A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES



Similar documents
DESIGN GUIDELINES FOR EARTH RETENTION

Module 7 (Lecture 24 to 28) RETAINING WALLS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Optimised Design for Soil Nailed Walls 1

Embedded Parts Introduction - Anchors

Numerical Simulation of CPT Tip Resistance in Layered Soil

Soil Screw Design Manual Edition 2

PART TWO GEOSYNTHETIC SOIL REINFORCEMENT. Martin Street Improvements, Fredonia, Wisconsin; Keystone Compac Hewnstone

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Helical Piles. A Practical Guide to Design and Installation

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

High Strain Dynamic Load Testing of Drilled Shafts

Geotechnical Building Works (GBW) Submission Requirements

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

THE METALITH PERIMETER SECURITY SYSTEM INSTALLATION INSTRUCTIONS. Attention

Drained and Undrained Conditions. Undrained and Drained Shear Strength

COSMOS 2012: Earthquakes in Action COSMOS 2012

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Report to INFRASTRUCTURE SERVICES Committee for noting

The Verdura Wall check with your local building department

MSE Wall Engineering A New Look at Contracting, Design, and Construction. Presented by: James M. Schmidt, P.E., P.Eng. 1 Daniel L. Harpstead, P.E.

DIRECTIONAL DRILLING

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

PDHonline Course S151A (1 PDH) Steel Sheet Piling. Instructor: Matthew Stuart, PE, SE. PDH Online PDH Center

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

King Post Wall Information

Safe & Sound Bridge Terminology

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

The unit costs are based on the trend line of the 3 low bids for the average quantity.

How To Retaining Wall Guide

Technical Notes 3B - Brick Masonry Section Properties May 1993

CIVL451. Soil Exploration and Characterization

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Emergency repair of Bridge B421

SECTION 1 GENERAL REQUIREMENTS

SECTION SUPPORT OF EXCAVATION

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

System. Stability. Security. Integrity. 150 Helical Anchor

High Capacity Helical Piles Limited Access Projects

Types of Retaining Walls - Gravity walls - Pre-cast crib walls - Gabion walls - Reinforced concrete walls - Sheet pile walls - MS walls (mechanically

Chapter 3 Pre-Installation, Foundations and Piers

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

METHOD OF STATEMENT FOR STATIC LOADING TEST

1. ASTM C Sampling and Testing Concrete Masonry Units 2. ASTM C 1372 Standard Specification for Dry-Cast Segmental Retaining Wall Units

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Bracing Webs in Trusses that have Dissimilar Configurations

PDCA Driven-Pile Terms and Definitions

6 RETROFITTING POST & PIER HOUSES

Underpinning Systems 14.1 FOUNDATION REPAIR. Helical Piles

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Integrated Manhole Ladder System

Guidelines for Earthquake Bracing Residential Water Heaters

Wang, L., Gong, C. "Abutments and Retaining Structures." Bridge Engineering Handbook. Ed. Wai-Fah Chen and Lian Duan Boca Raton: CRC Press, 2000

Cable Trays Technical Instructions & Specifications

Building Pit Roche Building 1 Basel, Switzerland

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

TECHNICAL MEMORANDUM SUMMARY REPORT:

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

EGYPTIAN CODES FOR DESIGN AND CONSTRUCTION OF BUILDINGS

Evaluating the Condition of Seawalls/Bulkheads

Stabilenka HUESKER. and Separation. Engineering with Geosynthetics SKER HUESKER HUESKER HUESKER HUESKERHUES

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

Unit Price Averages Reports

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

SECTION EARTH MOVING

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

PART E SPECIFICATIONS

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations

What is QuickBase? Traditional foundations (left) compared with QuickBase (right)

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

The demand for new roadway

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1

FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

Program COLANY Stone Columns Settlement Analysis. User Manual

Chapter 2 Basis of design and materials

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)

The Stabilizer TM. Benefits. Supplemental support system for sagging beams and floor joists within a crawl space

GUIDELINE FOR HAND HELD SHEAR VANE TEST

Forensic engineering of a bored pile wall

Figure CPT Equipment

Value Engineering vs. Alternate Designs in Bridge Bidding

Transcription:

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES H. Turan DURGUNOGLU Ahmet SAHIN Onder AKCAKAL Zetas Zemin Teknolojisi A.S., TOKI-Housing Development Zetas Zemin Teknolojisi A.S., Istanbul-Turkey 34794 Adm., Ankara-Turkey 06800 Istanbul-Turkey 34794 ABSTRACT Recently new highway, motorway and railway projects take place in many developing countries within the aggressive infrastructure investment programme of governments. In rugged topography, engineers face the challenging problems of designing safe and cost effective cuts and fills for these projects especially under seismic loading and marginal stability conditions. Overall stability mechanism and safety of the cut generally controls the design decisions for the relevant section. In addition, because of the construction width limitations, in some mechanically stabilized earth wall projects sufficient width to accommodate the strip lengths of the retaining system cannot be provided. To eliminate all these problems, to minimize cut and backfill volumes and provide an innovative solution in such difficult terrains, soil nailing is implemented in the cut side together with the mechanically stabilized earth wall in the fill side together both are being flexible earth retaining structures. In addition, soil nails could be designed in such configuration and length that nails will also contribute to overall stability conditions of the cut slope. Furthermore, implementation of the system brings the advantage of reduction of both cut and fills volumes, therefore more cost effective and safer design. This paper presents application of this system in a recent case study, in Baku, Azerbaijan. INTRODUCTION Reinforced Earth (Mechanically Stabilized Earth) wall systems were successfully used for many years in highway and railway projects which require relatively large quantities of excavation and/or fill during the construction, Sankey and Hutchinson (2011), Freitag et al (2011). Especially, their applications in mountainous regions may bring further special stability problems. To overcome these disadvantages, a new system in the form of combination of both soil nailing and the reinforced earth systems have been developed as seen in Figure1., Freitag, et al(2005), Morrison, et al(2006). Fig. 1. Soil nailing linked to reinforced earth With this combined system, required strip length for a regular reinforced earth wall can be significantly reduced. The reinforced earth system has been widely implemented in highway and railway construction projects especially for forming a new platform on a different level from its surroundings. In addition, the system is also used for adding new lanes or tracks to the existing highway or railway respectively, (Freitag, 2012). Further, both soil nailing and Reinforced Earth are flexible retaining structures, as a result their behavior under major earthquakes have been very favorable in comparison to various rigid retaining structures, Mitchell et al (2000). When highway route passes through a steep terrain, required excavation quantity increases dramatically, as the reinforced earth wall base should be placed on the slope having a required base width of about 70 percent of the height. The earth-movement quantity also increases by the required minimum embedment depth of the reinforced earth wall. With the linked system the required strip lengths and base width of the reinforced earth wall could be reduced as a result more economical design could be implemented, Figure 2, Paper No. 3.36b 1

ssible uses Possible of TerraNail uses of system? TerraNail system? (Durgunoglu, 2012). ad construction At road on steep construction slopes on steep slopes TerraNail wall 2 Reinforced Earth Wall REINFORCED EARTH WALL TerraNail wall COMBINED WALL Fig. 2. Reinforced Earth and its combination with soil 8 nailing 8 9 Overall stability problem is one of the serious problems of reinforced earth and as well as rigid retaining walls when they are implemented in sloping areas. Further to achieve stability of the toe of the wall sufficient embedment depth should be considered as a function of slope angle. For this reason deeper excavations are required on steep slopes. With implementing combined systems of RE and Soil Nailing in these areas, there is a possibility to reduce the base width down to 30 percent of the wall height in order to reduce the earth volume required (Freitag, 2012), (Durgunoglu, 2012), Figure 2. COMBINED RE-SOIL NAILING SYSTEM To evaluate performance of combined wall system the Federal Highway Department FHWA, has tested the system using large scale site test and a centrifuge model. These tests have shown that base width reduced to 0.3H is sufficient for reinforced earth wall strip lengths to provide the stability requirements, Morrison et al (2006). The combined system is obtained by linking reinforced earth wall and soil nailing which are both known as flexible earth retaining systems. Obviously in the cut side, although they are in rigid form other supporting systems than nailing could also be implemented such as, sheet pile wall, diaphragm wall, intersecting or tangent piled wall or soldier piles as proposed by FHWA, 2006. Therefore recently the system has been also named as Terra Link, (Freitag, 2012). In soil nailing shoring system nails are located at a certain angle to horizontal and tensile forces will be developed by limited lateral displacements during excavations. Nails are placed into predrilled holes and are grouted through their complete lengths. Nails are connected to steel wire mesh and shotcrete lining at the face of the slope. In the combined system first the temporary excavation is done implementing nailing system and then reinforced earth wall is constructed in front. Soil nailing construction consists either temporary or 9 permanent nail preparation, drilling, installation, grouting, placement of steel wire mesh and connection of nail with the facing and finally shotcreting of the slope face. Drilling up to a specified length can be achieved with drill rigs at the site and soil nails are installed in the holes with injection tubes and protection sleeves prior to grouting. Recently pressurized grouting in order to increase the friction between the nails and the soil has also been implemented, (Seo et al, 2012). Facing is generally consist of shotcrete and wire mesh. Generally shotcrete is applied in two stages. Two layers of wire mesh are applied both back and front sides of the facing. After implementing the first layer of shotcrete and wire mesh, head plate and nut for the soil nail are installed and application is finalized with implementing last layer of shotcrete and wire mesh. Later, reinforced earth wall is constructed in front of the soil nailed wall using standard construction procedures. In addition, in permanent soil nailing, the followings should be fulfilled. (Morrison et al, 2006); Aggressive soil condition that causes the corrosion of nails must be protected with epoxy coating or polyethylene tubes. To avoid hydrostatic pressure, permanent drainage measures must be taken. Protection of the steel elements, such as nails, plates and nuts that is used should be covered with shotcrete Soil nailed wall will be designed based on internal stability and the global stability of the cut slope. The pullout resistance determined by the nail length and tensile resistance determined based on nail cross section both are considered in internal stability. The linked system could also provide advantage on long term overall stability of the slope. The wall design is performed in four-stages. In the first stage, reinforced earth wall internal stability, pullout capacity in selected backfill using width of the wall must be examined. To ensure the internal stability reinforced earth wall strip lengths are designed separately considering the minimum design requirements. In addition proper choice of strip sections are implemented in order to have sufficient factor of safety against tensile forces at various levels. At the second stage, external stability must be checked along the reinforced earth wall and soil nail interface. At the third stage, bearing capacity and settlement of backfill is checked and required replacement depth is determined. At the fourth stage, overall stability analysis of the combined system must be performed, (Morrison et al, 2006). In the design of the linked system, the most important factor is to provide the friction link between reinforced earth and soil nail walls. This could be achieved in two ways; one being the direct connection using synthetic extensible strips as in Figure 3, or using inextensible galvanized steel rod as in Figure 4. The second way is to employ the friction connection by using special galvanized steel ladder strips as in Figure 5. (Freitag, 2012), (Durgunoglu, 2012). Paper No. 3.36b 2

Design of TerraNail System (Cont d) Design of TerraNail System (Cont d) Connection types - Direct connection- With Synthetic strips o Connection types 2. Direct connection b) With steel strips Fig. 3. Direct Connections with Synthetic strips Eastern Cape, South Africa construction of RE walls. In fact, this will also hinder existing highway operation located at the top of the slope and it is likely to be detrimental to the overall stability of this section which is known to be problematic and marginal. In order to overcome these problems, the linked system is proposed to be constructed for a stretch of 540 m which will allow smaller amount of excavation and RE wall could be constructed with a smaller base width. This is achieved by means of combination of soil nail wall at the cut side and RE wall at the fill side employing additional special galvanized steel ladder friction members. Main lithological unit of siltstones at the site are very sensitive to erosion and getting wet in the presence of surface and subsurface water. Even without the presence of the planned retaining structure on the slope, the overall stability of the slope was critical and marginal. The stability of the slope at 19 the cut side was achieved by implementing long permanent soil nails at various elevations together with strict surface and subsurface drainage measures, Figures 6a and 6b. Design of TerraNail System (Cont d) Fig. 4. Direct Connection with Steel Rods 1. Friction connection Kei Cuttings, South Africa Number of steel ladder strips tied to every soil nail may be one or more according to the project Fig. 6a. Cut Slopes-Drainage and nailing requirements Fig. 5. Friction Connection with Galvanized Steel Ladder In the figure is a ladder strip tied to a soil nail head Strips CASE STUDY One of the challenging implications of this linked system as combination of flexible earth retaining structures has been achieved recently in Baku, Azerbaijan on the new periphery highway that is located on a very steep topography, Figure 6. Originally, classical reinforced earth retaining wall was considered however, it is known that the width of such walls are at least 70 percent of their heights; as a result, large amount of excavation will be required at the hillside prior to 18 Fig. 6b. Cut slopes-existing Highway Lanes At the lower part of the slope however, there was a necessity to construct a retaining structure on the existing slope in order to have required platform width for the new highway. Due to the special problems of the site given above, the linked system was proposed to be implemented, Figure 7. Paper No. 3.36b 3

TerraNail Applications by Reinforced Earth A.S. Turkey 1-Baku AzerbaijanTerraNail System Fig. 8. Typical Design Cross-Section The total surface area of the implemented retaining structure is 35 Fig. 7. Linked System Under Construction 3650 m² having a maximum height of 12.5 m. The construction has been completed in four months with a great The design requirements were to place a reinforced earth success. As seen in Figure 9, specially designed galvanized structure having minimum excavation and once the wall is steel ladders are used as friction connection. Two ladders are placed, the factor of safety against marginal overall stability connected to each soil nail in V shape in order to achieve the should not be reduced. Typical siltstone formation with required frictional resistance. Additional photographs of drained shear strength parameters of c =20 kpa and Ø =26 construction phases of the wall are given in Figures 10 and 11. were considered in the early stage design calculations based The wall is monitored by means of inclinometers after on the reported values in previous studies in similar completion for a period of one year due to the critical overall formations. Consequently, it was shown that, under this stability concerns. It is determined that the resulting maximum condition implementation of two rows of long soil nails at the lateral displacements were limited to few millimeters. As a toe of the structure having 38 mm diameter and 24.0 m length result, this case study could be classified as one of the TerraNail Applications by Reinforced Earth A.S. Turkey with s h =1.5 m horizontal spacing is compulsory in order to successful application of flexible linked system using both soil achieve overall factor of safety of FS=1.50 under static and nailing and reinforced earth on a very difficult topographical, FS>1.0 under earthquake loading conditions. Systematic 1-Baku AzerbaijanTerraNail lithological, System and drainage conditions. subhorizontal drains are considered in order to prevent pore Pertinent Data: pressure build up behind the wall. A=3650m² Hmax=12.5m In the meanwhile, a supplementary soil investigation program Duration: 4 month is submitted to be implemented at this specific section in order to verify the assumed soil conditions and drained shear strength parameters. In this respect, in-situ block samples of siltstone were taken and tested in the laboratory in a large displacement direct shear test in order to verify drained shear strength parameters. It is determined that residual strength parameters of saturated samples were very close to the values used at early stage of design. On the other hand, considering that no previous slope failure has occurred at this part of TerraNail the Applications by Reinforced Earth A.S. Turkey slope (i.e. lower elevations) at this location peak values of fully saturated samples are adopted for the final design for Fig. 9. Construction Phases Galvanised Steel Ladders 1-Baku AzerbaijanTerraNail System further cost optimization. These values are measured as c p =30 36 kpa, and Ø p =35. In such condition toe nails horizontal spacing were increased from original value of s h =1.50 m to s h =2.15 m to achieve required minimum safety factors for the global stability. In addition, some of the upper nail lengths were also decreased to 6.0 m. The typical implemented design cross-section for the linked wall system is given in Figure 8. It is seen that some of the soil nails in the cut side is long, in order to intersect the potential critical slip surface. Further in order to place the wall with a minimum base excavation on a sloping terrain at the reinforced earth part, toe of the wall was also tied back to original slope by means of long nails. Fig. 10. Construction Phases Panels and RE Wall Paper No. 3.36b 4 38

REFERENCES Durgunoglu, H.T, [2012]. Combined MSE Wall Applications with Ground Reinforcement Techniques, ISSMGE-TC211, IS-GI Brussels 2012, Short Courses-3, Rigid Inclusions and Soil Reinforcement, May 30, 2012 Freitag, N. et al [2005]. Innovative Solution for Reinforced Earth Walls: Friction Connection, ICSMGE, Osaka, Japan Fig. 11. Construction Phases Drainage Measures CONCLUSIONS The linked system of soil nailing and reinforced earth satisfies the significant need of highway and railway construction with its advantages in reducing the earthwork and providing the possibility of increasing global stability of sloped terrain. In conventional reinforced earth wall road widening at steep terrain brings the need of large amount of excavation which in some cases may lead to failure in global stability. Besides, the excavation works significantly increase the cost and decrease in speed of construction. With the application of the combined system, all the disadvantages of the classical reinforced earth wall on steep sloping terrain could be eliminated. Both design and construction of a flexible linked system is presented in the case study, and based on the results of observations, it was proved to be successful and this is further verified by the results of subsequent monitoring programme employing inclinometers. Freitag, N. et al [2011]. Reinforced Earth, A Promising Solution for the Development of Railways International Symposium, Georail 2011 Freitag, N. [2012]. TerraNail Seminar, April 20, 2012, Lima, Peru Mitchell, J.K, Martin, J.R., Olgun, C.G., Emrem, C., Durgunoğlu, H.T., Cetin, K.O. and Karadayilar, T. [2000]. Chapter-9-Performance of Improved of Improved Ground During the 1999 Turkey Earthquakes Earthquake Spectra, Supplement A to Vol. 16, December 2000, pp. 191-225 Morrison, K.F., Harrison, F.E., Collin, J.G., Dodds, A., Arndt, B. [2006]. Shored Mechanically Stabilized Earth (SMSE) Wall Systems Design Guidelines, Publication No: FHWA CFL/TD-06-001, Federal Highway Administration Sankey, J.E., Hutchinson, D. [2011]. Experience with Support of Railways Using Mechanically Stabilized Earth in the USA, International Symposium, Georail 2011 Seo, H.J. et al [2012]. Pullout Resistance Increase of Soil Nailing Induced by Pressurized Grouting, ASCE Journal of Geotechnical and Geoenvironmental Engineering, Vol. 1s38 No.5, May 2012 Paper No. 3.36b 5