Temporary Works. Jan Andresen BEng CEng MIStructE HM Specialist Inspector of Health and Safety. 12 October 2012



Similar documents
The Construction (Design and Management) Regulations 2007

Excavation & Trenching Procedure

2007 No. 00 HEALTH AND SAFETY. The Construction (Design and Management) Regulations 2007

Excavation Safe Working Practices

Demolition Works Measures for Public Safety

DEPARTMENT OF LABOUR. No. R February 2014 OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 CONSTRUCTION REGULATIONS, 2014

PreventING falls from height Introduction How will worksites be targeted? Approach Who will be targeted?

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

Mobile cranes overturning on construction sites. A guide to loss prevention

Need building work done?

Tower cranes collapsing on construction sites. A guide to loss prevention

Federation of Piling Specialists

2015 No. 51 HEALTH AND SAFETY. The Construction (Design and Management) Regulations 2015

Geotechnical Building Works (GBW) Submission Requirements

Contractor s Safe Working Agreement

SG4:10 Preventing Falls from Scaffolding Collective Fall Prevention.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Accidents - how to deal with them

Health and safety policy

Construction occupational safety and health for construction workers. ILO Construction OS&H

Occupational health and safety specification for construction works contracts

Dr. K.N.Jha Department of Civil Engineering Indian Institute of Technology Delhi Block V, Room No. 322

Working at Height. Procedure

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

Managing health and safety in construction

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

The Guide to Safer Scaffolds

Trenching and Excavation Safety

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting

Health and Safety at Work Inspectorate Annual Report 2013

A Short Guide to The Safety, Health and Welfare at Work Act, 2005

WORK AT HEIGHT UNIT 4

Level 1 Award in Health and Safety in a Construction Environment

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

FATAL CRANE INCIDENT 22 nd nd October 2007

RCD Health and Safety Guide for Ropes Course Owners and Operators

KP3 Offshore maintenance management template. Communication between onshore support staff and offshore maintenance technicians

Management of Lifting with Mobile Cranes

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Question and answer brief for the construction industry on the Work at Height Regulations 2005

WORKING AT HEIGHT GUIDELINES. Version II

Procedure for Working in or around Excavations

CONSTRUCTION SITE HEALTH AND SAFETY SELF AUDIT

Guidance produced jointly by BIS, the UK Association of Notified Bodies and. March 2014

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

Ground Conditions for Construction Plant

Further Reading Monitoring cracks Contacts Historic Scotland Technical Conservation Group Conclusion

Interim Guidance on Collective Fall Prevention Systems in Scaffolding

Working at height A brief guide

Building façade maintenance

Working at height - Practical Guidance for Schools

Corporate Health and Safety Policy

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015

Competent. Person Manual. Course Preview TRENCHSAFETY

OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details

A Great Workforce A Great Workplace. 19 August 2015 OSH Inspectorate OSHD, MOM

East Anglia Construction Safety Group. Tower Crane Safety Update

Working in a quarry guidelines

RESPONSIBILITIES IN MOBILE CRANE OPERATIONS CONSTRUCTION SAFETY ASSOCIATION OF ONTARIO

CODE OF PRACTICE FOR SITE SUPERVISION 2009

What are the risks of working on fragile surfaces? Which surfaces present a particular risk? The following are likely to be fragile:

ALLOWABLE LOADS ON A SINGLE PILE

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

WHS CONTRACTOR MANAGEMENT PROCEDURE

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

WHS Contractor Management Procedure

Clients in Construction Best Practice Guidance

A Guide to Accident Investigations

`Fall Protection Guidelines in Construction

Work at Height / Falling Objects

68 Metal Industry Guidelines for Safe Work

SECTION SUPPORT OF EXCAVATION

Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, , , , and1926.

COPYRIGHT. Dincel Construction System Pty Ltd

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

Tremline Pty Ltd trading as The Hills Bark Blower

Health and Safety Legal Update. Laura Cameron

Ladder, Scaffolding, and Excavation Safety Plan

The Work at Height Regulations 2005 (as amended) A brief guide

SECTION 25. Excavation and Trenching

Jersey Safety Council. End Users Scaffolding Seminar

Are you developing property? A quick guide to your legal responsibilities as a client under the Construction (Design and Management) Regulations 2007

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

2016 No. 253 HEALTH AND SAFETY. The Health and Safety and Nuclear (Fees) Regulations 2016

A Casebook of Fatal Accidents Related to Work-at-Height

SUPPLY CHAIN PREQUALIFICATION PACKAGE

How To Repair A House

The Electrical Safety Regulation (pre and post 1 January 2014)

Crane Stability on Site

CONTRACTORS COMBINED SUPPLEMENTARY PROPOSAL FORM THE RIGHT TOOL FOR THE JOB

Corporate Standard. Contractor Management

THE MORAY COUNCIL. Guidance on data security breach management DRAFT. Information Assurance Group. Evidence Element 9 appendix 31

LAC 67-2 rev3 - Annex B

Professional Engineers Providing Services for Demolition of Buildings and other Structures

SECTION SHEETING, SHORING AND BRACING

Construction OS&H Working at height

Transcription:

Temporary Works Jan Andresen BEng CEng MIStructE HM Specialist Inspector of Health and Safety 12 October 2012

Doing what's right isn't the problem. It is knowing what's right. Lyndon B Johnson

worksafe.vic.gov.au

Definitions of Temporary Works Temporary works means all temporary works of every kind (other than contractors equipment) required on site for the execution and completion of the permanent works and remedying any defects (International Federation of Consulting Engineers (FIDIC) Conditions of Contract Definition) All temporary works of every kind required in or about the construction and completion of the works. (ICE Conditions of Contract Definition)

Definitions of Temporary Works Temporary Works is defined in BS5975 : 2008 as parts of the works that allow or enable construction of, protect, support or provide access to the permanent works and which might or might not remain in place at the completion of the works

Alternative Definition: Temporary Works Anything the contractor has to provide or do in order to construct the permanent works.

Temporary works Hoardings Welfare facilities Services Platforms Earth support Access Propping & shoring

Temporary Works Topics Earthworks - trenches, excavations, underpinning, piling platforms and cofferdams etc. Structures formwork, falsework, backpropping, façade retention, edge protection, re-propping, scaffolding, bailey bridges, hoarding, and signage etc Plant - mobile crane outrigger design, tower crane bases etc.

Problems With Temporary Works No planning or procedure. No design or poor design. Lack of competent contractor / developer. No temporary works equipment available. Inappropriate use of TW equipment or other non TW equipment being used for the purpose of temporary works.

Job creep, the enemy of planning

carry out proper investigation of ground conditions, services or adjacent structures.

carry out proper investigation of ground conditions, services or adjacent structures.

Inadequate horizontal and or diagonal bracing to resist lateral (wind) loads.

Lack of knowledge and inexperience of persons involved in temporary works design / and or erection/maintenance.

Inadequate foundations.

Unauthorised changes to an approved temporary works design.

Proper planning, by a competent person..

Who is a Competent person? A competent person is one who can demonstrate that they have sufficient professional or technical training, knowledge, actual experience and authority to enable them to:- Carry out their assigned duties at the level of responsibility allocated to them. Understand any potential hazards related to the work (or equipment) under consideration Detect any technical defects or omissions in that work (or equipment), recognise any implications for health and safety caused by those defects or omissions, and be able to specify a remedial action to mitigate those implications.

Pictures of hoardings Hoardings

Hoardings

Hoardings F L M

Hoardings F L M

Hoardings

Hoardings

Pictures Proprietary hoardings and fencing

Proprietary hoardings and fencing Still the same issues as before (wind / overturning etc) But now designed by manufacturer So does the contractor know / understand the limitations of the hoarding and what the system has been designed to take? Have they installed them correctly? Have they changed things (e.g. sheeted it or added a dirty great big advertising sign?)

Fencing

Excavations basic principles No ground can be relied upon to stand unsupported. 1.2m depth rule is often quoted on site but went years ago. Steps shall be taken where necessary to prevent danger to any person

HSE enforcement expectations for excavations Prior to C(HSW) 1996 all excavations in which someone was working required shoring C(HSW) 1996 Risk assessment based approach not intended to impose lower standard CDM 2007 contains old C(HSW) provisions Excavation deeper than 1.2m being worked in without shoring Prohibition Notice unless justified by suitable & sufficient risk assessment

Soils fail in different ways Stiff clay Soft clay

Soils fail in different ways Sand

Basement / Deep underpinning construction High Risk Work Need Temporary works engineering input Method Statement should be in place Clear method of shoring excavations In poor soils - will need sacrificial back shutter HSE/ Bldg Ctrl Interface Dangerous Structures

Underpinning failure to survey existing wall and to prop Internal wall External wall Heading

Construction (Design and Management) Regulations, 2007 Regulation 31 (1) All practicable steps shall be taken, where necessary to prevent danger to any person, including, where necessary, the provision of supports or battering, to ensure that (a) any excavation or part of an excavation does not collapse; (b) no material from a side or roof of, or adjacent to, any excavation is dislodged or falls; and (c) no person is buried or trapped in an excavation by material which is dislodged or falls.

Construction (Design and Management) Regulations, 2007 31 (2) Suitable and sufficient steps shall be taken to prevent any person, work equipment, or any accumulation of material from falling into any excavation 31 (3) Without prejudice to paragraphs (1) and (2), suitable and sufficient steps shall be taken, where necessary, to prevent any part of an excavation or ground adjacent to it from being overloaded by work equipment or material;

(source E Little The building of the Barton High Level Bridge)

Temporary Works Barton Bridge disaster 1959 Whilst erecting 4No, 200 ton steel girders, 80ft above the ground, the supporting scaffolding collapsed bringing down the girders and killing 4 men. 60 men, that would normally have been on the girders, were lining up for their pay at the time. 21 children were left fatherless. (source E Little The building of the Barton High Level Bridge)

Temporary Works Evidence given at the Inquest: Scaffolding not installed in accordance with the design drawings The design drawing was not a working drawing and only gave an indication of the structure Worn and corroded scaffold tubes had been used (source E Little The building of the Barton High Level Bridge)

Temporary Works Lack of lateral bracing Design carried out by an estimator draughtsman. Not passed by an engineer Bulging of the scaffold noted but not acted upon (source E Little The building of the Barton High Level Bridge)

Temporary Works Tragedy struck again Scaffold supporting 4 steel girders, 250ft long failed, killing 2 workers and injuring 8 others. (source E Little The building of the Barton High Level Bridge)

Temporary Works The Coroner concluded that.the general picture was one of men fumbling about not knowing where anything was, or where to get anything (source E Little The building of the Barton High Level Bridge)

Temporary Works That was 50 years ago

this wasn t..

Temporary works guidance SIM 02/2010/04 The management of temporary works in the construction industry BS 5975:2008 Code of practice for temporary works procedures and the permissible stress design of falsework BS 5531:1988 Code of practice for safety in erecting structural frames (Withdrawn but gives useful advice)

Temporary Works So what does the law require?

Temporary works guidance Foreword to BS 5975:2008 states: The term temporary works co-ordinator (TWC) has been adopted to reflect the need for procedural controls of all temporary works and to recognise that the majority of contractors already control temporary works in this manner. Compliance with the Construction (Design and Management) Regulations 2007 (CDM) [3], [8] has been incorporated, particularly in respect to the interface between the design of permanent

Temporary works guidance CDM applies to all design requirement for the design of the Temporary Works to be co-ordinated to ensure that the risks are properly controlled. CDMC would have the competence to assess the safety considerations in the permanent works design, unlikely to have the competence to deal with the specialised area of Temporary Works. It is to cover this potential gap that the code of practice creates the role of the TWC.

Appointing a Temporary Works Coordinator, is it a legal requirement? Broadly, HSWA outlines the duty that work activity should be carried out, SFAIRP, without risk to the health and safety of those that may be affected by the work. CDM requires that design activities are coordinated with each other and that proper consideration is given by designers to ensuring that risks arising out of the construction of their design can be properly controlled. To this end,

Think of temporary works as A project within a project. The PC is responsible for the TW, and is therefore the client as he is procuring the work. The TWC is therefore the CDMC for the TW project

Temporary works That s fine for the big jobs, what happens lower down in the market? To most contractors, Temporary Works means propping using our old friend, the Acrow prop

Acrows

Acrows

Strongboy, safe load 350kg

Domestic jobs Often see the contractor overreaching by taking on work that isn t within his experience or competence

Temporary Work Procedure Appointment of a Temporary Works Co-ordinator (TWC). Completion and Maintenance of a Temporary Works Register. Preparation of Design Briefs for Elements Identified in Register. Production of Temporary Works Designs. Preparation of Risk Assessments / Method Statements. Pre-erection / Installation Inspection of Materials & Components. Supervision of Erection / Installation of Temporary Works. Inspection & Check of Temporary Works Prior to Use. Approval Permit to Load (Temporary Works Loaded). Approval to Dismantle Following Checks Permit to Dismantle. Temporary Works Dismantled and Signed Off.

CDM (2007) 28. (1) All practicable steps shall be taken, where necessary to prevent danger to any person, to ensure that any new or existing structure or any part of such structure which may become unstable or in a temporary state of weakness or instability due to the carrying out of construction work does not collapse. (2) Any buttress, temporary support or temporary structure must be of such design and so installed and maintained as to withstand any foreseeable loads which may be imposed on it, and must only be used for the purposes for which it is so designed, installed and maintained. (3) No part of a structure shall be so loaded as to render it unsafe to any person.

Temporary Works What is HSE doing? What sort of questions might we ask?

Temporary Works Do you have a formal TW procedure? Who is the named TWC? What is their background? Do you have a TW register? Is there a design brief?

Temporary Works Has the work been designed? Has the design been independently checked? What checks have been made to ensure that the works have been installed in accordance with the design? What involvement has the CDM-C had?

Temporary Works What do we hope to see?

Temporary Works Attention to temporary works management arrangements and procedures..commensurate with the scale and complexity of the project and the construction risks involved Medium / large projects formal procedures Small, simple projects principles of BS5975

Temporary Works What have we been finding?

It depends.. Temporary Works

Temporary Works For the larger projects, then normally some form of TW procedure. Some follow BS5975 quite closely, some follow the principles. But not much involvement by CDM-Cs

Temporary Works and the smaller projects?

Temporary Works At best, a recognition that TW can be hazardous and needs particular attention

Temporary Works But more often

Temporary Works I don t see what the problem is. Adequately supported? Adequately supported?..i ve been in this game for 40 years

Temporary Works

Temporary Works Erm, no, I ve not spoken to an Engineer

Temporary Works

Temporary Works

Temporary Works

Temporary Works common failings Lack of adequate lateral stability Inadequate foundations Overloading Inappropriate parts being used Poorly designed (if at all) Poorly constructed

Temporary Works common failings Workforce not competent for tasks required Don t appreciate the true force of wind No investigation of existing conditions (ground, services, structural condition etc) Ad hoc changes made General lack of control, management and supervision

Temporary Works Design Brief Purpose of temporary works including drawings of permanent works and any specifications. Required dimensions and any known constraints. Particular loads including impact loads - loadings from construction material, plant and personnel in addition to environmental loads. Ground conditions information soils, groundwater etc provide geotechnical information.

Temporary Works Design Checks High Risk temporary works - independent check, normally a designer in a different office or design organisation. Medium Risk temporary works - check can be by the same organisation if documentary proof of independence of checkers. Low Risk temporary works the checks can be by someone in the site team or the design team.

REMEMBER The majority of contractors are aware of the need to prop vertically but often fail to understand the importance of maintaining the lateral stability of the supports. Most things fail sideways rather than vertically. Preventing sideways movement can eliminate the most common cause of unintended collapses.

Temporary Works Inadequate or poor TW is implicated in many incidents Research carried out by CIRIA and Loughborough University for HSE identified 8 key issues Issue 6: The effective management of TW is crucial to success Free to download Issue 5: Competence is key

FEE FOR INTERVENTION.those who break the law should pay their fair share of the costs to put things right - and not the public purse Government policy Fee for Intervention - a legal duty placed on HSE to recover its costs for carrying out its regulatory functions under HSWA. The aim is to shift some of the costs of health and safety regulation from the public purse to businesses and organisations that break health and safety laws. Triggered when there has been a material breach Material breach - when in the inspector s opinion there is or has been a contravention of health and safety law requiring notification in writing of that opinion, either by notification of contravention, improvement notice, prohibition notice or prosecution. Came into force 1 st October 2012