2014 Sewer Replacement Project



Similar documents
SANITARY SEWER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix D

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

Construction Specification for Sewer Bypass Flow Pumping

First in Service First in Safety

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Weeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario

WSSC is replacing the water mains in your neighborhood. Here s what you need to know.

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST BID PROPOSAL

DESCRIPTION OF WORK:

City and County of San Francisco 2030 Sewer System Master Plan TASK 400 TECHNICAL MEMORANDUM NO. 405

Township of Enniskillen. Asset Management Plan

Kansas City s Overflow Control Program

Lansdowne Stormwater UPDATE

See Appendix A for additional information, or contact ASTM directly.

SECTION STORM DRAINAGE TABLE OF CONTENTS

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards

DEPARTMENT OF ENVIRONMENTAL QUALITY

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

SECTION GRAVITY SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

LS 2540 SEWER LATERALS AND INSPECTION TEES

Beechmont Park Project

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION ABANDONMENT OF SEWER MAINS

The City of Owen Sound Asset Management Plan

Contracting Opportunities Vendor Day May 17, 2011

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates. Private Sewer Lateral Inspection and Repair Program

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

FY15 Gravity Sewer and Manhole Rehabilitation

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST

ENVIRONMENTAL ASSESSMENT (EA) VILLAGE OF EAU CLAIRE - BERRIEN COUNTY INFILTRATION/INFLOW REMOVAL PROJECT APRIL 2015

Guidelines for. Permeable Pavement

C. Section TESTING LABORATORY SERVICE.

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000

How To Install An Overhead Sewer

SANITARY SEWER BACKUP. Causes & Prevention

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

Storm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses

Request for Proposal Public Works Asset Management System

SEWER BACKUPS WHAT TO DO AND HOW TO PREVENT

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

The Clean Water Project What Is The Stormwater Impact?

West Thornhill Stormwater Flood Remediation Phase 1 Construction. Community Information Meeting

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

OVER-HEAD SEWER ASSISTANCE GRANT

Sewer Backup Protection Grant Program. Guidelines, materials and frequently asked questions

ORDINANCE NO. 15 BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Durango Migrates its Infrastructure GIS to an Asset Management System

Downspout to storm sewer. Leaky laterals

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

SECTION STORM DRAIN SYSTEM

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON

SANITARY SEWER SPECIFICATIONS

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

BASEMENT FLOODING. Prevention Guide for. Homeowners

Town of Bellingham DEPARTMENT OF PUBLIC WORKS. Snow and Ice Control FAQs. Q. Can I push snow from my property onto the sidewalk or street?

Memorandum. PROJECT: Postmark Emergency Storm Repair Alternative Analysis

FOR IMMEDIATE RELEASE September 17, 2013 Contact:

Appendix B. Property Owner Questionnaire

Concrete Waste Management

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Water & Sewer Utility Maintenance SC-76

Engineering Major Service Actual Budget Projected Request Executive Adopted

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC, WISCONSIN SECTION 400 SEWER AND WATER CONSTRUCTION

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010

SECTION EIGHT BONDING REQUIREMENTS

Update on the Metro Nashville Consent Decree Program. Scott Potter Ron Taylor

Special Specification 7021 Water Main and Sewer Line Replacements

ORDINANCE NO AN ORDINANCE AMENDING CITY CODE CHAPTER RELATING TO REQUIREMENTS FOR PRIVATE LATERAL SEWER LINES.

CITY OF DULUTH PRIVATE SEWER SERVICE GRANT PROGRAM PROGRAM GUIDELINES

Transcription:

Palmer, Massachusetts 2014 Sewer Replacement Project Public Meeting January 27, 2014 TIghe&Bond 10 1 Background Poor Pipe Condition Closed circuit television inspection showed that pipe replacement due to disrepair is required for 23,000 linear feet of sewer in five distinct locations in town: - Brainerd Street Area (Depot Village) - Riverview Parkway Area (Deport Village) - Chudy Street Area (Three Rivers) - South High Street Area (Bondsville) - High Street (Thorndike) Blocked Sewers The current condition of the sewer pipes has lead to blockages and back-ups. Tighe&Bond 1

dims Project Objectives Replace Sewer Pipe Replace sanitary sewer system in the five distinct locations of town Replace Deficient VC (Vitrified Clay) sewer pipe Currently undersized and impacted during wet weather events Health and Environment Improvements Currently back-ups as well as leakages may lead to public health and environmental nutrient issues. Water Quality Improvements The new sewer line will prevent leakages and back-ups that could compromise the nearby public groundwater supply. TIghe&Bond Project Schedule Construction Bids and Contract Award January through March, 2014 Construction Start April, 2014 Pipeline Work Complete & Partial Paving November, 2014 Final Paving Spring/Summer, 2015 TIghe&Bond 2

Typical Pipeline Defects of Sewer Lines Video Inspection of Existing Lines Typical Pipeline Defects of Sewer Lines 3

- - ; 0, Project Scope Sanitary Sewers - 23,000 feet (4.35 miles) Additional 8,500 feet of services laterals to connect 320 services 500 feet of storm drain and 72 Catch Basin Replacements Pavement Resurfacing on all Disturbed Streets 25 Handicap Ramps Approximately 7,000 feet of Curbing Approximately 5,000 feet of Sidewalk Tighe&Bond Palmer Sewer Replacement Project Brainerd Street Area Park Street Brainerd Street Winthrop Street Cabot Street Alden Street Geraldine Street June Street Emelda Street Beverly Street Carol Street Deborah Street Norma Street 4

Palmer Sewer Replacement Project Riverview Parkway Area South Main Street Strong Street Conant Street Salem Street Riverview Parkway Palmer Sewer Replacement Project Chudy Street Area Streets Affected: Chudy Street Overlook Drive Sasur Street Barker Street Sibley Street Sylvia Street Glenn Street Edgewood Street Linda Street Tighe&Bond 5

Palmer Sewer Replacement Project South High Street Area. Palmer Sewer Replacement Project High Street Area 6

Multiple Steps of Sewer Construction Typical Sequence 1. Install Sewer Main Pipe, Manholes and Wyes 2. Patch Pavement Over Sewer Main 3. Install Sewer Services / Connect to New Pipe Patch Pavement Over Sewer Services Pavement Restoration - Full Roadway Width Restore Lawns 411111116 Tighe&Bond Typical Sewer Construction Sequence Existing Conditions 0 7

CO

Typical Sewer Construction Sequence Step 3 - Install Services / Connect to New Pipe Typical Sewer Construction Sequence Step 4 - Patch Pavement Over Services 9

Typical Sewer Construction Sequence Step 5 - Restore Full-Width Pavement Width Typical Sewer Construction Sequence Step 6 - Restore Lawns_ 10

Must be: - Disconnected from the new sewer system, and - Reconnected to the storm drain system or discharged to grade. Temporary Impacts to Neighborhood Emergency vehicles will have access as needed. Residents / Owners will have access, but subject to temporary delay or detour. Services (school bus, mail, trash collection) will be maintained, but subject to temporary delay or detour. Some level of traffic delay, noise and dust is inevitable! Tthe&Bond 11

=.40.0. hilt n July 2013 -Project was awarded funding from the Clean Water State Revolving Fund Awarded $6,090,000 in low interest funding Some debt forgiveness is anticipated (value to be determined after April 2014) Tighe&Bond Anticipated Construction Schedule Bondsville Start April 2014 Complete Pipes, and Trench Patches May 2014 Road Resurfacing August 2015 Thorndike Start July 2014 Complete Pipes and Trench Patches August 2014 Road Resurfacing November 2014 Three Rivers Start Summer 2014 Complete» Pipes and Trench Patches November 2014 Road Resurfacing August 2015 Tighe&Bond 12

Anticipated Construction Schedule Continued Depot Village Start July 2014 - Complete» Pipes and Trench Patches November 2014» Road Resurfacing August 2015 Overall Start April 2014 Complete August 2015 Tighe&Bond Contact Information Town of Palmer Charles Blanchard - Town Manager Phone: (413) 283-2603 Gerald Skowronek - Wastewater Superintendent Phone: (413) 283-2671 Engineer - Tighe & Bond Antonio J. da Cruz - Project Manager Phone: (508) 471-9617 Jeffrey Faulkner - Project Engineer Phone: (508) 471-9620 TIghe&Bond 13

General Questions? Questions Regarding Specific Streets / Addresses? Available to answer immediately following this meeting TIghe&liond 14