PROJECT CONTROLS NEWSLETTER SCHEDULING BEST PRACTICES SERIES



Similar documents
Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group

MODEL SCHEDULING SPECIFICATION

Developing Critical Path Method Scheduling (CPM)

MATCHDAY September 2014

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

CRITICAL PATH METHOD (CPM) SCHEDULES

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

CFL Guidelines for Developing October 2006 Critical Path Method Schedules (CPMs)

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Academic Calendar - UNDERGRADUATE. All Other Classes Begin; Late Registration Begins. Last Day to Drop a Class without a W on Transcript;

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Scheduling Best Practices

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

Ocoee, FL July 01, 2016 Advertisement No. 1

Basic CPM Calculations

EXHIBIT 2-2-C PROGRESS SCHEDULES

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Academic Calendar for Faculty

Professional RN to BSN Cohorts and Bridge to BSN Academic Calendar

Trading Calendar - East Capital UCITS Funds

Real-Life MS Project: Dependencies and Leveling

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

Computing construction logic in a multi-calendar environment using the Chronographic Method

The Value of Weekend Leads Unveiled:

In initial planning phases In monitoring and execution phases

DATA RECOVERY SOLUTIONS EXPERT DATA RECOVERY SOLUTIONS FOR ALL DATA LOSS SCENARIOS.

Project Time Management

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR

Academic Calendar

Cambridge International AS and A Level Computer Science

SECTION COST LOADED CRITICAL PATH SCHEDULE

Almost everyone in the planning and scheduling profession

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

2015 Settlement Calendar for ASX Cash Market Products ¹ Published by ASX Settlement Pty Limited A.B.N

TOWN OF HILLSBOROUGH BUILDING & PLANNING DEPARTMENT DESIGN, CONSTRUCTION AND LANDSCAPE PROFESSIONAL NEWSLETTER Fall Greetings 2013

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Advancements in Construction Project Administration Session: 41 October 28, 2014

Linear Schedules for Tunnel Projects

11 p.m. to. Tuesday, June. will remain open. 14. closed

Scope management can be defined as controlling what is and what is not a part of the project.

An Introduction to the Management Principles of Scheduling

Job Description. Highways Foreman

Cyber Security: Guidelines for Backing Up Information. A Non-Technical Guide

SCHEDULING AND PROJECT MANAGEMENT

Reviewing a Baseline Schedule

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

Ocoee, FL May 13, 2016 Advertisement No. 1

Price Fact Sheet Lumo Advantage QLD Residential Electricity Energex Prices included in this document are correct as at 3 September 2013.

Scheduling Best Practices

Duke University School of Medicine - M.D. Program Academic Calendar

METHODOLOGIES FOR DETERMINING CONSTRUCTION CONTRACT TIME AND EVALUATING CONTRACT TIME EXTENSIONS FINAL REPORT

Best Practices/Task Definition

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

// Benchmarking Project Schedules

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Project Management Guide

D. R. Horton Homeowner Manual

Project Management Planning

PAID HOLIDAYS. I. PURPOSE To identify holidays that are observed and paid to eligible employees by the Shelby County Board of Education.

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015

Collaborative Scheduling using the CPM Method

Project Time Management

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

How project management software can smooth the way

Scheduling Glossary Activity. A component of work performed during the course of a project.

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.

Household Contact Requirements for Sponsors of Centers

International University of Monaco 27/04/ :55 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

International University of Monaco 21/05/ :01 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

Critical Steps for a Successful Data Conversion Moving Legacy Data to Your Case Management System

Grocery Shopping: Who, Where and When

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Appendix S ATTENDANCE MANAGEMENT POLICY

Strategies for creating accurate updates of CPM construction schedules.

Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006

White Paper: Efficient Management of Cloud Resources

WORK PROGRAM GUIDELINES

Transcription:

PROJECT CONTROLS NEWSLETTER SCHEDULING BEST PRACTICES SERIES The sixth article in the Scheduling Best Practices series is Multiple Calendars Blessing or a Curse. Our colleagues, Jodi Staub, Senior Consultant in Warner s Scheduling Group and, contributing editor, Larry Conley, in Warner s Disputes Resolution Group, are both recognized experts in scheduling and scheduling best practices. Jodi Staub has over 15 years of experience in the construction industry, including estimating, bidding, purchasing, scheduling, inspections and field supervision. Her construction experience has focused on schedule preparation, management and analysis. Mark Anderson Multiple Calendars Blessing or a Curse By Jodi Staub, Senior Consultant in Warner Scheduling Group and, contributing editor, Larry Conley in Warner s Disputes Resolution Group. Continuing our series of articles on scheduling, Warner examines the pros and cons of using multiple calendars in a single project schedule. Through this article and the series of Best Practices articles we will pass along observations and highlight the best practices for schedulers and project managers alike. Multiple calendars, as those who have had experience with them should know, can be both a blessing and a curse depending upon their use. This article will illustrate ways that multiple calendars can be used as an effective tool as well as point out why they may be an ineffective and even deceptive instrument. This article is divided into two sections; first looking at the positive aspects of using multiple calendars, and secondly describing their ineffective use or abuse. First, we should describe the rational behind the use of multiple calendars. A work week is typically described as a five-day week. What we often call a calendar week is a seven-day scheduling calendar, that is; all seven days are counted. The distinction is reflected in a statement such as, This activity is going to take eight work-days or ten calendar-days. For the purpose of this article we define maintaining different calendars as the placement of activities (or resources) on specific calendars that reflect only the days on which a particular activity can be performed. Using different calendars, schedulers can identify what days are available for work to be completed. Page 1 Multiple Calendars

Multiple calendars may also be used with particular trades as well, thus putting resources on different calendars. One such example occurs when some trades are available for shift work, extending their hours or days available for work in a given week, whereas other trades may not be similarly available. It would be burdensome to calculate an update without multiple calendars in this situation. Thus, when the days available for work vary for different activities or for different resources, the use of multiple calendars in scheduling software becomes a valuable tool. Benefits of Multiple Calendar Use There are many positive reasons to use multiple calendars in the appropriate scheduling scenario. Without them, the schedule may become an inaccurate reflection of how and when work is able to be performed. This section discusses positive uses and gives examples of the appropriate use of multiple calendars. Multiple calendars should be used to more accurately represent how activities are planned. For example, trying to schedule a two work-day activity that can only be performed on Saturdays and Sundays using a five day calendar would be inaccurate. The scheduler could schedule the activity in this example as a two day activity (constrained to Friday and Monday) in order to cover the weekend when the work is actually being performed. An example of this type of situation would be if there is a power shut-down or plumbing tie-in to be performed for an existing business that cannot afford to close during the week. The problem is, when this activity is delayed by even one day it cannot be moved to Monday and Tuesday, it has to jump to the next Friday. Thus, the scheduler would have to keep two sets of books in order to be able to convert the non-standard calendar activities when updating the schedule. This double accounting of durations would lead to inaccurate reporting, and the schedule logic itself would not be recorded accurately. Without the use of multiple calendars there are constant adjustments that would be needed to the schedule for activities which have different available work days or time periods. Examples of situations, similar to the above, where multiple calendars can be used effectively, and should be used to incorporate accurate schedule logic are as follows: Concrete curing activities which can be performed on a seven-day calendar as opposed to just a five day calendar. After all, concrete cures whether you re on the jobsite or not. Page 2 Multiple Calendars

Work performed where an allowance for extreme weather conditions is needed. Some areas may not be accessible after winter snows begin, while other areas may require a reduced work schedule during periods of extreme heat. Winter weather shut-downs for landscaping, paving, or grading activities in areas where frozen ground prohibits such work. Work required to be performed during non-peak or non-business hours. This example is often found on State or Federal highway projects. Seasonal bridge or roadway closures may also affect the schedule in a way that requires an adjusted calendar. Mandatory weather days per State regulations (also found in roadway building). Other weekend or off-peak time work as mentioned above and in commuter rail construction. Multiple calendars are also effectively used when milestone activities are on a different calendar than the work-day calendar. For instance, if contract duration is expressed in calendar days (7 days per week) and the work-day calendar is a typical five-day week, an alternate calendar for completion milestones should be used. This is important if there is an adjustment to the completion date; if it is delayed or advanced for any reason. The calendar-day to work-day adjustment does not have to be hand calculated with the dreaded, and not precise, 5/7 conversion each time an impact is encountered. Instead, an accurate representation may be made demonstrating how much gain or loss the schedule is experiencing. As mentioned above, resources may also be put on alternate calendars. This may become especially important if the project requires acceleration. If certain trades are able to staff the project with two shifts, while others can work ten-hour days, and still others only eight-hour days, the scheduling of a recovery effort can become very burdensome. However, if multiple calendars are used, the scheduler can quickly, easily, and accurately determine the effect of extending work hours. This can be a vital tool when determining accurate time extensions. It also gives the scheduler a greater flexibility in scheduling the work. Page 3 Multiple Calendars

Disadvantages of Multiple Calendar Use There are disadvantages and dangers in the use of multiple calendars of which a scheduler should be well aware. These disadvantages and dangers should also be known by both the owner and contractor alike. A major disadvantage stems from how the use of multiple calendars complicates schedule evaluation. The complications encountered are due to several factors including; calculating float, finding the critical path, and inaccurate use of multiple calendars. Total float on a given activity is calculated based on its calendar, thus the use of multiple calendars can make the evaluation of float more difficult. The reason for this is illustrated when two activities of the same duration are on different calendars, for example one on a seven-day calendar and the other on a five-day calendar. The activity on the seven-day calendar may show more float than the activity on the fiveday calendar, even though they both must be completed on the same fixed calendar date (for example June 1 st ). Thus both activities would have the same late-finish date, yet show different total float. This can become confusing if the multiple calendar use is not made patent on schedule reports. Thus, looking at activities with the lowest total float may not give an accurate picture of what is on the critical path. In order to overcome this problem, calculating the longest path (through the use of filters) must be done in order to determine the true critical path; that is the path with the most work-days. It is easy to see how the use of multiple calendars can be abused by schedulers. By adjusting the calendars, float may be altered and the critical path hidden if printed in a report that does not demonstrate the longest path or indicate the use of multiple calendars. This is made worse when intermediate milestones are to be met. However, using an intelligent activity identification system, combined with the longest path filter, a more accurate picture may be presented. An intelligent activity identification system will group activities within a particular interim completion date (milestone). Activities can then be filtered according to completion date (milestone) in order to find the longest path leading to that particular intermediate milestone. Page 4 Multiple Calendars

Conclusion The use of multiple calendars can be both a blessing and a curse. They are a blessing to schedulers in the respect that they can accurately show when activities may be completed. However, they can easily become a curse if not managed properly through intelligent activity identification systems and the use of the longest path filters. Schedulers should be encouraged to use multiple calendars when appropriate because of the improved accuracy of the schedule logic but must be wary of their use and properly manage their implementation. Page 5 Multiple Calendars