3 25 2 15 f y= 24.1 ksi f u= 25.7 ksi 1 5 Figure 7 - S tress vs. S train Specimen CORR-5 3 25 2 15 f y= 246.1 ksi f u= 246.8 ksi 1 5 Figure 8 - S tress vs. S train Specimen CORR-6 11

3 25 2 15 f y= 245. ksi f u= 245. ksi 1 5 Figure 9 - S tress vs. S train Specimen CORR-7 12