SECTION 02401 SHEETING, SHORING AND BRACING



Similar documents
SECTION EARTH MOVING

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SECTION SUPPORT OF EXCAVATION

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

High Strain Dynamic Load Testing of Drilled Shafts

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

SECTION GRAVITY SANITARY SEWERS

SECTION 1 GENERAL REQUIREMENTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

C. Section TESTING LABORATORY SERVICE.

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

Wastewater Capital Projects Management Standard Construction Specification

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

CHAPTER 6 - SANITARY SEWER

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION ABANDONMENT OF SEWER MAINS

SETTLEMENT INSTRUMENTATION & MONITORING

Machine Foundation Design

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

SECTION 5: SANITARY SEWER SYSTEM DESIGN

CONSTRUCTION PERMIT REQUIREMENTS

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

Section 2100-Trenching and Tunneling

Section SEWER PIPE INSTALLATION AND TESTING

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

CLEANING, INSPECTION, AND TESTING OF SEWERS

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

MDWASD 8/1999 SECTION TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

SECTION STORM DRAIN SYSTEM

Section EXCAVATION AND BACKFILL FOR UTILITIES

INSTALLATION OF INSITUFORM LINER

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

LS 2540 SEWER LATERALS AND INSPECTION TEES

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

550 PIPE CULVERTS, SEWERS AND DRAINS

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Beacon Hill Sewer District Standard Specifications

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

Code of Standard Practice for Timber Frame Structures

Geotechnical Building Works (GBW) Submission Requirements

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

SECTION 5 DRAFTING STANDARDS

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

SECTION PRECAST CONCRETE UTILITY STRUCTURES

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

UNIVERSITY OF CHICAGO ELEVATOR PIT LEAK REPAIR

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

Trenching and Excavation Safety

SECTION STORM DRAINAGE TABLE OF CONTENTS

SECTION EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Stormwater/Wetland Pond Construction Inspection Checklist

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Specification Guidelines: Allan Block Modular Retaining Wall Systems

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

CITY ENGINEERS ASSOCIATION OF MINNESOTA

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

SECTION 7- STORM SEWER

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

FY08 SEWER POINT REPAIRS BID TABULATION

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES

SECTION NONREINFORCED CONCRETE SEWER PIPE

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Sewer Line Rehabilitation

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Transcription:

SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State of Washington. PART 1 GENERAL 1.01 SCOPE Describe the work that will require sheeting, shoring and bracing. EXAMPLE: The work includes installation and removal of shoring for the Wet Well shaft and the installation of the 24-inch sanitary line between an existing manhole and the Wet Well as indicated in the Plans. Shaft details shown in the Plans are for conceptual purposes. Where shoring, sheeting, bracing, or other supports are necessary, they shall be furnished, placed, maintained and, except as shown or specified otherwise, removed by the Contractor. Delineate acceptable and unacceptable methods of sheeting, shoring and bracing for the project based on the recommendations of the Geotechnical Engineer. EXAMPLE: Contractor shall select the means and methods for providing support of the excavations in accordance with safety requirements, Plans and these Specifications. Methods that utilize dewatering, such as soldier pile and lagging may be considered. Specifications for Dewatering are in Section 02405. Other methods that do not require dewatering such as: jet grouting, secant piles, ground freezing and installing a steel casing, all with a shaft bottom seal, may also be considered. Use of sheet piling and sinking caisson methods are discouraged due to the soil conditions. Due to noise and vibration considerations, impact hammers will not be allowed on the site. Vibratory hammers are acceptable. 1.02 REFERENCES This section references the latest revision of the following documents. They are a part of this section as specified and modified. In case of conflicts between the requirements of this section and those of the listed documents, the requirements of this section shall prevail. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, whether or not the document has been superseded by a version with a later date, discontinued or replaced. 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common 02401-1 [Contract Name]

Reference Chapter 49.17 RCW Chapter 296-155 WAC OSHA Part 1926 AISC ASTM D 1557 Title Washington Industrial Safety and Health Act Part N, Excavation, Trenching, and Shoring Subpart P, Excavation, Trenching and Shoring Steel Construction Manual Laboratory Compaction Characteristics of Soil using Modified Effort 1.03 DESIGN REQUIREMENTS The design, planning, installation, and removal of all sheeting, shoring, lagging, and bracing shall be accomplished in such a manner as to maintain the required excavation or trench section and to maintain the undisturbed state of the soils below and adjacent to the excavation. The Contractor shall provide the design, prepared by a professional engineer licensed in the State of Washington, for sheeting, shoring, and bracing in accordance with WAC 296-155. Horizontal struts below the barrel of a new pipe and the use of the pipe as trench support are not acceptable. When the construction sequence of structures requires the transfer of bracing loads or forces to the completed portions of any new structure or to any existing structure, the Contractor shall provide the Engineer with a complete design analysis of the expected impact of that bracing on the structure. This action shall in no way absolve the Contractor of responsibility of damage resulting from said bracing. Steel shoring, bracing and sheeting shall meet the following design requirements: 1. Allowable stresses shall not exceed those allowed by AISC Steel Construction Manual. 2. Steel struts shall have a slenderness ratio of less than 120 and a maximum axial stress of 14,000 pounds per square inch. 3. Connections between struts, walers and wall system shall be designed for a tensile and shearing load equal to at least 10 percent of the design compressive strut load. Delete references to ground freezing if it is not an acceptable means of sheeting and shoring. Ground freezing shall meet the following requirements: 1. Provide a multi-unit refrigeration plant that can be easily reconfigured to provide back-up cooling in case of breakdowns. Size the refrigeration plant with a cooling capacity capable of maintaining brine temperature of at least 20 degrees Fahrenheit. Refrigeration plant must have an acoustic enclosure to minimize noise disturbance. [Contract Name] 02401-2 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common

1.04 SUBMITTALS 2. Pressure test each freezing pipe before and after installation to ensure that coolant does not leak into the ground. 3. Install sufficient electrical temperature sensors (thermisters) in the ground around the shaft to verify extent of ground freezing. Thermister strings shall have thermisters spaced at not more than 5-feet. Provide a minimum of six thermister strings located symmetrically around the excavation and equidistant from adjacent freeze pipes. Provide at least four more thermister strings away from the circulation pipes centerline to determine the thickness of the frozen annulus. 4. Monitor thermister and brine temperatures as required during the freezing process and at least daily thereafter. 5. Monitor piezometers and excavation water levels to verify ground-freezing closure. 6. Brine shall have a specific gravity between 1.24 to 1.28. Brine shall not be capable of freezing in the pumps or circulation lines. Brine shall be non-toxic and comply with applicable environmental requirements. 7. Provide a brine tank with a method to determine if brine has been lost during the freezing operation. If the brine loss is determined to be excessive by the City, the Contractor shall implement the necessary means to reduce leakage including the replacement and abandonment of freezing pipes or at the discretion of the City, abandoning the freezing method of temporary ground support. At least 30 days prior to commencing excavation work requiring sheeting, shoring, and bracing, the Contractor shall transmit its plans for trench and excavation support systems to the Engineer. No excavations shall be started until the Contractor has obtained written acceptance of the trench support system. Said acceptance will be to assure the of the Contractor's general compliance with the Washington Safety Standards for Construction Work (Chapter 296-155 WAC, Part N) and shall not be construed as a detailed analysis for adequacy of the support system, nor shall any provisions of the above requirements be construed as relieving the Contractor of its overall sole responsibility and liability for the work. Reference the Geotechnical Report or Geotechnical Engineer s recommendations in this paragraph. The Contractor s calculations and plans for trench and excavation support systems shall be prepared, stamped, and signed by a civil or structural engineer licensed in the State of Washington and experienced in the design of the proposed excavation support system. The Contractor s Trench and Excavation Support Systems Designer shall determine the lateral soil and water pressure and surcharge loads that could result from the anticipated and actual construction methods and dewatering activities. Shoring lateral pressures as contained in the (EXAMPLE: Supplemental Geotechnical Report and Pumping Tests at 93rd & Hosmer Street Pump Station Upgrade, dated February 1999), are for reference only, and shall be considered 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common 02401-3 [Contract Name]

minimum shoring lateral pressures. Appropriate surcharge loading shall be used to account for construction operations. The (EXAMPLE: Supplemental Geotechnical Report and Pumping Tests at 93rd & Hosmer Street Pump Station Upgrade, dated February 1999), is provided with the project manual. The following information shall be submitted in accordance with (Reference submittal submission requirements) prior to beginning site excavations: 1. Design assumptions, engineering calculations, shoring dimensions, and information on the proposed method of installation and removal of all shoring, trench boxes and/or ground freezing systems. 2. If ground freezing design is used by the Contractor, the submittal shall include the circulation pipe layout, size and depths, details of refrigeration equipment, type of brine, calculations for wall stability and heat transfer requirements, insulation materials, methods for monitoring temperatures and brine losses. 3. Detailed shop drawings showing dimensions, member sizes, plate thickness, welded and/or bolted connections, dimensions of coolant circulation system, and any other details necessary for construction. Construction stationing shall be shown on all drawings, where applicable. 4. Provide as-built drawings of the shoring system including final location of soldier piles, jet grout columns, secant piles or the tops of the brine circulation pipes as applicable for the method selected. 5. Detailed shop drawings for temporary utility support, where necessary. 6. Detailed construction sequence and schedule for the design, review, installation, monitoring and removal of the shoring system. 7. The Contractor's proposed method of monitoring movement and settlement of the shoring and adjacent pavements. Indicate location and types of survey monuments including benchmarks. Readings shall be accurate to 0.01 foot. 8. Provide all survey measurements to the Engineer in a tabulated form within 12 working hours of taking measurements. 9. The Contractor s proposed procedure and corrective measures to be used should horizontal movement or settlements occur adjacent to the shored excavation or trench. 10. Name and experience of the designated Project Safety Supervisor. PART 2 PRODUCTS NOT USED. [Contract Name] 02401-4 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common

PART 3 EXECUTION 3.01 CONSTRUCTION A. INSTALLATION All shoring shall be installed to the dimensions, elevations, and the sequence shown in the reviewed Trench and Excavation Support Systems Plan. The method and sequence shall not cause damage to adjacent structures, utilities, or improvements. At least 14 days prior to the implementation of any changes to the reviewed Trench and Excavation Support Systems Plan, the Contractor s Trench and Excavation Support Systems Designer shall submit the proposed changes to the Engineer for review. Contractor shall provide support of existing structures where shown, specified, and at all other locations where excavation side slopes are greater than 1-1/2:1 or where excavation infringes upon a 1-1/2:1 slope extending from the bottom of the footing or adjacent structure being protected. Stockpiling of excavated materials is not allowed within 40-feet of any installed shoring. The area around installed shoring shall be graded to prevent surface runoff from entering shored excavations. Piezometers will be necessary for monitoring groundwater levels in and adjacent to excavations. Confirm the location and number of existing piezometers and adjust the number of piezometers required for monitoring groundwater levels during construction based on the recommendations of the Geotechnical Engineer. The Contractor shall measure the water level of the three existing piezometers and survey shoring reference points at least once a day during dewatering and excavation. A minimum of two piezometers shall be operational at all times. In the event that a piezometer is damaged during construction, the Contractor shall replace the damaged piezometer at the Contractor s expense. After the excavation is completed, and prior to backfilling, the Contractor shall measure water levels of piezometers and survey reference points once every week or more frequently if necessary. Horizontal deflection of the shoring system into the excavation shall be limited to oneinch. If the deflection exceeds one-inch, the Contractor shall stop the excavation and take immediate corrective actions to prevent further inward movements. Prior to installing pumping station structures, the Contractor shall verify that the subgrade is firm and unyielding. Prior to backfilling the shored excavation, the Contractor shall remove all unacceptable materials such as wood and metal debris and loose soils from the bottom of the excavation. B. REMOVAL: Shoring and cribbing shall be removed in a manner that does not loosen the bedding or backfill associated with the pumping station structures. Shoring may be removed during the backfilling operation. The Contractor shall not excavate soil, or create voids, which may result in pipe or structure deformation or backfill settlement. If the Contractor elects to leave any 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common 02401-5 [Contract Name]

shoring or cribbing in place, it shall be cut off a minimum 5 feet below finish grade. Any wood shoring and cribbing that is left in place shall have been pressure treated to minimize decay. For the ground freezing alternative, abandon ground freeze pipes by filling with cement grout or by removing the pipes and grouting the holes. All pipes shall be cut-off a minimum of 5- feet below finished grade. Where sheeting, shoring, and bracing cannot be removed with the progression of backfill, it shall be designed in such a way that its removal shall not adversely affect the integrity of the pipeline or adjacent structures and the backfill shall be reconsolidated after final removal to the satisfaction of the Engineer. Where sheeting, shoring, or bracing cannot be removed without resulting in damage to the pipeline or adjacent structure, or where such sheeting, shoring, or bracing is specified to remain, it shall be cut off five feet (5') below finish grade and the cut off portions shall be removed from the site. All voids which exist behind the sheeting or shoring left in place, together with all other sheeting or shoring, shall be backfilled in a manner acceptable to the Engineer. Sheeting, shoring, and bracing placed as a cutoff wall between dewatered and recharged areas shall remain in place as long as dewatering is required. Following removal, the resulting voids shall be backfilled in lifts not exceeding 8 inches. Compact backfill to 90 percent of optimum density as determined from the Modified Proctor Test. C. MONITORING AND SUPERVISION: The design of the shoring system, method of construction, and stability monitoring of the shored excavations by surveying methods shall be the responsibility of the Contractor. The Contractor shall ensure that the integrity of the existing structures and pipelines are maintained and that appropriate construction techniques are employed at all times to protect existing structures and pipelines. In the event the shoring becomes unstable or large surface settlements occur, the Contractor shall be responsible for implementing corrective measures. The Contractor shall be solely responsible for any and all liability that may arise from his failure to provide adequate shoring or sheeting as necessary to support the excavation under any and all of the loading conditions that may exist or arise during construction. The Contractor shall be responsible for maintaining a safe work site and shall protect workers and the public health and safety from the consequences of its operations. The Contractor shall provide fencing and barricades around shored excavation to prevent unauthorized persons to access the shored excavation during non-working hours. Trenches shall be covered and barricaded after completion of the day s work, weekends, and other times as necessary. The Contractor shall appoint a project safety supervisor, other than the Project Superintendent who shall be experienced in the installation, maintenance, and removal of the selected support system. The project safety supervisor shall have full authority over the work in all job safety matters and shall be on the job at all times when work is in progress in excavations and trenches. [Contract Name] 02401-6 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common

D. EXISTING PIPING: Contractor shall provide sheeting, shoring, and bracing to protect existing piping where excavation could expose the pipe and/or cause damage to the pipe. 3.02 SEQUENCING Describe any sequencing requirements associated with sheeting, shoring and bracing. Sequencing requirements should also be reflected in a specification section on work sequence requirements for the entire project. Excavation shall not commence until the Engineer has returned review comments on the Contractor s design for sheeting, shoring, and bracing. The 24-inch sanitary line between the existing manhole and the Wet Well shall be installed after the Wet Well shaft has been constructed. 3.03 PAYMENT Coordinate payment requirements with the bidding schedule. To satisfy state law, the bid schedule must have a line item for Trench and Excavation Support Safety Systems if trenching and excavation is included in the project. The line item for Trench and Excavation Support Safety Systems should be as defined by state requirements and should not be defined to include sheeting, shoring and bracing activities. The lump sum contract price for Pumping Station Installation in (Reference Bid Item Description) shall be full payment for all labor, materials, tools, and equipment needed to install and remove the temporary sheeting, shoring, and bracing for the new pumping station, wet well, and 24-inch sanitary sewer line; including installation, maintenance and removal of all necessary dewatering systems; providing a project safety supervisor; and designs, submittals, and revisions of the temporary sheeting, shoring, bracing, and dewatering plans. **END OF SECTION** 4/22/2004 11:02 AM p:\21058\200\207\final Draft\Specs\Common 02401-7 [Contract Name]