ROOT CAUSE ANALYSIS OF VTUAV FIRE SCOUT S NUNN-MCCURDY BREACH Patricia Fazio Bronson and Christopher Martin



Similar documents
Northrop Grumman Corporation

WEAPONS ACQUISITION REFORM

Selected Acquisition Report (SAR)

Selected Acquisition Report (SAR)

ODIG-AUD (ATTN: Audit Suggestions) Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA

U.S. Forces in Iraq. JoAnne O Bryant and Michael Waterhouse Information Research Specialists Knowledge Services Group

Selected Acquisition Report (SAR)

Selected Acquisition Report (SAR)

Technology Readiness Assessment (TRA)

WEAPONS ACQUISITION REFORM

Improvements Needed for Awarding Service Contracts at Naval Special Warfare Command

Using Parametric Software Estimates During Program Support Reviews

Fleet Ballistic Missile Eastern Range Operations Supporting Navy Testing and Deployment

F-35 JOINT STRIKE FIGHTER. Problems Completing Software Testing May Hinder Delivery of Expected Warfighting Capabilities

Operation IMPACT (Injured Military Pursuing Assisted Career Transition)

Naval Energy. A Strategic Approach

IAI/Malat Solutions for the Maritime Arena

AeroVironment, Inc. Unmanned Aircraft Systems Overview Background

Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D )

For More Information

Selected Acquisition Report (SAR)

Air Force Officials Did Not Consistently Comply With Requirements for Assessing Contractor Performance

Distribution Restriction Statement Approved for public release; distribution is unlimited.

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC

Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM david.karr@us.af.

American Recovery and Reinvestment Act Project Repair and Modernization of Littoral Combat Ship Squadron Building at Naval Base San Diego, California

MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices

GAO. DEFENSE INFRASTRUCTURE Funding Risks in Services 1999 Central Training Programs

United States Government Accountability Office GAO. Report to Congressional Committees. July 2009 COAST GUARD

F-35 JOINT STRIKE FIGHTER Preliminary Observations on Program Progress

GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices

A Cure for Unanticipated Cost and Schedule Growth

Space Launch System Status Briefing to NAC Space Operations Committee

Space and Naval Warfare Systems Center Atlantic

Department of Defense MANUAL

DEPARTMENT OF THE NAVY OFFICE OF THE CHIEF OF NAVAL OPERATIONS 2000 NAVY PENTAGON WASHINGTON, DC

OPNAVINST A USFF/CNO N3/N5 10 Nov 2014

DEFENSE ACQUISITIONS. DOD Efforts to Adopt Open Systems for Its Unmanned Aircraft Systems Have Progressed Slowly

DEFENSE LOGISTICS. Army Should Track Financial Benefits Realized from its Logistics Modernization Program. Report to Congressional Requesters

Department of Defense INSTRUCTION. SUBJECT: Information Assurance (IA) in the Defense Acquisition System

Selected Acquisition Report (SAR)

Product Manager Soldier Protective Equipment Program Overview To Joint Advanced Planning Brief for Industry

SECRETARY OF THE NAVY SAFETY EXCELLENCE AWARDS

Accident & Emergency Department Clinical Quality Indicators

Cost and Time Overruns for Major Defense Acquisition Programs

Taipei Economic and Cultural Representative Office in the United States PATRIOT Advanced Capability-3 Guided Missiles

Natural Gas Diversification Strategy for PREPA GOVERNMENT DEVELOPMENT BANK FOR PUERTO RICO

Availability and Reduce Cost NAVAL AVIATION MATERIALS, MANUFACTURING & MAINTENANCE WORKSHOP

For More Information

Department of Defense INSTRUCTION

Overview and Program Update

COMBATSS-21 Scalable combat management system for the world s navies

2.3. Performs inventories and ensures timely correction of discrepancies. Inspects and evaluates inventory management activities.

Using Spiral Development To Reduce Acquisition Cycle Times

PEO Land Systems Marine Corps. It s s all about the Warfighter! NDIA Tactical-Wheeled Vehicle Conference Monterey, CA 4 Feb 08

Military Transactions

Information Technology

Departures to the south from Runways 16L and 16R.

NATO Developments in UAS Airworthiness and Sense & Avoid Functional Requirements. Mr. Dave Seagle US HoD, NATO FINAS

(1) Acquisition Professional of the Year. (3) Major Acquisition Activity Award. (4) Field Acquisition Activity Award

Presentation to NDIA Ground Robotics Division. 2 September 2010

STRENGTHENING DEPARTMENT OF DEFENSE LABORATORIES David Graham, Robert Leheny, and Susan Clark-Sestak

Final reports on deepened defence cooperation between Finland and Sweden

How To Discuss Unmanned Aircraft System (Uas)

Rapheal Holder From Platform to Service in the Network Centric Value Chain October 23, Internal Information Services

Total Ownership Cost (TOC) and Cost as an Independent Variable (CAIV)

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community.

Review of DoD s Program Managers

F 35 Lightning II Program Quality Assurance and Corrective Action Evaluation

bñåéêéí=ñêçã=íüé== mêçåééçáåöë= çñ=íüé= péåçåç=^ååì~ä=^åèìáëáíáçå= oéëé~êåü=póãéçëáìã=

OPERATING AND SUPPORT COST-ESTIMATING GUIDE

Major Contracts on Schriever Air Force Base

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

How Does Foreign Industry Sell to the U.S. Department of Defense

How To Do Business With Northrop Grumman

DEPARTMENT OF THE NAVY COMMANDER NAVAL EDUCATION AND TRAINING COMMAND 250 DALLAS STREET PENSACOLA, FLORIDA

Defense Acquisition Review Journal

Ocean Class AGOR Program Acquisition Status. Prepared by PEO Ships, PMS325Q For UNOLS Annual meeting 13 October 2009

Joint Operational Medicine Information Systems Program

Expeditionary Combat Support System: Root Cause Analysis

CHAPTER 2 AIR TRAFFIC CONTROLLER (AC) NAVPERS F CH-64

WATCHKEEPER X UNMANNED AIRCRAFT SYSTEM (UAS)

UNCLASSIFIED. UNCLASSIFIED Office of Secretary Of Defense Page 1 of 9 R-1 Line #139

Department of Defense INSTRUCTION

The Unmanned Little Bird (ULB) Decking Risk Reduction Test Approach

Improvement Needed for Inventory Management Practices on the T700 Technical, Engineering, and Logistical Services and Supplies Contract

PM UAS Fleet Management (Depot Maintenance) OCT 19, 2011

NAVAL AVIATION ENTERPRISE

Helicopter Emergency Medical Service (HEMS)

The Program Managers Guide to the Integrated Baseline Review Process

Navy Seal Procurement Strategies - Using MYP and BBC

Review of U.S. Coast Guard's FY 2014 Detailed Accounting Submission

Information Technology (IT) Investment Management Insight Policy for Acquisition

Forecast to Industry 2015 External Contracting Opportunities

a GAO GAO DEFENSE WORKING CAPITAL FUND Military Services Did Not Calculate and Report Carryover Amounts Correctly

GAO CONTRACT MANAGEMENT. Small Businesses Continue to Win Construction Contracts. Report to Congressional Committees

Enterprise Resource Planning Systems Schedule Delays and Reengineering Weaknesses Increase Risks to DoD's Auditability Goals

Strike section 133 and insert the following new section:

WORKFORCE COMPOSITION CPR. Verification and Validation Summit 2010

2012 Regional Overview

Transcription:

ROOT CAUSE ANALYSIS OF VTUAV FIRE SCOUT S NUNN-MCCURDY BREACH Patricia Fazio Bronson and Christopher Martin The Problem The root cause of the VTUAV Fire Scout Program s Nunn-McCurdy breach needs to be determined. IDA s methodology for conducting a Root Cause Analysis of Nunn- McCurdy breaches is a four-step process centered on the Root Cause Narrative described by PARCA. A Nunn-McCurdy breach occurs when a program experiences cost or schedule growth exceeding any of the established Nunn-McCurdy thresholds. The Weapon Systems Acquisition Reform Act (WSARA) of 2009 mandates that a Root Cause Analysis (RCA) defined in WSARA as an assessment of the underlying cause or causes of growth in cost, schedule slips, or poor performance of a program be conducted when such a breach occurs. The Director, Performance Assessments and Root Cause Analyses (PARCA) is responsible for conducting the required RCA. At PARCA s request, IDA has conducted eleven RCAs over the past few years, in support of PARCA memoranda to the Under Secretary of Defense for Acquisition, Technology and Logistics (USD(AT&L)) describing the root causes of cost growth in programs that have experienced a critical Nunn-McCurdy breach. When the Congress requires the Department to recertify a program because it has experienced a Nunn-McCurdy breach, PARCA s memos are submitted in support of the Department s recertification decision for that program. 18 RESEARCH NOTES METHODOLOGY FOR PARCA RCAS IDA s methodology for conducting a Root Cause Analysis of Nunn-McCurdy breaches is a four-step process centered on the Root Cause Narrative described by PARCA. This methodology repeatedly produces compelling arguments for the conclusions of the root cause: 1. Official Statement of the Breach. We take this from the Program Deviation Report to the Defense Acquisition Executive. 2. Timeline of Events Leading up to the Breach. We construct the initial version of the timeline from the program s historical Selected Acquisition Reports (SARs) and add to it as discovery proceeds. 3. Root Cause Narrative. Starting with the statement of the breach, we work backward linking the contributing factors and classifying them as symptoms; proximate causes; bad things that happened that do not have anything to do with the cost growth; and root causes. WSARA provides seven categories of root causes to consider, but permits others.

WSARA Categories of Root Causes Unrealistic performance expectations Unrealistic baseline estimates for cost or schedule Immature technologies or accepting excessive manufacturing or integration risk Unanticipated design, engineering, manufacturing, or technology integration issues arising during program performance Changes in procurement quantities Inadequate program funding or funding instability Poor performance by government or contractor personnel responsible for program management. To the extent possible, we apportion the cost growth to the contributing factors, providing graphs and data as evidence without comment or conclusion. The purpose of the Narrative is to simply and even-handedly display the relevant facts and circumstances by which a program ended up in a ditch. (Gary Bliss) 4. Root Cause Analysis. We tell the story of the breach starting at the root of the problem, and allocate the contributing factors and their cost to each root cause. We discuss problems of inception and execution, and identify exogenous causes. The RCA on the Vertical Takeoff and Landing Unmanned Aerial Vehicle (VTUAV) Fire Scout program (system shown in Figure 1) exemplifies the process. Figure 1. MQ-8A VTUAV Fire Scout ROOT CAUSE ANALYSIS OF VTUAV FIRE SCOUT PROGRAM On March 10, 2014, the Program Manager for the Navy and Marine Corps Multi-Mission Tactical Unmanned Air Systems Program Office (PMA-266) submitted a Program Deviation Report that announced the VTUAV program would breach the Nunn-McCurdy critical cost thresholds of 25 percent for the Average Procurement Unit Cost (APUC) and Program Acquisition Unit Cost (PAUC) in the approved VTUAV Acquisition Program Baseline (APB). The initial concept in 1999 for the Fire Scout was to make unmanned a Schweitzer 330 helicopter. After initial tests on the MQ-8A, the Schweitzer aircraft selected was found to have inadequate lift capacity and endurance to satisfy the Navy s desired operational needs. To address this, the Navy and Northrop Grumman www.ida.org 19

further modified the aircraft to increase its performance by adding a rotor blade, extending the tail boom, and adding sponsons for additional carrying capacity. These changes to the helicopter, now designated the MQ-8B, increased the maximum gross weight and provided nearly three hours more time on station. As developmental tests proceeded, however, restrictions surfaced that limited its use. Meanwhile, U.S. Africa Command put out an urgent request for the Rapid Deployment Capability (RDC), whose performance needs necessitated not additional purchases of MQ-8B, but the development of a third variant outside the Program of Record (POR). This new aircraft, the MQ-8C, uses a far more capable helicopter (the Bell 407), which has room and power to be a versatile weapon system. The Navy has since adopted the MQ-8C as the POR aircraft for all future procurements on the VTUAV program. According to the Navy, the more capable aircraft meant they could deploy two MQ-8Cs in place of three MQ-8Bs and reduce the total number needed to meet the Littoral Combat Ship (LCS) requirement. Figure 2 shows major events in the evolution of the Fire Scout program from its original configuration (RQ-8A), to the configuration developed in the POR (MQ-8B), to the third configuration, developed under an RDC Joint Urgent Operational Needs (JUON) program outside the POR (MQ-8C) 1. VTUAV ACAT II MS II approval Elevated to ACAT 1C May 2007 MS C Significant NM Breach Critical NM Breach RQ-8A 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Dec 2001 production funding cut U.S. Army awards contract for 7 RQ-8B Mar 2004: RQ-8B development contract awarded MQ-8B first flight 18 Dec 2006 23 Jun 2006 development contract definitized Jan 10 Army terminates involvement 21 Jun 2007 LRIP long lead contract award 21 Dec 2007 LRIP lot 1 Sep 2008 LRIP lot 2 Jan 2009 LRIP lot 3 Dec 12 Install RDR-1700 on 9 MQ-8B 23 Apr 12 contract for 2 development & 6 LRIP MQ-8C 6 LRIP MQ-8C Jun 2010 LRIP lot 4 May 2011 Conversion May 2012 LRIP lot 5 5 LRIP MQ-8C Jul 13, NG delivers first MQ-8C for test MQ-8B RQ-8C Figure 2. VTUAV Fire Scout Timeline 1 The non-por status means that not all costs incurred for development and procurement (of the new requirements) are included in the program baseline. 20 RESEARCH NOTES

This article discusses only the critical Nunn-McCurdy breach in APUC over the original 2006 baseline, calculated to be 71.5 percent. The Navy offered that the change in aircraft purchase quantity was the sole reason for increased APUC values for VTUAV. Since quantity change rarely occurs alone, we believe that determination of other factors must precede the quantity change calculation. The VTUAV SARs reveal that the Navy added $327 million (FY06 dollars) to the procurement program and stretched the procurement schedule by 17 years before they decided not to procure any more MQ- 8Bs. Figure 3 shows the VTUAV Fire Scout planned procurement profiles from the annual SARs. A fixed cost analysis of annual procurement cost by quantity yields an annual fixed cost estimate of approximately $20 million, which translates into a $340 million increase in the procurement cost estimate over the course of the program. The major contributors to the schedule delays were a replan of the initial, unrealistic acquisition profile; better alignment of aircraft procurement with LCS procurement; a five-year delay in the scheduled date for operational evaluation (OPEVAL); and allowance for more time for the development of the MQ-8C. Cost experience on procurement of the VTUAV provided by the Navy revealed that recurring costs for the MQ-8B had increased by 7 percent and that the more capable MQ-8C would cost about $1 million more than the MQ-8B s current estimated cost (another 11 percent). 40 35 Initial profile not efficient VTUAV POR Quantities by SAR Submission 17 years 30 25 20 15 10 5 0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Dec-06 Dec-07 Dec-09 Dec-10 Dec-11 Dec-12 Dec-13 Quantity cut 8 year production break Figure 3. VTUAV POR Quantities by SAR Submission www.ida.org 21

Figure 4 shows IDA s estimates of the relative contributions for each of the reasons. There remain 32 percentage points of APUC growth for which the quantity change is accountable. With 32 percent of the APUC increase associated with a reduced number of aircraft systems to be bought, the question is why the Navy decided to stop buying MQ-8Bs, an aircraft the Navy had reported met operational requirements. In reviewing test reports and performing analyses of demonstrated performance, we found that, during developmental testing and through experience in the field, the MQ-8B had restricted wind envelopes and reliability issues, and required greater engine maintenance costs than anticipated. Figure 5 shows the aggregate Wind Over Deck envelopes 2 allowed for the MQ-8B on board LCS-1 superimposed on the objective and threshold requirement. 3 The white areas within the threshold fan are Figure 4. Relative Contributions of Causes of APUC Growth 2 Naval Air Training and Operating Procedures Standardization (NATOPS) Flight Manual, Navy Model MQ 8B, Unmanned Aerial Vehicle, November 1, 2013 Change 1 March 1, 2014, Document Number A1 MQ8BA NFM 000. 3 Capabilities Production Document, Vertical Takeoff and Landing Tactical Unmanned Aerial Vehicle (VTUAV) System, Prepared for Milestone C Decision, Version 4.3, December 20, 2006. 22 RESEARCH NOTES

VTUAV Wind Restrictions on LCS-1 White space does not meet threshold requirements Operations at operational weights may force engine to exceed limits reducing engine lifetime and increasing maintenance actions (NATOPS manual, Figures 8-6ff) 290 280 270 260 300 310 250 240 320 340 330 230 220 210 200 350 190 0 45 40 35 30 25 20 15 10 5 0 10 20 30 40 50 60 Radial Axis is Wind Over Deck in KTS 70 120 130 140 150 160 180 170 80 90 100 110 The differences between port and starboard are caused by the tail rotor control Starboard Departure Stern Approach Starboard Departure Port Approach Port Departure Stern Approach Port Departure Starboard Approach Threshold Objective Figure 5. Aggregate Wind Over Deck Envelopes Allowed for MQ-8B On Board LCS-1 conditions in which the system does not meet the threshold requirement. The shortfalls seen in Figure 5 are due primarily to inadequacies in tail rotor authority at nominal power settings and aircraft weights. 4 In addition, operational assessments revealed that the aircraft needed to operate at near maximum gross weight to meet time on station requirements. The engine operations at high power settings needed to meet these requirements reduced the mean time between failures, increased mean time to repair, and required additional spare parts. 5 Furthermore, the aircraft could not be operated at standard military hot temperatures due to engine overheating issues. 6 Cooling air scoops 7 are being added to the current MQ-8Bs so they can safely operate at temperatures above 30 C. IDA assesses that the Navy abandoned the MQ-8B because it did not meet their performance expectations. Because of this, we find that the increases in recurring cost, the OPEVAL delays, the development time for the MQ-8C, and the change in quantity are all consequences of the MQ-8B design not meeting performance expectations. Furthermore, we assess that even with the modifications made 4 CDR Van Patrick McLawhorn, USN, and Mr. Richard Paletta, Status of MQ-8B Developmental Testing, Inclusive of Software Increment 9.1.3.1, Report No: NAWCADPAX/ISR-2012/62, May 24, 2012. 5 Quick Reaction Assessment of VTUAV, COMOPTEVFOR, September 12, 2012. 6 McLawhorn and Paletta, Status of MQ-8B Development Testing, May 24, 2012. 7 MQ-8 AIRFRAME CHANGE NO. 16. To provide modification instructions for Engine Bay Access Panels to add cooling air scoops to reduce operating oil temperature levels. www.ida.org 23

from the MQ-8A to the MQ-8B (increasing vehicle weight, improving rotor performance, and increasing engine horsepower), the Schweitzer 330 aircraft and engine were limited in overall capability and were not going to be able to meet the payload and endurance expectations across the range of intended operational conditions. Because of this, we allocate 56 percentage points of the 71.5 percentage points in APUC growth to the WSARA Root Cause Category poor performance by government personnel responsible for program management. The remaining APUC growth we attribute to a faulty initial procurement plan and LCS schedule delays. Dr. Bronson is a Research Staff Member in IDA s Cost Analysis and Research Division. She holds a doctorate in applied physics from Old Dominion University. Mr. Martin is a Research Staff Member in IDA s Science and Technology Division. He holds a Master of Science in aerospace engineering from the University of California, Los Angeles. References McLawhorn, Van Patrick, CDR, USN, and Mr. Richard Paletta. Status of MQ-8B Developmental Testing, Inclusive of Software Increment 9.1.3.1. Report No: NAWCADPAX/ISR-2012/62. May 24, 2012. MQ-8 AIRFRAME CHANGE NO. 16. MQ-8B Hot Weather Delta Modification, Installation of (WUC 1000000). Cognizant Code(s): PMA-266/AIR-4.3.5.1/6.7.1.2. Issue Date: September 27, 2012. MQ-8B Capabilities Production Document (CPD). Vertical Takeoff and Landing Tactical Unmanned Aerial Vehicle (VTUAV) System, Version 4.3. Prepared for Milestone C Decision, December 20, 2006. Naval Air Training and Operating Procedures Standardization (NATOPS) Flight Manual, Navy Model MQ 8B, Unmanned Aerial Vehicle, November 1, 2013 Change 1 March 1, 2014. Document Number A1 MQ8BA NFM 000. Quick Reaction Assessment of VTUAV, from Commander, Operational Test and Evaluation Force, to Chief of Naval Operations. September 12, 2012. VTUAV Program Deviation Report from PMA-266 to ASN(RDA), Mar 10, 2014. 24 RESEARCH NOTES