July 2015. Oklahoma Capitol Restoration Project. Interior Rehabilitation Monthly Progress Report



Similar documents
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Analysis One Code Desc. Transaction Amount. Fiscal Period

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Every Student I Every Day I Every Possibility

PROJECT: DLS Website Redesign STATUS REPORT May-June 2015

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Walton Centre. Document History Date Version Author Changes 01/10/ A Cobain L Wyatt. Monitoring & Audit

Computing & Telecommunications Services Monthly Report March 2015

STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY Small Commercial Service (SCS-1) GSR

2012 CBECS: Preliminary Results and Timeline for Data Release

May 2014 Texas School Bond Elections

Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct

FY 2015 Schedule at a Glance

Bb Upgrade Timeline. Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan PDFmyURL.com

Employers Compliance with the Health Insurance Act Annual Report 2015

2016 Examina on dates

City & County of San Francisco Permit & Project Tracking System

2015 Examination dates

EXHIBIT 2-2-C PROGRESS SCHEDULES

Annexure B: Planning, Budgeting and Performance Management Programme

Request for Proposal Campus Master Planning Consultant

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

Design Development Quality Management Phase Checklist Project Phase Checklist Series

CPSC ITDS/RAM Pilot System: PGA Message Set

1. Introduction. 2. User Instructions. 2.1 Set-up

BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun Jul Full Force Calc

Project Management Planning

CONSTRUCTION MANAGEMENT REPORT NO. 2

ESTABLISHMENT OF A NEW BUSINESS

CAFIS REPORT

Request for Qualifications

Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory

Supervisor Instructions for Approving Web Time Entry

Consumer ID Theft Total Costs

Architectural Services Data Summary March 2011

GTA Board of Directors September 4, 2014

Discussion Outline. A. KPIs Defined. B. Why KPIs Matter. C. KPI Menu. D. Implementation. E. Example KPIs. F. Pitfalls

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013

Roles: Scrum Master & Project Manager

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015

Media Planning. Marketing Communications 2002

The Interagency Security Committee and Security Standards for Federal Buildings

GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4

Release of the Draft Cybersecurity Procurement Language for Energy Delivery Systems

A Resource for Free-standing Mathematics Units. Data Sheet 1

Request for Proposal for Architectural Services Scope of Work and Design Documents for

An Introduction to the. Society Program Portfolio Management Process

Coordination and air quality monitoring during emergencies. Colin Powlesland Environment Agency

Florida s Private Rebuilt Vehicle Inspection Program. Pilot Program Report January 30, Terry L. Rhodes, Executive Director

Business Idea Development Product production Services. Development Project. Software project management

Independent Accountants Report on Applying Agreed-Upon Procedures

ATLANTA, April 19, 2004 Swan House, a Neoclassical style home-turned-historic house

5-Minute Primer for Commercial Building Energy Audits

TECH. Tracking Progress. Project Schedule PHASE 1 STEP 1 ACTIVITY 1.1. Activity and Milestone STEP 1 STEP 2 : ACTIVITY 2.2 : ACTIVITY 1.

US Army Corps of Engineers. Vision Statement. Be the premier stewards of entrusted hydropower resources

2017 Budget and Grid Management Charge Initial Stakeholder Meeting

Training Calendar GTC Energy: Training Calendar / 165

Detailed guidance for employers

Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association

Executive Branch IT Reorganization Project Plan

Implementing Carbon Reduction Without Impacting Working Capital. Presented by Dylan Crompton

Stephen Doune HRIS Project Manager Plan International

AgriLife Information Technology IT General Session January 2010

Choosing a Cell Phone Plan-Verizon

State Annual Report Due Dates for Business Entities page 1 of 10

Managing Projects with Practical Software & Systems Measurement PSM

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:

Capital Project Delivery Handbook

Department of Public Welfare (DPW)

Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property

Accident & Emergency Department Clinical Quality Indicators

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

RBC Insurance Fetes Online Auto/Home Insurance Growth

Maximising Ability, Reducing Disability. Dr. Áine Carroll Clinical Lead Valerie Twomey Programme Manager

Volume II- Project Development Processes

The principles, processes, tools and techniques of project management

Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500. Supported Versions

Transcription:

July 2015 Oklahoma Capitol Restoration Project Interior Rehabilitation Monthly Progress Report

TABLE OF CONTENTS Design-Builder Progress Summary... TAB 1 Design Progress Summary... TAB 2 Project Schedule... TAB 3

1. Design-Builder Progress Summary 1 P a g e

WORK IN PROGRESS & NOTABLES Best Practices of Capitol Management In mid-july, several members of the Interior Rehabilitation Team met with the Architect of the U.S. Capitol (AOC), Mr. Stephen T. Ayers, FAIA, Leed AP. Manhattan Construction Company also constructed the U.S. Capitol Visitor Center Project in Washington, D.C. This experience and expertise has provided a valuable opportunity to further study best practices of Capitol management beyond the restoration process. Mr. Ayers answered specific questions regarding Management and Oversight, Budget and Finance, Maintenance and Improvement Projects, as well as Communications revolving around the U.S. Capitol operations. Mr. Ayers is the 11th Architect of the Capitol and has served since May 12, 2010. Mr. Ayers is responsible for the facilities maintenance and operation of the historic U.S. Capitol Building, the care and improvement of more than 553 acres of grounds and the operation and maintenance of 17.4 million square feet of buildings including: the House and Senate Congressional Office Buildings, the Capitol Visitor Center, the Library of Congress Buildings, the U.S. Supreme Court Building, the Thurgood Marshall Federal Judiciary Building and other facilities. He is responsible for the care of all works of art in the Capitol under the direction of the Joint Committee on the Library and is responsible for the maintenance and restoration of murals, outdoor sculpture and other architectural elements throughout the Capitol complex. He also serves as Acting Director of the U.S. Botanic Garden and the National Garden. The Architect of the Capitol has approximately 2,300 employees and an annual budget of nearly $600 million. 2 P a g e

Images below: Members of the Interior Rehabilitation Team meeting with Mr. Stephen T. Ayers, FAIA, Leed AP, Architect of the Capitol in the U.S.Capitol on July 16, 2015. 3 P a g e

Working Sessions One of the most important aspects of the design process is the sharing and development of ideas. Seldom does a first draft of anything see the light of day without planning and revision. To that extent, the Interior Rehabilitation Team has been participating in a process of working sessions aimed to provide a consistent approach throughout the schematic development process. These working sessions have thus far concentrated on: i. Defining priorities associated with the Scope of Work Priority Matrix within the construction cost limitations associated with the project. ii. Historic Preservation Zones and defining specifications and terminology associated with Preservation, Restoration, Rehabilitation and Adaptive Reuse. iii. Preliminary Master Plans for Mechanical, Electrical, Plumbing and Fire Protection Systems to be implemented through the Interior Rehabilitation Project. iv. Programming efforts required to adhere to the Oversight Committee s goal to improve historic aesthetics and establish a master place for efficient use of space. Image below: Members of the Interior Rehabilitation Team in a Working Session reviewing the Preliminary Master Plan for MEP & FP Systems on July 21, 2015. 4 P a g e

Image below: Members of the Interior Rehabilitation Team in a Working Session reviewing the Historic Preservation Zones and Methodology on July 21, 2015. Risk Assessment & Management Plan The ability to define risks associated with a project is often a living document developed over the course of a project. It is only fully understood once all project stakeholders acknowledge the multitude of risks associated with a design-build project of this caliber. The entire project team has expended exhaustive efforts towards risk identification which is crucial to the overall project success strategy. Defining risks with a desired outcome to mitigate said risks is paramount. Risk management and mitigation plans are being analyzed by the entire project team for adoption within the project. 5 P a g e

Priority Matrix We are actively working with the Owner Project Team to refine and evaluate the Scope of Work Priority Matrix. This process is providing clarification of the scope of work that can be included within the existing funding parameters ($91.6MM). This is a process of identifying priorities in relation to project goals and criteria adopted by the State Capitol Repair Expenditure Oversight Committee (SCREOC). The scope of work being evaluated includes building repairs, restoration, betterments and functional enhancements. Coordination: Oklahoma State Fire Marshal s Office - Our team is engaged with coordinating initial plans for the Interior Rehabilitation with the Oklahoma State Fire Marshal s Office (OSFM). Future improvements will upgrade Life Safety Systems within the historic structure. We are extremely appreciative of the efforts and involvement from the OSFM to facilitate a project of this caliber. Photo below: Our team is shown meeting with Mr. Luke Tallant with the Oklahoma State Fire Marshal s Office to review initial analysis and implementation of Life Safety Systems and code requirements for the Oklahoma Capitol Restoration on July 14, 2015. 6 P a g e

Design Assist Strategy Collaboration and planning lead to a successful design-build strategy. Major renovations, such as the Oklahoma Capitol Restoration, can be complex in design and scope development, therefore presenting the challenge of maintaining a fully operational facility during construction. We have a proven recipe for success from delivering multiple projects in and around The State Capitol. Our experience has produced not only a team of Oklahoma s very best, but a world class team to undertake this project. We have partnered with the highest quality team of Oklahoma-based talent in the country to ensure cost control measures are in place and actively maintained as well as expediting resources and procurement opportunities. Photo below: MEP & FP master planning sessions with our design-assist partners shown in progress. 7 P a g e

LOOKING AHEAD Milestones & Deliverables Schematic development efforts are rapidly being completed as plans are being expedited to start Phase 1 Prerequisites for the Interior Restoration. Phase 1 will start the Single-Move Strategy by creating space to vacate portions of the basement slated for Phase 2 Renovations. In addition, Phase 1 allows for intrusive investigations to begin exposing concealed conditions so that we can identify hazardous materials. In addition, Phase 1 spaces serve as a laboratory for historic preservation analysis. Our historic preservation consultants are analyzing original paint colors, finishes, performing testing required to restore original marble floors, and taking core samples to properly identify original flooring materials. 8 P a g e

2. Design Progress Summary 9 P a g e

Monthly Project Status Report Frankfurt Short Bruza Architects Engineers Planners Date: July 30, 2015 Project: 15151DB Capitol Interior Restoration To: From: Name Company/Position Phone Email Kyle Nelson Manhattan Construction Co. 405.254.1050 knelson@manhattanconstruction.com Steve Scovel, Architect / Project Manager Re: Monthly Project Status Report July 2015 This project status report is being provided to you to in order to document our current status on the subject project as required by OMES. The following is a summary of our contracted work broken down by project SOW and Status: BIM MODEL FSB has continued to update the model to incorporate refined assessment information. The BIM model will include the existing architectural, mechanical, electrical and fire protection systems in the Capitol as observed in the room-by-room and system assessments CONDITIONS ASSESSMENT All of the room-by-room assessments have been completed and information is being loaded into the model (as stated above). The building assessment information is currently being compiled utilizing the Field 360 program implemented during the assessments. BUILDING SYSTEMS ASSESSMENT The building systems assessments have been completed and information has continued to be loaded into the model. PROGRAMMING All of the preliminary programming with the Capitol agencies has been completed. Programming information which was gathered from each agency during the programming meetings is being edited for final draft. FSB has been working in conjunction with SJK, Inc. to establish the Preservation Zones in regard to Historic Preservation as part of the final 35% deliverable package. In addition, work has taken place regarding Historic Preservation as it relates to the pre-requisite remodeling for the 1 st floor House of Representative and the 3 rd floor Senate spaces. DESIGN STANDARDS FSB continues to build upon the design standards as set forth in the preliminary report by Mass Architects. FSB has meet with OMES staff in several meetings to review the preliminary architectural interiors, MEP/FP systems and Historic Preservation zones as they relate to the 35% deliverable package. 5801 Broadway Extension, Suite 500, Oklahoma City, Oklahoma 73118-7436 Telephone (405) 840-2931 Facsimile (405) 842-7750 Website www.fsb-ae.com Page 1 of 1

3. Progress Schedule 10 P a g e

Activity ID Activity Name Cost % Compl Master Plan Preconstruction / Schematic Design Preconstruction Deliverables & Milestones Orig Rem Dur Dur PRE-600 20% SCREOC Presentation 0 0 11-Jun-15 A PRE-700 Phase 1 Contract Completion Milestone-35% Deliverable 0 0 30-Oct-15* Start Finish 2015 2016 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 20% SCREOC Presentation Phase 1 Contract Completion Milestone-35% Deliverable Schematic Development 02.1 20% SCREOC Deliverable - HAMMOCK 59 24 08-Apr-15 A 31-Aug-15 03 Preservation Zoning $75,000.00 98% 59 24 08-Apr-15 A 31-Aug-15 04 Room By Room Conditions Assessment $535,000.00 98% 34 24 27-Apr-15 A 31-Aug-15 05 Programming Development $175,000.00 85% 29 24 20-Apr-15 A 31-Aug-15 06 Scope of Work Definitions $65,000.00 70% 102 67 27-Apr-15 A 30-Oct-15 07 Priority Scope Matrix $90,000.00 70% 59 24 08-Apr-15 A 31-Aug-15 07.1 35% SD Deliverable - HAMMOCK 102 24 27-Apr-15 A 31-Aug-15 08 Risk Management Plan $25,000.00 90% 102 24 23-Jun-15 A 31-Aug-15 09 Risk Assessment $25,000.00 90% 102 24 23-Jun-15 A 31-Aug-15 10 35% SD's & Specifications $240,000.00 60% 87 24 11-Jun-15 A 31-Aug-15 11 Cost Modeling $80,000.00 70% 102 24 11-Jun-15 A 31-Aug-15 12 Phasing Approach & Definition $25,000.00 98% 159 24 09-Apr-15 A 31-Aug-15 20% SCREOC Deliverable - HAMMOCK Preservation Zoning $75,000.00 Room By Room Conditions Assessment $535,000.00 Programming Development $175,000.00 Scope of Work Definitions $65,000.00 Priority Scope Matrix $90,000.00 35% SD Deliverable - HAMMOCK Risk Management Plan $25,000.00 Risk Assessment $25,000.00 35% SD's & Specifications $240,000.00 Cost Modeling $80,000.00 Phasing Approach & Definition $25,000.00 Start Date 23-Feb-15 Finish Date 07-Mar-16 Data Date 29-Jul-15 Run Date 03-Aug-15 Page 1 of 1 OCRI-04 Actual Level of Effort Actual Work Remaining Work Suspension Remaining LOE Critical Remaining Work Milestone Critical Milestones Oklahoma Capitol Restoration-Interior Rehabiliation Oklahoma City, Oklahoma MCC Project #3707 TASK filters: 2 Month Back + All Remaining, Master Plan Only.