2010-2011 Contractor of the Year

Similar documents
STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

SECTION SHEETING, SHORING AND BRACING

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

High Capacity Helical Piles Limited Access Projects

High Strain Dynamic Load Testing of Drilled Shafts

FY08 SEWER POINT REPAIRS BID TABULATION

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

Independent Contractor Policy

Trenching and Excavation Safety

SECTION 3 SANITARY SEWER DESIGN

Mobile Equipment Safety

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

SANITARY SEWER BACKUP. Causes & Prevention

Federation of Piling Specialists

SECTION 1 GENERAL REQUIREMENTS

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Transformer Deluge Systems

How To Install An Overhead Sewer

Moving Small Mountains Vesuvius Dam Rehab

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301)

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Chaudière Crossing Bridge Rehabilitation

Baton Rouge Foundation Repair

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

CLIFTY CREEK PLANT MADISON, INDIANA

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

Excavation Safe Working Practices

CONSTRUCTION SAFETY POLICY

Elevating Your House. Introduction CHAPTER 5

2013 Pile Driving Safety Presentation

minimum deductible may be increased significantly.

City of Shelbyville Site Inspection Checklist

Chapter 3 Pre-Installation, Foundations and Piers

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

BRIDGES ARE relatively expensive but often are

INTRODUCTION Purpose Policy Exception for Short-Term Workplace Visits Relevant Legislation and Regulations...

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Jackson Gulch Outlet Canal Rehabilitation Project

RESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

CITY OF NORTH RIDGEVILLE 7307 AVON BELDEN ROAD NORTH RIDGEVILLE, OH (440)

Disputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process

BROWNSVILLE STRUCTURES STUDY. July Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania

Safe & Sound Bridge Terminology

SECTION 807 PUMP STATION REHABILITATION

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County

Slip, Trip & Fall Program Table of Contents

Texas Building Pros Foundation Repair Services

Gas Meter Clearances and Service Installation Requirements

Unit Price Averages Reports

May 5, Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,

FIBER-OPTIC CABLE PLAN CHECK

Electrical. This section applies to the design and installation of building power distribution systems.

SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

Swannanoa River Flood Risk Management Study

EL LAGO BUILDING DEPARTMENT PERMIT ISSUANCE PROCEDURES As of February 20, 2013

Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway

Underground Commercial Electric Service

Gas Meter Clearances and Service Installation Requirements

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

How To Prevent An Accident From Happening

7. Do you perform any out of state work?... If yes, in what states and provide details of work performed

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards

BASEMENT FLOODING PART II: Reducing Flooding Risks on Your Property HISTORIC CHICAGO BUNGALOW ASSOCIATION

Structural Failures Cost Lives and Time

What Causes Foundation Leaking?

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action

Flood Checklist ACTION TO BE TAKEN BEFORE THE FLOOD SEASON

Cuyahoga County s Clean Ohio Revitalization Fund Round 5 Application Great Lakes Shipyard Expansion Project Attachment A1 Application Summary Document

Protect Your Home From Flooding. A guide for Lethbridge Residents

bout your HOUSE Avoiding Basement Flooding CE 50

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

GLOSSARY OF TERMINOLOGY

Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist

UFGS (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

Building Foundation and Structure

contractors, etc. and establish relationships with lease and rental companies.

PROPOSAL FOR CONTRACTORS ALL RISKS

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP

FLOOD DAMAGE PRECAUTIONS

Transcription:

U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United States Army Corps of Engineers (USACE) began work in 1990 on a multi-phased flood control project along Northwest Indiana s Little Calumet River. In 2010, Thatcher Foundations Inc. mobilized two crews to install sheet piling on Stage VII of the Little Calumet River, Local Flood Protection project, as a subcontractor to Ceres Environmental Services Inc. The sheet piling was driven into the hard-pan clay along the riverbed, and several feet of permeable soil was placed on top, and finally covered with concrete. Residents living near the Little Calumet River expressed concern publicly that the piling installation would cause damage to their property. To limit the amount of vibration and lessen the noise created by the pile driving operation, Thatcher installed the sheet piling with a fixed-mast machine, rather than the traditional crane-and-hammer setup. In order to meet the aggressive schedule, and to compensate for inclement weather, Thatcher mobilized a second fixed-mast machine to the jobsite, and worked the machines concurrently one installing sheet piling on the north bank, and one installing it on the south bank. Thatcher worked closely with the general contractor and other subcontractors to keep the project moving as efficiently as possible. Thatcher s team worked with the general contractor to fabricate special corner sheets as required to follow the river. Thatcher also used crane mats to access several narrow work limit areas. Thatcher installed approximately 10,000 WF of sheet piling on this project, completing 5,425 manhours safely, despite the challenges of working very close to a river in both muddy and slippery conditions.

ArcelorMittal: H-3 Blast Furnace Slag Pit Sheet Piling Installation East Chicago, Indiana 65 Years of Engineered Piling Solutions Careful coordination was key to performing this project in an operating facility. Thatcher Foundations Inc. installed 530 wall feet of JZ 120 steel sheet piling for the H-3 Slag Pit walls on a cost-plus contract. The project was fast tracked, with Thatcher s crew working six ten-hour shifts each week. The soil profile was cemented slag and steel slag, which was excavated and backfilled by others. Careful coordination with ArcelorMittal was key to keeping everyone on schedule. Thatcher completed the project ahead of schedule, and under budget on a cost-plus basis. Thatcher worked with the ArcelorMittal engineers during project development, consulting about the types of steel sheet piling that would be best suited to the extreme heat and corrosion caused by the molten slag and quenching operation. Thatcher also worked with its steel supplier to find an appropriate type of sheeting which would be available to meet the accelerated schedule. When the project was postponed after materials had been delivered, Thatcher made room in its yard for the 306 tons of material, and stored it until the project began six months later. Thatcher maintains an A rating in ArcelorMittal s safety system with ISNetworld, so with the addition of a site-specific safety plan and a crew-wide plant safety orientation, Thatcher was able to mobilize quickly. More than 900 incident-free hours were worked by Thatcher employees on this project, including members of Local 578 Pile Drivers, Indiana Local 150 Operators and Indiana Local 142 Teamsters.

US Steel: Gas Line Repair Installation of Steel Sheet Piling and Bracing Gary, Indiana 65 Years of Engineered Piling Solutions Thatcher installed sheet piling and bracing to support a nearby railroad embankment. As a subcontractor to The American Group of Contractors (TAG), Thatcher Foundations Inc. safely completed 586.5 manhours under the NMAPC on this sheet piling and bracing project. Thatcher s earth retention design provided stabilization for the adjacent railroad embankment. After Thatcher s employees from Local 578 Pile Drivers, Indiana Local 150 Operators and Indiana Local 142 Teamsters were mobilized to the jobsite, field conditions necessitated a change of plans. A previously unknown pipe crossing was discovered during excavation, requiring Thatcher s in-house engineers to alter their design. The drawings were revised, and the project continued, allowing for a successful repair. Thatcher was able to mobilize quickly to this nitrogen leak repair project, because Thatcher maintains an A rating with US Steel through ISNetworld s safety evaluation system. The unusual working atmosphere required each employee to wear an individual air quality monitor, and welders and burners had supplied air. Each Thatcher crew member, including the supervisor, had 40 Hour HazMat training, and had previously completed confined space training.

Obstructions being removed prior to installation of sheeting Sheeting installation with fixed-mast piling machine

Sheeting installation Maintaining 15 clearance working under 60 70 overhead wires

Thatcher installed 200 WF of sheeting and bracing Bracing layout was adjusted to accommodate the elevation of the pipe

Merrillville Conservancy District 65 Years of Engineered Piling Solutions Merrillville Conservancy District: Taft Street Lift Station Expansion Sheet Piling Installation Merrillville, Indiana The sheets were successfully driven with an impact hammer, after the true soil conditions were discovered. As a subcontractor to Bowen Engineering Corporation, Thatcher Foundations Inc. installed a 3-sided steel sheet piling pit with materials provided by Bowen Engineering. Thatcher fabricated a tight corner to complete the pit. 466.5 safe manhours were worked by Thatcher employees on this project. Actual soil conditions were not accurately represented by a boring taken within 25 of the sheeting installation. Due to the unexpected finding of very stiff clay, Thatcher replaced the vibratory hammer initially brought on-site with an impact hammer, allowing the sheets to be driven to the design depth. The renovations to the Taft Street Lift Station will double its capacity, creating greater potential for expansion in the southwest corner of Merrillville. The Independence Hill Conservancy District also benefits from the renovations, as its lines flow into the Taft Street Lift Station before reaching the Gary Sanitary District. The Independence Hill Conservancy District anticipates that the increased capacity will result in fewer sewer backups for its residents, particularly following a heavy rainfall.

Indiana American Water: Proposed Emergency Generator Pad Timber Piling Installation Gary, Indiana Thatcher s timber pile alternate saved the owner nearly $70,000. Working as a subcontractor to Bowen Engineering Corporation, Thatcher Foundations Inc. drove 8 timber piles to a capacity of 25 tons each to form a foundation for an emergency generator pad. Thatcher employees contributed 162 accident-free manhours to this project. The bid plans for this project called for augercast pilings, which Thatcher estimated would cost $108,000. It is necessary to maintain a 10 spacing between augercast pilings during installation to avoid compromising adjacent piles. Because only 12 piles were necessary for the foundation, the spacing requirements would necessitate three to four separate days of drilling. Instead, Thatcher proposed H-pile and timber pile alternates, which could be driven in a shorter timeframe, and would therefore be less expensive to the owner. By selecting Thatcher s timber pile alternate, Indiana American Water was saved $69,500.

Town of Schererville: Bracing for New Interceptor Sewer Installation of Channel Bracing Schererville, Indiana Interceptor sewer support bracing - installed Thatcher Foundations Inc. completed this subcontract for Grimmer Construction, Inc. Two design challenges arose in the field. First, after Thatcher had mobilized, it became clear that the spring floods had altered the below ground conditions, and a change of design was required. The bracing frames were modified from a 30 setup to a 20 setup to accommodate the changed installation methods. Secondly, the initial project documents called for galvanizing of the material. Thatcher communicated to the general contractor that galvanizing would not be practical because of the field cutting and welding involved in the construction of this portion of the project. The project engineer agreed with Thatcher s assessment, and the galvanizing requirement was waived for this work. Safety challenges were also present on this project. Spring rains raised the level of a nearby creek, and the below-grade workspace was flooded on one workday. Grimmer crews brought in additional pumps to clear the water from the workspace, and Thatcher s crew stayed onsite and completed its portion of the day s work after the water was removed. Despite the wet conditions, Thatcher safely completed 233 manhours on this project. Spring rains caused the work site to flood.

Southern Lake County Conservation Club: Bridge Construction Installation of Pipe Piles Schneider, Indiana The bridge project successfully raised the bridge height by 7. The Southern Lake County Conservation Club is a non-profit organization in Schneider devoted to the education of hunting safety and the promotion of sustainable hunting and fishing practices. The club members requested Thatcher s assistance to replace an unsafe bridge on the club s property. The existing wood piles supporting the bridge were rotten and broken. Thatcher employees donated their time, and the company donated use of its equipment, and sold the club the required pipe piling and steel bracing at a scrap price. Work on the bridge was completed entirely by volunteers, most of them Thatcher employees. Pile Drivers from Local 578 and Operators from Local 150 also donated their time and skill. All crew members provided and wore their own basic PPE. The volunteer crew also cleaned pre-existing rubble and debris from the work area when they removed the scraps from their construction work. The crew drove 12 pipe piles 33 35 deep to underpin and the existing 36 main bridge support members were jacked back into place. The piling was driven through the existing deck to limit fall hazards. Ultimately, the underpinning and jacking was successful, and the bridge height was raised by 7.

Before: timber pilings had broken loose from the bridge structure Before: the bridge was visibly unlevel

Setting first sections into place Welding underpinning to pile