Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery



Similar documents
CONTRACTOR DEFAULT & SURETY PERFORMANCE:

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Strategic Program Management

LOGGING SUBCONTRACT. Recital

photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada

CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE

EASY LED Oy General Terms of Sale

Local Government Energy Efficiency Resources Guidebook 5: Project Management

PPP Basics and Principles of a PPP Framework

Construction Management for Owners

CONTRACT CONDITIONS FOR LOGISTICS (2014)

King Fahd University of Petroleum and Minerals

ICE Legal Notes Series

Schedule 12 - Insurances

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING

Guidance on the template contract for social impact bonds and payment by results

Managing Risk in Mega-EPC Projects Where Do We Start?

Managing construction procurement risks

The Economics of Public-Private Partnerships

Chapter 3 Office of Human Resources Absenteeism Management

BLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE

Using Risk Assessment to Improve Highway Construction Project Performance

Evaluating Project Delivery Options

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

Generic CMMS Quality Assurance Plan

INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242

MAJOR EQUIPMENT PURCHASE CONTRACT

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

Procurement Routes. Curtin University of Technology

Contracting Practices in Mega Projects

Developing a Public-Private Partnership Framework: Policies and PPP Units

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS

Bonding and Insurance Workshop. Presented by Ingrid Merriwether, President & CEO

ONYX BUSINESS AUTO POLICY COVERAGE

Guide on drawing up contracts for large industrial works

Customer Service Strategy

Information Pack for Applicants to the MIDLANDS CONNECT PROJECT TEAM

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

Health and Safety Policy and Procedures

Construction Management Standards of Practice

Competency-Based Organization For Project Management

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

ENERGY PERFORMANCE CONTRACT

Lao PDR Public-Private Partnership Policy

CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS

Engineering Council of South Africa

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

TERMS & CONDITIONS CONTRACTOR SERVICES

The fact is that 90% of business strategies are not implemented through operations as intended. Overview

REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES

The programming, design

A new global standard on revenue

Documented Evidence of Property Management Value, Part 3

General Conditions of Purchase (as of March 2002) Abbr.: AEB of the Salzgitter Bauelemente GmbH, Salzgitter

General Procurement Terms and Conditions of SMEPRO INTERNATIONAL B.V.

Contracts, agreements and tendering

Network Support Service Contract Terms & Conditions. Business Terms describes this agreement for the provision of support services to the client;

PLUMBING ON TAP (REG CO NO: ) TERMS AND CONDITIONS OF BUSINESS

IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6

Introduction to Project Management

SUPERVISORY AND REGULATORY GUIDELINES: PU GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS

Contracting Strategy of a Project

DESIGN IS GOOD BUSINESS

Document Comparison. AIA Documents A and A131CMc 2003

VIEWPOINT ARTICLE. Facility Management Outsourcing: Negotiating the Business Model. AgileOAK.com

CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES. Proposal Due Date: April 13, 2016

GENERAL CONDITIONS OF LATVIAN NATIONAL ASSOCIATION OF FREIGHT FORWARDERS and LOGISTIC LAFF

POST AWARD CONTRACT MANAGEMENT

Contract Management. Brief 22. Public Procurement. September 2011

Lifting the fog* Accounting for uncertainty in income taxes

Management of Business Support Service Contracts

A New Model for development: USAId MANAgeMeNt & process reform JUNe 2014

Value Extended Warranty and Premium Extended Warranty. Terms and Conditions

6.0 Procurement procedure 1 Infrastructure

Contract Works and What you need to Know

COMMISSION REGULATION (EU)

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

Professional Practice 544

A Guide to Small Works. A brief explanation

Revenue from contracts with customers The standard is final A comprehensive look at the new revenue model

Management Excellence Framework: Record to Report

Workers Compensation 101

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project

ENHANCEMENT CONTRACTS - AVAILABILITY OF INSURANCE TO NETWORK RAIL

Transcription:

Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery By Bob Prieto Design Bid Build (DBB) and Design Build Finance Operate Maintain (DBFOM) project delivery differ in significant ways as shown in the table at the end of this article. In simplest terms, under DBB, the owner retains significant interface risk between the designer and builder and in multi-prime projects also retains integration risk across the primes as shown in the following figure. Effectively this is the white space risk between each of the contracting parties and is often not adequately considered in project planning, budgeting and schedule development. Multiple parties create difficulties in effective partnering and project performance is adversely impacted if these risks emerge. In all instances the owner is warranting the completeness and accuracy of the design to the contractor thus directly holding this interface risk. Owner Designer Designer Contractor Contractor Contractor Interface Risks between Designer and Contractor Integration Risks across Multiple Primes 2012 Bob Prieto www.pmworldlibrary.net Page 1 of 7

The use of a DBFOM project delivery approach significantly modifies the risk profile of the owner as the DBFOM contractor now assumes both this interface risk as well as the integration risk across all project elements. This can be seen clearly in the next figure. The Owner holds risks associated with his contract with the DBFOM contractor. These risks may include any shared risks or owner retained risks as they have negotiated. Owner DBFOM CONTRACTOR Design Subcontractor Design Subcontractor Sub Contractor Sub Contractor Sub Contractor O&M Contractor Examples of How Risk Transfer Differs Let s look at two examples to illustrate the differences between DBB and DBFOM risk transfer. Design Error or Omission In a complex highway project the designer makes an error in calculating the maximum span lengths and the supporting columns already constructed must be removed and new, more closely spaced columns constructed. The designer s E&O insurance is inadequate and the designer has limited assets that will not cover the contractor s increased costs. The owner holds the risk and therefore the compensation due to the contractor is from the owner. (The owner may obtain partial recovery from the Engineer or his E&O carrier) 2012 Bob Prieto www.pmworldlibrary.net Page 2 of 7

Under a DBFOM approach this risk would have been transferred to the DBFOM contractor and the owner should have no obligations to the DBFOM contractor. Scope Not Adequately Defined In the execution of new, complex urban rail project under a DBB approach the owner has hired multiple engineers and contractors and is serving as the overall project manager. He has developed detailed scope documents for each engineer and subsequently approved the detailed scopes put out for construction bids on a low bid basis. His scope documents though did not include any provisions for heavy maintenance of the transit vehicles. This necessary feature is identified late in the design and construction process and delays initial system startup. The owner holds all risks and will bear all costs. Under a DBFOM approach the DBFOM contractor would be given a functional specification to safely design, build, finance, operate and maintain the desired system to an established performance standard. This standard could not be met without a heavy maintenance facility for the transit vehicles. The risk and any associated cost would be fully to the DBFOM contractor s account. Depending on his performance requirements he may choose to implement other solutions including a more limited, but functional temporary facility. Unexpected Maintenance Issues beyond a Normal Warranty Period On a major cable stayed bridge carrying an electrified rail line, accelerated corrosion of the cables was noticed seven years after project completion and well beyond the warranty period of the cables. Inspection of the cables shows no latent material defects and they were installed correctly per the design drawings by the bridge builder. A review of design drawings and specifications showed them to meet or exceed industry codes and standards as well as the owner s own required standards. Independent experts suspect that transient loading of the bridge may create temporary pathways for stray currents in ways that had not been previously understood. Under a DBB approach the risk is retained fully by the owner as is the cost of repair or replacement of the cables. It is an unexpected operating cost and not a warranty or defective workmanship item. If the owner had selected a DBFOM approach with a performance specification that limited force majeure events to acts of god, civil strife and sovereign actions, the risk and associated costs would be borne entirely by the DBFOM contractor and not by the owner. These three examples illustrate how white space risks, especially those related to: Interfaces between designer and contractor Integration risks across all project elements 2012 Bob Prieto www.pmworldlibrary.net Page 3 of 7

Operating phase risks caused by no-fault design and construction inadequacy are transferred from the owner to the DBFOM contractor. The differences go well beyond risk transfer and are enumerated in the following table. Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery Parameter DBB DBFOM Strategic Business Objectives Top Level Key Performance Indicators (KPIs) Politically driven; technically and funding constrained Cost and schedule Economically driven; technically and politically constrained Return on Investment; cash flow; availability or other performance payment indicators Strategy Outputs focus Outcomes Focus Government Commitment Incremental Front end loaded Procurement Process Transparent procurement Transparent procurement Competitive selection; limited innovation Competitive selection; competition of ideas Low bid construction cost competition Lifecycle & financing cost competition Stakeholder Management Owner responsibility Significant DBFOM role Project Selection Step-wise decision framework Life cycle decision framework State cannot advocate for a preferred option Private sector may advocate for a preferred option Project Management Multi-party partnering a challenge for owner Sequential design and construction Process Procurement begins with construction. Execution responsibility shared between designer and builder; owner holds significant responsibility for Rigorous project selection and avoidance of political white elephants Owner partnering focus is with DBFOM contractor only Parallel design and construction Process Procurement may begin prior to construction (early design elements). DBFOM has execution responsibility 2012 Bob Prieto www.pmworldlibrary.net Page 4 of 7

Scope interface risk Scope completeness a requirement for bidding construction Wants enter into project scope at various stages without full life-cycle impacts being understood Design influence throughout design phase Functional performance specification completeness a requirement Functional specification ensures needs are met and the cost of wants not incurred Limited design influence beyond what specified in functional specification Schedule drives design process Schedule Design process may drive schedule Limited schedule acceleration Incentivized schedule opportunity performance Budget Best estimate of cost Life-cycle cost certainty Risk Focus Initial delivery Life Cycle Risk Reserves Quantitative risks Quantitative and event risks Risk Management Exposure to multi-party disputes (derived from integration and interface risks) Disputes limited to single contractor Integration Risk Integration risk (multiple primes) Integration risk transferred to DBFOM contractor Interface Risks Interface Risk (Design to Constructor) Interface risk transferred to DBFOM Contractor E&O Risk E&O risk starts with owner Owner has no E&O exposure Change Control Continuous design influence Limited design influence; fit for function test against performance specification Decision Making Frameworks Value Improvement Safety Sustainability Owner decision and review process (e.g. change approval) extensive and lack of timeliness adds cost and delays Time value of money not apparent Limited builder input in planning, design or work packaging (multi-prime) No common safety culture across contractors during construction Objectives established; benefits accrue to owner Owner decisions and reviews (less changes) are more limited Time value of money a key driver Builder able to significantly influence planning, design and work packaging. Common safety culture driven by DBFOM contractor Minimum objectives established by owner; direct benefits accrue to DBFOM contractor Promotion of environmental and 2012 Bob Prieto www.pmworldlibrary.net Page 5 of 7

Quality Lifecycle Focus Warranty Owner assumes responsibility for design quality Owner undertakes quality assurance of construction First cost emphasis Long term maintenance and renewal funding may be uncertain System warranty limited by owner operation Limited warranty social sustainability as the DBFOM contractor focuses on efficient use of resources and materials over the project lifecycle. DBFOM contractor responsible for design quality DBFOM contractor largely responsible for quality Life cycle cost analysis Contractual framework increases availability of long term maintenance and renewal funding Owner has general performance warranty Effectively an extended warranty Facility Performance Owner responsible DBFOM contractor responsible to Owner Improved level of service, especially for projects requiring user charges or achievement of performance levels for compensation Facility Renewal Subject to annual appropriations; statutory Performance driven requirements only Facility Turnover None Defined at time of DBFOM contract Public Finance Required May or may not be required depending on DBFOM model Preservation of public capital Cash Flow Often annual appropriation limited; creates inefficiencies capacity Project financing provides needed cash flow support for efficient execution Skills Required Current skill sets New skill sets related to performance specifications and financial modeling References: 1. Role of Project Delivery Systems in Infrastructure Improvement; Construction Research Congress 2003; Michael J. Garvin, Ph.D., P.E.* 2. A Guidebook for the Evaluation of Project Delivery Methods; TCRP REPORT 131 2012 Bob Prieto www.pmworldlibrary.net Page 6 of 7

About the Author Bob Prieto Senior Vice President Fluor Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He is responsible for strategy for the firm s Industrial & Infrastructure group which focuses on the development and delivery of large, complex projects worldwide. The group encompasses three major business lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and Manufacturing and Life Sciences. Bob consults with owner s of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of Strategic Program Management and The Giga Factor: Program Management in the Engineering and Construction Industry published by the Construction Management Association of America (CMAA) and Topics in Strategic Program Management as well as over 400 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11 th by the New York City Chamber of Commerce. Previously, he established a 20-year record of building and sustaining global revenue and earnings growth as Chairman at Parsons Brinckerhoff (PB), one of the world s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com. 2012 Bob Prieto www.pmworldlibrary.net Page 7 of 7