Schedule Risk Analysis A large DoD Development Program



Similar documents
Basic Schedule Analysis

Project Time Management

Importance of Finish to Start Successors

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Project Time Management

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

Quantitative Risk Analysis with Microsoft Project

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

The Basics of Best Practices. Elden F. Jones II, MSPM, PMP, CMII

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

INT 3 Schedule Risk Analysis

Chapter 6. (PMBOK Guide)

Problems, Methods and Tools of Advanced Constrained Scheduling

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

LLamasoft K2 Enterprise 8.1 System Requirements

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

Project Day Numbering

Project Management Using Earned Value

Scheduling Glossary Activity. A component of work performed during the course of a project.

Systems Analysis and Design

Instruction Manual Service Program ULTRA-PROG-IR

Representing Uncertainty by Probability and Possibility What s the Difference?

A collection of Safran Project report samples for project professionals

DCMA 14-Point Assessment Metrics

Scheduling Process Maturity Level Self Assessment Questionnaire

USER S GUIDE for DSM@MIT

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

WORK PROGRAM GUIDELINES

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita

Schedule Assessment Guide. Best Practices for Project Schedules

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field

PROJECT TIME MANAGEMENT

PROJECT RISK MANAGEMENT

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

The Plan s Journey From Scope to WBS to Schedule

MSP How to guide session 2 (Resources & Cost)

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Project 2010 Introduction

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

DYNAMIC PROJECT MANAGEMENT WITH COST AND SCHEDULE RISK

Monte Carlo analysis used for Contingency estimating.

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Amajor benefit of Monte-Carlo schedule analysis is to

Basic CPM Calculations

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

Project Time Management

Chapter 4: Project Time Management

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

PROJECT RISK MANAGEMENT

CRASHING-RISK-MODELING SOFTWARE (CRMS)

Project Management by Using MS PROJECT 2013

Risk Workshop Overview. MOX Safety Fuels the Future

2. Filling Data Gaps, Data validation & Descriptive Statistics

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

Introduction. Page 1

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

Introduction to Project Management

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Agile and Earned Value. A white paper. October Author Stephen Jones, Sellafield Ltd

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

OTC Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

PMI Lexicon of Project Management Terms

Project Scheduling: PERT/CPM

Simulation and Lean Six Sigma

SPREADSHEET VALIDATION 101: CREATE AND VALIDATE FDA-COMPLIANT MS EXCEL SPREADSHEETS

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

CHAPTER 1. Basic Concepts on Planning and Scheduling

PMP Exam Preparation Answer Key

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Schedule Risk Analysis Simulator using Beta Distribution

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On

Web Load Stress Testing

Optimization: Continuous Portfolio Allocation

Microfinance Credit Risk Dashboard User Guide

ORACLE S PRIMAVERA RISK ANALYSIS

SOLUTION BRIEF: SLCM R12.7 PERFORMANCE TEST RESULTS JANUARY, Load Test Results for Submit and Approval Phases of Request Life Cycle

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Tech-Clarity Insight: Integrating PLM and MES. Realizing the Digital Factory

Scheduling. Anne Banks Pidduck Adapted from John Musser

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

Transcription:

Schedule Risk Analysis A large DoD Development Program

So, who s the dude? Jim Aksel PMP, PMI SP Microsoft MVP 35 Years experience aerospace/defense Co Author PMI Practice Standard for Scheduling Program and Scheduling Excellence Guide (PASEG) DID MGT 81861 Full EVMS capabilities Scheduling Yoda 2008 13 jim@projectpmo.com ProjectPMO PO Box28113 Anaheim, CA 92809 0137 (714) 312 3120

What is a Schedule Risk Analysis Monte Carlo Simulation of a compliant Schedule Model Assists in establishing timeframe for event completion If Schedule Model is cost/resource loaded, can predict costs too

The Goal Land in the red box

Today s Example USN Missile Program Prime with 1 subcontractor Master/Subproject file 5277 discrete nonloe tasks Requires correlation Requires probabilistic branching

Preliminaries Schedule Model preparation Excel/Computer preparation

Schedule Model Preparation Proper Schedule Model status Consider an analysis tool such as DCMA14 Point Assessment Things that were supposed to happen actual did! No time warps Everyone has a proper successor xf

Schedule Model Preparation Custom Fields Clear all formulas, lookup values, etc. Consider deleting data Retain only Min, Most likely, Max Level of Effort Hammock Task Pure Level of Effort Constraints Remove MFO, MSO, SNET, SNLT, FNET, FNLT Retain only those from external constraints. @Risk Monte Carlo Engine does not need custom field calculations Level of Effort should never drive a path remove it. Think very carefully about constraint dates Schedule logic may change: FS, FF, SS, SF.

Excel and Computer Preparation Excel Latest Service Packs Enable Multi Threaded Calculations RAM! Consider Office x64 bit Windows manages Virtual Memory Disable power management including within the BIOS It will take some time, use a different machine

Triple Point Estimates Remaining Duration Minimum, Most Likely, Maximum Consider these Tasks with no upside (Min close to Most Likely compared to Max) Tasks with no downside (Max close to Most likely compared to Min) Inherent high risk (Max Min exceeds 25% of Most Likely) Or better... Is data available to support more realistic distributions? Requires only a mean and standard deviation or other factor

More on Triple Point Estimates Banding +x/ y need not be symmetrical Simple, not very rigorous More rigor required on Critical Path tasks (1 st,2 nd,3 rd ) Historical Performance Decomposition Analogy Ratio/Parametric Units Expert opinion Effort

Probability Distribution Use Triangular unless you have some valid reason to use something else. Why? Has the largest Standard Deviation of the common distributions Drives uncertainty Spreads the results Easily understood and adaptable Only requires three points

Match the Distribution to the Data Is this triple point truly Normally Distributed?

@Risk Tool Hints Check Simulation Engine settings for faster results (Standard, Accelerated) Consider using Project/Excel 2007 MS Project Table ready as you want it (Remaining Duration) Save frequently

@Risk Tool Hints Unprotect the Tasks Sheet to apply filtering

Correlations Tasks split between $ and hours (EVMS Requirement) Long preparation time Long test time

Probabilistic Branching A choice of task paths exists after completion of a task One to Many relationship (at least 2) Each successor path has a mutually exclusive probability Must sum to 1.0 Chains can be anywhere in the Schedule Model Need not end in same place Should trace forward to final task Use Inactive Tasks Could be Risk Register Items?

Probabilistic Branching Prerequisite branches Choice 1a 90% Choice 2a 10%

Probabilistic Branching Certain material obsolescence issues (90/10) Setup logic drives both paths At least 1 day duration

The Main Event!

Effects of Conditional Branching

Tornado Chart

Tornado Correlations

Did we do enough? 1000 Iterations run Desired granularity ±1 day Error Term µ

Did we do enough? From Statistics Z=1.96 (95 th Percentile) s=σ=31.28 from prior slide Set error = 1 day Solve for n n=3759 At n=1000, Error is about 1.93 days

Output Convergence At some point, output changes small enough to be ignored You can effectively stop at this point See Simulation Settings

What We Learned Systems Engineering has more impact to Critical Path than we thought Balloon Squeezing is difficult Mitigations on the Tornado Tasks is only one way to do it. Forces creativity to increase probabilities of reaching set dates The Golden Rule

For Consideration Resource Leveling not considered Leveling delays? Overloaded resources? Money constraints Mitigate through corporate funding or other cost shares? Does it produce progress gaps (standing army)? Reduce conditional branching if possible Eliminate Correlation through improved logic?

Jim Aksel ProjectPMO PO Box 28113 Anaheim, CA 92809 0137 jim@projectpmo.com (Office) 800 985 3317 or 714 312 3120 (Cell) 714 813 4025