A Step-by-Step Approach for Planning Your Small Project



Similar documents
Project Time Management

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.

Project Time Management

Systems Analysis and Design

Chapter 6: Project Time Management

Scheduling Glossary Activity. A component of work performed during the course of a project.

Certified Associate in Project Management (CAPM) Examination Content Outline

PMP Exam Preparation Answer Key

The Plan s Journey From Scope to WBS to Schedule

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Chapter 6. (PMBOK Guide)

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Project Time Management

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

Chapter 4: Project Time Management

PMP 2013 Exam Prep. Course Overview

Time Management. Herb Pollard III

Project Time Management

Manual on Training Preparation

PMI Lexicon of Project Management Terms

CCPM: TOC Based Project Management Technique

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Project Management Professional PMP PMBOK 5

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP

Project Planning and Scheduling

Sam Sena, PMP ISACA Bermuda Chapter

Project Managing to Support Change. Cathryn Stam, PMP Tina Salaris, RN, PMP

Chapter 2: Project Time Management

Information Technology Project Management

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics

Introduction to Project Management. What is a Project? Project Management Institute (PMI) Chapter 1 Introduction

Making project management indispensable for business results. Project Management 101

Time Management. Part 5 Schedule Development. Richard Boser

Leaving Certificate Technology. Project Management. Student Workbook

The Project Planning Process Group

Course Overview. Course Learning Objectives

Project Time Management

2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster

Course Syllabus. Project Management Certificate

Module 3: The Project Planning Stage

Project Management Dr. James A. Bednar

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

Project Management Professional Training

Project management Project Management

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Acompany that consistently selects the right projects and

The 10 Knowledge Areas & ITTOs

MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION

Introduction. Page 1

LECTURE 5: SOFTWARE PROJECT MANAGEMENT. Software Engineering Mike Wooldridge

SWEN 256 Software Process & Project Management

Real-Life MS Project: Dependencies and Leveling

Introduction to IT Project Management

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

PMI Certified: PMP - Project Management 5 Days

Release 1. BSBPMG410A Apply project time-management techniques

This is Project Time Management, chapter 8 from the book Beginning Project Management (index.html) (v. 1.0).

Legal Project Management

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: # Program Cost: $4,690 Duration: 52.

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

CLASS: Introduction to Engineering Project Management GNEG 3061 P GNEG 3061 P02 NEW SCIENCE A101 UNTIL FURTHER NOTICE

Project Management Professional (PMP ) Exam Preparation

Use project management tools

Basic Project Management & Planning

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Practical Project Management Principles & Fundamentals

Certification Preparation Course LATVIKON (R.E.P.)Centre

CLASS: Introduction to Engineering Project Management GNEG 3061 P01

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

Input, Output and Tools of all Processes

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them

Project Scheduling page i. Facilitator Information. Contents. Learning Objectives (for content & process)


PMLead. Project Management Professional. edition. Based on PMBOK Guide 4 th.

EXAM PREP COURSE. Course Overview. Course Objectives. Course Materials Include: Our PMP Exam Prep (Fifth Edition) training program:

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

output: communications management plan

Chapter 3 Managing the Information Systems (IS) Project

Guidelines: Project Schedule Project Management Office (PMO)

Project Management Concepts and Strategies

8. Project Time Management

Methodical Notes for part-time BMCF TM study course M_SM / PROJECT MANAGEMENT

Project Management Skills for Trainers. William H. Dannenmaier

Is Critical Chain Project Management Really a Novel Technique?

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Cambridge International AS and A Level Computer Science

A Glossary of Project Management Terms

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

Transcription:

A Step-by-Step Approach for Planning Your Small Project Dohn Kissinger, MBA, PhD, PMP Planning for a small project is difficult. The PMBOK Guide (PMI, 1996) is an impressive document, which thoroughly discusses a generalized approach to planning and managing a project. The PMBOK approach is appropriate for large projects. However, project planning using the PMBOK approach takes a long time, sometimes months. Because of this long time, some project managers of small projects are inclined to skip the planning process altogether to get to the real part of the project. Another problem with typical project plans is that there is no allowance for increases in duration or cost of each task. This lack of built-in schedule and cost contingencies leads to overruns in the project schedule and budget. One could ask, What is the minimum level of planning required for a small project? In response to this question, I have developed a seven step approach that I believe answers this question. In addition to the usual schedule planning methodology, it creates schedule and budget contingencies for the project, protecting against schedule and cost overruns. I call these seven steps The 7 Steps to Project Success. Each step has a chart associated with it. The charts associated with each step are: 1. Project Success Chart 2. Work Breakdown Structure 3. Task Assignment Matrix 4. Task duration table 5. Project network diagram 6. Gantt (bar) chart schedule 7. Project budget chart To illustrate these steps, I will use a simple small project, making a birthday for my daughter s birthday, as an example. Step 1 Project Success Chart The Project Success Chart, shown in Exhibit 1, lists the factors vital to the success of the project the project objective, the project deliverable(s), and the project success criteria. The project objective is what will be achieved by when. In our example project, the project objective is Bake a in time for my daughter s birthday party. The project deliverable(s) are what will be delivered by when. In this case, our project deliverable is one 2-layer chocolate with Pokemon, in time for the birthday party. The project success criteria is what will meet or exceed the expectations of each stakeholder. The first step is to list all of the stakeholders. In this case, they consist of my daughter, her parents, and the birthday party guests. The expectations of my daughter are that the be chocolate, with Pokemon, and that it be on time for the party.

The expectations of her parents are that the be a reasonable cost, and that it be available on time. The expectations of the guests are that the be available in sufficient quantity, that it taste good, and that it be available in time. The advantage of the Project Success Chart is that the elements of the project that enable its success can be communicated to the project team members in a very short period of time. Project Objective (what will be achieved by when) Bake a in time for my daughter s birthday party. Project Deliverables (what will be delivered by when) One 2-layer chocolate with Pokemon, in time for the birthday party. Success Criteria (what will meet or exceed the expectation of each stakeholder) Stakeholders Daughter Parents Birthday party guests Success Criteria Chocolate, Pokemon, on time. Reasonable cost, on time. Sufficient quantity, taste, on time. Exhibit 1. Project Success Chart Step 2 Work Breakdown Structure The Work Breakdown Structure, shown in Exhibit 2, is one way of organizing all of the tasks in the project. The method used is to break the project objective (in this case, the birthday ) into sub-objectives. For each sub-objective, I list the tasks necessary to achieve the sub-objective. In this case, the Make Cake sub-objective consists of 1) Look in recipe book, 2) Measure/mix ingredients, 3) Cool, and 4) Bake. Notice that the tasks do not have to be listed in the correct time sequence. The important thing is to not miss a task necessary for the achievement of the sub-objective. The Make Frosting sub-objective consists of 1) Look in recipe book, and 2) Measure/mix ingredients. The Purchase Ingredients sub-objective consists of 1) Drive to store, 2) Drive back from store, and 3) Buy. Notice again that the tasks are not necessarily listed in the correct time sequence. In many projects, there is an integration function. In this case, we must put the,, and together. I will call this the Perform Integration sub-objective, consisting of 1) Put on, and 2) Slather on.

Birthday Make Make Purchase Perform Cake Frosting Ingredients Integration Look in Look in Drive to Put recipe book recipe book store on Measure/mix Measure/mix Drive back Slather ingreds ingreds from store on Cool Bake Buy Exhibit 2. Work Breakdown Structure (WBS) Step 3 Task Assignment Matrix The Task Assignment Matrix, shown in Exhibit 3, lists the tasks and the task owners. In our case, we assign the making tasks to Dad, the and integration tasks to Mom, and the purchase ingredients tasks to Grandpa. Thinking Grandpa might need some help with selecting the Pokemon, we assign our son to help Grandpa with the Buy task. Also, Dad is available to help Mom with the integration tasks. And, of course, we need to get the approval for the and their location on the from our daughter. Task Task Owner Support Inform Approval Look in recipe book Dad Measure/mix ingreds Dad Cool Dad Bake Dad Look in recipe book Mom Measure/mix ingreds Mom Drive to store Grandpa Drive back from store Grandpa Buy Grandpa Son Put on Mom Dad Daughter Slather on Mom Dad Exhibit 3. Task Assignment Matrix

Step 4 Task Duration Table The Task Duration Table, shown in Exhibit 4, lists three estimates for each task optimistic, most likely, and pessimistic. The optimistic values usually have a probability of occurring 10-20% of the time, the most likely values 50% of the time, and the pessimistic values about 80-90% of the time. These percentages can be varied depending on the schedule criticality of the project end date. At this point you may wonder what we going to do with all of these estimates. I will address this in the next two sections. Task Optimistic Most likely Pessimistic Actual Look in recipe book 20 30 60 Measure/mix ingredients 10 20 40 Look in recipe book 20 30 60 Measure/mix ingredients 10 20 30 Bake 40 50 60 Cool 30 60 90 Drive to store 10 20 30 Buy 10 20 40 Drive back from store 10 20 30 Slather on 5 10 20 Put on 20 30 40 Exhibit 4. Task Duration Table (in minutes) Step 5 Project Network Diagram The Project Network Diagram, shown in Exhibit 5, shows the logical flow of tasks in the project. After starting the project, we can either first look in the recipe book, look in the recipe book, or drive to the store to buy the. From our Task Assignment Matrix, we can see that we can do all of these tasks simultaneously, because we have assigned different resources to each of these tasks. Even if we have fewer resources, however, we have established that there are at least three paths of tasks available in our project. After we look in the recipe book, we can measure/mix the ingredients. We are then ready to slather the on the. However, we have to wait for the to be baked and cooled before we do this task.

After we look in the recipe book, we can measure/mix the ingredients, bake and cool the. The is then ready for the. After Grandpa drives to the store, buys the Pokemon (with my son s help), and drives back from the store, we can put the on the. However, we have to wait for the frosted before we put the on it. After we complete all of these tasks in these three parallel paths, the is complete and ready for the birthday party. Look in recipe book Measure/mix ingredients Start Look in recipe book Measure/mix ingredients Bake Cool Slather on Drive to store Buy Drive back from store Put on Complete Exhibit 5. Project Network Diagram The Critical Path is the longest path of the project. To determine the Critical Path, we combine the results above with our Task Duration Table from Step 4. From the Task Duration Table, we use the most likely estimates of task duration to determine the longest path in the project, or Critical Path. This path is shown in Exhibit 6 as the shaded tasks Look in recipe book, Measure/mix ingredients, Bake, Cool, Slather on, and Put on. The parallel paths to the Critical Path are called feeding paths, because they feed into the Critical Path. We have two feeding paths in our project 1) Look in recipe book, and Measure/mix ingredients, and 2) Drive to store, Buy, and Drive back from store.

Look in recipe book Measure/mix ingredients Critical Path Start Look in recipe book Measure/mix ingredients Bake Cool Slather on Drive to store Buy Drive back from store Put on Complete Exhibit 6. Project Network Diagram with Critical Path Step 6 Gantt (Bar) Chart Schedule We would like to use the information in our Task Duration Table from Step 4 to determine a contingency to protect the project due date from schedule overruns. Goldratt (Goldratt, 1997) has proposed a simple method of calculating this contingency, which he terms a project buffer. This buffer is placed at the end of the Critical Path to protect against overruns in the duration of the tasks on the Critical Path. (We assume that the feeding paths have sufficient leeway, or schedule float, to allow for schedule overruns in the feeding tasks.) Listing only the Critical Path tasks, as shown in Exhibit 7, we see that the pessimistic estimates for the Critical Path tasks total to 300 minutes, and the most likely estimates total to 200 minutes. Goldratt s suggestion is that we take half of the difference between the total of the pessimistic and most likely estimates as the project buffer, which in this case would be 50 minutes. Critical Path Task Optimistic Most likely Pessimistic Actual Look in recipe book 20 30 60 Measure/mix ingreds 10 20 30 Bake 40 50 60 Cool 30 60 90 Slather on 5 10 20 Put on 20 30 40 Totals 200 300 Exhibit 7. Critical Path Tasks

We can then construct the Gantt (bar) chart for our project, including the 50 minute project buffer. The completed Gantt chart, shown in Exhibit 8, indicates that if we start the birthday project by 8 am, we should have it ready for the birthday party scheduled for 12:30 pm in the afternoon. ID Task Name 1 Birthday Cake Project 2 Start 3 Look in recipe book. 4 Measure/mix ingredients 5 Look in recipe book. 6 Measure/mix ingredients 7 Bake 8 Cool 9 Drive to store 10 Buy 11 Drive back from store 12 Slather on 13 Put on 14 Project buffer 15 Complete 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 45 0 15 30 45 0 15 30 45 0 15 30 45 0 15 30 45 0 15 30 1/11 Critical Path 1/11 Exhibit 8. Gantt (bar) Chart Schedule Step 7 Project Budget Chart We would like to calculate the budget for the project to ensure that it meets the reasonable cost success criteria specified in the Project Success Chart by the parents. As shown in Exhibit 9, cost estimates for each task are listed in terms of optimistic, most likely, and pessimistic. Again, the optimistic values usually have a probability of occurring 10-20% of the time, the most likely values 50% of the time, and the pessimistic values about 80-90% of the time. We then calculate the budget based on the most likely cost values plus a budget contingency. The contingency is computed using the Goldratt approximation of 50% of the difference between the pessimistic values and the most likely values. In our project, the most likely cost estimates total to $9.00, and the pessimistic estimates total to $16.00. Taking half of the difference between the pessimistic estimate and the most likely estimates gives us a budget contingency of $3.50. Adding this budget contingency to the most likely total of $9.00 gives us a budget of $12.50. We can then use this budget value to determine if this is a reasonable cost according to the parents success criteria.

Task Optimistic Most likely Pessimistic Actual Look in recipe book 0 0 0 Measure/mix ingredients.50 1.00 2.00 Look in recipe book 0 0 0 Measure/mix ingredients 1.00 2.00 3.00 Bake.25.50 1.00 Cool 0 0 0 Drive to store.50.75 1.00 Buy 2.00 4.00 8.00 Drive back from store.50.75 1.00 Slather on 0 0 0 Put on 0 0 0 Totals 4.75 9.00 16.00 Budget contingency = 0.50 x (Pessimistic total Most likely total) = 0.50 x ($16.00 $9.00) = $3.50 Budget = Most likely total + Budget contingency = $9.00 + $3.50 = $12.50 Conclusions Exhibit 9. Project Budget Chart (in dollars) For small projects, the PMBOK approach can be overwhelming. Project managers of small projects need a simpler process for planning their projects. The step-by-step approach I have described will enable them to produce faster project plans, and it will help protect against project schedule and cost overruns. References A Guide to the Project Management Body of Knowledge (PMBOK Guide), 1996, Project Management Institute, Newtown Square, PA. Goldratt, Eliyahu M., Critical Chain, 1997, The North River Press, Great Barrington, MA.