Olkiluoto 3 Experience



Similar documents
Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY

MDEP Generic Common Position No DICWG 02

Ensuring Quality Going Down the Supply Chain

December 5, 2013 VENDOR INSPECTION PROGRAM ANNUAL SELF-ASSESSMENT REPORT FOR FISCAL YEAR 2013

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Nuclear Safety. Policy

AREVA: supply chain network principles and company s vision

Human Factors in Design and Construction Regulatory Perspective

Human Resource Management in Nuclear Safety

R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

Structural Integrity and NDE Reliability II

QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G A, Appendix A, )

ELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY

May 7, SUBJECT: NRC INSPECTION REPORT FOR AREVA-NP GmbH / , NOTICE OF VIOLATION, AND NOTICE OF NONCONFORMANCE

How To Decommission A Nuclear Plant

IAEA Safety Standards for Regulatory Activities

NOT PROTECTIVELY MARKED

CORDEL Cooperation in Reactor Design Evaluation and Licensing

UAE Nuclear Power Programme : Status and Update

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012

Flamanville 3 Nuclear Power Plant

Join the UK Nuclear Renaissance. Procurement & Quality Process

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES

The OL3 Nuclear Power Plant Construction Project. A Learning Experience

US EPA REGION III QUALITY MANAGEMENT PLAN REVIEW CHECKLIST

Schweppes Australia Head Office Level 5, 111 Cecil Street South Melbourne Victoria

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

QUALITY ASSURANCE GUIDE FOR PROJECT MANAGEMENT

NZQA registered unit standard version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract

This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM

Sellafield Ltd, Registered in England number

ENEC Management System and Quality Assurance Program

NEI 06-13A [Revision 0] Template for an Industry Training Program Description

The World Nuclear Supply

C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities

Linac Coherent Light Source (LCLS)

1.040 Project Management

AP1000 European 18. Human Factors Engineering Design Control Document

Nuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system

Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201

VDOT GOVERNANCE DOCUMENT

POWER & RENEWABLE ENERGY SERVICES

STANDARD REVIEW PLAN

SAFETY SOFTWARE QUALITY ASSURANCE FUNCTIONAL AREA QUALIFICATION STANDARD. DOE Defense Nuclear Facilities Technical Personnel

How To Write A Contract For Software Quality Assurance

MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)

QUALITY MANAGEMENT SYSTEM (QMS) MANUAL

U.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN. Organization responsible for the review of instrumentation and controls

ISO/IEC QUALITY MANUAL

RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND

King Fahd University of Petroleum and Minerals

POWER & RENEWABLE ENERGY SERVICES

Nuclear Consultancy & Engineering Services

Swiss media visit to Olkiluoto August 15, 2014

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary

I S O I E C I N F O R M A T I O N S E C U R I T Y A U D I T T O O L

Title: Rio Tinto management system

Quality Assurance Program Plan. July U.S. Department of Energy Office of Legacy Management

Section 100 Contractor Quality Control Program

Quality Assurance QUALITY ASSURANCE PLAN

Guidance for the Quality Assurance of Fire Protection Systems

Steel procurement in major projects: Guidance on the application of social issues. Purpose

Horizon NSL Pre-Application Intervention Strategy

MAINTENANCE MANAGEMENT PROGRAM FOR DOE NUCLEAR FACILITIES

IAEA-TECDOC Configuration management in nuclear power plants

IMPLEMENTING THE REGULATORY AUTHORITY INFORMATION SYSTEM (RAIS)

IAEA-TECDOC Assuring the competence of nuclear power plant contractor personnel

INVESTIGATION REPORT 1/06 Nuclear Reactor Regulation Translation

NRC INSPECTION MANUAL

International Association of Scientific Innovation and Research (IASIR) (An Association Unifying the Sciences, Engineering, and Applied Research)

TfNSW Standard Requirements TSR T Technical Management

F4E-QA QUALITY CLASSIFICATION

Rev: Issue 4 Rev 4 Quality Manual AOP0101 Date: 10/07/13. Quality Manual. CBT Technology, Inc. 358 North Street Randolph, MA 02368

Quality Management System-A Revision 7 (NRC-approved Version)

CHAPTER 6. Supply Chain Management CONTENTS

HOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY

BASE CONSTRUCTION INC

PROJECT MANAGEMENT BASICS

TVO and Nuclear Waste Management at Olkiluoto. Corporate Adviser

The Essential Guide to the new build nuclear supply chain

Develop Project Charter. Develop Project Management Plan

Quality Assurance Manual. QAM-2013-Rev2

Supply Chain Management Forum Stellenbosch

Supplier Quality Management System Audit Checklist (ISO 9000:2000, TS 16949:2002)

IAEA-TECDOC-1328 Solutions for cost effective assessment of software based instrumentation and control systems in nuclear power plants

Executive Director for Operations AUDIT OF NRC S CYBER SECURITY INSPECTION PROGRAM FOR NUCLEAR POWER PLANTS (OIG-14-A-15)

6. Q: A: No, however it is anticipated that the PM firm will need to understand FEMA and HUD CDBG compliance as part of the scope of services. 7.

Audits must be conducted with due concern for employee safety and environmental protection.

Quality Management in the Design and Construction of Enclosure Systems. Mike Steffen Martin Houston Walsh Construction Co.

Transcription:

Olkiluoto 3 Experience CNRA International Workshop on New Reactor Siting, Licensing and Construction Experience Hosted by the State Office for Nuclear Safety Prague, Czech Republic 15-17 September 2010 Petteri Tiippana Director Nuclear Reactor Regulation Radiation and Nuclear Safety Authority, STUK

Outline General about Olkiluoto 3 project Regulatory framework in the country of construction Design completion and management Experience and know how Role of Quality Management New and advanced manufacturing technologies Licensee s responsibility Safety culture Regulatory oversight and issues Conclusions 28.7.2010

OL3 Project - General OL3 is the first EPR being constructed OL3 is a turn key project Owner and operator (Licensee) is TVO Constructed by Consortium of Areva and Siemens Project is progressing but is more than three years behind original schedule Photos: TVO 28.7.2010

Regulatory framework in the country of construction Regulator Vendor and licensee are familiar with regulatory framework in the country of construction Owner Owner Licensing, regulatory system and requirements are understood by vendor and licensee Vendor Vendor Safety criteria are clear and known even before bidding process starts Subcontractor Use of different technical standards in the project are clarified early Regulatory approvals needed during the project (hold points) are known and understood by the licensee and vendor Design Approval of Detailed design Manufacturing documentation Approval of Manufacturer Inspection Org Testing Org Manufacturing Inspections during and at the end of manufacturing Installation on site Installation Inspection Commissioning Commissioning Inspection

Completion and management of the plant s design Design of the plant Completion of the design prior construction New design features, Resources needed for the design work Management of the design Explicit design and implementation requirements Design configuration and change management Operational Operation Transparent path of requirements from plant level to the design of systems, structures and components Interfaces between technical disciplines, between different organisations, between design and procurement Safety Others Owner Vendor PSAR Vendor/ Sub contractors Systems Components Structures Sub contractors Manufacturing Construction Sub contractors Installation Installation inspections, Tests FSAR Commissioning

Experience and know how of the licensee and vendor, management of subcontractors Key persons (project management, QA, QC, Safety) experience in nuclear power construction and operation Adequate human resources (staffing studies covering the whole project) Subcontracted work need to be carefully managed vendor in house capabilities vs. what needs to be subcontracted how subcontracting is managed (selected, trained, qualified and controlled) length of subcontractor chains? are subcontractors ready for the project? Owner Vendor Subcontractor

Role of quality management Nuclear specific requirements vs. conventional Unambiguous link between safety significance and quality requirements Common understanding on QA requirements throughout the project Regulator, licensee, vendor and its subcontractors For example definition and classification of a non conformance Management is committed to QA Trained, interested, uses QA as a management tool Quality Policy Top Management s Commitment to high Quality and Safety Culture

New and advanced manufacturing technology Qualification of a new construction or manufacturing method may take time First pieces coming from manufacturing may not meet all specifications 28.7.2010

Licensee s responsibility in turn key contract Licensee is always responsible for everything Has to control and oversee everything - Independently of the contract type Highlights the importance of clear and explicit requirements for design, manufacturing and construction, commissioning... systematic, transparent and traceable requirement management together with strong and competent QA/QC to be able to verify compliance with the requirements Subcontractor SSC1 SSC2 Licensee Vendor Subcontractor

Safety culture in a construction project Quality Familiarity with and understanding of safety culture aspects in a construction project Safety and quality has higher priority than costs and schedule Understanding of the safety significance of the work, to promote personal responsibility for own performance Understanding and respect of the hazard - Observance of design criteria, inspection and quality requirements Open reporting of safety and quality issues, feedback to workers Foremen personnel management skills Multiculturalism of the projects and the construction site Cost Schedule Photos: TVO

Regulatory oversight and inspections Trust but verify Stringent regulatory approach and inspections are needed to verify that performance and equipment meet the specifications set by the designer and approved by the regulator The QC inspectors may be under too much financial pressure from the manufacturer, vendor, and licensee, and may not be in a position to order stoppages and necessary corrections if work is not progressing as expected. Regulator is not part of the QC of the project 28.7.2010

Regulatory issues in new construction Safety requirements are up to date before project starts Independence of the regulator with strong powers and enforcement tools Adequate resources, tools etc. for the work Regulatory system and decisions are transparent and traceable Regulator is ready for media and public interest on the project International issues Co-operation between regulators (bilateral, MDEP etc.) has been very useful IAEA services (IRRS, INIR, Pre- OSART etc) 28.7.2010

Conclusions Starting new build has been demanding because much of the earlier experience and resources have been lost from the nuclear industry Highlights the importance of good preparation for the project Construction of a nuclear power plant is a complex project and requires nuclear specific know how safety culture aspects has to be taken into account from the beginning Roles and responsibilities of participating organisations have to be clear (Regulator, Licensee, Vendor, Subcontractors) Clear need for regulatory inspections during construction and manufacturing 28.7.2010