Cost and Time Overruns for Major Defense Acquisition Programs
|
|
|
- Eustacia Thomas
- 10 years ago
- Views:
Transcription
1 Defense-Industrial Initiatives Group Center for Strategic & International Studies Cost and Time Overruns for Major Defense Acquisition Programs An Annotated Brief Authors: Joachim Hofbauer Gregory Sanders Jesse Ellman David Morrow Project Directors: David Berteau Guy Ben-Ari Contributing Researcher: Nicholas Lombardo April 2011 Center for Strategic and International Studies 1800 K Street NW Washington DC, David Berteau [email protected] This material is based upon work supported by the Naval Postgraduate School Acquisition Research Program (Grant No.N )
2 Abstract Cost and time overruns in Major Defense Acquisition Programs (MDAPs) have become a high-profile problem attracting the interest of Congress, government and watchdog groups. According to the GAO, the 98 MDAPs from FY2010 collectively ran $402 billion over budget and were an average of 22 months behind schedule since their first full estimate. President Obama s memorandum on government contracting of 4 March 2009 also highlighted this issue. This paper presents findings of research on the root causes of cost and schedule delays for 92 MDAP active in 2010 and 12 cancelled programs. The results do not establish causality but do indicate multiple notable correlations. Inaccurate cost estimates are responsible for the strongest correlation with net cost growth changes and are associated with 40 percent of the accumulated cost overruns. In addition, the start year has little impact on the compound annual growth rate of cost overruns. This suggests that relatively better performance of newer programs may prove illusionary as programs age. Finally, fixed price contracts appear to have relatively smaller overruns, although this may tell us more about which programs are likely to receive fixed price contracts rather than what effect fixed price contracts may have on program performance. 2 P a g e
3 Real cost overruns (in 2010 billions, quantity adjusted) Introduction Cost and time overruns in Major Defense Acquisition Programs (MDAPs) have become a high-profile problem attracting the interest of Congress, government and watchdog groups. According to the GAO, the 98 MDAPs from FY2010 collectively ran $402 billion over budget and were an average of 22 months behind schedule since their first full estimate. President Obama s memo on government contracting of 4 March 2009 also highlighted this issue. This paper presents findings of research on the root causes of cost and schedule delays for MDAPs, incorporating 2010 SAR data. Figure 1: Relative cost overruns versus absolute cost overruns for FY2009 MDAPs F (20) FCS -200% 0% 200% 400% Real cost overruns (in percent, quantity adjusted) CHEM DEMIL -ACWA (2) -25% 0% 25% 50% Note: The sample includes 92 FY2010 MDAPs with a baseline estimate beyond Milestone B in the June 2010 SAR as well as twelve additional cancelled programs, notably including the Future Combat System (FCS). 3 P a g e
4 Problem Definition Past studies on this topic either have not offered rigorous data analysis or were focused on a critical but still narrow aspect of the problem, such as technical maturity. Meanwhile, Congressional leadership often focuses on different issues such as contract type and competition. As a result, acquisition reform efforts like the Weapon Systems Acquisition Reform Act of 2009 are hampered by an insufficient analytical basis. For instance, in its annual assessment of selected weapon systems, the Government Accountability Office predominantly focuses on knowledge-based factors such as technology maturity and associated program decisions as causes for these problems. Former Under Secretary of Defense for Acquisition Technology & Logistics John Young claimed in a memorandum on March 31, 2009, that many of the allegations of the GAO are based on inadequate analytical methods and that consequently many of the results are misleading. This disagreement is exemplary of the diverging set of opinions that exists regarding the root causes of MDAP cost overruns and schedule delays. The result amplifies disagreement regarding potential fixes. On the government side Senator McCain identified the usage of cost plus contracts as a major source for cost increases and Secretary Gates pointed towards the contract structures as a key source of cost and schedule overruns in some MDAPs. Defense contractors, on the other hand, regularly cite the altering of requirements in advanced program stages as an important factor for cost increases. The currently ongoing process of reforming and fixing the defense acquisition system still lacks the foundation of a detailed evaluation of the causality chain of cost overruns and program delays of MDAPs. This lack of understanding of underlying mechanisms makes the design of adequate solutions inherently difficult and renders them potentially ineffective. This study directly aims at developing the urgently needed knowledge base that will better guide efforts to correct the growing trends of cost increases and schedule overruns. Methodology This report analyzes a series of variables namely realism of baseline program cost estimates, government management and oversight, the role of contractors and lead military services, levels of competition, and contract structures to determine what factors might contribute to or be correlated with the observed cost overruns in the execution of MDAPs. This research draws on three primary data sources: Selected Acquisition Reports (SARs): The SARs track Major Defense Acquisition Programs, reporting on their schedule, unit counts, total spending, and progress through milestones. The unit of analysis is the programs themselves, making it the ideal source for top level analysis. 4 P a g e
5 Federal Procurement Data System (FPDS): The FPDS is a database of every government contract, with millions of entries each year. Each entry has extensive data on the contractors, contract type, competition, place of performance, and a variety of other topics as mandated by Congress. Crossreferencing individual contracts with MDAPs is possible using the system equipment codes (which match up with those of MDAPs). This source provides the most in-depth data on the government contracting process. Department of Defense budget documents: In addition to budget data, these documents provide topical information on each MDAP and its subcomponents. They will primarily be used to categorize projects as well as to support and double check spending figures from the other two sources. The report focuses on MDAPs from the FY2010 MDAP list. Within this sample group the analysis is limited to 104 MDAPs with cost estimates set at Milestone B or beyond, including MDAPs that were cancelled between 1999 and today. That gate is meant to be a hurdle that requires programs to reach a certain level of technological maturity. As a result Milestone B is normally the initiation of an acquisition program. 1 This common starting point ensures that only programs in a relatively mature acquisition phase are compared. Cancelled programs are included to avoid the selection bias that results from excluding several of the worst performing proposals from analysis. Figure 1 provides an overview of the cost overruns of these 104 programs. Unfortunately, full data are not available on all 104 MDAPs when examining contract type and competition, because not all of the programs have at least 50 percent of the SARs contract value accounted for in FPDS data. As a result, the unclear category is used to signify this missing data in competition and contract type findings. In addition, FPDS totals for program spending are sometimes higher than the funding status according to the SARs. In those cases, the SAR totals are treated as the more reliable figure. These snapshots provide an adequate starting point for detecting correlations between a series of potentially relevant factors and cost growth. The charts reflect the basic information; arranged across a variety of data elements, but they do not constitute a sufficient basis for establishing causality or policy changes, for which further analysis would be needed. 1 Acquisition History Project Working Paper #3: The Evolution of DoD Directive Acquisition Management Policy Defense Acquisition History Project. Accessed 5/25/ P a g e
6 Real cost overruns (in 2010 billions) Real cost overruns (in percent) Analysis This analysis focuses on examining the impact of baseline cost estimates, quantity and schedule changes, as well as engineering problems, the extent of competition, contract structure, lead branch of military service, and identity of prime contractor on the cost performance on MDAPs. Figure 2: Functional reasons for cost overruns $240 $180 Cost Increase 21% 30% $120 $60 $- $(60) $124 3% $203 13% 9% 8% $50 3% 4% $63 $51 2% 4% 3% $3 -$3 -$4 -$3 $0 -$16 0% 0% 15% 0% $(120) -$86 Cost Decrease Breaking down cost growth by functional areas as provided in the SARs identifies variances in the estimating process as the primary driver for cost growth, being responsible for $202.8 billion in cost growth for the 104 MDAPs analyzed. Another noteworthy observation from Figure 2 is the fact that the cost savings achieved through quantity changes equals approximately two thirds of the cost growth originating from changes in unit numbers. This is not encouraging, as for programs with upfront research and development costs, reducing the number of units lowers the overall program cost but it increases the per-unit cost, effectively curtailing the government s buying power. In turn, cost increases deriving from increases in the number of units require a higher overall program budget but lower the price per unit. -15% Quantity Schedule Engineering Estimating Support Other Cost Increase Cost Decrease Average Increase Baseline-Weighted Average Increase Nunn-McCurdy breaches, for instance, are based on the growth in the per-unit acquisition cost rather than overall program cost in order to account for this fact. This presentation therefore focuses on quantity-adjusted cost changes. The Selected Acquisition Reports do not list the exact methodology for quantity adjustments; unfortunately, the adjustment is not equivalent to the sum of cost adjustments that are not attributed to quantity changes. This complicates analysis of the functional reasons for cost growth. 6 P a g e
7 Real compound annual cost growth rate (in percent, adjusted for quantity changes) Figure 3: Time-cost correlation 160% 140% C-130 AMP 120% 100% 80% 60% 40% 20% EFV 0% -20% Year of last baseline estimate The next explanatory variable examined for its impact on program performance is the time-cost growth correlation. If cost increases accrue over time, then programs with an older baseline estimate would tend to accumulate relatively higher cost increases. The data for the analyzed programs show that older programs indeed experience larger overruns. However, Figure 3 shows that when measured in compound annual growth rate 2 rather than aggregate relative cost growth, the time-cost growth correlation is almost constant. The C-130 AMP project is distorting this trend, because its estimate was not changed when it was given a new baseline in Notwithstanding C-130 AMP, this growth correlation not only provides further evidence for the assertion that cost growth occurs steadily throughout the program lifespan, but it also suggests that younger programs are not performing better than older programs. 2 The compound annual growth rate describes the average year-to-year cost growth of a program spending since its baseline. Thus if comparing two programs with same percentage of cost growth since their baseline estimate, the program with an earlier baseline year would have a smaller compound annual growth rate. 7 P a g e
8 Real cost overruns (in 2010 billions, quantity adjusted) Figure 4: Cost overruns by lead service (I) F FCS (20) CHEM DEMIL- ACWA -100% 0% 100% 200% 300% Real cost overruns (in percent, quantity adjusted, service averages are unweighted) - (2) -25% 0% 25% 50% Air Force Army Navy DoD-wide Air Force Average Army Average Navy Average DoD-wide Average The analysis on the correlation between the lead branch of military service responsible for MDAPs and cost growth patterns reveals that programs led by the Army appear to have fewer, smaller overruns, followed by the Navy and then the Air Force, while DoD-wide programs tend to accrue significant larger cost overruns. The picture alters slightly when utilizing baseline-weighted averages with the Navy showing the least overruns followed by the Army, the Air Force, and DoD-wide programs. The considerable difference for the Army s results 11 percent on average versus 20 percent for baselineweighted averages is driven by the cancelled Future Combat System. It is important to note that DoDwide includes both programs managed by DoD agencies and joint programs such as the Joint Strike Fighter. The outcome of this data analysis might be skewed based on the relatively small sample group utilized in this analysis. For instance, it appears that the DoD-wide category might be heavily influenced by the negative cost developments in the Joint Strike Fighter program. As for the other components, further analysis with larger sample groups are required to validate observed trends. Any conclusions from Figure 4 identifying superior program management of existing programs by service are premature, even if additional data and analysis were to confirm this variation in cost performance based on lead service. A number of other factors may explain the differences, such as a tendency toward less risk-prone MDAPs. Further research will be needed to analyze the underlying causality and detect the true root causes for these trends. 8 P a g e
9 Real cost overruns (in 2010 billions, quantity adjusted) Real cost overruns (in percent, quantity adjusted) Figure 5: Cost overruns by lead service (II) $150 $120 Cost Overruns 75% 60% $90 44% 41% 45% $60 $30 $73 20% 11% $89 23% 17% 22% 16% $58 $124 30% 15% $- $(30) -$3.9 -$1.9 -$0.5 -$4.3 Cost Savings Army Navy Air Force DoD-wide 0% -15% Cost Overruns Cost Savings Average Overrun Baseline-Weighted Average Overrun Figure 5 supports the conclusion of the previous chart, with the poorest cost performance in DoD-wide managed MDAPs, while Army and Navy MDAPs, depending on what kind of average is utilized, display the smallest cost overruns. In absolute terms the Air Force shows the lowest total in real cost overruns. Notably, while the Navy performs relatively well on a percentage basis, it also has the largest share of overruns in absolute terms for any of the three service branches. This can be attributed to the size and duration of many Navy programs. This comparison provides further support for the assertion that MDAPs managed by the Army and the Navy suffer smaller overruns, while DoD-wide managed MDAPs tend to accrue larger overruns. However, the level of analysis conducted so far does not allow for any firm conclusions on the actual role of any service s program management skills in these trends. 9 P a g e
10 Real cost overruns (in 2010 billions, quantity adjusted) Figure 6: Cost overruns by prime contractor (I) F FCS CHEM DEMIL- ACWA (20) -100% 0% 100% 200% 300% Real cost overruns (in percent, quantity adjusted, prime averages unweighted) Boeing General Dynamics Lockheed Martin Northrop Grumman Raytheon Other Another predictor for program performance could be the identity of the prime contractor for a given program. One striking trend in Figure 6 that is visible for the big five U.S. defense companies is the fact that Raytheon on average appears to be associated with significantly better cost performance outcomes than other defense companies. Due to a lack of data granularity, the other companies category includes joint ventures and projects that are split between multiple contractor. The preliminary character of the analysis does not fully validate any findings of superior management or outcomes. In addition, even if confirmed, it would be premature to start praising any company for better program execution, as other factors such as specialization in technologically more mature program areas might be the true drivers behind this trend. As was the case for the breakdown by lead service, further research will be needed to analyze the underlying causality. (2) -25% 0% 25% 50% Boeing Average Lockheed Martin Average Raytheon Average General Dynamics Average Northrop Grumman Average Other Average 10 P a g e
11 Real cost overruns (in 2010 billions, quantity adjusted) Real cost overruns (in percent, quantity adjusted) Figure 7: Cost overruns by prime contractor (II) $150 $120 Cost Overruns 50% 40% $90 $60 $30 $- $(30) 31% 30% $90 -$0.1 Boeing $37 -$6.5 20% 13% General Dynamics $132 29% 19% 17% 14% 13% 9% $50 $26 $9 -$0.9 -$1.6 -$0.3 -$1.2 Lockheed Martin Northrop Grumman Raytheon Cost Savings Other 24% 17% 30% 20% 10% 0% -10% Cost Overruns Cost Savings Average Overrun Baseline-Weighted Average Overrun The comparison between the share of cost growth and the share of contract value for MDAPs, aggregated by prime contractor, correlates with the finding that MDAPs for which Raytheon is the prime contractor appear to exhibit the best cost performance amongst the big five defense companies. When it comes to the remainder of the big five, Figure 7 shows that their average performance varies based on the means used to measure it with different results when the programs are weighted by the baseline estimate than if all of the MDAPs are treated as having an equal weight. Again, this variance gives reason to be cautious in extrapolating from these results. 11 P a g e
12 Nominal cost overruns (in then year billions, quantity adjusted) Nominal Cost Overruns (In percent, weighted by percent of MDAP accounted for in FPDS, quantity adjusted) Figure 8: Cost overruns by type of competition $240 Cost Overruns 60% $200 50% $160 $120 $80 $40 $- $(40) 32% 35% 31% $209 31% 31% 26% 22% 23% 19% $167 19% 18% 15% 9% 9% $19 $2 $5 $6 $6 -$2.5 $0.0 -$0.1 $0.0 $0.0 -$0.9 -$6.5 Cost Savings Full comp. (2+ bids) Full comp. (1 bid) Partial comp. (2+ bids) Partial comp. (1 bidder) Follow on to competed action No comp. Unclear comp. Cost Overruns Cost Savings Average Overrun Baseline-Weighted Average Overrun 40% 30% 20% 10% 0% -10% The type of contract award process could potentially also be correlated with cost performance of MDAPs. The findings in Figure 8 are decidedly mixed. In absolute dollar terms, competitive contracts produce less cost growth than contracts awarded with no competition or under unclear circumstances. This is driven by the comparative scarcity of competed contract dollars in the sample. As a result, when comparing relative cost overrun rates the results are different. Only partial competition 3 with multiple bidders displays a notably better outcome. Perhaps surprisingly, full and open competition with multiple bidders performs on average worse than no or unclear competition. Only when considering baseline-weighted averages does full and open competition with multiple bidders perform better than no or unclear competition. Based on the SAR s data, this can be attributed to full and open competition with multiple bidders having the highest percentage of estimating variance of any of the categories. This result is consistent with the hypothesis that bidders may propose lower costs in order to win price-based competitions. However, further study would be needed to determine whether full and open competitions also suffer from a selection bias or other unexplained cause. 3 Partial competition refers to forms of competition other than full and open because the number of bidders is legally limited. 12 P a g e
13 Nominal cost overruns (in then year billions, quantity adjusted) Nominal Cost Overruns (In percent, weighted by percent of MDAP accounted for in FPDS, quantity adjusted) Figure 9: Cost overruns by contract type $225 $200 Cost Overruns 44% 45% 40% $175 $150 $125 $100 $75 20% 20% 28% 27% 32% 28% 35% $211 31% 19% 35% 30% 25% 20% 15% $50 $25 $- $(25) $67 $69 $52 $20 Cost Savings -$1.2 $0.0 -$2.2 -$0.1 -$6.5 Fixed price Combination Cost-plus award/incentive Cost (all other*) Unspecified Cost Overruns Cost Savings Average Overrun Baseline-Weighted Average Overrun * Cost (all other) includes time and materials contracts as well as labor hours contracts. Contract structure provides another possible determining factor for the performance of MDAPs. One key observation from Figure 9 is that fixed price contracts appear to have on average less cost growth and the cost all other contract types appear to have more, when comparing the share of cost growth and the share of contract value for MDAPs. An interesting finding is the fact that unspecified contract types, while responsible for the majority of cost overruns in absolute terms, perform best when measured based on baseline-weighted averages. 10% 5% 0% -5% Acquisition reformers often point toward cost-plus contracts as a factor driving cost overruns. This argument is supported by the high average cost overruns percentages of both categories of cost plus contracts. The type of fee structure used also appears relevant, as cost-plus award/incentive contracts have lower relative cost growth than all other forms of cost reimbursement contracting, although this is driven in part by the outsized influence of the F-35 project which falls within the cost (all other) category. However, fixed price contracts are more commonly the vehicle of choice for mature technology in full rate production, which are generally considered low risk. 13 P a g e
14 Findings This report provides a foundation for future researchers and reformers grappling with the problem of cost overruns in major defense acquisition projects. The results discussed below have been validated by the two most recent Selected Acquisition Reports and together with the underlying data and methodology provide a roadmap for future work. The strongest correlation with net cost growth is shown in Figure 2: changes in cost estimates are responsible for around 40 percent of the accumulated cost overruns. Of similarly importance, Figure 3 shows that the start year has little impact on the compound annual growth rate of cost overruns. This suggests that relatively better performance of newer programs may prove illusionary as programs age. Finally, figure 9 shows that fixed price contracts appear to have relatively smaller overruns, although this may tell us more about which programs are likely to receive fixed price contracts rather than what effect fixed price contracts may have on program performance. There are three logical avenues for future research to build on these results. First, additional factors could be added to the mix to help allocate responsibility to underlying characteristics of an MDAP versus the methods chosen to implement it. Second, the dataset could be steadily expanded to include completed projects and to widen the historical scope and sample size of the project. Third, researchers could examine cost growth throughout the history of a select number of programs and also better control for the effects of updated baselines on older projects. Finally, the government could facilitate all three approaches and enable a range of assessments by allowing outside researchers to access the data that underlies the Selected Acquisition Reports. Reformers and others studying this issue can take the next step by accessing the data, which will be posted at the Defense-Industrial Initiatives Group website ( in time for the May 2011 Naval Post-Graduate School conference. The authors intend to stay fully engaged with this issue as the root causes underlying the crisis in MDAP cost growth are being identified and addressed. 14 P a g e
15 Biographies David J. Berteau is a Senior Adviser and Director of the CSIS Defense-Industrial Initiatives Group, covering defense management, programs, contracting, and acquisition. His group also assesses national security economics and the industrial base supporting defense. Mr. Berteau is an adjunct professor at Georgetown University, a member of the Defense Acquisition University Board of Visitors, a director of the Procurement Round Table, and a fellow of the National Academy of Public Administration. He also serves on the Secretary of the Army s Commission on Army Acquisition and Program Management in Expeditionary Operations. Guy Ben-Ari is Deputy Director of the Defense-Industrial Initiatives Group at the Center for Strategic International Studies, where he works on projects related to the U.S. technology and industrial bases supporting defense. His current research efforts involve defense R&D policies, defense economics, and managing complex defense acquisition programs. Mr. Ben-Ari holds a Bachelor s degree in political science from Tel Aviv University, a Master s degree in international science and technology policy from the George Washington University, and is currently a PhD candidate (ABD) at the George Washington University. Joachim Hofbauer is a fellow with the Defense-Industrial Initiatives Group at the Center for Strategic and International Studies (CSIS). He specializes in U.S. and European defense acquisition and industrial base issues and their impact on the transatlantic defense market. Before joining CSIS, Mr. Hofbauer worked as a freelance defense analyst in Germany and the United Kingdom. His analysis has been published in several U.S. and German defense publications. Mr. Hofbauer holds a B.A. in European studies from the University of Passau and a M.A. with honors in security studies, with a concentration in defense analysis, from Georgetown University. Gregory Sanders is a fellow with the Defense-Industrial Initiatives Group at CSIS, where he gathers and analyzes data on U.S. defense acquisition and contract spending as international defense budgetary and trade trends. He has also studied data visualization and ways to use complex data collections to create succinct and innovative tables, charts, and maps. Mr. Sanders holds an M.A. in international relations from the University of Denver and a B.A. in government and politics, as well as a B.S. in computer science, from the University of Maryland. 15 P a g e
16 Jesse Ellman is a research associate with the Defense-Industrial Initiatives Group at the Center for Strategic and International Studies (CSIS). He specializes in U.S. defense acquisition issues, with a particular focus on recent U.S. Army modernization efforts. Mr. Ellman holds a B.A. in Political Science from Stony Brook University, and a M.A. with honors in Security Studies, with a concentration in Military Operations, from Georgetown University David Morrow is a research associate with the Defense-Industrial Initiatives Group (DIIG) at CSIS, where he focuses on federal professional services contracting, U.S. naval shipbuilding, and private security contracting. Previously, Mr. Morrow interned at the U.S. Department of State s Office of European Security and Political Affairs and at the U.S.-Russia Business Council. He holds a B.A. in international affairs from James Madison University and an M.A. in European and Eurasian Studies from the George Washington University. 16 P a g e
17 About CSIS At a time of new global opportunities and challenges, the Center for Strategic and International Studies (CSIS) provides strategic insights and policy solutions to decisionmakers in government, international institutions, the private sector, and civil society. A bipartisan, nonprofit organization headquartered in Washington, DC, CSIS conducts research and analysis and develops policy initiatives that look into the future and anticipate change. Founded by David M. Abshire and Admiral Arleigh Burke at the height of the Cold War, CSIS was dedicated to finding ways for America to sustain its prominence and prosperity as a force for good in the world. Since 1962, CSIS has grown to become one of the world s preeminent international policy institutions, with more than 220 full-time staff and a large network of affiliated scholars focused on defense and security, regional stability, and transnational challenges ranging from energy and climate to global development and economic integration. Former U.S. senator Sam Nunn became chairman of the CSIS Board of Trustees in 1999, and John J. Hamre has led CSIS as its president and chief executive officer since April CSIS does not take specific policy positions; accordingly, all views expressed in this presentation should be understood to be solely those of the author(s). 17 P a g e
Defense Contract Trends
Defense Contract Trends U.S. Department of Defense Contract Spending and the Supporting Industrial Base An Annotated Brief by the CSIS Defense-Industrial Initiatives Group PROJECT DIRECTORS David Berteau
DEFENSE ACQUISITION WORKFORCE
United States Government Accountability Office Report to Congressional Committees December 2015 DEFENSE ACQUISITION WORKFORCE Actions Needed to Guide Planning Efforts and Improve Workforce Capability GAO-16-80
WEAPONS ACQUISITION REFORM
GAO United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate September 2011 WEAPONS ACQUISITION REFORM Actions Needed to Address Systems Engineering and Developmental
GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices
GAO United States Government Accountability Office Report to Congressional Addressees March 2013 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices
DoD Workforce Cost Realism Assessment
a report of the csis defense-industrial initiatives group DoD Workforce Cost Realism Assessment Authors David Berteau Joachim Hofbauer Jesse Ellman Gregory Kiley Guy Ben-Ari May 2011 a report of the csis
WEAPONS ACQUISITION REFORM
GAO United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate December 2012 WEAPONS ACQUISITION REFORM Reform Act Is Helping DOD Acquisition Programs Reduce
INSPECTOR GENERAL DEPARTMENT OF DEFENSE 4800 MARK CENTER DRIVE ALEXANDRIA, VIRGINIA 22350-1500
INSPECTOR GENERAL DEPARTMENT OF DEFENSE 4800 MARK CENTER DRIVE ALEXANDRIA, VIRGINIA 22350-1500 MAY 2 8 2014 MEMORANDUM FOR DISTRIBUTION SUBJECT: Government Accountability Office (GAO) Weekly Activity Repati
a GAO-06-530 GAO DEFENSE WORKING CAPITAL FUND Military Services Did Not Calculate and Report Carryover Amounts Correctly
GAO United States Government Accountability Office Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives June 2006 DEFENSE WORKING CAPITAL FUND Military
STRATEGIC SOURCING. Opportunities Exist to Better Manage Information Technology Services Spending
United States Government Accountability Office Report to Congressional Requesters September 2015 STRATEGIC SOURCING Opportunities Exist to Better Manage Information Technology Services Spending GAO-15-549
GAO. DEFENSE CONTRACTING Progress Made in Implementing Defense Base Act Requirements, but Complete Information on Costs Is Lacking
GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, May 15, 2008 United States Government Accountability Office Testimony Before the Committee on Oversight and Government Reform, House of
Information Technology
September 11, 2002 Information Technology The Defense Advanced Research Projects Agency s Transition of Advanced Information Technology Programs (D-2002-146) Department of Defense Office of the Inspector
GAO. DEFENSE INFRASTRUCTURE Funding Risks in Services 1999 Central Training Programs
GAO United States General Accounting Office Report to the Chairman, Committee on the Budget, House of Representatives February 1999 DEFENSE INFRASTRUCTURE Funding Risks in Services 1999 Central Training
DOD BUSINESS SYSTEMS MODERNIZATION. Additional Action Needed to Achieve Intended Outcomes
United States Government Accountability Office Report to Congressional Committees July 2015 DOD BUSINESS SYSTEMS MODERNIZATION Additional Action Needed to Achieve Intended Outcomes GAO-15-627 July 2015
STATEMENT BY DAVID DEVRIES PRINCIPAL DEPUTY DEPARTMENT OF DEFENSE CHIEF INFORMATION OFFICER BEFORE THE
STATEMENT BY DAVID DEVRIES PRINCIPAL DEPUTY DEPARTMENT OF DEFENSE CHIEF INFORMATION OFFICER BEFORE THE HOUSE OVERSIGHT AND GOVERNMENT REFORM COMMITTEE S INFORMATION TECHNOLOGY SUBCOMMITTEE AND THE VETERANS
GAO DEFENSE INVENTORY. Defense Logistics Agency Needs to Expand on Efforts to More Effectively Manage Spare Parts. Report to Congressional Requesters
GAO United States Government Accountability Office Report to Congressional Requesters May 2010 DEFENSE INVENTORY Defense Logistics Agency Needs to Expand on Efforts to More Effectively Manage Spare Parts
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Defense Acquisition Executive Summary (DAES)
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Defense Acquisition Executive Summary (DAES) Portfolio Management and Integration Directorate DCMA-INST 406 DCMA-PII Validated current,
The Program Managers Guide to the Integrated Baseline Review Process
The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...
Managing Cost Reimbursable Contracts
Managing Cost Reimbursable Contracts Providing Guidance in Difficult Waters Management Guide & Desk Reference Compiled and Written by: Don Philpott Scott P Cook 233 Pages ISBN: 978-0-9844038-6-8 Published
Information Technology
May 7, 2002 Information Technology Defense Hotline Allegations on the Procurement of a Facilities Maintenance Management System (D-2002-086) Department of Defense Office of the Inspector General Quality
June 16, 2015 PURPOSE
June 16, 2015 BACKGROUND MEMO TO: FROM: RE: Members, Subcommittee on Economic Development, Public Buildings, and Emergency Management Staff, Subcommittee on Economic Development, Public Buildings, and
GAO CONTRACT MANAGEMENT. Small Businesses Continue to Win Construction Contracts. Report to Congressional Committees
GAO United States General Accounting Office Report to Congressional Committees June 2001 CONTRACT MANAGEMENT Small Businesses Continue to Win Construction Contracts GAO-01-746 Contents Letter 1 Results
WEAPON SYSTEM ACQUISITIONS. Opportunities Exist to Improve the Department of Defense s Portfolio Management
United States Government Accountability Office Report to Congressional Committees August 2015 WEAPON SYSTEM ACQUISITIONS Opportunities Exist to Improve the Department of Defense s Portfolio Management
ort Office of the Inspector General Department of Defense YEAR 2000 COMPLIANCE OF THE STANDARD ARMY MAINTENANCE SYSTEM-REHOST Report Number 99-165
it ort YEAR 2000 COMPLIANCE OF THE STANDARD ARMY MAINTENANCE SYSTEM-REHOST Report Number 99-165 May 24, 1999 Office of the Inspector General Department of Defense Additional Copies To obtain additional
GAO FEDERAL PROPERTY DISPOSAL. Information on DOD s Surplus Property Program
GAO United States General Accounting Office Testimony Before the Subcommittee on Government Management, Information, and Technology, Committee on Government Reform and Oversight, House of Representatives
a GAO-02-635 GAO DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting Issues Remain
GAO United States General Accounting Office Report to the Chairman, Committee on Government Reform, House of Representatives May 2002 DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010
THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 ACQUlsmON, TECHNOLOGY AND LOG ISTICS AUG 1 0 2011 MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT
DEFENSE LOGISTICS. Army Should Track Financial Benefits Realized from its Logistics Modernization Program. Report to Congressional Requesters
United States Government Accountability Office Report to Congressional Requesters November 2013 DEFENSE LOGISTICS Army Should Track Financial Benefits Realized from its Logistics Modernization Program
Acquisition Decision Memorandum for the Defense Integrated Military Human Resources System
Report No. D-2010-041 February 5, 2010 Acquisition Decision Memorandum for the Defense Integrated Military Human Resources System SPECIAL WARNING This report contains DoD Planning, Programming, and Budget
Deficits as far as the eye can see
Testimony of Mark A. Calabria, Ph.D. Director, Financial Regulation Studies, Cato Institute Submitted to the Subcommittee on Insurance, Housing, & Community Opportunity House Committee on Financial Services
GAO DEFENSE WORKING CAPITAL FUNDS. DOD Faces Continued Challenges in Eliminating Advance Billing
GAO United States General Accounting Office Testimony Before the Subcommittee on Military Readiness, Committee on National Security, House of Representatives For Release on Delivery Expected at 2 p.m.
FACT SHEET. General Information about the Defense Contract Management Agency
FACT SHEET General Information about the Defense Contract Management Agency Mission: We are the independent eyes and ears of DoD and its partners, delivering actionable acquisition insight from the factory
Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D-2004-109)
August 17, 2004 Acquisition Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D-2004-109) Department of Defense Office of the Inspector General Quality
Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054)
February 23, 2004 Acquisition Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054) This special version of the report has
The Financial Returns from Oil and Natural Gas Company Stocks Held by American College and University Endowments. Robert J. Shapiro and Nam D.
The Financial Returns from Oil and Natural Gas Company Stocks Held by American College and University Endowments Robert J. Shapiro and Nam D. Pham December 2012 Table of Contents I. Executive Summary..
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL BACKGROUND
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL July 23, 2013 AUDIT SERVICES Control Number ED-OIG/A09L0001 James W. Runcie Chief Operating Officer Federal Student Aid U.S. Department
CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS
Chapter Six CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS Bibliographic Information: Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental
FEDERAL PERSONNEL Observations on the Navy s Managing To Payroll Program
United States General Accounting Office GAO Report to the Chairman, Subcommittee * on Federal Services, Post Office and Civil Services, Committee on Governmental Affairs, U.S. Senate March 1990 FEDERAL
REVIEW OF NASA S INTERNAL CONTROLS FOR AWARDS WITH SMALL BUSINESSES
FEBRUARY 28, 2013 AUDIT REPORT OFFICE OF AUDITS REVIEW OF NASA S INTERNAL CONTROLS FOR AWARDS WITH SMALL BUSINESSES OFFICE OF INSPECTOR GENERAL National Aeronautics and Space Administration REPORT NO.
David J. Berteau Senior Vice President and Director of International Security Program, Center for Strategic & International Studies
David J. Berteau Senior Vice President and Director of International Security Program, Center for Strategic & International Studies David J. Berteau is senior vice president and director of the CSIS International
GAO DEFENSE CONTRACTING. Contract Risk a Key Factor in Assessing Excessive Pass-Through Charges. Report to Congressional Committees
GAO United States Government Accountability Office Report to Congressional Committees January 2008 DEFENSE CONTRACTING Contract Risk a Key Factor in Assessing Excessive Pass-Through Charges GAO-08-269
GAO MILITARY EDUCATION. DOD Needs to Enhance Performance Goals and Measures to Improve Oversight of Military Academies
GAO United States General Accounting Office Report to the Subcommittee on Defense, Committee on Appropriations, House of Representatives September 2003 MILITARY EDUCATION DOD Needs to Enhance Performance
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
Faculty Productivity and Costs at The University of Texas at Austin
Faculty Productivity and Costs at The University of Texas at Austin A Preliminary Analysis Richard Vedder Christopher Matgouranis Jonathan Robe Center for College Affordability and Productivity A Policy
AUDIT REPORT. Follow-up on the Department of Energy's Acquisition and Maintenance of Software Licenses
U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT Follow-up on the Department of Energy's Acquisition and Maintenance of Software Licenses DOE/IG-0920
Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected].
Overview of SAE s AS6500 Manufacturing Management Program David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected] 1 Outline Background Objectives Requirements Implementation
Deputy Chief Financial Officer Peggy Sherry. And. Chief Information Security Officer Robert West. U.S. Department of Homeland Security.
Deputy Chief Financial Officer Peggy Sherry And Chief Information Security Officer Robert West U.S. Department of Homeland Security Testimony Before the Subcommittee on Government Organization, Efficiency
NAVY WORKING CAPITAL FUND. Budgeting for Carryover at Fleet Readiness Centers Could Be Improved
United States Government Accountability Office Report to Congressional Requesters June 2015 NAVY WORKING CAPITAL FUND Budgeting for Carryover at Fleet Readiness Centers Could Be Improved GAO-15-462 June
DoD Business Process Reengineering CONSTRUCTION IN PROGRESS REQUIREMENTS DOCUMENT
DoD Business Process Reengineering CONSTRUCTION IN PROGRESS REQUIREMENTS DOCUMENT Office of the Deputy Undersecretary of Defense (Installations & Environment) Business Enterprise Integration Directorate
F-35 JOINT STRIKE FIGHTER. Problems Completing Software Testing May Hinder Delivery of Expected Warfighting Capabilities
United States Government Accountability Office Report to Congressional Committees March 2014 F-35 JOINT STRIKE FIGHTER Problems Completing Software Testing May Hinder Delivery of Expected Warfighting Capabilities
Information Technology (IT) Investment Management Insight Policy for Acquisition
MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT CHIEFS OF STAFF UNDER SECRETARIES OF DEFENSE DIRECTOR, DEFENSE RESEARCH AND ENGINEERING ASSISTANT SECRETARIES OF DEFENSE GENERAL
F-35 JOINT STRIKE FIGHTER Preliminary Observations on Program Progress
For Release on Delivery Expected at 9:00 a.m. ET Thursday, March 5, 2015 United States Government Accountability Office Testimony Before the Subcommittee on Tactical Air and Land Forces, Committee on Armed
Subject: GSA On-line Procurement Programs Lack Documentation and Reliability Testing
United States General Accounting Office Washington, DC 20548 December 21, 2001 The Honorable Stephen A. Perry Administrator General Services Administration 1800 F Street NW Washington, DC 20405 Subject:
Part II: Agency R&D Budgets
Part II: Agency R&D Budgets 5 Department of Defense Travis R. Doom Consortium for Science, Policy and Outcomes Highlights Department of Defense (DOD) R&D would continue its recent downward trend since
A Cure for Unanticipated Cost and Schedule Growth
+ Thomas J. Coonce Glen B. Alleman A Cure for Unanticipated Cost and Schedule Growth We have lots data. Let s use it create more credible estimates to help tame the growth beast + Why Are We Here? 2 In
by taking critical systems out of action and creating safety hazards.
United States Government Accountability Office Washington, DC 20548 September 10, 2012 Congressional Committees Subject: Defense Management: The Department of Defense s Annual Corrosion Budget Report Does
Page 1. June 26, 2012. The Honorable Carl Levin Chairman The Honorable John McCain Ranking Member Committee on Armed Services United States Senate
United States Government Accountability Office Washington, DC 20548 June 26, 2012 The Honorable Carl Levin Chairman The Honorable John McCain Ranking Member Committee on Armed Services United States Senate
ELECTRONIC HEALTH RECORDS. Fiscal Year 2013 Expenditure Plan Lacks Key Information Needed to Inform Future Funding Decisions
United States Government Accountability Office Report to Congressional July 2014 ELECTRONIC HEALTH RECORDS Fiscal Year 2013 Expenditure Plan Lacks Key Information Needed to Inform Future Funding Decisions
How Does Foreign Industry Sell to the U.S. Department of Defense
0 How Does Foreign Industry Sell to the U.S. Department of Defense Mr. Jeff Grover, Senior Procurement Analyst Contract Policy & International Contracting OUSD(AT&L) Defense Procurement and Acquisition
VA Office of Inspector General
VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Audit of Office of Information Technology s Strategic Human Capital Management October 29, 2012 11-00324-20
DEPARTMENT-LEVEL ACCOUNTING ENTRIES FOR FY1999. Report No. D-2000-179 August 18, 2000. Office of the Inspector General Department of Defense
DEPARTMENT-LEVEL ACCOUNTING ENTRIES FOR FY1999 Report No. D-2000-179 August 18, 2000 Office of the Inspector General Department of Defense Additional Copies To obtain additional copies of this audit report,
STRATEGIC SOURCING. Selected Agencies Should Develop Performance Measures on Inclusion of Small Businesses and OMB Should Improve Monitoring
United States Government Accountability Office Report to Congressional Requesters January 2014 STRATEGIC SOURCING Selected Agencies Should Develop Performance Measures on Inclusion of Small Businesses
AN ANALYSIS OF UNEMPLOYMENT TRENDS AMONG IEEE U.S. MEMBERS. Laura Langbein, Ph.D.
AN ANALYSIS OF UNEMPLOYMENT TRENDS AMONG IEEE U.S. MEMBERS Prepared by Laura Langbein, Ph.D. Professor of Public Affairs The American University Based on a Survey of Unemployed US IEEE Members Conducted
Navy s Contract/Vendor Pay Process Was Not Auditable
Inspector General U.S. Department of Defense Report No. DODIG-2015-142 JULY 1, 2015 Navy s Contract/Vendor Pay Process Was Not Auditable INTEGRITY EFFICIENCY ACCOUNTABILITY EXCELLENCE INTEGRITY EFFICIENCY
Review of U.S. Coast Guard's FY 2014 Detailed Accounting Submission
Review of U.S. Coast Guard's FY 2014 Detailed Accounting Submission January 23, 2015 OIG-15-28 HIGHLIGHTS Review of U.S. Coast Guard s FY 2014 Detailed Accounting Submission January 23, 2015 Why We Did
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 3204.01 August 20, 2014 USD(AT&L) SUBJECT: DoD Policy for Oversight of Independent Research and Development (IR&D) References: See Enclosure 1 1. PURPOSE. This
EDWARD G. LEWIS 556 East Gill Way, Superior, Colorado 80027-8002 Tel: 303-494-6537; Fax: 303-494-0645; E-Mail: [email protected]
556 East Gill Way, Superior, Colorado 80027-8002 Tel: 303-494-6537; Fax: 303-494-0645; E-Mail: [email protected] PROFESSIONAL EXPERIENCE 2001 - Present Member, Board of Directors, National Veterans Business
Big Data and Analytics Survey. Exclusive Research from
2015 Big Data and Analytics Survey Exclusive Research from 2015 Big Data & Analytics Survey Insights into Initiatives and Strategies Driving Data Investments Companies are still scrambling to manage ongoing
Statement. Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation. Before
Statement of Mr. Paul A. Brinkley Deputy Under Secretary of Defense for Business Transformation Before THE UNITED STATES SENATE ARMED SERVICES COMMITTEE (SUBCOMMITTEE ON READINESS AND MANAGEMENT SUPPORT)
A Study of Career Patterns of the Presidents of Independent Colleges and Universities
A Study of Career Patterns of the Presidents of Independent Colleges and Universities Harold V. Hartley III Eric E. Godin A Study of Career Patterns of the Presidents of Independent Colleges and Universities
GAO AIR FORCE WORKING CAPITAL FUND. Budgeting and Management of Carryover Work and Funding Could Be Improved
GAO United States Government Accountability Office Report to the Subcommittee on Readiness and Management Support, Committee on Armed Services, U.S. Senate July 2011 AIR FORCE WORKING CAPITAL FUND Budgeting
Funding Invoices to Expedite the Closure of Contracts Before Transitioning to a New DoD Payment System (D-2002-076)
March 29, 2002 Financial Management Funding Invoices to Expedite the Closure of Contracts Before Transitioning to a New DoD Payment System (D-2002-076) Department of Defense Office of the Inspector General
Using Parametric Software Estimates During Program Support Reviews
Using Parametric Software Estimates During Program Support Reviews Version 1.0 Chris Miller Office of the Deputy Director, Software Engineering and System Assurance SYSTEMS & SOFTWARE ENGINEERING Office
Defense Logistics Agency Effectively Managed Continental U.S. Mission-Critical Batteries
Report No. DoDIG-2014-032 I nspec tor Ge ne ral U.S. Department of Defense JA N UA RY 2 7, 2 0 1 4 Defense Logistics Agency Effectively Managed Continental U.S. Mission-Critical Batteries I N T E G R I
Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger
DODIG-2012-051 February 13, 2012 Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger Additional Copies
AIR FORCE WORKING CAPITAL FUND. Actions Needed to Manage Cash Balances to Required Levels
United States Government Accountability Office Report to the Subcommittee on Readiness and Management Support, Committee on Armed Services, U.S. Senate July 2014 AIR FORCE WORKING CAPITAL FUND Actions
Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck?
Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck? Breakout Session #: F05 Presented by: Gail Guseman Deloitte Consulting, LLP Date: July 23, 2013 Time: 4:00 pm
Office of the Inspector General Department of Defense
INDEPENDENT REVIEW OF THE DEFENSE FINANCE AND ACCOUNTING SERVICE COST COMPARISON STUDY OF CIVILIAN PAY FUNCTION Report No. D-2001-173 August 14, 2001 Office of the Inspector General Department of Defense
2012 Capital Insight. Federal Perspective. Day Two Friday, November 16. The Hay-Adams One Lafayette Square at 16th and H Streets Washington, DC
2012 Capital Insight Federal Perspective Day Two Friday, November 16 The Hay-Adams One Lafayette Square at 16th and H Streets Washington, DC Day Two Friday, November 16, 2012 Federal Perspective 7:30 am
VA Office of Inspector General
VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Review of the Management of Travel, Duty Stations, Salaries and Funds in the Procurement and Logistics Office
Accenture Federal Services. Federal Solutions for Asset Lifecycle Management
Accenture Federal Services Federal Solutions for Asset Lifecycle Management Assessing Internal Controls 32 Material Weaknesses: identified in FY12 with deficiencies noted in the management of nearly 75%
How To Write A Defense Science And Technology Policy Report
United States Government Accountability Office Report to Congressional Committees March 2015 DEFENSE SCIENCE AND TECHNOLOGY Further DOD and DOE Actions Needed to Provide Timely Conference Decisions and
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains Mary J. Simpson System Concepts 6400 32 nd Northwest, #9 Seattle, WA 98107 USA Joseph J. Simpson System Concepts