Construction Specifications for Keyhole Pavement Coring and Reinstatement

Similar documents
The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

C. Section TESTING LABORATORY SERVICE.

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

SECTION PRECAST CONCRETE UTILITY STRUCTURES

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS

Division 2 Section Section 02795

Construction Management Program

OHIO ASPHALT PAVING CONFERENCE

SECTION 1 GENERAL REQUIREMENTS

Construction Specification for Concrete Curb and Concrete Curb and Gutter

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT

APPENDIX B. I. Background Information

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Porous Pavement Alternatives Cost Analysis

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

Guidelines for Excavations

SECTION STORM DRAINAGE SYSTEM

Commonwealth of Pennsylvania PA Test Method No. 632 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

CA-48 TECHNICAL SPECIFICATION

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

Example Specification for Concrete using Current Building Code Requirements

SECTION ABANDONMENT OF SEWER MAINS

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

CID STREET INFRASTRUCTURE ASSESSMENT

Quality Assurance Concepts. Outline

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Advancements in Permeable Pavements

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

GUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

Advancements in GPR for a Sustainable Tomorrow

Guide Specification Precast Concrete Products

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM

Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson

PRE INSTALLATION MANUAL

PERMEABLE INTERLOCKING CONCRETE PAVEMENT

High Performance PSA in Sheet Membrane in Water Protection

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

CONSTRUCTION PERMIT REQUIREMENTS

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Section 402. STORM SEWERS

Reflectex TM Reflective Concrete Interlayer Geotextile INSTALLATION GUIDELINES

Permeable Pavement Construction Guide

PC-Concrete Injectable Concrete Anchoring and Repair System

SECTION 4Aggegate Subbase

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

Wastewater Capital Projects Management Standard Construction Specification

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON ROAD SURFACE REQUIREMENTS FOR EXPRESSWAYS AND HIGH SPEED ROADS

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

Treatment of a surface or structure to resist the passage of water in the absence of hydrostatic pressure. presence of hydrostatic pressure.

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

SECTION CAST-IN-PLACE CONCRETE

Guide to Specifying Concrete Performance

SECTION UNIT PAVERS. Logo Display hidden notes to specifier by using Tools / Options / View / Hidden Text.

Concrete pavers with sand filled joints. Bedding sand 1-1/2 in. (25-40 mm) thick

SECTION PERVIOUS INTERLOCKING CERAMIC PAVERS

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

LABORATORY DETERMINATION OF CALIFORNIA BEARING RATIO

Building Your Interlocking Concrete Pavement to Last a Lifetime

Lighthouse Engineering, L.L.C.

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

SECTION REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

La Nueva AASHTO Guia de Diseno de Pavimentos Hormigon

symptoms of a faulty foundation

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

ICPI TECH SPEC NUMBER 10 Application Guide for Interlocking Concrete Pavements

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

AquaPaver & SF-Rima Permeable Interlocking Concrete Pavers

WATERPROOFING FOR CONCRETE STRUCTURES

Bonding Agents: The Good, the Bad, and What Works. Bond with Your Concrete

Cold Weather Concrete Practices

Unit Price Averages Reports

SUDAS Revision Submittal Form

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

Transcription:

F I N A L Construction Specifications for Keyhole Pavement Coring and Reinstatement Gas Technology Institute 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gastechnology.org Version 13 October 2011 The preliminary information contained within this report is to be considered in draft form only. All of this information contained herein is subject to further review.

Legal Notice This information was prepared by Gas Technology Institute ( GTI ) for GTI s Keyhole Consortium Project Sponsor s. Neither GTI, the members of GTI, the Sponsor(s), nor any person acting on behalf of any of them: a. Makes any warranty or representation, express or implied with respect to the accuracy, completeness, or usefulness of the information contained in this report, or that the use of any information, apparatus, method, or process disclosed in this report may not infringe privately-owned rights. Inasmuch as this project is experimental in nature, the technical information, results, or conclusions cannot be predicted. Conclusions and analysis of results by GTI represent GTI's opinion based on inferences from measurements and empirical relationships, which inferences and assumptions are not infallible, and with respect to which competent specialists may differ. b. Assumes any liability with respect to the use of, or for any and all damages resulting from the use of, any information, apparatus, method, or process disclosed in this report; any other use of, or reliance on, this report by any third party is at the third party's sole risk. ii

Table of Contents Page Table of Contents... iii 1. Scope... 1 2. Definitions... 1 3. References... 2 4. Material... 2 4.1 Supply of Materials... 2 4.2 Bonding Material for Keyhole Cores:... 2 4.3 Laboratory Testing of Bonding:... 3 4.4 Performance Requirements for Bonding Material... 3 4.5 Backfill Material... 4 5. Construction... 4 5.1 General... 4 5.2 Keyhole Coring... 4 5.3 Backfilling... 5 5.4 Reinstatement of Keyhole Cores... 5 5.5 Quality Control... 5 iii

1. Scope Keyhole pavement coring procedure involves cutting a core in paved surfaces, removing it, vacuum excavating to expose the underground utilities, performing any necessary operation and maintenance activities, backfilling and reinstating the pavement core. These specifications cover the requirements for coring and reinstatement of the keyhole cores in pavements, sidewalks and other paved surfaces as a permanent repair of pavement within the jurisdiction of the municipality or highway agency. 2. Definitions For the purpose of this specification, the following definitions apply: - Bonding Material: cementitious, rapid hardening, high strength, asphalt (asphalt/concrete (AC)) and/or concrete repair material, used to bond the keyhole core to the pavement from which it was removed. - Composite Pavement: A rigid pavement having an asphalt concrete (AC) surfacing layer over Portland Cement Concrete (PCC) base (with or without granular base/subbase). See also Rigid Pavement. - Controlled-Low Strength Material (CLSM) (Flowable fill): A mixture of aggregates, cement, and water, with or without fly ash or air entrained agents. The mix self flows, compacts and hardens into a material with higher strength than soil but able to be excavated with hand tools after 28 days. - Flexible Pavement: A roadway pavement consisting of a layer(s) of asphalt concrete (AC) placed over granular base and subbase. - Granular Backfill: Acceptable fine and coarse aggregate for construction of base and subbase soil as per DOT specifications. - Keyhole Pavement Coring: means the operation of cutting a small (typically 18-24-inches in diameter or less) circular hole through roadway pavement, sidewalk or other paved surface, using a coring device that is capable of adjustment to ensure that the core is cut in an alignment that is perpendicular in both planes to the horizon and not the paved surface, using a diamond tipped core saw, to allow the intact core of pavement to be removed so that the underlying base and subbase materials can be removed by water or air assisted vacuum excavation, to expose the buried infrastructure.. - Keyhole Pavement Core Reinstatement: means the permanent repair process whereby the AC or PCC sections, base, and subbase materials, which were removed during keyhole excavation, are reinstated or replaced to condition acceptable by the municipality or highway agency. 1

- Rigid Pavement: means a pavement having a Portland Cement Concrete (PCC) surface or composite structure (AC layer over PCC base) over granular base and/or granular subbase. - Roadway: means the portion of the street designed, improved and ordinarily used by vehicle traffic. - Sidewalk: means the part of a public street that is improved for the exclusive use of pedestrians. - Street: means an open way that is improved for the use of vehicles, persons, or animals on land. - Utility: means the underground facility owner/operator or their contractor(s). 3. References [Note: This section includes references of the City, State and Highway specifications relevant to this standard.] 4. Material 4.1 Supply of Materials Unless otherwise specified, the Utility shall supply all materials necessary for the execution and completion of the work. 4.2 Bonding Material for Keyhole Cores: Bonding material when mixed with the appropriate quantity of water should flow easily up and around the reinserted core and, with no voids, completely fill the annular space around the core to achieve a waterproof, mechanical joint between the keyhole pavement core and the original slab of pavement from which it was originally extracted.". Bonding material shall be a packaged dry mix, non-shrinkable, and impervious to water penetration at the joint after application. Specifications for the bonding material shall follow the performance requirement listed in this specification. The material shall be placed in accordance to the manufacturers recommendations. All mixing, handling and curing practices recommended by the manufacturer shall be followed and will be considered a part of these specifications. 2

4.3 Laboratory Testing of Bonding: 4.3.1 Specifications for Packaged, Dry, Rapid-Hardening Cementations Materials for Concrete Repairs- ASTM C928 4.3.2 Compression- ASTM C109 or C39 4.3.3 Freeze/Thaw - ASTM C666 Standard Test Method for Resistance of Concrete to Rapid Freezing and Thawing 4.3.4 Set Time - ASTM C266 Standard Test Method for Setting a Hydraulic-Cement Paste by Gilmore Needles 4.3.5 Shear Strength (Slant Shear) - ASTM C882 4.3.6 Thermal Expansion and Shrinkage - ASTM C531 4.4 Performance Requirements for Bonding Material 4.4.1 The bonding material shall comply with the requirements of ASTM C928. In addition, the bonding material shall have the following bond strength characteristics of Table 1. Table-1 Minimum 1-day and 7-day bond strength 1 day 7 days Bond Strength, Minimum (psi) 1500 2000 4.4.2 In addition, the bonding material shall, at a maximum of one hour at 50 O F (10ºC) carry an equivalent traffic loadable condition that is at a minimum greater than 2 times the half-axle load of the AASHTO standard 18-Kip Equivalent Single Axle Load (EASL) or AASHTO H-25 truck load. For the AASHTO H-25 truck load, the minimum acceptable shear stress of the bonding material after one hour for an 18-inch diameter core is as shown in Table 2. Table-2 Minimum 1-hour bond strength for various core thicknesses 3

4.4.3 For pavement coring installations at temperatures below 50 O F (10ºC), extended curing time, or the use of additives or core heating procedures may be used to accelerate core setting duration. Contact bonding material manufactures for recommendations on installations below 50 O F (10ºC). 4.5 Backfill Material The type and gradation of the granular backfill should be according to the construction specifications and provisions of the municipality or highway agency. 5. Construction 5.1 General All work performed by the Utility using keyhole methods shall be carried out in such a manner that the pavement or sidewalk surfaces worked upon are restored and matched as close as possible to the original condition of the surface. 5.2 Keyhole Pavement Coring Cutting of existing pavements shall be performed with an appropriate keyhole-coring saw. The vertical alignment of the keyhole-coring saw shall be perpendicular to the horizon, and the cutting shall be extended to the full depth of the existing pavement structure. Coring operator shall place a temporary mark (paint) on the pavement core and adjacent pavement prior to cutting to insure that the pavement core, when replaced, will have the same orientation as when it was first cut and removed. Pavement cores shall be either removed from the work site or stored in a safe and secure on-site location until it is reused. 4

5.3 Backfilling Proper backfilling and compaction is necessary in order to properly reinstate the pavement core and eliminate any future settlement. Backfilling and compaction shall be performed per the requirements of the municipality or highway agency where the work is being performed. 5.4 Reinstatement of Keyhole Pavement Cores The pavement surface shall be restored to its original condition by setting the reinstated pavement core flush with and in its original orientation. Bonding material meeting the requirements of Section 4 (Materials) shall be used for pavement core reinstatement. Excess bonding material shall be removed from the restored pavement surfaces. A pavement core that is fractured in the vertical plane is considered to be defective and shall not be used to reinstate the pavement. If another equivalent core of sound condition and similar existing pavement of the same diameter, depth and composition as the defective core is available, it may be reinstated in substitution of the defective core. If the pavement core is limited to the horizontal delimitation of two or more successive layers of pavement, that core may not be considered to be defective if the layers are capable of being re-bonded to each other with the bonding material during reinstatement. In flexible pavements, where the pavement layer is less than 4 inch (100 mm) thick, bonding material may be used in filling of the keyhole to a depth equal to the thickness of the pavement layer, in lieu of reinstating the excavated core if the core is cracked, damaged, or deformed such that it is not practical to reinstate it. In this circumstance, the bonding material should satisfy the structural requirements of the original structure and match the color of the pavement. In the event that a keyhole cored pavement cannot be reinstated and will be left unattended, the opening shall be covered with an approved form of an appropriatelysized, circular steel road plate fitted with a collar that, when inserted into the keyhole, will prevent the hole cover from tipping, tilting, bouncing or spinning out of the hole in all types of the traffic conditions. Figure 1 shows a view of the keyhole restoration scheme. 5.5 Quality Control The reinstated core shall be flush and level with the adjacent pavement. No gap, attributable to the positioning of the core should be found between the bottom of the straightedge and the surface of the pavement when a 3 ft long straightedge is placed in 5

any direction on the surface of the keyhole pavement core, except across the crown or drainage gutters. Figure 1 - Schematic of the Keyhole restoration in pavement [End of Specifications] 6