TEMPORARY AND PERMANENT SUPPORT OF HYDRO OTTAWA DUCT BANKS WHEN UNDERCUT BY AN EXCAVATION



Similar documents
Ontario Electrical Safety Code - Info Sheet

CONSTRUCTION PERMIT REQUIREMENTS

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

DESCRIPTION OF WORK:

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SECTION EARTH MOVING

UNDERGROUND ELECTRIC TEMPORARY SERVICE PANEL

Permit No. Permit Fee: $ Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: Address:

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

SECTION GRAVITY SANITARY SEWERS

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

DIVISION 4300 STORM DRAINAGE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

SHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Chapter 3 Pre-Installation, Foundations and Piers

HIGH TENSION CABLE BARRIER

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

Excavation & Trenching Procedure

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Utilities and existing services

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

REQUEST FOR ELECTRIC SERVICE Commercial

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

Cold Weather Concrete Practices

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

Storm Drain Inlet Protection - IP

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

SECTION SHEETING, SHORING AND BRACING

Underground Commercial Electric Service

Elevating Your House. Introduction CHAPTER 5

Guidelines for Excavations

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

your electric service: from overhead to underground

SIKA AT WORK THE KAENG KRACHAN ELEPHANT HOUSE AT ZURICH ZOO

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

SECTION SITE PREPARATION

SECTION 1 GENERAL REQUIREMENTS

1 Campus Cabling Systems Introduction

How To Build A Luxury Apartment Complex In London

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

City of Shelbyville Site Inspection Checklist

Machine Foundation Design

Trenching and Excavation Safety

How To Safely Dig For Natural Gas

C. Section TESTING LABORATORY SERVICE.

How To Retaining Wall Guide

OSU Extension FACT SHEET

Handling and Installation of Cables up to and including 33kV

4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

Design and Construction of Cantilevered Reinforced Concrete Structures

SECTION SUPPORT OF EXCAVATION

SECTION 603 SANITARY SEWER FORCE MAINS

SECTION SELECTIVE DEMOLITION

How To Get A Power Line Extension

Technical Notes 3B - Brick Masonry Section Properties May 1993

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS

DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

Network Standard Advice No. 1420C 9/6/2011

Mineral waterproof coating PCI Dichtschlämme

Construction Specifications for Keyhole Pavement Coring and Reinstatement

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

Excavation Safe Working Practices

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL

Cable Support Solutions

Cable usage designation. Number of ducts required Number of spare ducts to be provided < > 11

CHAPTER 2 QUANTITY TAKE-OFF

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd

Merrimac Municipal Light Department. Residential Developments Policy

Transcription:

TITLE: Engineering Specification RECOMMENDED: C. Proulx APPROVED: C. Malone REV. DATE: 2002-09-12 NO: UDS0013 1 OF 5 REV: 0 TEMPORARY AND PERMANENT SUPPORT OF HYDRO OTTAWA DUCT BANKS WHEN UNDERCUT BY AN EXCAVATION For Hydro Ottawa Use Only 2002 See Hydro Ottawa s Web site for the Latest revisions at: www.hydroottawa.com

REVISION SHEET Revision Description Date Initials 0 Original Document 2002-09-12 cp/csm For Hydro Ottawa Use Only 2002 UDS0013 Rev.0 Page 2 of 5

Table of Contents 1.0 GENERAL...4 2.0 LOCATING DUCTS... 4 3.0 TEMPORARY SUPPORT... 4 4.0 PERMANENT SUPPORT... 5 5.0 COLD WEATHER CONCRETING... 5 6.0 MISCELLANEOUS... 5 REFER TO HYDRO OTTAWA SPECIFICATIONS UDS0011 Temporary Support of Existing Duct Bank Construction Detail UDS0012 Permanent Support of Existing Duct Bank Construction Detail For Hydro Ottawa Use Only 2002 UDS0013 Rev.0 Page 3 of 5

1.0 General In large-scale excavations involving the location of Hydro Ottawa duct banks, arrangements shall be make for supporting the duct banks in a temporary way during the excavation and in a permanent way during the backfilling operation. Hydro Ottawa duct banks are constructed in various sizes. Generally the formations are about 630 mm wide by 630 mm high, and weight approximately 900 kg per linear metre. Generally the duct banks are constructed with unreinforced concrete and therefore have very little ability to be self-supporting in a free span. If any excavation undermines more than 1.5 meters of duct bank, intermediate supports shall be installed under the duct bank, and a permanent support shall be installed during the backfilling operation. 2.0 Locating Ducts Prior to excavating, Hydro Ottawa shall be notified as 738-5499 local 522. An Hydro Ottawa Cable Locator will be sent to the site to indicate the location of the underground duct structure. The ducts shall be located by hands, i.e. not using mechanical excavating equipment. Arrangements shall be made to have a Hydro Ottawa Underground Inspector present while the ducts are being exposed. 3.0 Temporary Support The Hydro Ottawa Specification no. UDS0011 Temporary Support of Existing Duct Bank shows the method of support. On shorter spans, up to approximately 3 meters, a wood-supporting beam may be adequate. On spans over 6 meters, provisions shall be made to counteract any possible torsion or horizontal deflection in the supporting beam. Such forces arise due to unequal loading at the edge of the flange by the wire rope lashing. Methods of counteracting such forces are by lateral bracing of the supporting beam or by using a box-girder as the supporting beam. In most cases, a wide flanged I-beam of acceptable strength has been adequate. If the trench is adequate shored at the location of the supporting beam, it will be sufficient for the beam to extend 1 meter on each side of the trench limit. If the trench is not shored, the supporting beam shall extend on each side of the trench limit a distance not less than one-half of the trench depth. In addition for an unshored trench, the wire rope lashing shall start immediately adjacent to the trench face. For a shored trench, the wire rope lashing shall start no further than 1 meter from the trench face. The temporary support shall be installed in the presence of the Hydro Ottawa Underground Inspector. For Hydro Ottawa Use Only 2002 UDS0013 Rev.0 Page 4 of 5

4.0 Permanent Support The Hydro Ottawa Specification no. UDS0012 Permanent Support of Existing Duct Bank shows two methods of support. The Hydro Ottawa Underground Inspector will specify if Detail A or Detail B shall apply. In either case the backfill shall be compacted to not less than 95% of the maximum density under the duct bank. Certified test results shall be presented to the Hydro Ottawa Inspector if requested. The backfill shall be brought up as close to the ducts as possible. Special care shall be taken to ensure that no voids exist in the concrete under the duct structure. It is suggested that the cradle support (Detail B, of drawing UDS0012) be place in two operations. For a period of seven days after the concrete is placed, no equipment shall be allowed to pass over the duct structure. All forms shall be adequately braced. The Hydro Ottawa inspector shall be present when the concrete is being placed. 5.0 Cold Weather Concreting At temperatures below 4ºC the following conditions shall apply: a. The fresh concrete, prior to placing, shall be between the temperature limits of 15ºC minimum to 21ºC maximum. b. As soon as the concrete is placed, the structure shall be covered with clean dry straw, and then covered with a tarpaulin or polyethylene sheet, for a minimum of forty-eight hours. After this time the temporary support may also be removed. 6.0 Miscellaneous All work shall be subject to the approval of the Hydro Ottawa Underground Inspector. Additional provisions may be required if Hydro Ottawa considers that the safety of their cable is jeopardized. On smaller excavations (maximum trench of approx. 1.5 m) permanent support may consist of a concrete column from undisturbed earth up to the center of the duct structure, but this will be subject to approval by Hydro Ottawa. To obtain exact sizes and weights of duct structures contact Hydro Ottawa at 738-5499 local 216. Prior to the commencement of any large-scale excavation, Hydro Ottawa shall be notified of the detail of the proposed work. For Hydro Ottawa Use Only 2002 UDS0013 Rev.0 Page 5 of 5