E.ON Offshore Wind Energy Factbook

Similar documents
E.ON Offshore Wind Energy Factbook

The installation and servicing

Offshore Work Packages

Monobuckets and the competitiveness versus monopiles and jacket structures.

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

Offshore Wind. IEEE Boston PES - November 16, 2010

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS

Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen LICENGINEERING A/S

installation, operations & maintenance

Offshore Wind: some of the Engineering Challenges Ahead

Dutch wind energy strength

Nautischer Verein zu Bremerhaven Bremerhaven, Nautischer Verein

London Array Off-Shore Wind Farm

Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines. The new standard for offshore. siemens.com/wind

Nordex SE. Nordex goes Offshore

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

INNWIND.EU Offshore wind energy DTU Contributions to WP4.2 Technology, ecomony, trends and research. Henrik Bredmose Thomas Buhl

GRAVITY BASE FOUNDATIONS

Offshore Windpark DanTysk. Cost-Effective Foundations Design to Installation

Offshore Wind Challenges for the Insurance Industry. AIMU Marine Insurance Issues 2011

Wind Service Offshore. We can t conquer the elements But we can outthink them

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Case Study 5 Use of Wind Turbine Technology

COWI offshore wind marine engineering services

The Market for Installation Vessels

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

London Array. Operations and Maintenance

Civil Engineering and Marine Works (CEM) Offshore Branch Office

Installation, future demands for recruitment and competencies. Speaker: Hans Schneider Date: 4 April 2013

The Monopod Bucket Foundation

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Offshore Wind OPERATIONS & MAINTENANCE. A National Renewables Infrastructure Plan Stage 2 Information Paper

Steel construction. Solutions for the renewable energy and offshore sectors. published by energyengineering magazine

The WindFloat Project

HV Submarine Cable Systems Design, Testing and Installation

Overturning Stability of Offshore Wind Power Substructure with Bucket Foundation

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

Best Practice Guide. How to Choose an Offshore Wind Transport & Installation Provider March 2013

Trends in offshore wind economics the past and the future

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Nordex SE. Capital Markets Day Products & Sales - Lars Bondo Krogsgaard

Offshore Base Cuxhaven. Dr. Hans-Joachim Stietzel Head of Dept. for Economic Development City of Cuxhaven Germany

Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines. Reduced complexity, increased profitability. siemens.

OWPST & Titan 200 & UK Offshore

E.ON Business Deep Dive - Renewables. December, 2015

Offshore Windfarm Egmond aan Zee 4 years of Operation

Scottish Enterprise. Offshore Wind Power: Priorities for Research and Development (R&D) and Innovation. Supporting a globally competitive Scotland

Title: IEC WT 01 vs. IEC Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group.

ROADMAP ON MARINE RENEWABLE ENERGY

De Industrie. KIvI Niria Jaarcongres De uitdagingen voor windenergie op zee. Ballast Nedam Offshore. Dolf Elsevier van Griethuysen

Danish Society for Naval Architecture and Marine Engineering, Danish Maritime Society, The Transport Innovation Network & Danish Wind Energy Group

STENSEA. Stored Energy in Sea. The Feasibility of an Underwater Pumped Hydro Storage System. Dr. Andreas Garg Christoph Lay Robert Füllmann

Translating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU

WIND ENERGY - THE FACTS PART III THE ECONOMICS OF WIND POWER

Depth-independent solution for Offshore Wind the WindFloat

DONG Energy offshore wind experience

OFFSHORE WIND PROCUREMENT

COOLING SOLUTIONS WIND

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT

Turnkey cable solutions to better deploy your windfarm infrastructure

Network Interconnection of Offshore Wind

Essex... A great location for offshore wind

Profile. Offshore Wind Projects. Sustainable EPC and Marine Contractors

The European offshore wind industry key trends and statistics February A report by the European Wind Energy Association

Viking Link Interconnector

EXPERIENCE WITH DP-SYSTEMS ON BOARD

Onshore Wind Services

QUALITY OF WIND POWER. How does quality affect the cost of electricity generation from wind power?

The Delft Offshore Wind Turbine Concept (DOT)

V MW. Your best option for low cost energy production at low and medium wind sites. Federico Gonzalez Vives. Director Technology.

Firth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information

Strategy of the German Government on the use of off-shore wind energy

GE Renewable Energy. GE s 3 MW Platform POWERFUL AND EFFICIENT.

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India

Future Offshore Wind Power Sites -2025

Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems

Logistic solutions for the installation of offshore wind farms

Innovation in Offshore Wind support structures

GE Power & Water Renewable Energy. Digital Wind Farm THE NEXT EVOLUTION OF WIND ENERGY.

Wind Power Overview - with offshore focus. Jörgen Svensson Industrial Electrical Engineering and Automation

Why Offshore Wind? Our focus is on driving down the costs of offshore wind through the development of appropriate innovative engineering solutions.

Brochure. Generators for wind power Proven generators reliable power

Electricity market drivers

NORDEX USA, INC. GREAT LAKES SYMPOSIUM

Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?

OFFSHORE WIND INDUSTRY IN DENMARK

Offshore Wind Operations. Fife, at the heart of renewable energy development in Scotland

E.ON Wind Turbine Technology and Operations Factbook

Newsletter September 2013

Seed Bed Combination Korund 8

The Reliance on Wind Energy Depends on Advancements in Blade Pitch Control

Transcription:

E.ON Offshore Wind Energy Factbook E.ON Climate & Renewables September 2012

Introduction 3 Offshore Wind Industry 5 Challenges of Offshore Wind 9 Technical Solutions 14 E.ON s Approach 37 Factsheets of E.ON s Offshore Wind Projects 41 Key Learnings 59 Picture taken at E.ON Offshore Project - Robin Rigg (United Kingdom, 2009) 2

Dear Reader, Offshore wind is one of the most fascinating industries in the renewable energy sector and is experiencing a remarkable growth. By mid of 2012, around 4,300 MW of installed offshore wind capacity was operating in Europe. By 2020 around 40,000 MW should be installed, a 10-fold increase. E.ON is committed to being a leading player in the offshore wind industry. In 2010, we commissioned 46% of all new offshore wind installations in Europe. We have already invested around 2 billion into our offshore wind farms. This includes five operational offshore wind farms across the North and Baltic Sea, and the ongoing construction, with partners Dong and Masdar, of the London Array which will be the world s largest offshore wind project when fully completed. This unique experience enables us to move our offshore wind activities from a project-by-project basis to a portfolio approach, thereby leveraging E.ON s skills and procurement capabilities. Using our extensive and diversified project pipeline, we will commission an offshore wind farm every 18 months while significantly reducing costs by 40% by 2015. By 2015, E.ON will invest another 2 billion in three further offshore wind farms in Germany, UK and Sweden. In total these projects will have an installed capacity of around 550 MW. Our long-term lease of a specialist construction vessel will support the construction of these projects. In this Factbook we would like to give you some insights into the offshore wind industry, its challenges, growth prospects, and our own projects. We hope that you find it useful, and we would welcome your comments and feedback. Kind regards, Mike Winkel, CEO E.ON Climate & Renewables GmbH 3

Picture taken at Offshore Project London Array ((United Kingdom, 2012) - a Joint Venture of E.ON (30%), DONG (50%) and Masdar (20%) 4

Offshore Wind Industry Offshore Wind Development and Milestones in the EU 4.500 4.000 MW Installed Capacity in the EU 1,371 offshore wind turbines installed and connected to the grid Around 250 new offshore wind turbines in 2011 3.500 3.000 New Build in the EU World s 1st far-shore wind farm Alpha Ventus (Germany) 60 MW** 2.500 1st 100+ MW offshore wind farm Horns Rev 1 (Denmark) 160 MW* 1 GW operational capacity Annual Growth >200 MW 2.000 1.500 1.000 1st commercial offshore wind farm Vindeby (Denmark) 4.95 MW 1st E.ON offshore wind farm Blyth (United Kingdom) 4 MW 500 0 1991 1992-2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 After a slow and pilot-project driven development before 2001, offshore wind energy has developed into one of the key renewable energy industries in the EU In 2010, with almost 3,000 MW installed offshore wind capacity, the EU is a world leader in offshore wind Source: European Wind Energy Association **JV of E.ON 26.25%), EWE (47,5%) and Vattenfall (26,25%) 5

Snapshot of the EU Offshore Wind Industry European Installed Offshore Wind Capacity (2011) UK UK DK DK United Kingdom 55% 2,094 MW Denmark 23% 857 MW Netherlands 6% 247 MW Germany 5% 200 MW Belgium 5% 195 MW Sweden 4% 164 MW Finland 0.6% 26 MW Ireland 0.6% 25 MW Good to know Over 95% of global operational offshore wind installations are located in European waters More than 55% of the total offshore wind installed capacity in the EU is located in the United Kingdom, and another 40% in Denmark, the Netherlands, Germany, Belgium and Sweden In 2011 a total of 886 MW of offshore wind capacity was brought online mostly in UK and Germany Utilities have realized about 90% of EU offshore wind projects. E.ON commissioned 46% of new installed European offshore wind capacity in 2010 The first offshore wind farms outside Europe were commissioned in 2010 in China and Japan Norway, Portugal 0.1% 4 MW Total 100 % 3,813 MW Sources: European Wind Energy Association, Emerging Energy Research 6

European Outlook on Offshore Wind Energy Development and forecast of installed capacity MW ~ 40,000 MW 40.000 Installed Capacity 35.000 New Build Capacity 30.000 25.000 21,500 MW 20.000 15.000 10.000 5.000 3,000 MW 0 2000 2002 2004 2006 2008 2010 2015 2020 Good to know Following a rather slow growth until 2010, offshore wind energy in Europe is supposed to grow strongly over the next decade: from 3,000 MW in 2010 to about 21,500 MW in 2015 to about 40,000 MW in 2020 Many European countries aim to build up offshore wind energy, especially in the North Sea and Atlantic: UK: 13,000 MW by 2020; 33,000 MW by 2030 Germany: 10,000 MW by 2020; 25,000 MW by 2030 France: 6,000 MW by 2020 Netherlands: 5,000 MW by 2020 Denmark: 1,300 MW by 2020 Sources: National Renewable Energy Action Plans of EU Member States, European Wind Energy Association,, Emerging Energy Research, 7

Global Perspective of Offshore Wind Energy Installed offshore wind capacity and targets worldwide North America Status in 2010: 0 MW Target for 2020: 3,000 MW EU Status in 2011: 3,800 MW Target for 2020: 40,000 MW China Status in 2010: 100 MW Target for 2015: 5,000 MW South Korea Status in 2011: 0 MW Target for 2020: 3,000 MW So far, development of offshore wind energy has mainly taken place in Europe, with the first offshore wind farms commissioned in Japan (25 MW) and China (100 MW) in 2010 Europe will remain the leading region with a target of about 40,000 MW of offshore wind by 2020 Source: EWEA, Price Waterhouse Coopers 8

Challenges of Offshore Wind Offshore wind is different from onshore wind Sun heats earth Temperature differences Pressure differences Air movement/wind The creation of wind is a simple physical process: The sun radiation heats the earth thereby creating temperature differences which lead to pressure differences causing the air to move Wind conditions onshore and offshore differ essentially. While the landscape, trees and buildings distort the flow of onshore wind, offshore wind flow can develop without obstacles with higher wind speeds and a more even flow close to the surface which also allows lower tower heights In order to use wind at its best, offshore wind farms are laid out in a specific way: The wind farm layout depends on the main wind direction and the conditions of the seabed To avoid turbulence from other wind turbines, wind farms are designed with a minimum distance between individual turbines of 5-8 times rotor diameter in main wind direction 9

Offshore is more than onshore in the water Main differences between onshore and offshore wind energy projects Onshore Wind Offshore Wind Resources Dimensions Wind potential for 2,000 full load hours Limited sites available 1 3 MW wind turbines Wind farms of 10 50 MW installed capacity Investment of 30 70 million per wind farm At full load, one wind turbine produces a household s annual consumption* in 200 minutes Wind potential for 4,000 full load hours Large sites still available 3 7 MW wind turbines Wind farms of 50 1,000 MW installed capacity Investment of 1 3 billion per wind farm At full load, one wind turbine produces a household s annual consumption* in 40 minutes Environment Foundations Land-based conditions Unrestricted access (24 hours / 7 days a week) Built on solid ground Standard concrete foundations cast on site Rough marine conditions Distance to shore 1 70 km Access limited by high waves and storms Differing soil conditions (sand, clay, rock) and erosion Foundation type depends on water depth and soil consistency (e.g. monopiles, gravity, tripod) Offshore wind energy has a greater energy potential but marine conditions pose great challenges to project delivery weather, wind and waves can significantly influence the outcome Thus, a whole new approach to wind power is needed, in terms of turbine technology and scale, foundation types, infrastructure, logistics and maintenance *based on average annual electricity consumption of 3,500 KWh 10

Offshore is not offshore Coast Distance to shore Water depth Wind resources Power Generation REVENUE Distance to shore Water depth Each offshore wind energy project has its individual characteristics depending on factors such as wind conditions, the consistency of the seabed, water depth and the distance to shore: Project developers choose their foundations and wind turbines considering the individual wind conditions, the consistency of the sea bed and the particular water depth Logistics, Operations & Maintenance (O&M) concepts and the accessibility of the turbines are strongly influenced by the distance to the shore Far-shore projects with a greater water depth need larger wind turbines and a higher energy output in order to balance costs and revenue Seabed Wind farm design: Size of wind farm Wind turbines Foundations Logistics COSTS 11

Different offshore conditions require different solutions Different offshore conditions in the North and Baltic Sea and their impact on offshore wind projects Tide Waves North Sea Baltic Sea Impact on High difference of water level of 2 m to 10 m High waves Partly breaking waves Low tide below 50 cm Lower waves Installation O&M activities Installation O&M activities Water depth Up to 40 m Up to 25 m Foundation design Seabed conditions Distance to shore Mostly sand with some rocks Near-shore in many countries German projects in North Sea more than 40 km away Variety of seabed conditions: e.g. flint stones, clay, foundlings, chalk layers Near-shore Location Foundation design Installation O&M activities Grid connection Ice No sea ice Partial sea ice in winter Foundation design (e.g. use of ice cones) Current Strong currents Medium currents Installation O&M activities Apart from the wind conditions, the natural site conditions in European waters differ significantly which requires different project planning and technical solutions to cope with varying sea bed conditions, water depth, accessibility and ice formation 12

Milestones Offshore projects require extensive long-term planning Origination Development Construction Operation Initial screening of potential sites Preliminary evaluation of seabed and wind conditions Securing of project and property rights Application for permission Wind Assessment/ Ground Survey Environmental Impact Assessment (EIA) Technical planning Securing of grid connection Receiving of construction permit Component contracts signed Installation of foundations and wind turbines Connection to onshore grid Commissioning and start of operation Hands-on and proactive operation Regular check and maintenance of technical equipment Repairs, overhauls and upgrades At end of lifetime: decommissioning or repowering The realization time of an offshore wind park, from the first idea to the start of the project, might require up to 10 years of continuous work and a complex project management Pictures taken at E.ON Offshore Project Robin Rigg (United Kingdom, 2009) 13

Technical Solutions for Offshore Wind Offshore Wind Foundations - Overview Gravity Foundation Monopile Foundation Tripod Foundation Jacket Foundation Re-enforced concrete Steel structure Heavy steel structure Laterace steel structure Max. water depth = 30m Max. water depth = 25m Max. water depth = 35m Max. water depth = 45m Suitable for 5 MW turbines Limited to 3.6 MW turbines Suitable for 5 MW turbines Suitable for 5 MW turbines Good experience Mostly used foundation Little experience Little experience Water depth and consistency of the seabed determine the choice of foundation. So far, there is no universal foundation type suitable for all kinds of seabed conditions With a share of 75% in 2011, monopile foundations were the most commonly used foundation type, followed by gravity foundations with a share of 21% Significant research and development are still necessary to develop a cost-efficient concept for production at industrial scale. New concepts, e.g. floating foundations, are being tested Source: European Wind Energy Association, 14

Gravity Foundation Manufacturing and Delivery Assembly of the steel formwork Foundations are cast in concrete Completed gravity foundation Gravity foundations are preferably used in waters with a maximum depth of 30 meters Made of reinforced concrete, one gravity foundation can weigh up to 1,400 tons at a height of 15 meters To increase weight and stability, gravity foundations are often filled with gravel and stones From arrival at site, the complete cycle of installation of a foundation takes less than 24 hours E.ON has gained experience with gravity foundations in its Danish project Rødsand 2 To date, E.ON has successfully installed 162 gravity foundations Pictures taken at E.ON Offshore Project Rødsand II (Denmark, 2009) 15

Gravity Foundation - Installation Foundations shipped to site Heavy lift vessel on site Positioning of 1,300 ton foundation Foundation lowered to seabed Level checks on the foundation Installation complete Pictures taken at E.ON Offshore Project - Rødsand II (Denmark, 2009) 16

Monopile Foundation Manufacturing and Delivery Monopile delivered to harbor Monopiles loaded out on jack-up barge Monopile being up-ended for installation Monopile foundations can be used in waters with a maximum depth of 25 meters Made of steel, one monopile foundation weighs up to 800 tons About 30 meters of the monopile is driven into the seabed Monopiles are the most common foundations so far, especially for projects in the sandy North Sea seabed Pictures taken at E.ON Offshore Project Scroby Sands (United Kingdom, 2003) 17

Monopile Foundation - Installation Pile gripper for exact pile positioning Pile hammer (300 t of force) driving monopile Installation complete From arrival at site, the complete installation of a foundation takes less than 24 hours E.ON has gained experience with monopile foundations in its United Kingdom projects at Blyth, Scroby Sands and Robin Rigg To date, E.ON has successfully installed more than 250 monopile foundations Pictures taken at E.ON Offshore Project Scroby Sands (United Kingdom, 2003) and Robbin Rigg (United Kingdom 2009) 18

Tripod Foundation - Manufacturing and Delivery Tripods being welded in Norway Tripod up-ended for shipping Tripods arriving at Wilhelmshaven port Tripod foundations can be used in deeper waters with a maximum depth of 35 meters Made of steel, one tripod foundation weighs up to 700 tons with a total height of up to 50 meters In an extensive manufacturing process, all different pieces of the tripods have to be welded together Tripods are still in the development phase and are rarely put to use in offshore wind installations Pictures taken at E.ON Offshore Project Alpha Ventus (Germany, 2009, Source: DOTI) 19

Tripod Foundation - Installation Heavy-lift crane ship on site Tripod foundation lowered to seabed Installation complete For the installation of a tripod foundation, three securing steel piles, each 30 meters long and weighing 100 tons, are needed to fix the tripod to the ground From arrival at site, the complete installation of a foundation takes 2-3 days but the installation process will benefit from larger capacity jack-up crane vessels E.ON has gained experience with the successful installation of six tripod foundations in the German offshore wind project Alpha Ventus Pictures taken at E.ON Offshore Project Alpha Ventus (Germany, 2009, Source: DOTI) 20

Jacket Foundation - Manufacturing and Delivery Jackets at Burntisland Fabrication, Scotland Jackets at Eemshaven port, Netherlands Jackets being shipped to site Jacket foundations can be used in water depths of more than 40 meters Made of steel, one jacket foundation weighs up to 500 tons with a total height of up to 45 meters In the manufacturing of the jackets, many single steel beams need to be welded together Next to monopile and gravity foundations, jacket foundations are the third most common type of foundation, quite often also used for transformer stations Pictures taken at E.ON Offshore Project Alpha Ventus (Germany, 2009, Source: DOTI) 21

Jacket Foundation - Installation Jacket foundations during transport Installation complete Offshore transformer station on jacket foundation at alpha ventus wind farm Jacket foundations are also used for the installation of larger offshore structures like offshore transformer stations with a weight of up to 2,400 tons From arrival at site the complete installation of a foundation takes up to three days E.ON has gained experience with the successful installation of six jacket foundations in the German offshore wind project Alpha Ventus and at the installation of the transformer station Pictures taken at E.ON Offshore Project Alpha Ventus (Germany, 2009, Source: Stiftung Offshore-Windenergie, DOTI) 22

Wind Turbines - Technology Main components of a wind turbine 3 4 5 6 2 1 2 3 Tubular steel tower Nacelle with main mechanical and electrical components Hub with three rotor blades, rotating at slow speed 4 Main shaft transmitting rotation from hub to gearbox 5 Multistage gearbox with high gear transmission ratio 1 6 Fast turning generator, producing electricity Offshore wind turbines must be highly robust and reliable to avoid costly standstills, since they cannot be accessed at some times because of wind, wave and weather conditions Most offshore wind turbines have a conventional design that is also used in onshore wind turbines, which includes gearbox and generator in the nacelle, while gearless turbines do not have a gearbox In addition to normal wear and tear, offshore wind turbines may suffer damage from: Corrosion due to aggressive salty environment High wear due to heavy mechanical loads and higher utilization Failures may affect gearbox, generator, transformer, blades and transmission cables 23

Wind Turbines - Development Size and capacity of wind turbines have significantly increased Project Scroby Sands Rødsand II Robin Rigg Alpha Ventus Turbine Type Vestas V80 Siemens 2.3-93 Vestas V90 REpower/Multibrid Hub Height 60 m 68 m 80 m 90 m Rotor Diameter 80 m 93 m 90 m 126 m / 116 m Capacity 2 MW 2.3 MW 3 MW 5 MW Number of Turbines 30 90 60 12 Size and capacity of offshore wind turbines have increased considerably. At the moment, wind turbines with a capacity of up to 7 MW are being tested While at onshore sites the size of wind turbines is often limited by restrictions on height and rotor diameter, offshore wind turbines do not encounter these limits in the open sea In 2011, the average capacity of offshore wind turbines was about 3.6 MW Source: European Wind Energy Association 24

Wind Turbines - Pre-Assembly Pre-assembled turbine parts in the harbor Storage of wind turbine blades Pre-assembled turbine ready to be ship to the site Wind turbine components need to be pre-assembled onshore to allow quick installation offshore. The most important pre-assembly works are the stacking of tower segments Vessels with high cranes are needed to finally install the nacelle and the blades. This process needs a high level of precision and can only be fulfilled in good weather and with low wind speeds From arrival at site the installation of a wind turbine takes a minimum of 24 hours To date, E.ON is operating and installing more than 365 offshore wind turbines in three different countries Pictures taken at E.ON Offshore Project Robin Rigg (United Kingdom, 2009) 25

Wind Turbines - Installation Special vessels to install wind turbines A wind turbine is installed in several steps Once the tower is fully installed, the crane will pick up the nacelle and the blades Bunny ear method: Installation of the preassembled nacelle with two blades Pictures taken at E.ON Offshore Projects Robin Rigg (United Kingdom, 2009) and Rødsand 2 (Denmark, 2010) Rotor star method: Installation of a preassembled hub with three blades Installation complete 26

Offshore Vessels - Requirements Jack-up crane vessel during foundation installation Heavy-lift crane ship during foundation installation For the complex construction process of offshore wind farms, construction vessels need: sufficient storage capacity for large components sufficient height and lifting power the ability to quickly position and jack-up at the installation site the ability to operate year-round in a range of water depths, wave heights and currents Purpose-built vessels, which are especially equipped for the installation of foundations and offshore wind turbine installations, are key to successful offshore construction Pictures taken at E.ON Offshore Project Robin Rigg (United Kingdom, 2009) and Alpha Ventus (Germany, 2009) Source: DOTI 27

Offshore Vessels - Characteristics Heavy-lift crane ship Jack-up barge Jack-up crane vessel Very limited storage capacity Strong lifting power, low height Slow, hauler needed Susceptible to waves Limited storage capacity Sufficient lifting power and height Slow, hauler needed Less susceptible to waves Large storage capacity Sufficient lifting power and height Fast, flexible and independent Less susceptible to waves Jack-up crane vessels which are purpose-built for offshore wind energy installation represent the ideal solution, and a variety of designs have been presented to the market in recent years A new generation of jack-up crane vessels will be capable of installing turbines of the 5-6MW class and larger monopile and jacket foundations, with dynamic positioning systems for faster positioning at site E.ON has a six-year lease on a state-of-the-art jack-up crane vessel, the MPI Discovery, for use in upcoming projects Pictures taken at E.ON Offshore Projects - Robin Rigg (United Kingdom, 2009) and Alpha Ventus (Germany, 2009, Source: DOTI) 28

Optional HVDC offshore transformer station AC cable DC cable Grid Connection and Array Cabling Cable plowing onshore Cable pulling to foundation Installation complete Array cabling Offshore transformer station Onshore grid connection point Within the offshore wind farm, array cabling (AC) connects rows of wind turbines to the offshore transformer station The offshore sea-cable (AC or DC) connects the offshore transformer station to the onshore grid For larger distances from shore, High Voltage DC (HVDC) transformer stations are used to transmit the electricity via DC cable to the shore For safe operations, offshore cables are buried up to three meters deep into the seabed Pictures taken at E.ON Offshore Project Scroby Sands (United Kingdom, 2004) 29

Offshore Transformer Stations Transport of a jacket foundation of 500 tons Transformer topside installation (London Array) Installation complete (Alpha Ventus) Transformer substations need to be assembled onshore and installed as a single unit offshore Heavy lift crane ships are required for the installation of both foundation and transformer station For long distance power transport e.g. at German projects, DC cables are used, which require an additional AC/DC transformer station offshore and at the grid connection onshore At Alpha Ventus, the transformer station has a height of 30 meters above sea level and, together with the jacket foundation, weighs more than 1,300 tons Pictures taken at E.ON Offshore Project - Alpha Ventus (Germany, 2009, Source: DOTI) and London Array (UK, 2011) 30

Port Infrastructure Port storage for towers and nacelles Port storage for monopiles Offshore components awaiting shipment Offshore wind energy success comes from doing as much as possible onshore - every step completed onshore saves time and money during offshore installation and does not depend on offshore wind and wave conditions During the installation of offshore wind farms, port facilities have to allow for storage and pre-assembly of foundations and wind turbine components During the operation of offshore wind farms, the service parks have to allow quick loading of spare parts and 24/7 departure to offshore wind farms Pictures taken at E.ON Offshore Project Robin Rigg (United Kingdom, 2009) 31

Operations and Maintenance (O&M) Preparing boat landing at transformer station Transfer of O&M equipment Accessing the offshore wind turbine Quick O&M site access is crucial to avoid costly stand-stills Offshore access is constrained by weather and waves and can be impossible in winter or during storms Travel time is a big issue: small boat access to far-shore wind farms can take up to six hours New O&M concepts for far-shore projects need to be developed, including manned platforms and daily helicopter or speed boat transfer Pictures taken at E.ON Offshore Projects Robin Rigg (United Kingdom, 2009) 32

Health and Safety: Safety is first Priority! Wind turbine specialist fully protected in offshore survival suit Access to a 5 MW wind turbine The last 2 meters to the rest platform Safety is the first priority for working offshore, since any minor accident may cause major harm with medical help being far away Construction and maintenance work at offshore wind energy sites is very challenging and risky The staff has to face tough environmental conditions and work in great heights and in a remote environment dressed in special offshore suits all the time Pictures taken at E.ON Offshore Project Alpha Ventus (Germany, 2009, Source: DOTI) 33

Health and Safety: Ensuring a high Standard Offshore wind specialists on platform on top of the nacelle of a wind turbine To be independent from sea conditions the team is practising accessing a wind turbine by helicopter To allow, safe, fast and efficient execution, every work and safety routine has to be planned and trained thoroughly A systematic HSSE (Health, Safety, Security and Environment) approach helps to minimize risks associated with working offshore E.ON has successfully established and audited an HSSE Management System and is engaging proactively to set global harmonized industry standards for offshore safety Pictures taken at E.ON Offshore Project - Alpha Ventus (Germany, 2009) Source: DOTI 34

Sustainable development of offshore wind energy Algae, mussels and fish settling at offshore foundation E.ON is committed to the sustainable implementation of offshore wind energy by actively supporting research and development of suitable solutions to mitigate the impacts on ecosystems As part of the consenting process, an Environmental Impact Assessment (EIA) is carried out to evaluate possible impacts of an offshore project on the marine ecology To learn more about the impacts of offshore energy on the environment, IUCN in cooperation with E.ON carried out the study Greening Blue Energy with essential findings: Wind farms create safe habitats due to the exclusion of trawling and limitations to fishing These new habitats become potential breeding areas Wind farms, especially foundations, can provide artificial reefs which enhance biodiversity Piling noise is a major issue that requires further technical improvements Animals tend to avoid wind farms during piling in the construction phase, but usually return afterwards Source: IUCN (International Union for Conservation of Nature) 35

Research on marine life and sustainable concepts Seals resting close to offshore wind farm Bubble curtain to reduce piling noise Cormorants at offshore wind turbine E.ON s first German offshore wind project Alpha Ventus is accompanied by the Research at Alpha Ventus (RAVE) project with studies on the marine ecosystem. Further, E.ON is involved in testing and developing technical solutions to mitigate piling noise, including bubble curtains and hydro sound dampers. Soft-start piling, i.e. gradually increasing the piling power, allows animals to leave the construction area before full power is reached. At projects in the UK, marine mammal observers constantly monitor the construction site during piling e.g. with hydrophones. Observations at E.ON s offshore wind farms show a variety of wild life living around the offshore wind farm, from seals feeding on fish at the base of the wind turbines to various birds resting on the foundations and hunting at the offshore site Source: IUCN (International Union for Conservation of Nature), E.ON 36

E.ON s Approach 40 35 30 25 20 15 10 5 0 E.ON has a leading competence in offshore wind energy E.ON s offshore wind projects Water depth [m] London Array I 1 Kårehamn Blyth Rødsand 2 0 10 In operation Robin Rigg 20 Rampion Humber Gateway Scroby Sands Utgrunden II 30 40 Under construction alpha ventus 2 Arkona Amrumbank West 50 Delta Nordsee 60 Under development Size of this circle corresponds to 200 MW wind farm size Södra Midjösbanken 70 80 E.ON is a leading player in offshore wind industry In 2010, E.ON commissioned about 46% of the European offshore wind farms Currently, around 470 MW of offshore wind farms in operation in UK, Denmark and Germany Four projects with about 750 MW under construction Project pipeline of more than 3,100 MW in European waters E.ON s strategy for offshore wind energy foresees large investments into projects while simultaneously reducing costs Realizing one offshore wind project every 18 months Reducing installation costs by 40% by 2015 * Joint Venture of E.ON (26.25%), EWE (47.5%) and Vattenfall Europe (26.25%), **Phase 1 (630 MW), Joint Venture of E.ON (30%), DONG (50%) and Masdar (20%) 37

E.ON s Offshore Wind Energy Projects Aa In operation Aa Under construction Ab In development 38

E.ON will commission an offshore wind project every 18 months Country Project Status Start of Operation Capacity E.ON Share UK Blyth Operational 2001 4 MW 100% UK Scroby Sands Operational 2004 60 MW 100% Germany Alpha Ventus * Operational 2009 60 MW 26.25% UK Robin Rigg Operational 2010 180 MW 100% Denmark Rødsand 2 Operational 2010 207 MW 100% UK London Array ** (phase 1) Construction 2013 630 MW 30% Sweden Kårehamn Construction 2013 48 MW 100% Germany Amrumbank West Construction 2015 288 MW 100% UK Humber Gateway Construction 2015 219 MW 100% Year to date, E.ON has already invested more than 2 billion into offshore wind projects, including London Array**, the world s largest offshore wind project currently under construction E.ON will invest around 2 billion into the offshore wind projects Amrumbank West, Humber Gateway and Kårehamn. This represents the largest investment into offshore wind by a single company so far E.ON s offshore wind growth is supported by a six year long-term charter of a purpose-built specialist vessel for efficient and reliable installation at E.ON s projects * Joint Venture of E.ON (26.25%), EWE (47.5%) and Vattenfall Europe (26.25%), **Phase 1 (630 MW), Joint Venture of E.ON (30%), DONG Energy (50%) and Masdar (20%) 39

E.ON target: 40% reduction of installation costs by 2015 Drivers to reduce costs of offshore wind projects Wind turbines Foundations Logistics Grid connection Examples Examples Examples Examples Wider choice of concepts Larger wind turbines Special design for offshore installation, operations and maintenance New, industrial-scale foundation concepts Lower material costs Shorter installation time and lower installation costs Purpose-built vessels Suitable ports Optimized processes allowing shorter installations times and better access to offshore sites Foresighted planning Building up of offshore grid infrastructure Efficient bundling of grid connections of offshore wind farms Offshore wind is still at the beginning of its development, with more providers of wind turbines, foundations, logistics and offshore vessels stepping into the market and new innovative concepts E.ON s offshore wind strategy targets at a significant reduction of costs of 40% by 2015 by realizing major savings potential in hardware costs, a standardized, integrated design approach to wind turbine generators and the optimization of installation and operations 40

Factsheets of E.ON s Offshore Wind Projects Blyth (United Kingdom, North Sea) Picture taken at E.ON Offshore Project Blyth (United Kingdom, 2004) 41

Blyth (United Kingdom, North Sea) Wind Farm Capacity 4 MW Status Operational Start of Operation 2001 Foundations Type Material Weight Monopile Steel 110 t Wind Turbines Type Vestas V66 Capacity 2 MW No. of Turbines 2 Distance to Shore 1 km Height 25 m Hub Height 60 m Max. Water Depth 8 m Diameter 4 m Rotor Diameter 66 m Good to know Built in 2001, Blyth marked the start of E.ON s activities in the offshore wind sector Blyth was a prototype build and the first offshore wind project in United Kingdom waters Monopiles at Blyth were drilled 10 meters deep into a rock seabed The total investment in Blyth amount to about 6 million 42

Scroby Sands (United Kingdom, North Sea) Picture taken at E.ON Offshore Project Scroby Sands (United Kingdom, 2005) 43

Scroby Sands (United Kingdom, North Sea) Wind Farm Capacity 60 MW Status Operational Start of Operation 2004 Distance to Shore 3 km Max. Water Depth 15 m Foundations Type Monopile Material Steel Weight 200 t Height 50*m Diameter 4.2 m * Up to 8m above sea level; buried up to 30m into ground Wind Turbines Type Vestas V80 Capacity 2 MW No. of Turbines 30 Hub Height 60 m Rotor Diameter 80 m Good to know Scroby Sands was E.ON s first commercial offshore wind farm Through the project E.ON gained valuable experience in installing a large series of offshore wind turbines with monopile foundations, even in the unfavourable winter season Operational improvements have led to a continuously high generation performance With an annual production of 171 million kwh, the wind farm is capable of supplying around 41,000 homes with electricity each year The total investment for the completion of Scroby Sands amount to 109 million 44

Alpha Ventus (Germany, North Sea) Picture taken at E.ON Offshore Project Alpha Ventus (Germany, 2010, Source: DOTI) 45

Alpha Ventus (Germany, North Sea) Wind Farm Capacity 60 MW Status Operational Start of Operation 2009 Distance to Shore 45 km Max. Water Depth 33 m Foundations Type Material Weight Height Diameter Tripod/Jackets Steel 700/500* t 45 m 30 m Wind Turbines Type Capacity No. of Turbines Hub Height Rotor Diameter Multibrid M5000 Repower 5M 5 MW 6 6 90 m 90 m 116 m 126 m * plus 300 tons for securing-piles Good to know 45 kilometers off the coast in waters more than 30 meters deep, Alpha Ventus is Germany s first far-shore project and represents a further step-change in offshore wind Alpha Ventus has been developed by a consortium of E.ON (26.25%), EWE (47.5%) and Vattenfall (26.25%) as a non-commercial pilot project The deep-water pilot project yields important experience for the development of future farshore wind projects The total investment in Alpha Ventus amount to at least 250 million In the time period between 2010 and early 2011 the overall generated electricity lay already 5% above the estimates 46

Robin Rigg (United Kingdom, Irish Sea) Picture taken at E.ON Offshore Project Robin Rigg (United Kingdom, 2009) 47

Robin Rigg (United Kingdom, Irish Sea) Wind Farm Foundations Wind Turbines Capacity 180 MW Type Monopile Type Vestas V90 Status Operational Material Steel Capacity 3 MW Start of Operation 2010 Weight 260 t No. of Turbines 60 Distance to Shore 10 km Height 50* m Hub Height 80 m Max. Water Depth 9 m Diameter 4.3 m Rotor Diameter 90 m * about 30m burried in the sea bed Good to know The project built on the experience gained at Scroby Sands, employing similar monopile foundations and wind turbines Realization of Robin Rigg benefited from the use of jack-up crane vessels that allowed to install foundations all year-round With an annual production of 550 million kwh, the wind farm is capable of supplying around 155,000 homes with electricity each year The total investment for the completion of Robin Rigg amount to around 420 million 48

Rødsand 2 (Denmark, Baltic Sea) Neues Bild oder Ausschnittvergrößerung Picture taken at E.ON Offshore Project Rødsand II (Denmark, 2010) 49

Rødsand 2 (Denmark, Baltic Sea) Wind Farm Foundations Wind Turbines Capacity 207 MW Type Gravity Type Siemens 2.3-93 Status Operational Material Concrete Capacity 2.3 MW Start of Operation 2010 Weight 1,300 t No. of Turbines 90 Distance to Shore 4 km Height 15 m Hub Height 68 m Max. Water Depth 10 m Diameter 15 m Rotor Diameter 93 m Good to know E.ON s offshore project Rødsand 2 builds upon established technology and installation contractors and was realized 3 months ahead of schedule The project benefits from a perfect offshore combination: good wind yield, closeness to shore, shallow waters with low tides and good soil conditions in the Baltic Sea With an annual production of 800 million kwh, the wind farm supplies 229,000 homes with electricity each year The total investment in Rødsand II amount to about 400 million 50

London Array (United Kingdom, Thames Estuary) Picture taken at Offshore Project London Array ((United Kingdom, 2012) - a Joint Venture of E.ON (30%), DONG (50%) and Masdar (20%) 51

London Array (United Kingdom, Thames Estuary) Wind Farm* Capacity Status 630 MW Construction Start of Operation 2013 Distance to Shore Max. Water Depth 22 km 25 m * Phase 1 (630 MW) *Phase 1 (630 MW), ** without the transitional piece * Phase 1 (630 MW) Good to know Foundations* Type Material Weight Height Diameter Monopile London Array will be built in two phases (phase 1 = 630 MW; phase 2 up to 370 MW) and will, upon completion, be the world s largest offshore wind farm The project is being developed jointly by Dong Energy (50%), E.ON (30%) and Masdar (20%) After full completion **, London Array will provide enough power for up to 750,000 homes The total investment cost of Phase 1 of London Array amount to around 2.2 billion Good progress is being made on the construction of the wind farm: by September 2012, 158 of 177 foundations and two offshore substations had been installed Steel 600** t 60** m 4.7-5.7* m Wind Turbines* Type Capacity Siemens 3.6 MW No. of Turbines 175 Hub Height Rotor Diameter 87 m 120 m *Phase 1 (630 MW) **Including phase 1 and phase 2 of the project 52

Kårehamn (Sweden, Baltic Sea) Artist impression of E.ON Offshore Project Kårehamn seen from Kårehamn (Öland, Sweden, 2011) 53

Kårehamn (Sweden, Baltic Sea) Wind Farm Foundations Wind Turbines Capacity 48 MW Type Gravity Type Vestas V112 Status Construction Material Concrete Capacity 3.0 MW Start of Operation 2013 Weight 1,800 t No. of Turbines 16 Distance to Shore 5 km Height 14-24 m Hub Height 80 m Max. Water Depth 21 m Diameter 18 m Rotor Diameter 112 m Good to know Kårehamn represents E.ON s first offshore wind project in Sweden The location near to shore reduces costs, logistic efforts and allows direct connection to the onshore electricity grid Kårehamn is one of three E.ON offshore wind projects which will be built in a coordinated way, using state of the art installation vessels shared across the projects The total investment in Kårehamn amount to around 120 million With an annual production of over 175 million kwh, Kårehamn will supply over 50,000 households with electricity* *based on average annual consumption of 3,500 KWh 54

Amrumbank West (Germany, North Sea) Artist impression of E.ON Offshore Project Amrumbank West, Germany, 2011 (copyright motum) 55

Amrumbank West (Germany, North Sea) Wind Farm Foundations Wind Turbines Capacity 288 MW Type Monopile Type Siemens Status Construction Start of Operation 2015 Distance to Shore 35 km Max. Water Depth 25 m Material Weight Height Diameter Steel 800 t 70 m 6 m Capacity 3.6 MW No. of Turbines 80 Hub Height 90 m Rotor Diameter 120 m Good to know Amrumbank West represents E.ON s first commercial offshore wind project in Germany, building on the pioneering experience of the pilot far-shore project alpha ventus Amrumbank West is one of three E.ON offshore wind projects which will be built in a coordinated way, using state of the art installation vessels shared across the projects After full completion, Amrumbank West will provide enough power for up to 300,000 homes each year* The total investment in Amrumbank West amount to about 1 billion *based on average annual consumption of 3,500 KWh 56

Humber Gateway (United Kingdom, North Sea) Artist Impression of E.ON Offshore Project Humber Gateway (United Kingdom, 2011) 57

Humber Gateway (United Kingdom, North Sea) Wind Farm Foundations Wind Turbines Capacity 219 MW Status Construction Start of Operation 2015 Distance to Shore 8 km Max. Water Depth 17 m Type Material Weight Height Diameter Monopile Steel 750 t 65 m 4.7 m Type Vestas V112 Capacity 3 MW No. of Turbines 73 Hub Height 80 m Rotor Diameter 112 m Good to know Humber Gateway will be E.ON s fifth offshore wind farm operating in the UK Humber Gateway is one of three E.ON offshore wind projects which will be built in a coordinated way, using state of the art installation vessels shared across the projects When commissioned in 2015, Humber Gateway will provide enough power for up to 170,000 homes each year The total investment for Humber Gateway is around 830 million 58

Key Learnings Offshore Wind - Key Learnings Offshore wind energy is more than onshore in the water Offshore wind energy requires substantially different technologies and processes compared to onshore wind energy Offshore is not offshore Every offshore site has its own specifications and requirements, especially when moving from near-shore to far-shore WWW - weather, wind and waves are the dominating factors in offshore wind Access to offshore sites is strongly restricted or even impossible in times of bad weather, strong winds and high waves Using the right tool for the right job Experience shows that installation times can be shortened by the right combination of purpose-built vessels, skilled crews and installation tools Offshore wind energy success comes from doing as much as possible onshore Every step carried out on land saves time and money in the offshore installation process E.ON has a leading competence in offshore wind energy Around 700 MW of offshore projects in operation or under construction, give E.ON an outstanding expertise in offshore wind energy. Offshore wind energy plays a key role in E.ON s Renewables strategy E.ON has already invested 2 billion in offshore wind projects and will invest another 2 billion into three projects by 2015, commissioning one offshore wind project every 18 months E.ON is targeting at a significant growth and cost reductions for future offshore wind projects E.ON has an extensive offshore wind project pipeline of 3,000 MW for further development and is aiming to drive costs of projects down by 40% until 2015 59

E.ON Offshore Wind Energy Factbook This Factbook may contain forward-looking statements based on current assumptions and forecasts made by E.ON management and other information currently available to E.ON. Various known and unknown risks, uncertainties and other factors could lead to material differences between the actual future results, financial situation, development or performance of the company and the estimates given here. E.ON does not intend, and does not assume any liability whatsoever, to update these forward-looking statements or to conform them to future events or developments. Contact: E.ON Climate & Renewables GmbH Brüsseler Platz 1 45131 Essen Germany ecr-communication@eon.com www.eon.com/renewables 60