Kostenreductie update, actieplan en governance. Ernst van Zuijlen 17 februari 2016

Similar documents
SDE+ tender Borssele december 2015

October TKI Wind op Zee Cost reduction options for Offshore wind in the Netherlands FID

How Dutch innovations support 40% cost price reduction. June 13th 2013 How Dutch innovations support 40% cost price reduction 1

PRIOR INFORMATION NOTICE

Far and Large Offshore Wind innovation program (FLOW) Presentatie IRO CEDA. Ernst van Zuijlen, 9 maart 2010, Den Haag

PPT Dutch offshore wind sector

Offshore Wind in Germany

Winddag 2015: Innovation need and necessity. Bob Meijer 20 juni 2015

Council of the European Union Brussels, 20 May 2016 (OR. en)

6 Oktober KIVI Niria congres Offshore Wind De uitdaging. Eneco wind. Ernst van Zuijlen

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele

Assessment wind measurement strategy

Employment in OWE in NL, 2010

Blue Energy: a new opportunity

OFFSHORE WIND ENERGY IS GETTING CHEAPER

ETIP Wind Steering Committee meeting Monday 7th March :00 16:45 EWEA office, Rue d Arlon 80 6th floor Bruxelles AGENDA

Financing Renewables and Energy Efficiency Projects in Developing Countries

De Industrie. KIvI Niria Jaarcongres De uitdagingen voor windenergie op zee. Ballast Nedam Offshore. Dolf Elsevier van Griethuysen

V2G initiatives, experiments and implementation path in The Netherlands

North Sea offshore wind Developments in the Netherlands

TenneT. Stakeholder engagement and Consultation Process OWFs. Day 1 ONL Michiel Müller / Rob van der Hage

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

Greening of and greening by IT

TENNET, NL OFFSHORE WIND FARM TRANSMISSION SYSTEMS

North Sea offshore wind Developments in the Netherlands

UK renewable energy an update

The pivotal role of TSOs in European energy market integration

5O&M. new trends in onshore wind

TKI Wind op Zee Subsidy schemes and tax regimes


Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

Energy Valley and NNOW in Offshore Wind an example

Getting smart(er) in Offshore Wind O&M

Four decades of windpower development: some value sensitive design lessons. Frans A. van der Loo Brussels 22 november 2013

Energies and Participatives in the World

DONG Energy offshore wind experience

Offshore Windpark DanTysk. Cost-Effective Foundations Design to Installation

Modern insurance solutions protect innovative technologies RENEWABLE ENERGY

North Sea offshore wind Developments in Belgium and the Netherlands

Conference call Fiscal year 2014»

Curriculum Vitae Nicolas Brizard

OFFSHORE WIND PROCUREMENT

Wadden Sea Region Climate Neutral by 2030?

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

Network Interconnection of Offshore Wind

Introduction. Part II: Insurance Structure Optimisation

Renewable Energies WIND

Solar Energy Application Centre. Toekomstige systemen voor opwekking zonneenergie. BIPV the time is now! October 13, 2015.

Areva & Gamesa Joint Venture: Creation of an Offshore Wind Leader

Asset Management in praktijk AMC Seminar 8 november Bertrand van Leersum, ATO

Future of Electricity Storage

Job profile Asset manager - NL. PLY Energy Nederland B.V.

Nordex SE Annual Results 2013

Profile. Offshore Wind Projects. Sustainable EPC and Marine Contractors

How To Improve The Performance Of Anatm

Integrating 300 GW wind power in European power systems: challenges and recommendations. Frans Van Hulle Technical Advisor

Stillingsbetegnelse: Team Lead, Offshore Site Management Rekvisitions-id Publiceret 16/04/ Danmark - Vejle - Energy Sector - Project

FP7 Energy Information Day Work Programme 2011

CONTRACTEREN VAN ENERGIE EN DE MOGELIJKHEDEN TOT KOSTENREDUCTIE

Optimization of the coupled grid connection of offshore wind farms

Investor Presentation

Insights into Tidal Stream energy

Dear shareholders. The first half of 2014/15 in brief. Renewable energies: Axpo focusing on wind

Offshore Wind Project Management

Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors

Alternatieven in de energievoorziening

Renewable and Alternative Energy Outlook

Dutch wind energy strength

Demonstratie van asset management in de wind industrie

Challenges to integrate Renewables In the French and European Power System. Michel Béna, SmartGrids Director

Green IT deployment for sustainable business and education in The Netherlands Dr.ir. Anwar Osseyran Managing Director SARA/Vancis

Introduction BAM and Van Oord GBF - Concrete Centre Conference, December 2012

THE NEW GUIDELINE FOR THE CERTIFICATION OF WIND TURBINES, EDITION 2010

Germany: Energy Briefing

Van SARA naar Vancis ICT voor de Kenniseconomie. Dr. Anwar Osseyran SARA/Vancis Managing Director

HIPPO STUDY DG Education And Culture Study On The Cooperation Between HEIs And Public And Private Organisations In Europe. Valorisatie 9/26/2013

Response to direct consultation questions

ESKITP Design and implement change management plans for IT enabled systems 1

What Is KAURI?

Geotechnical Engineering in Offshore Wind - how can we contribute to lowering the cost of electricity? DGF Seminar, Gentofte, 1 st April 2014

Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration

DELFT UNIVERSITY OF TECHNOLOGY THE NETHERLANDS. Office for Education and Research Policy

PRESS RELEASE. Propertize wind-down on track. Utrecht, 3 July 2015

Energy Agreement for Sustainable Growth

The Netherlands Licensing procedure offshore windfarms. Sander de Jong Rijkswaterstaat Noordzee

MAYORGAME (BURGEMEESTERGAME)

Macroeconomic. impact of the Wind Energy Sector in Belgium

Approaches to cost-reduction in offshore wind

The Ministry of Economic Affairs chairs the National Contact Point (NCP). Chairman and board: Advisory members NCP Secretariat:

EU SET-Plan Strategic Energy Technology Plan

M.Sc. INTERNATIONAL BUSINESS ANALYSIS OF THE

Supplier Registration System

MENA Wind Power Outlook

Competition in EU Electricity Markets The Role of Antitrust Policy

Global supply chain quality improvements with certification and what can be done beyond

Life-Cycle Cost of a Floating Offshore Wind Farm

GRAVITY BASE FOUNDATIONS

Economische en Beleidsinzichten van Energietransitiestudies voor Nederland

Assessment of the Economic Benefits of Offshore Wind in the Mid-Atlantic

TRACTATENBLAD KONINKRIJK DER NEDERLANDEN. 36 (1974) Nr. 1. JAARGANG 1975 Nr. 15

Transcription:

Kostenreductie update, actieplan en governance Ernst van Zuijlen 17 februari 2016

Kostenreductie opties in Nederland What is the goal of the study? 1. Potential 2. Options for cost reduction 3. Further actions 17 februari 2016 Borgingscommissie Energie Akkoord 2

Belangrijkste kosten drivers 17 februari 2016 Borgingscommissie Energie Akkoord 3

Potentieel voor 40% reductie Offshore wind cost could be reduced by more than 40% by 2020 Assessment of cost reduction potential across Technology, Market & Supply Chain and Finance from 2010 to 2020 (at final investment decision). It excludes aspects such as steel prices or changes in interest rates (noncontrollable). This takes into account the main cost reduction items (>1% LCoE reduction per item). The cost reduction potential is possibly larger if smaller items are also included. 17 februari 2016 Borgingscommissie Energie Akkoord 4

We zijn nog niet klaar 17 februari 2016 Borgingscommissie Energie Akkoord 5

Vertaling in SER-plan van aanpak 17 februari 2016 Borgingscommissie Energie Akkoord 6

Overall Results (priority) Area Action Lead and supporting partners Start finish Priority Technology Supply Chain More cooperation between businesses in technology development in the Netherlands and International Increase knowledge sharing and cooperation early on in the design phase to innovate in holistic manner by supporting R&D projects Data sharing and operational benchmarking Sufficient knowledge on offshore wind project management through education or training on the job. TKI and Government TKI and Supply chain 2016-2020 Medium TKI and Supply chain, government Developers, education institutes Finance Policy Demonstration Mitigate policy risk Knowledge and experience sharing Government, knowledge institutes, developers TKI, technical advisors, financers, certification bodies Policy for offshore wind development 2020 / 2023 Government Optimisation of the tender model Match making for demonstration projects also on international scale Government and developers TKI 2016 2019 Innovation Sites in Hollandse Kust Government 2016 17 februari 2016 Borgingscommissie Energie Akkoord 7

Overall Results (priority) Area Action Lead and supporting partners Start finish Priority Technology Supply Chain Finance Policy Demonstration More cooperation between businesses in technology development in the Netherlands and International Increase knowledge sharing and cooperation early on in the design phase to innovate in holistic manner by supporting R&D projects Data sharing and operational benchmarking Sufficient knowledge on offshore wind project management through education or training on the job. Mitigate policy risk Knowledge and experience sharing TKI and Government TKI and supply chain 2016-2020 Medium TKI and Supply chain, government Developers, education institutes Government, knowledge institutes, developers TKI, technical advisors, financers, certification bodies Policy for offshore wind development 2020 / 2023 Government Optimisation of the tender model Cooperation Knowledge sharing Knowledge sharing Long term policy Match making for demonstration projects also on international scale Cooperation Government and developers TKI 2016 2019 Innovation Sites in Hollandse Kust Government 2016 17 februari 2016 Borgingscommissie Energie Akkoord 8

Actions Market & Supply chain 1-2 Desired effect Actions Lead and supporting partners Start finish Priority Increase the level of vertical and horizontal collaboration Stimulate knowledge sharing through sector events like lessons learned sessions (such as TKI CoP), developer days, offshore wind conferences, (Q-) meetings. TKI and Supply chain, (incl. developers) Stimulate knowledge sharing in the supply chain through initiating and sharing studies on main topics of interest. TKI, NWEA, supply chain parties Smoothen processes by spending time with contracting parties on team building: dry runs or simulations to identify issues and find solutions, agree on decision making processes and timing, etc. Supply chain (contracting partners) Share technical monitoring data and define operational benchmarks. TKI and Supply chain, government Ensure sufficient competition er the entry barriers for new entrants: Ensure transparency by creating a Dutch offshore wind tender/market report that can be shared with potential new entrants. create a networking vehicle for international new entrants to get in touch with launching customers in this geographical scope. TKI and government Create a project pipeline to provide a concrete market outlook and timing (and stimulate asset sweating). Developers Increase awareness of developers and investors of new entrants (e.g. supply chain overview or monitor study, stimulate presentations of these parties at conferences and meetings, and trade missions). TKI, government and Supply chain 17 februari 2016 Borgingscommissie Energie Akkoord 9

Actions Demonstration Desired effect Actions Lead and supporting partners Start finish Priority Realised Leeghwater test site at Borssele Extension of current demonstration facilities Long term support for continued innovation Create a scientific research programme for Leeghwater. TKI 2015 2020 Organise a Match making event for Borssele test site tender. TKI 2016 2017 Organise the tendering process for innovations at the Borssele innovation site. TKI 2017 Explore the possibilities for off-grid facilities TKI and Supply chain Explore the possibilities for onshore test site facilities, for instance for offshore wind turbines. Explore the possibilities for demonstration of innovations at current wind farms Explore the possibilities for testing of grid innovations related to the substations and interconnections between substations Create international cooperation base for demonstration sites in European coordination, e.g. Demowind. Synchronisation with European demonstration facilities. TKI and Supply chain TKI and Operators TKI and TenneT TKI Reserve space in Hollandse Kust Zuid and Noord Government 2016 Medium Medium Ensure a pipeline for RD&D funds by increasing the TKI platform TKI and government 2016 Medium 17 februari 2016 Borgingscommissie Energie Akkoord 10

Governance van plan van aanpak (1) Benoemde actiehouders zijn: TKI Eigenaren, investeerders, ontwikkelaars, energiebedrijven (NWEA; EnergieNederland) Supply chain (NWEA) Overheid (EZ, RVO, I&M) Financiers (NII, VPM, NVB) TenneT Certificeerders 17 februari 2016 Borgingscommissie Energie Akkoord 11

Governance van plan van aanpak (2) Mogelijke samenwerkingsvorm: Onder SER Energie Akkoord Borgingscommissie Kostenreductietafel, bestuurlijk niveau, 2 keer per jaar Kostenreductiewerkgroep; 4 tot 6 keer per jaar; trekkers / deelactiehouders rapporteren TKI voert secretariaat? 17 februari 2016 Borgingscommissie Energie Akkoord 12