Feasibility Study Mzimvubu Water Project



Similar documents
Payments for Ecosystem Services: towards improved biodiversity conservation and water security in South Africa, a semi-arid, developing country

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

Frequently Asked Questions (FAQs) on Hydropower

Newsletter #5: Groundwater In The National Water Balance

INDONESIA - LAW ON WATER RESOURCES,

Assessment of hydropower resources

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

A Conceptual Software System for Water Allocation, Planning and Catchment Management

Technical Consultant

Design Considerations for Addressing Climate Change Vulnerabilities of Dams and Reservoirs

Remote Sensing and GIS Application In Change Detection Study In Urban Zone Using Multi Temporal Satellite

Figure 1.1 The Sandveld area and the Verlorenvlei Catchment - 2 -

Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005.

< SUBSURFACE DAMS TO AUGMENT GROUNDWATER STORAGE IN BASEMENT TERRAIN FOR HUMAN SUBSISTENCE BRAZILIAN EXPERIENCE >

APPLICATION OF GEOSPATIAL TECHNOLOGIES FOR SUSTAINABLE ENVIRONMENTAL MANAGEMENT

Stormwater Design Guidelines Frequently Asked Questions:

SKIERLEK INFORMAL SETTLEMENT PRE-FEASIBILITY STUDY THABAZIMBI LOCAL MUNICIPALITY

Title: Guiding Models and Norm Study for Water Storage: A new way of thinking?

Building Drought Resilience through Land and Water Management

Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Multi-Dam Systems and their Operation - J.J. Cassidy MULTI-DAM SYSTEMS AND THEIR OPERATION

City of London Climate Change Adaptation Strategy Dealing with Extreme Rainfall Events

6 STEP 6 - PREPARING THE ACTION PLAN 2

Orange River Integrated Water Resources Management Plan. Submitted By: WRP Consulting Engineers, Jeffares and Green, Sechaba Consulting, WCE Pty Ltd,

Abaya-Chamo Lakes Physical and Water Resources Characteristics, including Scenarios and Impacts

Construction Services

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún

Track II Project level analyses. Robert Lempert, RAND

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

Chapter One. Overview of the South African Water Sector. Overall Water Situation in South Africa. Section 2: The South African Water Sector framework

International Commission On Large Dams Environment August A Viewpoint from the International Commission on Large Dams

2 ND SEPTEMBER Report of the Bi-Borough Executive Director for Transport and Technical Services

Strategic Directions for Integrated Water Resources Management in the Lower Mekong Basin

New challenges of water resources management: Title the future role of CHy

WILLOCHRA BASIN GROUNDWATER STATUS REPORT

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

CIVIL ENGINEERING ASSOCIATE, 7246

Hydrological and Material Cycle Simulation in Lake Biwa Basin Coupling Models about Land, Lake Flow, and Lake Ecosystem

Domestic Policy Framework on Adaptation to Climate Change in Water Resources: Case Study for India. Working Together to Respond to Climate Change

Developments in Turkey in the Context of Participatory Approach Based on River Basin Management. Nermin ÇİÇEK, Özge Hande SAHTİYANCI

Guidelines for Minimum Standards Property Management Planning. Financial Management Module

CORUH RIVER DEVELOPMENT PLAN

Below is a step-by-step guide to the process of installing a borehole

edms 5. THAILAND 5.1 Water Resources Management Policies and Actions

Clean Development Mechanism Project Opportunities in Indonesia

HOW TO FUND BASIN MANAGEMENT PLANS? Invest in IWRM - it pays back!

Probabilistic Risk Assessment Studies in Yemen

Methods for Determination of Safe Yield and Compensation Water from Storage Reservoirs

In order to achieve these things, thereby delivering better outcomes for all Tasmanians, change is required.

Global water resources under increasing pressure from rapidly growing demands and climate change, according to new UN World Water Development Report

A Strategy for Teaching Finite Element Analysis to Undergraduate Students

LR 314 Working Group 5 Final Report

Living & Working Managing Natural Resources and Waste

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP LAWS OF SARAWAK, 1958 Ed.)

WATER RESOURCES MANAGEMENT IN TURKEY

World Water and Climate Atlas

4 Water supply description

Hydropower Projects Portfolio

Appendix D.1. Testing Requirements for Infiltration, Bioretention and Sand Filter Subsoils

Introduction. The vision of the West Yorkshire Combined Authority (WYCA) Flood Risk Partnership

River Basin Management in Croatia

How To Improve The Infrastructure Of The City Of Germany

1. Purpose and scope. 2. SEPA's role in hydropower and planning

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk

Water Resource (Great Artesian Basin) Plan Sale of general reserve unallocated water: Tender assessment report

WATER RESOURCES MANAGEMENT IN THE REPUBLIC OF AZERBAIJAN: OVERVIEW AND OUTLOOK

WATER RESOURCES OF MAHARASHTRA STATE The geographical area of the state is 30.7Mha. Cultivable area is 22.5 Mha.(73%GA). Out of this 40% area is

Monitoring alterations in vegetation cover and land use in the Upper Paraguay River Basin Brazilian Portion Period of Analysis: 2002 to 2008

FINANCIAL AND OPERATING HIGHLIGHTS

Hydrologic Engineering Techniques for Regional Water Resources Planning

APPLICATION OF GIS AND REMOTE SENSING IN IRRIGATION NETWORKS MANAGEMENT

Sample Micro Hydro Initial Report

Creating the environment for business

COST EFFECTIVE APPROACHES FOR PRESCRIBED DAM ASSET MANAGEMENT

The development of an information modelling system for regional water resource assessments

Concept Note for an IWRM Masters Degree Program. Armenia, Azerbaijan and Georgia 2012

Concept Note for an IWRM Masters Degree Program. Armenia, Azerbaijan and Georgia 2012

Project Evaluation Guidelines

Local Water Supply, Sanitation and Sewage

Payback period 2.4 years (7% improvement from 2.6 years stated in the MPFS);

Peter McVerry Trust Pre-Budget Submission

Henry Van Offelen Natural Resource Scientist MN Center for Environmental Advocacy

THE GREAT RUAHA RIVER PROFILE

PPC s Involvement in the Application of the WFD

Part B1: Business case developing the business case

How To Map A Lake In The North Of The Holland (Fiji)

Water Resource. 1 Initiating and Sustaining Water Sector Reforms : A Synthesis World Bank in collaboration with the Government of India, Ministry of

The Alternatives of Flood Mitigation in The Downstream Area of Mun River Basin

Master Plan on Water Resource Management

Guidelines for FEASIBILITY STUDY

Bolton s Flood Risk Management Strategy

Exploring the Possibilities of Small Hydropower Development Utilizing NRCS-Assisted Flood Control Dams

Development of Rural Drinking Water Security Plan A Case Study from Raipur Block, Bhilwara District, Rajasthan

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Climate vulnerability assessment Risks from urban flooding Interactive science and policy assessment

Hydroelectric power and development in Argentina

Dr. Lidija Globevnik Luka Snoj, Neven Verdnik, Peter Muck. Meta Povž

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Chehalis River Basin Flood Damage Reduction Capital Budget Approved by Legislature in June 2013

Cultivating Agricultural Information Management System Using GIS Technology

Transcription:

Feasibility Study Mzimvubu Water Project Newsletter 2/September 2013 Activities and Achievements to Date A Detailed Feasibility Study is underway in the Eastern Cape to investigate a potential site for a multipurpose dam to supply new water capacity for irrigation development, domestic and industrial water requirements, and hydropower usage in the Mzimvubu River catchment. As outlined in the first Newsletter of August 2012 the study, which began in January 2012, is divided into two distinct phases of which Phase 1 has been completed and Phase 2 is underway. Phase 1 involved a screening process to investigate 19 potential dam development sites that were identified under previous studies, to select the three sites which showed the most promise in meeting the specific requirements (i.e. domestic water supply, irrigated agriculture and hydropower) in a viable, affordable, sustainable and environmentally acceptable manner. After investigating these three options in some detail, and once all the relevant stakeholders had agreed upon the finally chosen single development option, this single dam option was to be taken forward for further more detailed investigation, in Phase 2 of the study. Phase 1: Report back on the findings of preliminary studies on the three dam development options The shortlisting process, undertaken in consultation with the Stakeholder Forum and members of the Project Steering Committee recommended the three dam development options as: Thabeng, Somabadi, and Ntabelanga sites which are located as shown in Figure 1. Figure 1: Three Dam Sites Selected for Further Investigation 1

The three sites were then rated comparatively to ascertain their viability as a development site. Economic and social aspects of each location were compared and additional detailed investigations included: 1. Hydrological investigation, 2. Topographical surveys, 3. Geotechnical investigations, 4. Investigations into water requirements (agriculture and domestic water supply), 5. Approximate dam sizing, 6. Hydropower potential assessment, and 7. Cost comparison. 1) Hydrological investigation A detailed hydrological assessment including rainfall analysis, rainfall- runoff modelling, stochastic streamflow analysis and yield modelling of both the Kinira and Tsitsa Rivers was undertaken. This allowed accurate and reliable yield assessments to be produced for each of the three dams which aided in making the optimisation and economic comparison of the three options more robust. The outputs of the modelling exercise were used along with the topographical survey data to provide improved and accurate storage depth versus surface area versus volume figures for each dam. Several scenarios were established as part of the yield modelling and these included a variety of dam sizes in order to establish the different yields that can be obtained for varying levels of assurance of supply at different dam sizes. The outcome of the analysis was that Ntabelanga generated the highest yield when viewing yield generated versus volume stored. 2) Topographical survey Whereas, the original intention was to undertake detailed topographical surveys only in Phase 2, it was decided by the Study Management Committee to advance the initial topographical surveys into Phase 1 in order to enhance the accuracy of calculation of the area vs depth vs volume curves for the three dams, as well as the calculation of more accurate cost estimations for each dam, which improved the reliability of these Phase 1 analyses. This approach was proven to be successful as it identified a large discrepancy between this new data and the data used in the pre-feasibility studies. 3) Geotechnical investigations It was further decided by the Study Management Committee that the advancement of some of the geotechnical investigations into Phase 1 would provide important information regarding potential fatal flaws that might exist regarding the technical suitability of each dam site, as well as informing the decisionmaking on optimum dam type and materials usage. These investigations also provided useful information regarding the further investigations that are required in Phase 2 for the single dam site selected from Phase 1. The conclusions were that the foundation conditions are reasonable at all three sites. Ntabelanga also appears to have adequate sources of rock, sand and clay (for core material), within the inundated basin upstream of the dam, whereas Thabeng s rock quarries lie more downstream, which could possibly have a higher environmental impact. 4) Water requirements Domestic water supply Meetings were held individually with each of the Water Services Departments from the Alfred Nzo, OR Tambo and Joe Gqabi District Municipalities (DM s) in order to obtain information on existing and planned water supply initiatives and to get an indication of the areas of need within each DM. Additional GIS analysis was undertaken utilizing the provided information in order to estimate the number of people that could potentially be supplied with water from each proposed dam site. These figures were used in the comparison of the three dam sites. The total demand, when compared to the Mean Annual Runoff (MAR) within the catchment, is low and the hydrological analysis combined with this information indicated that only a small storage would be required to meet the domestic water supply demand alone. Irrigated agricultural land Additional agricultural investigations were undertaken including ground truthing of the identified areas and a small amount of soil auguring on site. This process indicated that in some cases the actual area of land that would be suitable for irrigated agriculture was significantly less than those identified through desktop investigations. The outcomes were as follows: Ntabelanga Desktop estimate 840ha Revised estimate 500ha Somabadi Desktop estimate 1 327ha Revised estimate 1 000ha Thabeng Desktop estimate 1621ha Revised estimate 1 000ha Figure 2: Example of soil sample with a high potential for irrigated agriculture 5) Dam sizing based on requirements The range of sizes of dams analysed were for capacities ranging from 33 million m 3 to 490 million m 3. Increasing dam volume above this higher figure produces less benefit. The water requirements were compared with the yields produced by this range of dam sizes. It was noted that the minimum sized dam produced sufficient reliable yield to supply all of the water demand projections if the water was only going to be used for domestic water supply and irrigated agriculture. A base case and a high demand scenario were developed with the base case being the proposed minimum water requirement for domestic water supply and irrigation (incl. 2

scenario were developed with the base case being the proposed minimum water require domestic water supply and irrigation (incl. compulsory environmental releases) and the high scenario being the proposed maximum if supply areas were increased. The storage volumes at each dam site are shown in the table provided. Ntabelanga requires the smallest storage both the base case and high demand scenarios. compulsory environmental releases) and the high demand scenario being the proposed maximum if supply areas were increased. The storage volumes required at each dam site are shown in Table 1 below. NTABELANGA THABENG SOMABADI GRAND TOTAL WATER DEMAND 98% Reliable Dam Yield EWR DAM SIZE (GROSS VOLUME INCLUDING SEDIMENT ALLOWANCE) Dam FSL Water Depth ESTIMATED CONT. HYDROPOWER BASE HIGH BASE HIGH Mm 3 /a Mm 3 /a Mm3/a Mm3/a MAR x Mm3 m MW MW 7.83 21.97 26.80 52.82 0.10 33.00 31.00 0.27 0.27 9.19 23.62 24.80 84.33 0.20 58.00 33.00 0.35 0.35 8.59 21.47 21.32 104.98 0.15 54.15 44.53 0.40 0.40 6) Hydropower Potential Assessment A check was undertaken on each dam to ascertain the amount of reliable (continuous) hyd of the three dams. Calculating capital costs for the three dams that could be generated if a hydropower and station for various were dam to sizes be enabled built a immediately costing curve to downstre be produced for the full ranges of dam sizes, as shown in Figure 3 within, the dam wall. The figures shown below. in the table above indicate that, for the minimu dams this output would range from 0.27 to 0.40 MW for the three dams. The requireme Summary and conclusion of preliminary findings self-sufficient hydro-powered scheme cannot be met by these minimum dam sizes. 6) Hydropower potential assessment A check was undertaken on each dam to ascertain the amount of reliable (continuous) hydropower that could be generated if a hydropower station were to be built at the dam. The figures shown in the table above indicate that, for the smallest dam sizes this output would range from 0.27 to 0.40 MW for the three dams. The requirements for a self-sufficient hydropowered scheme cannot be met by these small dams. An analysis was therefore also undertaken to see how much larger the three dams would need to be built to be able to generate the required power requirements and to provide the necessary domestic and irrigation water supply. The incremental cost of these larger dams and installing hydropower plant for this latter scenario was thus calculated and included in the analyses described below. An analysis was therefore also undertaken were to see then run how which much included larger and dams higher with hydropower the three da need to be built to be able to generate the plant required installed to power both deliver requirements the required quantity to provide of raw the n water to meet the projected demands, as well as generating domestic and irrigation water supply. The sufficient incremental hydropower cost to meet of raising the energy the needs dam of walls the and water supply systems in the supply area served by the dam. hydropower plant for this latter scenario was thus calculated and included in economic described below. 7) Cost comparison For each of the options described above, capital cost estimates were prepared so that a discounted cash flow analysis could be undertaken to compare the cost of water produced by each Table 1: Dam sizes required to meet total water requirements Scenarios were firstly investigated for dams that supplied raw water to meet only the domestic and irrigation water demands, with no hydropower component. Other scenarios A summary of key outputs from the above analyses is given below for base case (low demand) scenario and the with and without hydropower options. The colour coding in Tables 2 and 3 below shows the ranking of the various selection criteria between the three dams. Figure 3: Cost comparison of three dams by volume impounded 3

Table 2: Comparison of dams by technical criteria Base demand case TECHNICAL CRITERIA NTABELANGA THABENG SOMABADI POPULATION SERVED FOR THIS SCENARIO 134,633 111,564 97,303 TOTAL POPULATION WITHIN 50 KM OF DAM 223,686 94,666 116,337 IRRIGATABLE AREAS WITHIN ECONOMIC LIMITS (ha) 504 1062 1062 COST OF DAM FOR RAW WATER SUPPLY ONLY (R million) 391 581 546 IS THE DAM SELF-SUFFICIENT FOR HYDROPOWER? NO NO NO INCREMENTAL COST OF LARGER DAM & HYDRO-PLANT (R million 194 287 141 DOES LARGER DAM MEET ALL SCHEME POWER REQUIREMENTS? YES YES YES TOTAL WATER AVAILABLE (Mm 3 /a) 113.82 96.88 54.08 UNIT REFERENCE VALUE OF TOTAL WATER AVAILABLE (R/m 3 ) 0.27 0.48 0.68 Note: Unit reference values of water are average figures for the whole demand. More detailed analysis will be undertaken in Phase 2. Other criteria have also been evaluated for each dam and ranked in a similar manner, which are listed below on Table 3. Table 3: Comparison of dams by other criteria Base demand case OTHER CRITERIA NTABELANGA THABENG SOMABADI AREA OF LAND INUNDATED (km 2 ) - NO HYDROPOWER 7.5 7.8 5.8 AREA OF LAND INUNDATED (km 2 ) - WITH HYDROPOWER 20 16 7.3 IMPACTS EXISTING NATIONAL ROAD AND OTHER INFRASTRUCTURE? LOWER HIGH MODERATE OTHER REGIONAL SCHEMES AND SOURCES EXISTING/PLANNED? YES YES YES CAN SCHEME WORK CONJUNCTIVELY WITH OTHER MAJOR SCHEMES? YES NO NO ECOSYSTEM RISK ASSESSMENT RESULTS LOWER HIGHER HIGHER JOB CREATION (ESTIMATED NUMBERS) TEMPORARY DURING CONSTRUCTION 200 to 300 200 to 300 200 to 300 DURING FIRST SEVEN YEARS OF CATCHMENT IMPROVEMENTS 635 635 635 PERMANENT WATER SUPPLY 30 to 50 30 to 50 30 to 50 PERMANENT ON IRRIGATED AGRICULTURE SCHEMES 50 106 106 PERMANENT ON ANNUAL CATCHMENT MANAGEMENT 167 167 167 Can scheme work conjunctively with other major schemes? This criteria is pertinent. This applies particularly to Ntabelanga, as this dam has the advantage that it can be used in tandem with a potential and significant hydropower scheme that was previously identified by ESKOM. This same dam could also be utilized to effect inter-basin transfer to the Orange River system, and could also potentially augment the Mthatha water supply via inter-basin transfer to the neighbouring catchment. The hydropower option is discussed further below, and whilst the two inter-basin transfer options have previously been discounted as being too expensive, they will be revisited again in Phase 2. Conclusions In terms of purely economic comparison of the three dam site options, Ntabelanga is clearly the highest ranked option, having the lowest capital cost and lowest URV of water produced for all configurations considered. It should be noted that the URV s of raw water produced by all three dams are high if only actual domestic and irrigation water usage is taken into consideration, rather than total water availability. Whilst the ranking is less clearly indicated when regarding the other impacts considered, the overall conclusion based upon the criteria considered is that the Ntabelanga Dam is the best single option to be taken forward into Phase 2 of this study. 4

The additional benefit that Ntabelanga has over the other two options is that it is well located so that it can be developed to work conjunctively and cost-beneficially with a potential large hydropower scheme on the same river, as well as having the potential to augment water supplies in other regions, if inter-basin transfers are deemed to be viable either now or in the future. If such additional uses can be realised, then the URV of water produced would reduce accordingly and the viability of the dam be assured. Phase 2 The Department of Water Affairs is moving ahead with Phase 2 of the Mzimvubu Water Project with the Ntabelanga Dam site on the Tsitsa River as the preferred option as outlined above. The intention is to develop a conjunctive scheme where the Ntabelanga Dam is developed such that it will provide water releases to a hydropower scheme based at the proposed Laleni Dam site near to Tsitsa Falls. This process got underway in May 2013. The Study Team is currently dealing with the Detailed Feasibility Study of the Ntabelanga Dam and the Department of Water Affairs is in the process of appointing an Environmental Consultant to undertake the legislated environmental process. The Study Team is finalising the detailed hydrology, undertaking geotechnical drilling and materials investigations, dam and spillway type analysis as well as detailed agricultural and domestic water supply planning investigations. Phase 2 is planned to be complete by April 2014. Further information Contact Persons: Department of Water Affairs Directorate: Options Analysis Sedibeng Building 185 Frances Baard Street Pretoria 0001 Tel: 012 336 6838; Fax: 012 336 7399 Contact: Mr M Mugumo mugumom@dwa.gov.za Documentation and Reports: This project will soon be available via the DWA Public Domain and Reports published as part of a website at: www.dwa.gov.za under Projects and Programmes. Professional Service Provider Jeffares & Green (Pty) Ltd P O Box 794 Hilton 3245 Tel: 033 343 6700; Fax: 033 343 6701 Contact: Mr A Pepperell pepperella@jgi.co.za 5