Introduction. The information is presented with concerns of a construction manager or general contractor in mind. 2

Similar documents
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Figure Test set-up

Technical Assignment 2 TABLE OF CONTENTS

STRUCTURAL STEEL DESIGN AND CONSTRUCTION. Gary S. Berman, PE GREYHAWK North America, LLC. GREYHAWK North America, LLC

Steel joists and joist girders are

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP

Figure A. Maximum load testing of new precast concrete floor plank system

2. Division 05 Structural Steel Framing for steel framework requirements

[TECHNICAL REPORT I:]

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/ Stud Welding

Breakaway Walls

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

How To Design A Post Tensioned Deck For A Building

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

King Post Wall Information

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center

METHOD OF STATEMENT FOR STATIC LOADING TEST

COMPOSITE SLABS AND BEAMS USING STEEL DECKING: BEST PRACTICE FOR DESIGN AND CONSTRUCTION

Index Series Prestressed Florida-I Beams (Rev. 07/12)

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Analysis II Façade Redesign: Architectural Precast Panels

Installation PowerPoint for Grasscrete Formers

STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES

Formwork for Concrete

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

APPENDIX H DESIGN CRITERIA FOR NCHRP PROJECT NEW BRIDGE DESIGNS

DENVER MODEL 30 X 30 SPECIFICATIONS

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Overhang Bracket Loading. Deck Issues: Design Perspective

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

Hunter College school of Social Work Thesis Proposal

Basics of Reinforced Concrete Design

SECTION COLD-FORMED METAL DECK FRAMING Elevations Steel Deck Framing by Trex

Residential Deck Safety, Construction, and Repair

Structural Failures Cost Lives and Time

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

Page & Turnbull imagining change in historic environments through design, research, and technology

FORM DESIGN. easy to work with, and generally available.

Field Welding Inspection Guide

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

9.3 Two-way Slabs (Part I)

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

Joist. Reinforcement. Draft 12/7/02

Code of Standard Practice for Timber Frame Structures

Elevating Your House. Introduction CHAPTER 5

How To Understand The World Trade Center'S Structural Design

STEEL. the healthcare structure PrototyPe ii. structural. Exploring Castellated Composite Framing. Your connection to i e n er

TECHNICAL BULLETIN. Oil Canning in Metal Roof and Metal Wall Systems. What Is Oil Canning?

EAST LYME HIGH SCHOOL

Construction Laborer Dies after Falling off Collapsed Precast Concrete Floor Slab

1.02 SYSTEM DESCRIPTION

CH. 2 LOADS ON BUILDINGS

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Civil Engineering and Architecture (CEA) Detailed Outline

STANDARD OPEN PATIO COVER

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Safe & Sound Bridge Terminology

Bridge Type Selection

Optimising plate girder design

Operations and Instruction Manual Might Swivel - Part # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn

6 RETROFITTING POST & PIER HOUSES

In-situ Load Testing to Evaluate New Repair Techniques

SECTION 1 GENERAL REQUIREMENTS

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Weld Cracking. An Excerpt from The Fabricators' and Erectors' Guide to Welded Steel Construction. The James F. Lincoln Arc Welding Foundation

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

High Strain Dynamic Load Testing of Drilled Shafts

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

Composite Construction with KÖCO- Stud Welding Technology IMPRESSIVE TECHNOLOGY 6/

MEZZANINE SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Quality Control and Quality Assurance Guide

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

The Analysis of Open Web Steel Joists in Existing Buildings

SERIES NG 1800 STRUCTURAL STEELWORK

Investigation of the November 2, 2013 collapse of concrete beams at Fort Lauderdale-Hollywood Airport runway project

Roof Deck Installation Guidelines

Precast Concrete Parking Structures

Scheduling Estimating Module

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

Chapter 3 Pre-Installation, Foundations and Piers

COLORADO MODEL. 35 x 65 SPECIFICATIONS

UL Online Certifications Directory

Design No. P736 September 26, Restrained Assembly Ratings 1, 1-1/2 or 2 Hr. (See Items 3, 7 and 8A)

Professional Engineers Providing Structural Engineering Services In Buildings

The ACR : Advanced Design Features for a Short Construction Schedule

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

PART 1 GENERAL 1.1 SECTION INCLUDES

bi directional loading). Prototype ten story

Transcription:

1 Introduction This presentation was developed as a teaching aid with the support of the American Institute of Steel Construction. Its objective is to provide technical background and information for composite construction and cambering. The information provided is based on common design and construction practices for structures of twelve stories or less. The AISC Digital Library case study presentations document the construction of a steel frame for an office building. The case study includes photographs that were taken throughout the construction of the structural steel frame including detailing, fabrication, and erection. Project data including plans, schedules, specifications and other details are also included. The case study presentations are available in the Learning Opportunities section at www.aisc.org. This presentation goes a step further in detail in the areas of composite construction and cambering. A more in-depth background is provided and impacts of the details and design choices on schedule, cost, sequence and overall project management are addressed. The information is presented with concerns of a construction manager or general contractor in mind. 2 1

What Will You Gain From This Presentation? General knowledge of structural steel Knowledge of the details of composite steel construction, the components that are used, and how they are installed An understanding of the impacts that composite steel construction may have on project schedule, cost, sequence and overall management Insight into the process of creating camber and why cambered beams are used Familiarity with situations where cambered beams should and should not be used, and how using cambered beams might affect a project 3 Benefits of Structural Steel Some benefits associated with use of structural steel for owners are: Steel allows for reduced frame construction time and the ability to construct in all seasons Steel makes large spans and bay sizes possible, providing more flexibility for owners Steel is easier to modify and reinforce if architectural changes are made to a facility over its life Steel is lightweight and can reduce foundation costs Steel is durable, long-lasting and recyclable (AISC 1999) 4 2

Unique Aspects of Steel Construction Procurement and management of structural steel is similar to other materials, but there are some unique aspects to steel construction: Steel is fabricated off-site (above left) On-site erection is a rapid process (above right) This gives use of structural steel some scheduling advantages Coordination of all parties is essential for achieving potential advantages (AISC 1999) 5 6 3

Introduction to Composite Construction Composite construction refers to two load-carrying structural members that are integrally connected and deflect as a single unit An example of this is composite metal deck with concrete fill, steel filler beams, and girders made composite by using headed stud connectors 7 Introduction to Composite Construction A steel beam which is made composite by using shear connectors, composite metal decking and concrete is much stronger and stiffer than the base beam alone Composite floor systems are considered by many to be the highest quality type of construction This has become a standard type of construction selected by many architects, engineers, and developers (AISC 1991) 8 4

Advantages of Composite Construction In a composite floor system the concrete acts together with the steel to create a stiffer, lighter, less expensive structure (Allen 1999) 9 Advantages of Composite Construction Connecting the concrete to the steel beams can have several advantages: It is typical to have a reduced structural steel frame cost Weight of the structural steel frame may be decreased which may reduce foundation costs Reduced live load deflections Shallower beams may be used which might reduce building height Increased span lengths are possible Stiffer floors 10 5

Disadvantages of Composite Construction The additional subcontractor needed for shear connector installation will increase field costs Installation of shear connectors is another operation to be included in the schedule A concrete flatwork contractor who has experience with elevated composite slabs should be secured for the job 11 Metal Decking Composite decking works together with the concrete fill to make a stiff, light-weight, economical floor system Compare the composite decking (above left), non-composite decking (above center), and the form decking (above right) Composite decking is available in various profiles and thicknesses 12 6

Composite Metal Decking Decking with deformed ribs (or embossed decking), as shown, is commonly used The deformations on the ribs allow for a stronger bond between the concrete and the decking (ASCE 2002) 13 Composite Metal Decking Less common styles of composite decking include: Decking with the ribs formed in a dovetail or fluted pattern (above) Decking with welded wire fabric welded to the ribs Decking with steel rods welded across the ribs Image courtesy of Epic Metals Corporation 14 7

Installation of Decking Metal decking is placed on the structural steel at predetermined points in the erection sequence Metal decking may be installed by the steel erection contractor or a separate decking contractor 15 Installation of Decking Per the Occupational Safety & Health Administration Standard 1926.760(c) the decking crew may work in a controlled decking zone while placing and attaching the decking A controlled decking zone is an area in which initial installation and placement of metal decking may take place without the use of guardrail systems, personal fall arrest systems, fall restraint systems, or safety net systems and where access to the zone is controlled 16 8

Installation of Decking Puddle welds (above right) are commonly used to attach the decking to the structural steel below Daily output for a four person decking crew ranges from 2700 S.F. to 3860 S.F. per day depending on the depth and gauge of the decking (Means 2004) 17 Installation of Decking As an alternative to welding, powder actuated tools may be used to attach metal decking to structural steel Powder actuated tools use the expanding gases from a powder load, or booster, to drive a fastener A nail-like fastener is driven through the metal deck into the steel beam The powder actuated tool, powder load, and fastener must be matched to the thickness of the structural steel beam flanges Images courtesy of Hilti Corporation 18 9

Shear Connectors Shear connectors are commonly referred to as studs or shear studs in the trade They are available in a range of sizes, materials, and grades Headed studs (as shown) are most commonly used Other, less common options for shear connectors include hooked studs or pieces of C-channel 19 Shear Connectors Depending on the welding process used, the tip of the shear connector may be placed in a ceramic ferrule (arc shield) during welding to retain the weld Shear connectors create a strong bond between the steel beam and the concrete floor slab which is poured on top of the metal decking This bond allows the concrete slab to work with the steel beams to reduce live load deflection 20 10

Installation of Shear Connectors Shear connectors are installed after the decking is in place Shear connectors may be installed by the steel erection contractor or a specialty shear connector installer The welding equipment required for installation is provided by the shear connector installer Daily output for shear connector installation averages about 1000 per day depending on the size of the connectors (Means 2004) 21 Installation of Shear Connectors The bracketed numbers on the drawing above give the number of shear studs to be installed at an even spacing on the respective beam When spacing is not uniform it will be indicated on the plan Specified spacing of the shear connectors is an important part of the composite design and must be adhered to Minimum spacings keep concentrations of compressive forces from occurring at the stud locations Maximum spacings help avoid separation of the slab from the beam and guarantee the uniform transfer of shear force (RLSD 2002) 22 11

Installation of Shear Connectors The electrical arc process is commonly used for stud welding An arc is drawn between the stud and the base metal The stud is plunged into the molten steel which is contained by the ceramic ferrule The metal solidifies and the weld is complete The ferrules are removed before the concrete is poured (ASCE 2002, AWS 2004) 23 Installation of Concrete Concrete is installed by a concrete contractor on top of the composite metal decking, shear connectors, and welded wire fabric or rebar grid (crack control reinforcing) Pumping is a typical installation method for concrete being placed on metal decking 10,000 to 15,000 sq. ft. of concrete slab may be installed per day depending on slab thickness and crew size (Ruddy 1986) 24 12

Installation of Concrete There is an art to the placement of concrete on metal deck and structural steel The work, unless shoring is used, must be executed on a deflecting surface An experienced concrete contractor should be employed for this work Concrete should be deposited over supporting members first, then spread toward the deck midspans The accumulation of a deep pile of concrete must be avoided (AISC 2003, ASCE 2002) 25 Installation of Concrete Concrete construction joints should be located over the beam or girder webs Sometimes this is not possible and the joint is located near the decking midspan Shoring should be placed beneath the construction joints until the concrete on both sides of the construction joint has reached 75% strength o This avoids a bond failure between the hardened concrete and the metal deck when the adjoining concrete is placed (ASCE 2002) Placement of construction joints must be reviewed by the Engineer of Record 26 13

Installation of Concrete The contractor must be aware of camber in the beams and the expected deflections Consultation with the structural engineer may be necessary As the concrete cures it forms a connection with the composite metal decking and shear studs The composite floor system is now complete (AISC 2003) 27 Quality Control The shear connectors used in composite construction require specific inspections and quality control Testing procedures are specified in the contract documents or by a local building authority AWS D1.1 Structural Welding Code Steel, Section 7: Stud Welding (AWS 2004) specifies the tests and inspections for shear studs 28 14

Quality Control As described in the AWS code (AWS 2004), jobsite conditions may exist that prohibit or delay the stud welding operation The primary issues affecting the installation of the shear connectors are: Moisture on the decking or ferrules Moisture between the decking and the steel beam below A steel temperature below 0 F In the pictures above, a torch is being used to remove snow (left) from the areas where shear studs are to be installed (right) 29 Quality Control Required quality control procedures for shear connectors include pre-production tests and fabrication inspections Pre-production testing is performed by the shear stud installer at the beginning of each work shift and includes the following steps: 1. Weld two sample studs 2. Inspect for flash 3. Perform bending test 4. Equipment settings are recorded The stud installer performs visual fabrication inspections as studs are installed Other testing may be specified or may be necessary if all visual inspections are not passed (SIN 1998) 30 15

Cost Impacts of Composite Construction When used appropriately, typical overall building costs will be less for composite construction than non-composite construction 31 Cost Impacts of Composite Construction The U.S. national average installation cost for shear studs ranges from $1.15 to $1.72 per connector (Means 2004) A cost comparison should be made between the reduced structural steel cost and the additional shear connector cost when determining whether or not to use composite construction 32 16

Scheduling of Composite Construction The duration for the installation of shear studs is project dependent and should be considered on a project by project basis Shear stud installation usually has little or no impact on the overall project schedule 33 Scheduling of Composite Construction It may be possible, depending on the size of the structure and the sequencing of erection and decking, to install the shear studs as erection proceeds It may also be possible to have a majority of the shear connectors in place and begin placing concrete for the floor slabs while structural steel is being erected in another area of the building On the structure shown above part of the composite first floor slab was placed while erection of the structural steel for the third floor proceeded 34 17

Image courtesy of CAMBCO Inc. 35 Introduction to Cambering Cambering is the process of creating an intentional slight curvature in a beam Image courtesy of CAMBCO Inc. 36 18

Introduction to Cambering Camber in a beam can be designed to compensate for either: A certain percentage of the dead load deflection The full dead load deflection The full dead load deflection as well as a percentage of the live load deflection (Ricker 1989) Camber is usually designed to compensate for deflections caused by pre-composite dead loads 37 Advantages of Cambering Supporting beams will deflect under the load of concrete being placed This deflection can be exaggerated in a composite floor system where the full strength of the system is not achieved until the concrete has cured Cambered beams (top diagram above) should deflect to a straight line (bottom diagram above), if load and deflection are predicted accurately and camber equals deflection This allows the floor slab to be flat while maintaining a consistent thickness (Larson and Huzzard 1990) 38 19

Advantages of Cambering If beams are not cambered (top diagram above) the deflection under the load of the wet (plastic) concrete will result in a ponding effect in the concrete (bottom diagram above) To create a flat floor in this situation the concrete will need to be thicker at the center of the bay where the deflection is the greatest The volume of concrete used will typically be 10-15% more than if the floor is a constant thickness (ASCE 2002) 39 Disadvantages of Cambering The use of cambered beams will, to a certain degree, be limited by other aspects of the design for a structure Due to the complexity in detailing, fabrication, and fit-up associated with moment connections (above left), camber should not be used in moment connected beams Beams with simple framing connections (above right) may be cambered because the end rotational resistance of a simple connection is small in comparison to that of a moment connection 40 20

Disadvantages of Cambering 1 Specified Top Of Slab Elevation 2 The processes used to create camber in beams as well as the actual deflections under load of cambered beams are not exact Care needs to be taken in the specification and fabrication of camber to ensure that a beam, once in place and under load, will perform within tolerances Levelness and consistent floor thickness can be a problem (ASCE 2002) The diagrams above show two possible results of cambered beams not deflecting as predicted under the load of the wet (plastic) concrete 1. Stud heads are exposed 2. Top of slab elevation out of tolerance 41 Alternatives to Cambering 1 2 Alternative methods for achieving a level floor slab without using cambered beams include: 1. Pouring a slab of varying thickness over deflecting beams 2. Using over-sized beams to minimize deflection 3 Shoring Concrete At 75% Strength 3. Shore the beams before placing the concrete (Larson and Huzzard 1990) 42 21

Shoring Shoring may be used in lieu of cambering The construction documents must specify the use of shoring There are several advantages to using shoring: Lighter floor beams may be used Cambers do not need to be designed or fabricated Less beam deflection allows for better control of the slab thickness Shoring can accommodate a contractor s special loading requirements 43 When to Camber Girder Beams Filler Beams Members with uniform cross section Composite Floor Beams (Ricker 1989) 44 22

When Not to Camber Cantilevered Beams (above left) Crane Beams Moment Connected Beams Braced Beams (above right) Spandrel Beams (above right) (Ricker 1989) 45 When Not to Camber Beams with moment connections (above left) Beams with non-symmetrical loading (Ricker 1989) Beams under 20 feet in length (above right) Beams with end plate connections 46 23

Heat Cambering Heated Areas Beam Support Beams may be cambered by applying heat to small wedge-shaped areas at specific increments along the beam (Ricker 1989) The beam is place upside down on supports so the bottom flange can be heated The heated flange expands under the heat and contracts as it cools Camber is induced in the opposite side of the beam as the heated flange cools Advancing this slide will begin an animation which shows the expansion and contraction that occurs in a heat cambered beam The animation will repeat after several seconds Top Side of Beam When Installed 47 Installation of Heat Cambered Beams A heat cambered beam should be erected with the heat marks on the bottom side of the beam (see top diagram above) This places the beam in a camber up (or concave down) orientation Heat marks can be seen on the beams in the bottom picture above 48 24

Cold Cambering Cold cambering methods are more widely used and generally more economical than heat cambering The beam is mounted in a frame and force from a ram(s) is used to bend the beam to create camber (Ricker 1989) Image courtesy of CAMBCO Inc. 49 Creating Camber Image courtesy of CAMBCO Inc. Cambering is most commonly done at the fabricator s shop after the connections are fabricated (AISC 2000) The fabricator may mark cambered beams to ensure proper installation 50 25

Natural Mill Camber Natural mill camber, which is a slight camber present in a beam when it is received from the mill, will exist in most beams If the natural mill camber is at least 75% of the specified camber, no further cambering by the fabricator is required If camber is not specified, the beams will be fabricated and erected with any natural mill camber oriented up (or concave down) (AISC 2000) 51 Cambered Beams on Structural Plans Cambered beams should be clearly marked on the structural plans (AISC 2000) 52 26

Cambered Beams on Structural Plans The structural plan above shows which beams are cambered The amount of camber is indicated for each cambered beam c=3/4 indicates that the beams are cambered 3/4 at the center c=1 ¼ indicates that the girders are cambered 1 ¼ at the center 53 Installation of Cambered Beams The installation of cambered beams is similar to that of other structural steel members No additional tooling, equipment, or hardware should be required 54 27

Quality Control Per the AISC Code of Standard Practice camber shall be measured in the Fabricator s shop in the unstressed condition. (above left) The amount of camber specified on the shop drawing (above right) is for the beam center line in an unstressed or unloaded condition Tolerances for camber are specified in the AISC Code of Standard Practice: Members 50 feet or less in length = minus 0 and plus 1/2 Members over 50 feet the plus tolerance is increased by 1/8 for every 10 feet over 50 feet (AISC 2000) 55 Quality Control It is possible for all or part of the induced camber to come out of a beam during shipment to a jobsite This is acceptable under the AISC Code of Standard Practice (2000), but the fabricator s quality control procedure should provide verification that the specified camber was measured in the shop 56 28

Cost of Cambering Cambered beams require additional fabrication resources which will make them cost more than non-cambered beams The additional cambering cost should be compared with Cost of additional concrete due to ponding Cost of using shored construction Cost of using a heavier section that does not need to be cambered Image courtesy of CAMBCO Inc. 57 Cost Savings from Cambering The cost to camber beams may be less than the alternatives A cost comparison can reveal the savings associated with the use of cambered beams Larson and Huzzard (1990), in their study of cambered beams and uncambered beams found a cost savings of approximately 4% A 30 x 30 bay size was used Filler beams were spaced at 10 o.c. 58 29

Impacts on the Schedule Image courtesy of CAMBCO Inc. There will be an increase in fabrication duration for structural steel to account for time required to create camber in beams The amount of time required to create camber is dependent on a fabricator s internal scheduling and fabrication methods 59 Impacts on the Schedule Delivery, shakeout, and erection durations should not be impacted by the use of cambered beams 60 30

Structural Steel: The Material of Choice 61 References AISC. (1991). Design Guide for Low- and Medium-Rise Steel Buildings. American Institute of Steel Construction, Inc. Chicago, IL. AISC. (1999). Construction Management of Steel Construction. American Institute of Steel Construction, Inc. Chicago, IL. AISC. (2000). Code of Standard Practice for Steel Buildings and Bridges. American Institute of Steel Construction, Inc. Chicago, IL. AISC. (2002). Designing With Structural Steel A Guide for Architects. American Institute of Steel Construction, Inc. Chicago, IL. AISC. (2003). Design Guide for Serviceability Design Considerations for Steel Buildings, Second Edition. American Institute of Steel Construction, Inc. Chicago, IL. Allen, E. (1999). Fundamentals of Building Construction Materials and Methods. John Wiley & Sons, Inc. New York, NY. ASCE. (2002). Construction Considerations for Composite Steel-and-Concrete Floor Systems. Journal of Structural Engineering, Vol. 128, No. 9, 1099-1110. American Welding Society, (AWS). (2004). Structural Welding Code Section 7: Stud Welding. ANSI/AWS D1.1-98, Miami, FL. 62 31

References Cont. Larson, J. W., and Huzzard, R. K. (1990). Economical Use of Cambered Steel Beams. Proc. AISC Engineering Conference, Chicago, IL. 3-21. Means, R.S. (2004). 2004 Building Construction Cost Data. R.S. Means Company, Inc., Kingston, MA. Occupational Safety & Health Administration, (OSHA). (1996). Concrete and Masonry Construction. Available at: http://www.osha.gov/doc/outreachtraining/htmlfiles/concrete.html. Viewed June, 2004. Ricker, Jr., D. T. (1989). Cambering Steel Beams. AISC Engineering Journal, 4, 136-142. Richard Lees Steel Decking, (RLSD). (2002). Composite Beams & Shear Studs Information Sheet CB5. Richard Lees Steel Decking. Available at: http://www.rlsd.com/. Viewed April, 2004. Ruddy, J. L. (1986). Ponding of Concrete Deck Floors. AISC Engineering Journal, 3, 107-115. Steel Inspection News, (SIN). (1993). Shear Connector Inspection a Tutorial. Steel Structures Technology Center, Inc. Available at: http://www.steelstructures.com/stlinspnews/news%20index.htm. Viewed April, 2004. 63 32