Appendix 3: Project Management Substation Guidelines (General Process Flow Template)



Similar documents
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Organization. Project Name. Project Overview Plan Version # Date

<name of project> Software Project Management Plan

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

OE PROJECT CHARTER TEMPLATE

At the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used?

Develop Project Charter. Develop Project Management Plan

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

Computing Services Network Project Methodology

Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

Project Management Plan for

Sound Transit Internal Audit Report - No

PROJECT MANAGEMENT PLAN CHECKLIST

Crosswalk Between Current and New PMP Task Classifications

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Project Knowledge Areas

PHASE 8: IMPLEMENTATION PHASE

Minnesota Health Insurance Exchange (MNHIX)

Step by Step Project Planning

ITRM Guideline CPM Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

Project Management for Everyone

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Software Project Management Plan (SPMP)

Positive Train Control (PTC) Program Management Plan

The Fast Track Project Glossary is organized into four sections for ease of use:

Central Agency for Information Technology

Project Management Guidelines

Program Lifecycle Methodology Version 1.7

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management

Sample marketing plan template

Project Management Professional (PMP)

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management

Risk Management Primer

Process Improvement Program Project Process

SCOPE MANAGEMENT PLAN <PROJECT NAME>

Appendix V Risk Management Plan Template

Guidelines: Project Schedule Project Management Office (PMO)

Business Continuity Position Description

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)

Project Management Manual Update Transportation Department City of Edmonton

[Paste client logos here]

Input, Output and Tools of all Processes

ownership We increase return on investment by We deliver reliable results by engaging

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

A COMPARISON OF PRINCE2 AGAINST PMBOK

Project Management Guidebook

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended.

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS

Happily Ever After: Project Management Tips and Tricks for the SAMHSA Grantee

Project Processes. Media Snapshot. Project Management Process Groups

All of these circumstances indicate that the world of tomorrow is as different as today s water utility business is from that of yesteryear.

A shift in responsibility. More parties involved Integration with other systems. 2

PHASE 3: PLANNING PHASE

IS&T Project Management: Project Management 101. June, 2006

Understand why, when and how-to to formally close a project

Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved

Project Managing Microsoft Dynamics CRM Implementations

Puget Sound Emergency Radio Network: Project Schedule and Cost Risks

Consultancy Services Proposal

Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition

Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at

BSB41513 Certificate IV in Project Management Practice

TECHNICALS LEVEL BUSINESS

Project Management Framework

Project Management Certificate (IT Professionals)

Project success depends on

PROJECT SCOPE STATEMENT

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

Maturity Model. March Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Project Management Simple Answers to Simple Questions

PROJECT MANAGEMENT PLAN

Assessment of NCTD Program Management Framework for Positive Train Control Program

State of California. Contents. California Project Management Office Project Management Framework. Project Management. Framework.

PLANNING FOR YOUR PROJECT

Questions Re: RFP for Consultant to the Community Oversight Board (COB) for the Philadelphia Department of Human Services (DHS) Posted: March 23, 2012

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

ITRM Guideline CPM Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE

Project Management Standards: A Review of Certifications/Certificates

Gartner, Inc. DIR-SDD-2042

PROJECT PLAN TEMPLATE

PHASE 3: PLANNING PHASE

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

PROJECT MANAGEMENT PLAN <PROJECT NAME>

Construction Management Standards of Practice

SFJ EFSM14 Manage the performance of teams and individuals to achieve objectives

Project Management. An Overview for IT. Author: Kevin Martin & Denise Reeser

Demonstrate and apply knowledge of project management in

PROJECT PLAN FOR. Project Name Here

Project Plan RESIDENTIAL PARKS ACT Review Project

Project organisation and establishing a programme management office

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA

MNLARS Project Audit Checklist

Frank P.Saladis PMP, PMI Fellow

REQUEST FOR PROPOSALS SERVICES FOR

Transcription:

365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It is designed as a tool for the project manager to communicate with the external world.w PMM-1 Project Initiation Responsibility Matrix PMM-2 Project Planning Responsibility Matrix

366 PMM-3 Project Execution Responsibility Matrix PMM-4 Project Controlling Responsibility Matrix PMM-5 Project Closing Responsibility Matrix INITIATION Background Information Project managers not only must rely heavily upon the traditional on-time, on-budget, and on-quality performance measures, but also with the added on-strategy dimension central to managing project success and to alleviate leadership challenges. A quadruple constraint is created with the insertion of the on-strategy dimension. The main thrust of this point is illustrated in Figure 1.

367 Figure 1. Project dimensions Many leadership tasks relate to developing a vision of the project outcome that is practical, yet capable of mobilizing and motivating team members to accomplish the project s goals and objectives. The leadership vision engages stakeholders who are not actively involved in the project; it also inspires them to maintain their support over the project s timeline. The solution-building negotiation approach to defining the scope of a project, and then clearly communicating this to the project team and other stakeholders defines a strategy for realizing the vision, and translating the strategies into operational plans and results. The core problem is the insufficiency of instability of strategy to properly develop and express project vision connected through measurement to tangible business outcomes. Organizations should link planned outcomes to their corporate strategy using a measurement framework, referred to as performance management, and is common within corporations. Details The process is designed to facilitate the formal authorization to start a new project. It is often performed external to the project s scope of control by the organization, which may blur the project boundaries for the initial project inputs. Clear descriptions of the project objectives are developed, including the reasons why a specific project is the best alternative solution to satisfy the current requirements (Figure 2). Essential Initiation Items General Project Charter Initial Date Project Document (design, estimates) Initial Date Preliminary Scope Statement Initial Date Preliminary Work Breakdown Structure Initial Date Critical Factors in the Project Initiation Phase Clear Project Vision Clear Goals and Objectives Formal Budget Executive/Sponsor Involvement

368 Figure 2. Project initiation process PLANNING Background Information The most important responsibilities of a project manager are planning, integrating, and executing plans. Project planning is described as a predetermined course of action within a forecasted environment. The project requirements set the milestones on the schedule. The planning must be systematic and flexible enough to handle unique activities. The course of action must be disciplined through reviews and controls. Moreover, the process must be capable of accepting multifunctional inputs in order to achieve the desired results. The nine (9) major components of planning are: Objective: A goal, target, or quota to be achieved over time. Program: Strategy followed/major actions taken in order to achieve objectives. Schedule: A plan showing activities/accomplishments started/completed. Budget: Planned expenditures required to achieve or exceed objectives. Forecast: A projection of what will happen by a certain time. Organization: Positions/duties/responsibilities to achieve objectives.

369 Policy: Guide for decision-making/individual actions. Procedure: A detailed method for carrying out a policy. Standard: A level of performance defined as adequate or acceptable. Details The process is designed to gather information from several sources with each having varying levels of completeness and confidence. This process identifies, define, and mature the project scope, cost, and the project activities that occur within the project. As new project information is discovered, additional dependencies, requirements, risks, opportunities, assumptions, and constraints will be identified (Figure 3). Figure 3. Project planning process

370 Essential Planning Items Scope Documents Initial Date Approved Work Orders Initial Date Approved Purchase Orders Initial Date Work Breakdown Structure Initial Date Engineering Design Package Initial Date Project Schedule Initial Date Project Management Plan Initial Date Cost/Resource Estimates Initial Date Critical Factors in the Project Planning Phase Clearly communicating project status Detailed Project Plan Detailed Work Breakdown Structure Detailed Staffing Plan Adequate Resources Appropriate Project Team Structure EXECUTION Background Information The execution phase is a key aspect of the project progress philosophy. The project manager must assemble the required resources and management plans soon after the go decision is made. By demanding that project team members link their own actions and decisions with the overall intended strategy of the project (an extension of the corporate strategy) can assist with on-strategy project execution. It extends a virtual leadership presence, which injects itself into every critical project event and decision. The associated administrative tasks involved in this phase (work orders, bid documents, status reporting, etc.) are extremely important in project management. Many of the key characteristics of the project (scope, cost, resources, procurement, quality, risk, communication) are identified and highlighted during this phase. Details The process is designed to coordinate people and resources as well as integrating and performing the activities of the project in accordance with the prescribed objectives/scope documentation (Figure 4). Essential Execution Items Bid Package Initial Date Contractor Evaluation Initial Date Work Authorization Initial Date Project Team Initial Date

371 Figure 4. Project execution process Project Schedule Initial Date Critical Factors in the Project Execution Phase Good Project Methodology Status Reporting Appropriate Project Team Structure CONTROLLING Background Information Many project managers are not fully schooled either in formal academic settings or through on-the-job project experience to necessarily note the subtle but important difference between perceived power and actual power. Learning to distinguish between influence and control to achieve results often means the

372 difference between temporarily controlling an outcome by forced compliance versus creating a lasting change in people s behavior. Some project managers, however, may not see the two techniques as very different. Consequently, project managers eventually conclude that they really cannot be everywhere at once to vet every decision to ensure that the team appropriately conducts itself in performing its roles and realizing the importance of the project. As a result, most managers revert to some kind of exceptionbased or situational leadership method to address ongoing challenges as recommended by established theory. While somewhat effective, this tactic does not completely address the issue. Project managers therefore are taxed to employ a variety of techniques to achieve the desired outcome to include a practical balance between traditional proactive risk management and reactive project troubleshooting. The proactive risk management approach minimizes the occurrences of anticipated problems to the extent that it is practical to do so. Project troubleshooting minimizes the impact of all unexpected disruptions, both large and small. The project manager s goal should not focus on avoiding risk; the project manager should strive to manage risk to prevent risk from disrupting the project. The aim is not simply risk mitigation and risk avoidance; the manager s goal is the total management of risk proactively and reactively. Details The process is designed for project management procedures associated with initiating, planning, execution, and closing. Corrective or preventive actions are taken to control the project performance. Monitoring includes collecting, measuring, and disseminating performance information and assessing measurements/ trends to effect process improvements (Figure 5). Essential Monitoring & Control Items Documented Corrective Actions Initial Date Documented Preventive Actions Initial Date Schedule/Cost Forecasts Initial Date Documented Quality Inspections Initial Date Documented Change Requests Initial Date Critical Factors in the Project Controlling Phase Project Tracking & Control Status Reporting Good Risk Management Practices Contingency Funds Clearly Communicating Project Status PROJECT CLOSE-OUT Background Information The orderly closure of a project is an essential function in project management. Projects are considered completed or closed-out after the sponsor receives and approves all reports as required by the terms and

373 Figure 5. Project controlling process conditions of the award, and notifies the responsible parties of its acceptance and closure of the project. It is the sole responsibility of the project manager to be aware of when reports are due and to submit them by the required due dates. Reports required at the close of a project are generally due within 90 days of the project end date to include: A final technical report to include the following: Project manager s name, Project Title, Performance period Significant results of the project Examples of progress Discussion of objectives and deliverables A final financial report to include the following: Final Invoices Cash flow close-out Resource Performance Evaluation(s) to include the following: Technical difficulties and solutions Activity verification Feedback reports

374 Equipment/Document specification updates and associated reports Capture Lessons-Learned Administrative closure Additionally, the project manager ensures that the accounting and planning departments are provided with accurate equipment data, costs, and plant-in-service dates. Details The process is designed to finalize all activities across all of the process groups to formally close the project (Figure 6). Essential Closure Items Close Project Initial Date Close Contracts Initial Date Equipment Updates Initial Date Drawing/Modeling Updates Initial Date Final Reports Initial Date Historical Documentation Initial Date Critical Factors and Questions in the Project Closing Phase What was done right? What was done wrong? What future recommendations can be made? How, when, and to whom should the information be disseminated? Were the schedules realistic? Was the level of detail correct? Was it easy to evaluate performance from the schedule? Was tracking easily accomplished?

Figure 6. Project closure process 375