New Safe Confinement



Similar documents
METHOD OF STATEMENT FOR STATIC LOADING TEST

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

INSTALLATION. General. Important Note. Design. Transport

PLM series Permanent load lifting magnets

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone:

BSF and BCC beam connections

Physics 125 Practice Exam #3 Chapters 6-7 Professor Siegel

RATCHET RELEASE SHACKLE

Handling, Erection and Bracing of Wood Trusses

Asphalt Shingle Application Requirements

39HQ Airovision Air Handling Units

2. Crane standing on firm, horizontal ground.

ARCHITECTURE. Asst. Prof. Meltem VATAN KAPTAN

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the FTP

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

RT100 ROUGH TERRAIN CRANE DATASHEET - IMPERIAL. Features:

Assembly Instructions for the InteliTrack 3000 Rail Tracking System

SECTION GUARDRAILS

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

GLOSSARY OF TERMINOLOGY

VITOSOL r 200-T SP2A. VITOSOL 200-T Type SP2A

CASE HISTORY #2. APPLICATION: Piping Movement Survey using Permalign Laser Measurement System

Boom and fly capacities for this machine are listed by the following sections:

PVE Piling and Drilling Rigs Powerful, Versatile and Efficient. PVE Piling and Drilling Rigs B.V. Worldwide supply of specialized foundation machines

Buildings Construction Procurement Strategy

2.0 External and Internal Forces act on structures

Integrated Solar Radiant Systems

inimi ing damage and repair osts to manufa tured omes during an eart ua e

I BEAM TRACK INSTALLATION

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Page & Turnbull imagining change in historic environments through design, research, and technology

Installation information. METTLER TOLEDO MultiRange DW150 / DW150T wall scale

Optimising plate girder design

High Strain Dynamic Load Testing of Drilled Shafts

Planning and Building Hay Barns that Work

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

Compression load testing straw bale walls. Peter Walker Dept. Architecture & Civil Engineering University of Bath Bath BA2 7AY.

Protecting YOUR NEW HOME FROM Wind Damage

Hanson Building Products. precast basement solutions

SECTION 1 GENERAL REQUIREMENTS

Elevating Your House. Introduction CHAPTER 5

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Code of Standard Practice for Timber Frame Structures

Chapter 6 ROOF-CEILING SYSTEMS

Solar air collectors for industry and larger halls S Ø. Efficient dehumidification and air heating for free...

Backup Plan Examples. What s Your Backup Plan?

Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc.

Chapter 2 Basis of design and materials

CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C Date of issue , Updated July 1, 2011

Ecopaint Robot Painting Station

Planning Information. Passenger and Freight Elevators.

CLEAR-DIVISIONS CENTERFOLD

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

Mechanical Engineering and Material Handling Aspects of NSDF

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Detailing of Reinforcment in Concrete Structures

MONDOATHENS BASKETBALL SET (Reference PK110)

Load Cell Troubleshooting

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

Installation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: No.: SE-...

OUTCOME 1 STATIC FLUID SYSTEMS TUTORIAL 1 - HYDROSTATICS

POST AND FRAME STRUCTURES (Pole Barns)

STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES

Scope of EN Clarification Document

PUMP JACK SYSTEM AND ACCESSORIES

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel

KWANG SING ENGINEERING PTE LTD

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

Residential Deck Safety, Construction, and Repair

PERFORMANCE TEST REPORT. Rendered to: FORMTECH ENTERPRISES, INC. SERIES/MODEL: Truline PRODUCT TYPE: PVC Seawall

Chapter 3 Pre-Installation, Foundations and Piers

Fixed Access Ladders. Table of Contents. 1. Legislative Requirements

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Maersk Resilient. Maximised drilling efficiency and uptime. Optimised for concurrent activities

Mounting Tripod Kit Installation Manual

BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof.

Automatic Door Selection Guide

American Society of Agricultural and Biological Engineers

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

Steel Tank Erection and Repair

NOTE: Additional user information for your printer may be available in the "Manuals" section at support.dell.com.

Uncovered Decks & Porches

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

301.7D. Mini Hydraulic Excavator

Adjustments for the Active Pneumatic Vibration Isolation Table during Final Installation (File version 6)

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

ENGLISH FORK GUIDE 2013

WiMo Antennen und Elektronik GmbH Am Gäxwald 14, D Herxheim Tel. (07276) FAX

MANUFACTURED HOUSING USED AS DWELLINGS

PaLLe t trucks Lifting carts t r g in t if L

Company DUOL. Dušan Olaj CEO

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

INTERIM WASTE STORE OPERATING LICENCE DESCRIPTION OF THE STRUCTURES, COMPONENTS, SYSTEMS AND EQUIPMENT

Transcription:

New Safe Confinement

Purpose and background The purpose of the NSC construction is to create a barrier against dissemination of radioactive substances contained in the OS and to create conditions for further OS deconstruction operations. The Project is financed from the Chernobyl Shelter Fund (CSF). Engineering and construction are performed by the Contractor (JV NOVARKA) that consists of two French companies: VINCI Construction Grands Projets and BOUYGUES Travaux Publics. Around 50 Ukrainian organizations participate in the NSC Project implementation.

Design NSC is designed for operation during 100 years and is resistant to seismic impact up to 6 points magnitude as well as tornado class 3. In view of the radiation conditions this construction is performed under, the NSC facility is one-of-a-kind in the world Protection of the environment from impact of radioactive materials contained in the Object Shelter is ensured by leak-tightness of the NSC. Leak-tightness functions are performed by: the Annular Space a gap between the internal and external claddings where the ventilation system maintains permanent overpressure relative to the Main Volume effectively preventing egress of radioactive substances into the environment; Elastic membrane that connects the Arch structure with the Object Shelter existing structures ensuring on one hand the leak-tightness and on the other minimization of impacts from the Arch to the existing structures of the OS.

Design NSC main elements are: Arch Foundations Technological Building Auxiliary Facilities: Electrical Equipment Building, Fire Water Pump Station with two 1500m3 fire tanks, Diesel Power Stations with diesel fuel stock tanks, North and South Storm Water Catching Basins, Storm Water Treatment Facilities. NSC facility fully envelopes the OS and the territory directly adjacent thereto and is intended to perform the entire range of activities on conversion of the OS into an ecologically safe system.

Design Height: 109 m Length: 162 m Width: 257 m Arch total weight: 36,479 t The NSC main load-bearing structure consists of 16 steel arch trusses with a span of 257.115m. The distance between the external and internal cladding of the Arch is 13.80m. The distance between the external and internal cladding of the Arch West Wall is 9.60m.

Arch external cladding A multilayer system of physical barriers preventing dissemination of moisture and heat. Provides resistance to weather impact (rain, extreme snow, extreme wind) for the entire 100 year operation life of the facility; Withstands temperature fluctuations and impact of Tornado class 1.5 without causing the steel permanent strain; Withstands Tornado class 3, allowing steel permanent strain without destruction of the structure; Preserves integrity and insulating effect in case of internal fire; Maintains required properties under exposure to radiation reaching 0.1 Gy/h.

Arch internal cladding A shell structure made of special 300 mm wide flat panels manufactured from corrosion-resistant steel. Prevents ingress of dust and particles from the Main Volume into the Annular Space; Limits impact of the internal fire to the Arch steel structures with minimum deformation; Maintains required properties under exposure to radiation reaching 0.1 Gy/h; Maintains its properties and functions during the entire 100 year operation life.

Arch assembly Arch assembly is performed away from the Object Shelter in a special Erection Zone, allowing to reduce radioactive exposure doses for personnel.

Service Zone Foundations The Service zone foundation is designed as two Ground beams arranged symmetrically with respect to the Arch axis on pile foundations, 175.275 m long each. The northern Ground beam consists of three expansion units, 58,635; 65.335 and 51.305 m long, which are separated by two expansion joints. The southern Ground beam consists of three expansion units 69,335; 54,635 and 51,305 m long. Design of contraction joints envisions arrangement of shear key to exclude relative linear displacement of adjacent blocks both in vertical and horizontal plane in the north-south direction and ensure free movement along the foundation axis. Ground beams will be supported by 1,0 m diameter reinforced concrete piles: 184 piles in the south Ground beam and 192 piles in the north beam. The piles will be CFA made of reinforced concrete with diameter of 1,0 m and a length of 19,0 m. In extreme expansion units, the piles are located in 4 rows and 3 rows in the middle unit. The Service zone foundations are connected to the Transfer zone foundations by expansion joints with connection tabs.

Transfer and Erection Zone Foundations In the Transfer zone, the foundation will consist of two Ground beams, each of them being 10,50 m wide and 121,81 m long, symmetrical relative to the Arch axis. The foundation will be a strip one, willow depth, with 114,000 bottom level. The foundations will be made as one unit, without any expansion joint. Foundation of the Erection zone is designed as two Ground beams arranged symmetrically about the Arch axis on pile foundations, with 8,50 m wide Ground beam bottom and 209,91 m long each. The Ground beams are composed of three expansion units 52,81; 75,00 and 82,10 m long separated by two expansion joints. The Erection zone foundations will be supported by 1,00 m diameter steel tube piles.

Foundations Service Zone Foundations South Strip Transfer Zone Foundations North Strip

NSC is complete with all necessary process systems Radiation Monitoring Electrical Power Supply Heating, Ventilation and Air Conditioning Main Cranes Fire Protection Integrated Control System Access Control Communication and CCTV Water Supply and Sewage Structural Monitoring Radioactive Waste Management System

NSC Main Cranes System (MSC)

Hook Level 77,00m Main Crane System (MCS) MCS is designed to ensure dismantlement/reinforcement of unstable structures of ChNPP Power Unit 4 and fuel containing materials and radioactive wastes management works The main functional parameter of the NSC MCS is ensuring implementation of tasks connected with early and deferred dismantling of structures located within its operating range (catching area).

Main Crane System (MCS) Main Cranes System catching area is between axes 40(+1.5 m) - 62 and rows С (+2.4 m) Б (not taking into account maintenance garages and the span of the MTP). Hook lifting mechanism coverage area will be: For the classic carriage: from temporary laydown area to +77,00 m. For the secure carriage: from temporary laydown area to +75,20 m. The recovery drum will lift up to +10 meters and lower -15 meters in recovery from the working hook elevation. For operations, the Mobile Tool Platform lifts from elevation +35 m to elevation +70 m and operates from +35 m to +68 m.

Dimensions of the MCS vs. dimensions of Boeing 737

Main Crane System (MCS) MCS configuration: 2 х 96 m bridges 1 х 50 ton classic carriage 1 х 50 ton secure carriage (for lifting of personnel the lifting capacity of the carriage will be limited to 40 t) 1 carriage equipped with Mobile Tool Platform (MTP) Carriage equipped with Mobile Tool Platform Classic Carriage Secure Carriage

Classic Carriage Specifiation: Capacity: 50 t Lifting speed: step speed adjustment from 1m/min up to 10 m/min, Loaded hook location relative to a defined position shall not exceed +/-50 mm. Hook lifting distance: from Lay Down Area level to elevation +77m Load weighing system with operator display (+/- 5% of full weighted value) Overload limiter that automatically shuts down the hoisting mechanism if the load mass exceeds passport lifting capacity of the crane by more than 15%. A possibility to disconnect the overload limiters during testing of the MCS shall be envisioned. Speed: step speed adjustment from 1 m/min up to 15 m/min, Carriage location relative to a defined position shall not exceed ±50 mm.

Secure Carriage Specification: Carriage fitted with one main single layer cable-winding drum and one reserve multi-layer cable winding drum, each one with 50 T capacity For lifting of personnel the lifting capacity of the carriage shall be limited to 40 T The recovery drum will lift up to +10 meters and lower -15 meters in recovery from the working hook elevation Capacity: 50 T. Lifting speed: step speed adjustment from 1 m/min up to 10 m/min. Loaded hook location relative to a defined position shall not exceed +/- 50mm. Hook lifting distance: from Lay Down Area level to elevation +75,2m Load weighing system with operator display (+/- 5% of full weighted value) Overload limiter that automatically shuts down the hoisting mechanism if the load mass exceeds passport lifting capacity of the crane by more than 15%. A possibility to disconnect the overload limiters during testing of the MCS shall be envisioned. Speed: step speed adjustment from 1 m/min up to 15 m/min, Carriage location relative to a defined position shall not exceed ±50 mm.

Carriage equipped with Mobile Tool Platform 12400 mm Specification: For operations Mobile Tool Platform lifts from elevation +35 m to elevation +70 m; The MTP tools operate within elevations from +35 m to +68 m; Concrete drill and jaw crusher fitted will be fitted on end of carrier arm 2.5m long Loads at the bottom platform at elevation 35m at the centre of the tensile truss connection triangle tooling dead weight between 10 000kg and 19 500kg shall be

Crane assembly West Bridge lift East Bridge assembly Assembled West Bridge with Classic Carriage and Secure Carriage

MTP installation onto the East Bridge

Arch sliding Deaerator Stack Block V Turbine Hall Block ASRU

Sliding operation After completion of Arch assembly in the Erection Zone the Arch will be slid over the OS. Arch sliding system includes the following components: Skid tracks; Jack boxes (shoes) including: Hydraulic suspension jack (main jack) fitted with a lock-nut and a swivel; Side shift; Skidding surface; Connection bars; Power packs and their manifold boxes; Control computer; Laser control system.

General view of the components of sliding system

Push-pull units There are 4 push-pull units per arch supporting nodes for the arches A0, A, B, C, D, E, F, G1+G2, H, J, K, L, M and N+N0, i.e. a total of 14 x 4 x 2 = 112 push-pull units for the skidding of the whole arch. Each push-pull unit consists of 2 hydraulic jacks with a stroke of 600mm and a gripper head (stop device), fixed on the retractable rod i.e. the total number of push-pull jacks of 224 units. The combined capacity of the 2 hydraulic push-pull jacks is 125 T in pushing mode and 90 T in pulling mode.

Arch sliding procedure (1) Operation of Arch sliding system in each support node will be ensured by diesel driven power pack fastened by supports to one of the jack boxes (shoes). The skidding process can be split into the following stages: Step 1: Set-up in the Central Computer the maximum expected vertical loads relevant for the considered skidding phase; Step 2: Check the weather forecast; Step 3: Load transfer from temporary bearings to Arch sliding system: Step 3a: Activate the suspension jacks to the load in increment (50% - 75% - 100%); Step 3b: Visually check if all arch feet are free; Step 3c: Jack-up the arch at +10mm; Step 4: Jack-up to skidding level (see Figure 6.20): Step 4a: Measurement of arch feet levelness with Laser Measurement System; Step 4b: Correct the stroke of the suspension jack with measured unlevelness of the arch feet; Step 4c: Set Zero Level ; Step 4d: Jack-up all arch feet to Skidding Level, by increasing the stroke of all suspension jacks by 50mm;

Arch sliding procedure (2) Step 6: Continuation of skidding: Step 6a: Repeat step 5a; Step 6b: Repeat step 5b; Step 7: Arrival at final position: Step 7a: Lock the push-pull units; Step 7b: Lower the suspension jacks to zero level; Step 7c: Measure deviation between actual and final position; Step 7d: Correct the deviation using the push-pull units; Step 7e: Transfer the load to the permanent/temporary bearings. The speed of 10 m/h (or 11.2m/h without contingencies) is an average speed during the skidding process. As highlighted above, the skidding process is made of a succession of stages when travelling occurs and stages without travelling of the arch.

Arch sliding procedure (3) Based on the targeted speed of 10m/h, the duration of the skidding phases is as follows: Skidding of the complete arch to final position: 33 hours of uninterrupted operations (skidding distance = 330.0m). Skidding can be performed within the selected 72 hours meteorological window and thus with sufficient margin for additional contingencies.